STOCK TRANSPORT ORDER  With in One company code

Dear Laksmipathi,
While RP delivery in stock transfer order  With in One company code, the sym will pick movement tyoe 641 and which ic configrued in SL .But  in STO  there is no sale order creation  that  i mean  SL  will pick only in sale order.
Here  order type UB and plant combination  sym will pick the Delivery type NL
NL -NORM -V sym will pick Item category  NLN  of Delivery not  of  sale order.
NLN-NN(Schedule line)
Generally we know the SL which is determined by  item category  and MRP  type , here  item category is coming only in RP  delivery document.
So my question is
Question  1.how  this  641  which  has  determined  while RP Delivery  document?
                               if it is  determining from schedule line NN , how  it can be consider since  sale      order is not  in the picture?
Question 2. In 641  the cost has been updating /Accounting document is getting generatiing  where as in VF01 billing doc  not relevent for Accounting  doc  .so  how we can settle or balance the  cost  of this material  while occured in 641  or  PGI?
Question 3.What  are the business benifits while  doing  STO?
i am new in this  and Pls  advice  how to give the  point  to  you .
Regards
ISHI

Dear Thakkar,
Pls  compare  my question and ur answer
Question 1.how this 641 which has determined while RP Delivery document?
if it is determining from schedule line NN , how it can be consider since sale order is not in the picture?
What is   I am not clearu2014that  if i641 is determining from schedule line NN , how it can be consider since sale order is not in the picture?
Ur Ans:
A1. In case if STO the item category is assign to Delivery typeitem category groupusages+ Item category of the higher-level item Tocde (ZERO)0VLK Taking the item category and and checking the schdeline assign to the same. In schedule line you will find 641.
Query
OVLK  which is  delivery header  and taking the item category of Delivery through  Delivery typeitem category groupusages+ Item category of the higher-leveL.
Can we determine the SL  with  delivery  type  and delivery  item category since sale order is not in the picture?
How we can take the sale  order item category  for  find SL since sale order is not in the picture?
Question 2. In 641 the cost has been updating /Accounting document is getting generating where as in VF01 billing doc not relevant for Accounting doc .so how we can settle or balance the cost of this material while occured in 641 or PGI?
What is   I am not clear-How settle cost  of this  material ?
Ur Ans : The accounting is happening for material value.
Are  you  think Is  it  correct  this  answer  yourself?
Question 3.What are the business benifits while doing STO?
I  am cleared in third answer which you   given   and I am appreciating to  you ur  response, but  the answer should be  according to my question.
Thanks
Ishi

Similar Messages

  • Stock Transport Order with Delivery via Shipping

    Hai
    I created stock transport order Intra process. within company two plants .. i configured supplying plant i assigned sal.org,dis.channel,division and receiving plant i assigned customer number also. in po its automatically picked the shipping data details. but in delivery VL10B with ref po , it show the error log error message as: An item with no delievery quantity is not permitted.Item will be deleted. but i checked all the setting in STO.. how to solve the error message in delivery?

    Is committed qty showing in the delivery schedule tab of item details(STO)?
    And also check the delivery creation date in the shipping tab.While creating the O/b delivery you should give the date as it's given in the Shipping tab.
    And Also maintain the Stock in the Supplying plant.
    Otherwise Give the Message no.
    Edited by: John Boeckle on May 23, 2008 2:24 PM

  • Intra company stock transport order with delivery to subcontracting vendor

    Hi Friends,
    We have an issue with Intra company stock transport scheduling agreement with delivery to subcontracting vendor.
    We have a scenario where the component is provided by another plant (Plant A -Intra company) directly to subcontracting vendor and the subcontracting vendor processes the component and sends us(
    Plant B) the finished good.
    We have a subcontracting scheduling agreement created with the subcontracting vendor with Item category u201CLu201D for plant B .(Document type LPA)
    And we created the stock transport scheduling agreement with document type LU (Between Plant A to Plant B) by entering the subcontracting vendor number to the "EMLIF- Vendor to be supplied/who is to receive delivery" field but the check box "LBLKZ-Subcontracting vendor" is hidden in the delivery address tab.
    Field selection with document type (LU) and Field selection with transaction code (ME37) did not help to bring the field to the delivery address tab.
    As a result, when we do PGI from the supplying plant, the stock is posted to "in transit" (Movement type 641) instead of "Component provided to vendor" (Movement type 641 u2013 O)
    The same behavior for purchase order with document type UB as well/
    Is the movement type u201C641-O u201C supported by standard SAP or do we have any other workaround to address the requirement. ?
    Now we are in ECC 6.0 EHP3.
    Your inputs will be highly appreciated.
    Regards
    Gobinathan G

    Hello,
    This EhP4 feature addresses only the one step Stock Transport Order to subcontracting vendor for intra company.
    Does anybody know how to do a two steps Stock Transport Order to subcontracting vendor for intra company?
    By "two steps" I mean:
    1- Goods Issue from supplying plant A to in-transit stock of the subcontracting vendor at receiving plant B.
    2- Inbound Delivery Notification (IDN) at receiving plant B + Goods receipt against this IDN into the subcontracting stock at receiving plant B.
    Thanks and regards,
    Stéphane

  • HELP for all 5 TYPES of  STO  Stock Transport Orders with detailed scenario

    PLEASE help me understanding the detailed scenarios for all 5 TYPES of STO s
    as in my day to day job activities , i frequently handles issues related to STO s
    PLEASE HELP WITH DETAILED STEP BY STEP SCENARIOS

    Hi Jagatram,
    Standard SAP has the following methods For Stock transport order:
    1) One Step Transfer stock without using purchasing documents; Use movement type 301.
    2) Two Step Transfer stock without using purchasing documents; Use movement type 303 in Supplying plant and movement type 305 in receiving plant.
    3) Using Standard Transport Order (STO) without delivery in two steps. STO created in T-Code ME27, receiving plant posts goods issue (for returns), movement type 351 and supplying plant post goods receipt from using movement type 101.
    4) Using Standard Transport Order (STO) with delivery in one step. STO created in T-Code ME27, Receiving plant creates shipment and Goods issue document (for materials to be returned) with movement type 647 and goods receipt document with movement type 101 both created in one step.
    5) Using Standard Transport Order (STO) with delivery in two steps. STO created in T-Code ME27, Receiving plant creates shipment and Goods issue posted (for materials to be returned) with movement type 641.Goods receipt is posted in the supplying plant, movement type 101.
    6) Using Transportation scheduling agreement (TSA) with delivery in two steps. TSA created in T-Code ME37. Receiving plant creates shipment and Goods issue document (for materials to be returned) with movement type 641. Goods receipt is posted in the supplying plant, movement type 101.
    To achieve it, necessary configurations has to be done in Tcode- OMGN.
    SPRO>> Materials management>> Purchasing>> Purchase Order>> Set up Stock transport Order:
    1. Plant: For the receiving plant, maintain customer No-Plant (If using STO with delivery), for the Sales Org, Dist channel and Division.
    2. Checking Rule: Create checking rule.
    3. Define checking rule : Usually no change required here.
    4. Assign delivery type/checking rule: Assign the document type(UB) - Supplying plant- Delivery type(NL).
    5. Purchasing document type: Maintain the supplying plant- Receiving plant relationships for the doc type-UB, either 1-step or 2-step, as per business.
    Hope this helps!
    Regards,
    Shilpa

  • Stock Transport order with Freight Charges- Payable to an external vendor

    Hello
    we are implementing the stock transport order between two plants in SAP 4.7. The document type is UB and it has to be a two step process. We need to post the Freight Charges as well. The freight Provider is external vendor.
    What is the best way of configuring this scenario for freight cost?
    I did put the freight forearder vendor code on the conditiond tab detail of condition tyep FRA1 but  can't do the invoice verification for the same.
    Any tips are appreciated.

    Hello,
    This EhP4 feature addresses only the one step Stock Transport Order to subcontracting vendor for intra company.
    Does anybody know how to do a two steps Stock Transport Order to subcontracting vendor for intra company?
    By "two steps" I mean:
    1- Goods Issue from supplying plant A to in-transit stock of the subcontracting vendor at receiving plant B.
    2- Inbound Delivery Notification (IDN) at receiving plant B + Goods receipt against this IDN into the subcontracting stock at receiving plant B.
    Thanks and regards,
    Stéphane

  • Stock transport order with BAPI_PO_CREATE1

    Hi,
    can anybody give me an advice how to use the function BAPI_PO_CREATE1
    to create stock transport orders?
    I´m getting some errors when I run it. Here is my test data I have used:
    poheader-comp_code: NO10
    poheader-doc_type: UB
    poheader-langu: EN
    poheader-purch_org: NO10
    poheader-pur_group: 999
    poheader-suppl_plnt: 2041
    in poheaderx I have set a flag for the filled fields.
    poitem-po_item: 00010
    poitem-short_text: test
    poitem-material: 100230
    poitem-plant: 2001
    poitem-quantity: 1
    poitem-po_unit: CYL
    poitem-conv_num1: 1
    poitem-conv_den1: 1
    poitem-prnt_price: X
    poitem-unlimited_dlv: X
    poitem-item_cat: U
    poitem-acctasscat: K
    poitem-gr_ind: X
    poitem-ir_ind: X
    poitem-gr_basediv: X
    poitem-preq_name: TEST
    I´m getting the following errors in the return table:
           ID                Num: 000 PO could not be creating using Enjoy-BAPI
    E     ID MEPO     Num: 002 PO header still faulty
    E     ID 06           Num: 098 Please enter supplying plant
    E     ID ME         Num: 018 Item category U can only be used with material
    W    ID ME         Num: 040 Can delivery date be met?
    E     ID ME         Num: 083 Please enter G/L account no.
    Any ideas how I can create one successfully?
    Cheers

    Hi,
    poitem-po_item: 00010
    poitem-short_text: test
    poitem-material: 100230
    poitem-plant: 2001
    poitem-quantity: 1
    poitem-po_unit: CYL
    poitem-conv_num1: 1
    poitem-conv_den1: 1
    poitem-prnt_price: X
    poitem-unlimited_dlv: X
    poitem-item_cat: U
    poitem-acctasscat: K
    poitem-gr_ind: X
    poitem-ir_ind: X
    poitem-gr_basediv: X
    poitem-preq_name: TEST
    fill the corresponding fields in POITEMX  table also with 'X'!
    Regards,
    Sooness.

  • Internal order shifting from one company code to another

    Hi All,
    I have an query regarding internal order.
    We have come up with a new company code B001
    Intially SAP was not functional over there.
    We have made purchases for this new company code in some another company codeA001.
    For this made one internal order in A001 and posted all POs for purchases for B001 against these internal orders.
    Now SAP is implemented in B001, and we need to carry costs from A001 (booked against internal orders) to new company code B001.
    Please guide me the procedure to perform this activity.
    I have made a new internal order in B001.
    What would be the next activity...??

    Hi,
    You should simply make inter-company financial posting crediting your I/O in A001 and debiting the new I/O in B001.
    Regards,
    Eli

  • Stock transport order with movement type 643 - post to COPA

    Hello SAP gurus,
    We use movement type 643 to post good issues for stock transport order (intercompany process). The delivery type is NLCC. We recently implemented account-based COPA. At the time of post goods issue, cost of goods sold should be posted to COPA, but it didn't. Could someone help me figuring out how to push PGI to COPA for stock transport order? Thanks in advance.
    Regards,
    Cassandra Wong

    The reason that PA segment is not populated in the good issue for STO is because the cost element of the COGS account was set to "01" instead of "12". I changed the cost element category and the PA segment is populated correctly.

  • Creating Stock Transport Order with Delivery

    Hi All,
    I am trying to create an STO with delivery option.
    I have been able to complete STO cycle without Delivery - both one step and two step.
    However, after choosing Delivery Type NL in SPRO, the ME21n for STO creation gives error - Unable to determine shipping data for Material 427.
    Sales org structure has been defined and assignments are complete.
    Shipping Point has been defined & assigned to the Supplying Plant.
    Recivering Plant has been given a Customer Number and both Receving & Supplying Plants are assigned sales area data. (MM->Purchase Order->Set Up STO)
    In Material Master, Loading & Transport groups have been assigned, and all views have been maintained.
    Any ideas on the possible cause of error??
    Thanks.

    Hi,
    Please check these links:
    ERROR"Not possible to determine shipping data for material XXX"
    Not possible to determine shipping data for material

  • Stock Transport Order with Delivery and Billing

    Dear all,
    I've manage to perform STO process for supplying plant -> delivery (VL10B) until post goods issue (VL02N).
    Now, when I attempt to perform standard SD billing (VF01) using the delivery number, the system proposes "IV" billing type (Interco Billing).
    My problem is there no net price for the billing document (VF01). Question: normally the pricing is carried over from Sales Order in a normal SD process. Since this is STO crossover from MM process into SD process, do I need to maintain the pricing condition manually in the billing document before saving?
    Thanks.
    Steven

    In the copy control (delivery --> billing document) you can define what the source of the price is, from where system should copy, determine it.
    Basically you have two options: determine the price based on sales condition records or copy the price from purchase order (see pasted link). If you use shipment, you can set that shipment cost should be copied as well (see OSS note 574850).
    You can find copy control settings under:
    SPRO > Sales and Distribution > Billing > Billing Documents > Maintain Copying Control For Billing Documents
    As for details please have a look at:
    Intercompany Billing Process
    (see Raghavendra's answer)
    if you are not familiar with SD, please contact your SD consultant to carry out the settings.
    Edited by: Csaba Szommer on Jan 14, 2011 12:38 PM

  • Stock Transport Order with Delivery and Billing Document/Invoice

    Dear Experts,
    We have implement the process in our system as required on SAP document:
    http://help.sap.com/saphelp_47x200/HELPDATA/EN/4d/2b911d43ad11d189410000e829fbbd/frameset.htm
    The problem is that when creation the PO the Shipping tab does not exist in the PO , and no  delivery can be created .
    We are using NB PO doc type,
    Delivery type implemented as  NLCC
    Please advise where is the problem ?
    Regards,
    Moshe

    >
    Moshe Stein wrote:
    > Hi Afshad Irani
    > Thanks for your prompt reply,
    > I have looked to all your pages , but could not find the problem why there is no Shipping Tab?
    >
    > Moshe
    Shipping tab is related to shipping points. You need to maintain shipping points, then shipping points are linked to storage location, and once you enter storage location your shipping point is picked. One of the above links tell you how its done.
    T-code OVL2
    Path logisitc excution-->shipping>basic shipping function--->assing shipingpoint s
    Shipping point
    Edited by: Afshad Irani on May 30, 2010 7:44 PM

  • Stock Transport Orders with Location Substitution or Determination

    Hi All,
    Is it possible to configure STO location substitution or determination in ECC 6 and SCM 5.0 environment? I have already gone through SCM 5.0 release restrictions note and it says STO's cannot be used with location substitution. Just wanted to make sure that there is no other way to implement this functionality.
    Thanks,
    Harish

    Hi Harish,
    Rules Based ATP has not be developed for STO's for the reason that STO's do not support sub items. And sub items are mandatorily created by RBATP.
    Regards
    Sanjeev

  • AP/AR in Stock Transport Order

    Is AP/AR Document will be Generated in stock transport Order with in a company code ?
    Is it Possible to have the Billing/Invoice with in a Comapny code.
    If Possible how to do?
    If it is not Possible ,why?
    Suitable answers will get Reward Points.
    Please reply Immediately.

    Hi Lakshmi,
    Don't show your rewards to get your replies.
    We are here to resolve your SAP issues / quires not for getting rewards!!
    Under one company code you can't generate AP/AR document at all.
    You can generate Excise documents not commercial documents because; Legal entity is company code in any organization. That means, Profit & Loss (Balance sheet) declared at company code level not at Plant level.
    Hope I have clarified your doubts.
    Bye,
    Muralidhara

  • Screen shots for creating Stock transport order

    hi,
    Can anyone send me the screen shots for creating Stock transport order between plants within company code?
    Regards,
    Swathi

    hi
    pls refer to HELP.SAP.COM INTHIS SELECT BEST PRACTISES and in that select building blocks it will ask country wise select india and give ur req type of industry .here u can see J05 AS materials management also other req  i mean  sto and all u can configure
    regards
    srinivas kona

  • Plant to Plant STO with excise invoice and taxes in one company code

    Hi,
    I have a new business requirement, we want to create only one company code and 12 plants in different states,  each plant will have separate purchasing and sales activity this is ok this can be done with separate excise and series group as ther will not be any issue for purchsing and saling of materisl with exice in each plant , but how we can transfer the material plant to plant  if the plant is in different states we want that the material should be transfer from palnt to plant  with excise invoice only,  as we have the company code common,  how to create the billing document for this, and how to pass the duty from the saling plant and capture the same in the recieving plant. with proper tax entry. Can we do the STO with biiling if the two plants are in single compnay code.
    regards,
    zafar

    hi,
    I am trying to create a Stock Transport Order (STO) with document type UB and item category U. My objective is to transfer material from Plant (supplying plant) 100 to Plant (receiving plant) 1100 within one company code (1000) with STO.
    For this purpose I created a raw material 1434 in plant 1000 with sales org 1 view and in that view entered in delivering plant field 1000 as delivery plant. After that I extended material 1434 to plant 1100 without changing anything what I did while creating the material first in Plant 1000 except in organizational level I entered 1100 in the plant field. I entered Sales org 1000 and distribution channel 10 in organization level for both plant while creating and extending the material. In me21n I chose Stock Transport Order with document type UB and item category as U also receiving Plant as 1100. With this when I tried to save the STO the message, I am getting an error,  Cannot determine shipping data for the material 1434? 
    I am doing solely mm function why I need to create Customer master? In this case plant 1100 is the customer right? 
    Solution:
    1. Mat.(1434) should be maintained in both the plants. (1000&1100).
    2. Should have enough stock in supplying plant(1000).
    3. Make its supplying plant as a vendor in vendor master record in receiving plant(1100).
    4. Make it receiving plant as a customer in customization.  
        Create customer (xd01) & and define the shipping data for plants in both the plants.
        Path: spro u2013 img u2013 m.mgmt u2013 purchasing u2013 po u2013 set up STO u2013 define shipping data (1 by1 )
        In Receiving plant (1100)                         In Supplying plant (1000)
        Customer num.  123345 (for ex.)              Customer num.  -
    (don't fill) 
        Sales org.yyy                                                  
        Dist. Channel                                                              
        Sales div.  y   
    5. Assign doc. Type is "NL" for intra company STO. If  STO is inter company, Assign doc. Type is "NLCC".
        Position doc type is "UB"
        Enter supplying plant(1000) & doc type (NL) & checking rule (ex:01)
    6. Assign doc. Type is "UB" to u'r plants.(PO)
        Go for new entries 
        Enter supplying plant(1000) & Receiving plant (1100) & doc type (UB).
    7. Create a PO, choose the doc type is `UB' & item cat.'U', Enter supplying plant as a vendor in PO  of the receiving plant(1100).
    8. Provide this num (PO) to SD people, they will do the delivery by using transactional code is VL10B.
    9. Sales people they will provide "out bound delivery num".
    10. Do the GR. In GR the second tab 05 out bound delivery instead of PO mov.type 101.
    11. See the stock over view in the receiving & supplying plants.  
    thanking you

Maybe you are looking for

  • Transfer of a fixed asset to a WBS

    Hello Everybody , I need your help. A new scenario has come over here and i am not getting how to implement it in SAP . Scenario is : 1. We have a fixed asset at cost center . 2. Now the asset is need to be replaced . 3. We settled new asset at that

  • PL/SQL Cursor Help

    I am trying to figure out how to get the following code to work. I am using a cursor to run a SELECT statement with a group function. How do I get the information from the group function to print out with a dbms_output.put_line statement? Just for my

  • Sql: remove special characters

    Hello! maybe someone has a hint for me how to remove special characters such as tab/new line characters from columns? Thanks in advance! Tiberius

  • Creating multiple BP Roles automatically after replicated BP to CRM

    Hi All, We are working on CRM 5.0 and ECC 6 as a back end system. As per our requirement we want the clarification for the below scenario. We are downloading Employee records from ECC to CRM.After replicating Employee records we want to add Consumer

  • Your estimated performance of a very simple SQL query

    Hi there.. Sometimes it seems hard to find answers for the most simple questions so I hope you can help me and be overbearing ;) I am going to have a table with a few million records in it, 30-40 columns of which 80% has data, indexes on maybe 10 col