Strategy plan- Automatic operation selection in tasklist

Dear PM Experts,
I have a requirement in strategy plan, where the strategy plan MIX_TRUCK which has 1M, 3M, 6M & 1Yr(Heirarchy-1) time based cycles.
Now i have a tasklist CON_TRUCK, which consist of all operations which covers all time cycles (1yr, 6M, 3M&1M)
I assigned this taskist & strategy plan to maintenance plan MIX_TR.
Now currently whenever the maintenance order created from this maintenance plan MIX_TR, all the operations in the task list are selected.
But my requirement is to select some operations for 1yr, and another set of operations for 6M, and different set for 3M.
Is it possible with configurable tasklist? If not is there any other alternate method to achieve?
Your valuable suggestions are highly appreciated........
VINOD.V

Attach your Operations assignment to Packages screen shot. Attach your Maintenance Strategy Packages screen shot. Attach your Call object operations tab which has been created screen shot.
Also, mention how do you want to have that??
Hope, you might have done something same like the above screen shot in your task list for operations assignment to packages.
If you want only "Operation 3" & "Operation 6" to be called at 3 months & only "Operation 4" & "Operation 5" to be called at 6 months interval, etc., use Hierarchy option for the packages in IP11.
Not sure, you are talking about this or something else. Please elaborate more if query is talking about something else.

Similar Messages

  • Manual operator selection BUG!!!

    I have an N73 phone. When i am abroad roaming and i use the manual operator selection the phone reverts to automatic operator selection within a minute and overrides my previous manual selection. I find this bug very irritating and i think nokia should post a solution ASAP. Anybody any ideas?
    Nik

    I did few test with different SIM card from different operator and at least for me seems that only TRE (Italy) and THREE (uk and ireland) are blocking the manual operator selection.
    When instead i used TIM (Italy) , or VODAFONE (italy or ireland) the operator selection was stick to MANUAL.
    I have a N95 unbranded latest firmware. but the same BUG is with my N73ME.
    Using a Samsung i600 with Microsoft WM6 the operator selection di work with all my SIM card .
    Does anybody have any idea why the Symbian s60v3 have this bug?

  • E65 won't remember manual operator selection (roam...

    Hi,
    while roaming, I can't get my e65 to remember manual operator selection, the setting will only last for one call, and then go back to automatic.
    My operator(3 Austria)'s service hotline claims that this is an issue in ALL Nokia handsets and can't be solved. I find this hard to believe, as that behaviour oft the phone is clearly a bug. If anything, I could imagine 3 gives out all the Nokia handsets (or not just the Nokia phones, but all of them) with this bug installed to make more money out of roaming fees.
    Any similar experiences?
    Any ideas if and how this could be fixed?
    thanks, Ben
    Solved!
    Go to Solution.

    Hi,
    I found something like a workaround for this problem.
    here goes:
    If you can't disable automatic operator selection, switch the network mode from dual (jumping between umts and gsm) to umts only. that way, in countries that have 3, you will almost always get 3 automatically selected, maybe because it doesn't have a gsm-signal but just umts.
    I don't know though about other operators in other countries, probably this method is always going to get you the operator with the strongest umts signal.
    cheers, Ben

  • Need to select all equipments (PRT) for a plan (routing) operation (PLPO)

    hi,
    I need to select all assigned equipments (PRT) for a plan (routing) operation (PLPO).
    Can anybody tell me the database table relation or is there a function module or a BAPI or something like this !?
    Thanks
    Olaf
    Edited by: Olaf Krüger on Feb 20, 2008 12:03 PM:  BADI to BAPI

    I suppose you have every PLPO needed (else look at function module WOSTS_TASKLIST_READ_FROM_DB)
    Then read
    PLMZ Allocation of bill of material items to operations
    STPO BOM item
    SELECT * FROM plmz INTO TABLE t_plmz
        FOR ALL ENTRIES IN t_plpo
        WHERE plnty = t_plpo-plnty
          AND plnnr = t_plpo-plnnr
          AND plnkn = t_plpo-plnkn.
      SELECT * FROM stpo INTO TABLE t_stpo
        FOR ALL ENTRIES IN t_plmz
        WHERE stlty = t_plmz-stlty
          AND stlnr = t_plmz-stlnr
          AND stlkn = t_plmz-stlkn.
    Regards

  • Automatic BOM Selection as per Stock availability

    Hi...
    I have a query.....How can i set an Automatic BOM selection as per stock availability
    Problem is that the client is having more than 1 type of raw material which can be used, so the user needs to consume the ROH as per the stock availability, in that case he has to manualy check and amend the Production Order accordingly.
    Hence, i want to set a system wherein the system would do the checking of the ROH material and then select that material and execute the production order accordinly.
    Requesting your valuable inputs.
    Thanks in advance,
    Harris

    Harris,
    Please explore the possibility of defining "Alternative Item Group", in the BOM Item level details(Basic data tab).
    From Application help for your referance,
    Alternative item: group
    Consolidation of alternative items within a BOM. Every material in the assembly can be included in the alternative item group.
    Use
    As soon as you enter an alternative item group, you see an additional dialog box with the following data: ranking order, strategy, usage probability.
    You can maintain alternative items in the following situations:
    Alternative positions with specific usage probability
    These alternative items are incorporated with a specific usage probability. Enter the usage probability for each alternative item in the group, so that:
    dependent requirements are determined in requirements planning
    dependent requirements are changed to a reservation in the production order
    Alternative positions as information
    You can enter an alternative item for information purposes. This item would then, for example, only be taken into account in situations involving missing parts.
    As there should be neither dependent requirements nor a reservation for this item, enter no usage probability.
    Procedure
    Enter the same character string to denote the alternative items of an alternative item group.
    Enter the same strategy for all alternative items in the alternative item group.
    Dependencies
    Alternative items are valuated in the following way:
    Dependent requirements determination
    Requirements planning determines the dependent requirements according to the usage probabilities that have been entered.
    If the usage probability is 0%, then no procurement is planned for the item. For information purposes, however, dependent requirements with 0 as quantity are created.
    Withdrawal posting
    You can control the withdrawal posting for the resevation in the production order in the following way:
    Withdrawal according to usage probability (manual change is possible)
    Withdrawal if there is 100% availability
    (Check ranking order and strategy)
    Example: See Strategy for alternative position
    Regards,
    Prasobh

  • Strategy plan: deletion of shortest cycle & determination of call horizon

    Dear colleagues,
    I'm facing a weird situation on a strategy plan:
    Initially I had following packages assigned in the task list: 1, 3 & 12 months. There have also been calls for the 1 month package.
    In the meanwhile I have deleted the 1 month package from the task list and only 3 and 12 months is active.
    When I take a look in IP10 at the next plan and call dates, I recognize that the call horizon for the call date is still calculated from the 1 months package.
    I think this is not correct - or did I simply miss to do a restart in IP10 after deletion of the 1 month package in the task list?
    Thanks in advance for your hints!
    Regards,
    Patrick

    Hi Santosh,
    I've tried to use the refresh button in IP10. After saving IP10 the situation is not getting better - the difference between plan and call date is still calculated based on the lowest cycle (1 month), which was deleted from the task list in the meanwhile.
    I've tried to run IP30 after the scheduling update in IP10 - but no change in situation.
    Did I miss anything or understand something wrong?
    Nevertheless, for the users it's be more easy to just push a button in IP10, then using the restart function with selecting a the right package as offset.
    Regards & thanks,
    Patrick

  • Strategy Plan with task list

    Hi all,
    can any one help me?
    I create a strategy plan with one maintenance item and one task list, with one task list item, for example. After scheduling I get a maintenance order with two items. One item from the task list and one from the maintenance item and it´s necessary to confirm both order items.
    It´s possible to create a maintenance order with only items from the task list?
    Thank you for your support
    Detlev

    Detlev,
    The PM/CS Order operations should only come from the task list that is assigned to the maintenance item.
    If you are getting additional operations than are on the task list then its possible that you have:
    - a system bug
    - developed some new functionality
    PeteA

  • Single and strategy plan( What does it means )?

    Hi all,
    Please explain me what does single cycle plan and strategy plan means.
    Following is my requirement.
    ( Since Swedish mills and other units use not only single cycle plans but also strategy plans , sometimes with multiple operations to each maint item,  there is a need for cycle and cycle unit (interval) and work center on operation level on the layout in the report  zpm_huvud.
    There is also a need for maint plan name, plant section and work center (on operation level) as search criteria in the variant. The reason for this is that we use plan name as grouping criteria for multiple objects in rounds. The criteria work center description text should be changed into main work center.
    We also need to be able to sort the answer in the layout in two ways : by functional location or by maintenance plan.
    The plans that have object lists and/or have no operation lists also need to be shown in the report. All text on maintenance plan should be shown in the report )
    Please explain me this with one example...
    Its urgent.
    Thanx in advance,
    Amruta.

    hi
    single cycle plan
    say for example you are planning to replace the bearing of a pump every 500 hrs of ruuning ,you use this plan to generated the maintenance order when the operating hours reaches 500 hrs.
    Stratergy
    In case of DG set there are lot of components to be maintained based on running hours for example for ever 100 hrs filters to be cleaned,every 500 hrs lub oil to be changed.In this case you can use strategy based maintenance plan .you can create 2 operation in the task list and assign to the respective package,so onec the 100 hrs has reached system will create maintenance call object as filters to be changed and in 500 hrs it will say lub oil replacement
    regards
    thyagarajan

  • Will automatic update select 'Adobe Reader X' after support ends for 'Adobe Reader 9.5.5' on 6/23?

      After the recent update for ‘Adobe Reader 9.5.5’ the end of support for this version is June 23, 2013. This is installed on an edition of ‘Windows Vista Home Premium Service Pack 2’. System type: 32-bit Operating System.

      Probably is the best way to go if end of support for ‘Adobe Reader 9.5.5’ is June 23, 2013. Does automatic update select the latest version of ‘Adobe Reader X’?

  • 5230 manual operator selection problem

    Hi,
    I recently detected that the manual operator selection does not behave as intended with my 5230 (Software release 20.0.005). I wanted to manually select "tre" in italy because I'm "drei"-customer in austria and 3 has this nice 3LikeHome feature where you have no roaming costs when you use a 3 network in a foreign country. So I switched the operator selection to be manual and after the nework search I selected 3 as provider. But as soon as I was out of the reception range of the selected network the phone automatically selected another network although the user manual says that if the connection to the manually selected network is lost, the device sounds an error tone and asks you to reselect a network. Can anyone confirm this behaviour?
    Thanks,
    Gerhard

    Sim card are activated only for one particular operator provider, selecting the other only means that the sim is not for the other one. In locations where there are plenty of providers you'll find as many as there are & being in manual you have to be certain which one. In automatic mode, it queries one after the other in round robin fashion until it gets an access. I've noticed that too, that different models of Nokia phone have diferent strenght of radio signals transmit/recieve. It's not surprising to to see one model have more bars (signal strenght) than others.
    Message Edited by android on 29-Aug-2009 02:14 PM
    Knowledge not shared is knowledge wasted!
    If you find it helpfull, it's not hard to click the STAR..

  • Strategy plans problem

    Hello every one,
    I want to know that when we make a strategy plan we can apply the conditions such as this package will be install or call object will be generated when certain limit is reached (like number of hours when exceeds 100 hours or temperature raised to 50 degrees etc)
    My question is that I want to make such a strategy that when there will be upper and lower limit like there is a device whose temperature if raised to 30 degrees or falls below 20 degrees then a call object is generated. How is that possible?
    Problem is that when I give the cycle length 20 degrees for first maintenance package and set the hierarchy level H1 for it and I give the cycle length 30 degrees for second maintenance package and set the hierarchy level H2 for it. That means when ever temperature is reached 20 degrees call object will be generated for all values greater then 20 degrees but I want to generate it for values less then 20 degrees.
    I want that call object will not be called between 20 to 30 degrees and always be called less then 20 and greater then 30 degrees. How I can apply the condition for less then 20?
    i want the answer very soon please help me out.

    Dear,
    Ur opinion about statergy is wrong.what ur talking about it is about condition based maintenance.which trigger the notification according to the ur lower and upper limits by sensing through temp. transducers and der is interface in between SAP and ur process instrument which fire the signal to the SAP and notifiaction created.
    Transferring Measurement and Counter Readings
    Purpose
    The PM-PCS interface transfers filtered data from a process control system (PCS) to the R/3 System. Measurement documents are created automatically in the R/3 System for the measurement and counter readings.
    You should implement this interface if you want to use measurement documents in the R/3 System as the basis for performing maintenance activities or for documenting information.
    Process Flow
    Process control systems provide a wealth of data that arises within a particular process, building, or infrastructure. SCADA systems perform a filter function in these circumstances. They filter out the maintenance-relevant data and, in this way, prevent the R/3 System from being flooded with process data.
    Use following Links
    [http://help.sap.com/saphelp_nw04/helpdata/en/a7/fa4c988f6611d29e8a0000e8323350/frameset.htm
    http://help.sap.com/saphelp_nw04/helpdata/en/a7/fa4c988f6611d29e8a0000e8323350/frameset.htm
    Regards
    Rakesh
    Edited by: rakesh mane on Feb 22, 2008 7:05 AM

  • Manual operator selection not sticking

    Hello
    I use international roaming on a daily basis.
    I am using a N95, when i go into networks/operator selection/manual selection. I select my network manually and it is fine.
    However it seems like whenever a stronger signal is detected it swaps , doesnt matter what network its on to.
    I have had my mobile swapped, with no effect, i have debranded the phone with no change, I loaded the latest firmware with no change.
    Can anyone let me know if this is another **bleep** im not adult enough to look make my own choices 'feature' on the nokia n95

    very strange, when i'm abroad and i loose signal from one operator the phone will prompt to select another, it wont automatically lock on,
    does it really matter who your roaming with? so long as u have signal that's all dat matters.
    Blackberry Bold

  • Manual Operator Selection

    Hi
    I have an factory unlocked 3gs and live in an area where the signals from mobile operators from a border country can be picked up. Occasionally, my Iphone changes operator automatically due to it picking up a stronger signal and the problems are obvious (namely that I get charged for receiving calls as I am roaming).
    So, my question is, can the Iphone be made to only switch to another operator upon request (such as all other mobile phones). I've gone through the obvious parts of the menus (network etc) but cant seem to find a way to do it...
    Many thanks

    Turn off automatic network selection. I think it's a case here of you can't have your cake, and eat it

  • Enforcing a strategy plan to only produce one order in a single month

    Hello All,
    I have created a strategy plan that kicks out orders monthly, quarterly, semi-annually and annually. I have used the cycle unit of "MON", so orders get generated in cycles of 30 days. Everything is working great.
    Now, here's a business requirement: only one order can be created in a single month. So, if this strategy kicks out an order on 01/01/09, and they complete it the same day, the next order will be created for 1/30/09. What is the most effective way to enforce SAP to only allow creation of one order in a single month?
    Thank you for your help in advance.
    Alex
    Reference:
    http://www.sapfans.com/forums/viewtopic.php?f=7&t=334722

    Hi,
    As Mr. Venu said along with the Key-date option the scheduling start date and call horizon is also important.
    Reg,
    NNR

  • Daily production plan for operations

    Hi, One Production order generally runs for more than 1 month and consist of more than 100 operations and order qty will be one. in this case we want to prepare daily prod plan for operations not for qty. say on 1.6.09 we will do cutting operation, 2.06.09 willdo painting etc in monthly prod paln or weekly prod plan? pls guide how to map this?

    Dear,
    In production order you will get the details of operation plan and scheduling.
    So in OPK8 do the setting for print of LG02     Op. control ticket, LG03     Job Ticket, LV01Time ticket,
    Take a print through CO04N - Print and sent it on shop floor also.
    You use the report like MCPW - Lead times or MCPK.
    Hope clear to you.
    Regards,
    R.Brahmankar

Maybe you are looking for

  • Xslt+servlet

    hai i am using xslt for transformation of xml to html/wml.if i am tring the java code for tht tht is working file.i want to get the output in the browser.so i want to use servlet.if i am tring the code as servelt tht is not working.any seeting r ther

  • Lenovo Helix - sending to second screen issues

    Hi, so i recently tried hooking up my lenovo helix up to my Sony TV (i don't have any more info on the TV than that, sorry) and a little bit of the screen on my helix was cut off, so i couldnt see the task bar at the bottom, or the tabs at the top of

  • Backlight on But no Words on display

    Ok I will be honest, I dropped my iPod... but not very high (knee height) and it was in a hard shell case. Once it hit the floor the iPod wouldn't turn on with just pushing the center button. So I tried to reset it. The screen lights up and the hard

  • Hiding some topics from Search mechanism

    Hi, I have some html pages, which i have used as popup in some topics. But i want to hide these html pages from the Search mechanism. I tried changing the html ext to xhtml and importing it as baggage file (i came across this sometime back when i was

  • When I try to open my iTunes in safe mode, it says visual plug-ins have been temporarily disabled

    How do I enable the visual plug-in?