Dear Friends,
I am sending 1 kg of material to receive back 1kg of material the sub contractor uses .90 kg to make 1 kg of the reqd material. So I do subsequent adjustment after MIGO for under consumption of 0.10kg
Now after doing subsequent adjustment, while doing reconciliation in J1ifq should I change the assigned qty to 0.90 kg ( as there was under consumption of 0.1kg ), I tried changing the assigned qty to 0.900 but its showing me the message u201Cmaterial xxx is not fully assigned, short by 0.10 kg& itu2019s not letting me reconcile.
Kindly suggest the correct procedure for reconcillation & sub con challan completion after subsequent adjustment.
Thanks
Hello,
Please check the process supported by SAP for
subcontracting with and without duty payment in the following link:
http://help.sap.com/saphelp_erp60/helpdata/en/09/ebf138cdd78a4be10000000
a114084/frameset.htm
It is quite helpful for challan reconciliation issues.
Keep in mid that for challan subcontrating you should perform the
following steps:
1) Create Sub contracting PO
2) Create MB1B ( 541 mov)
3) Create Challan from J1IF01 with reference to material document
4) Create GR using MIGO sub cont PO. ( faced error )
Please be ensure that the following note is already applied in your
system:
1423896 - The subcontracting challan validation - MIGO
Please chek if you have set the movement types
541 and 541 O as relevant for creation of challan. Also, you ha
ve to set the number of line items in a challan to be only 1 in the customi
sing node 'subcontracting attributes'.
So the system will create 1 challan per line of the transfer posting
document as it finds both 541 and 541 O movements.
If you do not want the system to create challan for 541 as is normal
then remove the movement type 541 from movement type group 0001. Also
remove 101 from movement type group 0002.
I hope it helps you.
Regards,
Fábio Almeida
Mm Consultant
Similar Messages
-
Sub contracting challan reconcillation
Hi Friends,
I am doing the subcontracting for sales order
1. I have created the po with account assignment E
2. Transferred the material from main store to sub contracting store
3. created sub contracting challan
3. created goods reciept and in that i have given reference of sub contracting challan
4. now i want to do the reconcillation , but system is giving error message as " challan material is different from material document..
so please suggest , what i have to do? please reply....Hi
Since you are transfering the material to subcontracting store, which is under your premises.You cannot do a reconsiltion.
If you have seprate subcontractor ,then its possible to do the reconsilation.
follow the below procedure subcontracting for sale order :
1.created the po with account assignment E
2. Issue the material to Subcontractor by creating a new mvt type 541 E. You cannot issue the sale order stock to subcontractor with 541 mvt.
3.Create Subcontracting challan
4.Do GR
5.Do the reconsilation
Thanks & Regards
Dhanapal. -
Error in sub cont challan reco in case subsequent Adjustment
Hi experts
I am facing the problem during the reconciliation against subsequent adjustment entry. Please see the below screen shot and guide what is missing.
Screen shot of MIGO.
Screen shot of error message during J1IFQ
Screen shot of customization
Regards
Parkash ChandEnsure that the fiscal year is same as you were trying to post.
G. Lakshmipathi -
Sub contracting - Subsequent Adjustment
Hi Experts
Sub contracting - Subsequent Adjustment
I have sub contract Whom I sent the material A - 100 Kg to get the Finsished product B - 100 Nos
He has delivered the material
MIGO done
Senario 1 He has utilised the only 95 kg to make 100 nos
2. He has utilised 105 kg to make 100 nos
How do u do in subsequent adjustment? Of he has consumed more quantity how to return him?
Thanks
TanviHi Tanvi,
After the subcontractor (as vendor) had delivered the ordered material (end product), you posted the goods receipt to the subcontract order. The system determined the necessary components for each purchase order item and created for each component a goods issue item with the quantity that was determined in the purchase order.
If the vendor informs you after these postings that a greater or smaller quantity of the subcontracting components was actually consumed than planned in the purchase order, you must post a subsequent adjustment to correct the component consumption.
If the component is a by-product, you must post the corrected by-product receipt (excess receipt) or by-product issue (short receipt).
"In Simple Words, suppose you have sent xx material 100 kgs to subcontractor for processing of 100 yy component. The subcontractor has produced 95 yy by using 100 kgs of xx. That means he has used 5 kgs excess material. But it was not of his fault. It was done on account of die / mould or some other reason. So you have to post a subsequent adjustment for 5 kgs of xx material and reconcile using J1IFQ for making subcontracting challan complete. Similar case can be understand when subcontractor processes 105 yy using 100 kgs of xx. That means 5 kgs of xx short consumed. These types of adjustment can be known using t-code mb51 and movement type 121."
reg,
Ashok -
Run time error while reconcillation for sub contracting challan
Hi,
Gurus please solve this issue ,
When i am trying to reconcillation for sub contracting challan against the GR DOC number.When we are assing the quantity for challan and save at that time i am getting abap dumpAnalyse in ST22
U may take abaper help -
Reconcillation of sub con challan
Hi,
I am getting an error while performing J1IFQ,the error is "excise doc is posted later to material doc",msg no:81576.Can anybody suggest me what may be the cause for the error.By product is end result of process along with material B.
You are not sending by product while issuing material to vendor using 57F4 Challan.
So it wont' appear in challan reconcillation. -
Material issue to sub-contractor
Sub-contractor needs 2 qty of X raw material to manufacture our finish product. instead of 2 qty sub-contractor needs 4 raw materials. how to handle the extra qty for sub-contracting?
Hi,
First please search on SAP online help and on MM forum in connecton with subcontracting, there's huge amount of threads...
My suggestio:
1. You can modify the PO item's component list from 2 pcs to 4 pcs (ME22N > "Material" tab of subcon PO item > "Components" icon) nad after that you can do the GR.
2. Subsequent adjustment - here first you post GR by consuming 2 pcs and after that you
http://help.sap.com/erp2005_ehp_04/helpdata/EN/4d/2b908943ad11d189410000e829fbbd/frameset.htm
You can use both MIGO and MB04 for this purpose.
Please also read the pdf attachment of OSS note 205454 that has many useful information on subcontracting.
Regards,
Csaba -
Dear Experts,
i have one doubt reagrding sub-contracting process involving the challan,
assume one FG material 'A' is need to produce with two raw materials one quantity B + one quantity C,
i have raised one SC PO to get 10 quantities of 'A",
for the above i have issued 10 qty B + 10 qty C,
i have created one SC challan,
Case 1.later on SC vendor told that 3 qty of B damaged, again i have issued 3 qty to that SC vendor,
for the above case 1.
1. how to maintain this excess qty with challan?
2. how to reconcile that damaged quntity ?
Case 2.
if we issue the material through sub sequent adjustments
1. how to handle the over consumption 'or' under consumption scenarios with SC challan,
Thanks in advance.
Lakshmi ReddyCase 1.later on SC vendor told that 3 qty of B damaged, again i have issued 3 qty to that SC vendor,
for the above case 1.
1. how to maintain this excess qty with challan?
U have to send 3 qty to vendor by 541 and u can send those qty with new sub contraction challan
2. how to reconcile that damaged quntity ?
While doing the GR you can manually put in 13 qty consumed instead of 10
OR
U can do the GR so as to consume 10 qty with original subcontracting challan
and then do 542 for 3 qty and reconcile the new subcontracting challan with this 542 document number
Case 2.
if we issue the material through sub sequent adjustments
1. how to handle the over consumption 'or' under consumption scenarios with SC challan,
MB04 is used for subsequent adjustment for under/over consumption in subcontracting.
If the vendor informs that he had consumed more raw material than you have issued to him,you can use this transaction code and post the material consumed.
It affects the price of finished products you recieved in subcon GR.
If the value of finished products is 20 when you performed GR,and you are posting a raw material worth rs.5 using MB04 for over consumption,then the price of the finished products now becomes rs.25.
Similar thing happens when you post for under consumption(price in MMR of finished product comes down by the value of raw material consumed)
hoe this helsp -
Quantity reconcilation of sub-contracting challan error
Hi Experts,
I am facing problem while doing Quantity reconcilation of sub-contracting challan.
Challan material is different from material document
Message no. 8I572
Thanks in advancehi..
please go to spro>log general>tax on goods movement>india>business transaction>subcontracting>maintain movment type group
and maintain as given
0001 102
0001 122
0001 541
0001 544 O
0002 542
0002 543 O
and
Also This can be solved as under. ( check for following also)
You will have to activate PO number as a required field for 541 mvmt.
Materials Management -> Inventory Management and Physical Inventory ->
Goods Issue / Transfer Postings -> Define Screen Layout.
For movement type 541 the purchase order field has to be maintained as
an optional entry or as a required entry here. (under normal condition it will be suppressed)
This has not been done, otherwise the error message would appear as the mseg-ebeln would not hold the PO number.
After doing this carryout a new cycle. you will not get any error.
Edited by: Kedar Kulkarni on Nov 12, 2009 6:06 PM -
SubCon Purchase order and Subsequent adjustment
Hello All
I am having an issue where I have a Sub con PO and its components.
Goods Receipt is done and along with GR automatic Backflush of the components is also done.
When I try to do subsequent adjustment MB04 to adjust the consumption of one of the component ( Iam using -ve sign so that I can reduce the consumption that has happeend on the PO) for some reason the Movement type that is getting picked up is 546 (GI issue SC by-prod)- I am not using any by-product functionality anywhere like in BOM or PO etc not sure why this is coming up. I am expecting the 541/542/543/544 movements.
Any help in this regard will be highly apprciated
ThanksHi Pratap
In MB04 we need to put -ve sign when the consumptions need to be reduced and a +ve value when the consumption needs to be increased that is the way it works. The -ve you might be referring is in the BOM for by-product.
Please advice
thanks -
ABAP Dump is encountered when doing the negative subsequent adjustment
Hi Experts !!!
An ABAP Dump is encountered when doing the negative subsequent adjustment (posting a 102 movt type) on a Purchase Order via the Z function module. The dump only happens if the scenario satisfies the following conditions:
1.Material is either (but may not be limited to) 3000000234, 4000000121, 3000000210 (These are the only reported materials)
2.Order unit in Purchase Order is in MT
3.At 2nd weigh, Net Weight is less than PO Order Qty.
Note: No error occurs if same process is done via MIGO.
Initial Analysis:
An exception/error occurs when calling function u201CMB_CREATE_MATERIAL_DOCUMENT_UTu201D .
Please see below error anlysis report from after executin Zfunction module code.
Error analysis
Short text of error message:
Material 3000000234 / US01 Column 0001: MSEG-BPMNG not in quantity table
/not consistent
Long text of error message:
Diagnosis
Before the system posts a material document for an HPM/TDP material
(MARA-CMETH = 1 or 2), it performs the following consistency
checks:
o For each unit of measure in the Unit of Measure Group
(MARC-UOMGR), a line item has to be present in the additional
quantity appendix table (Table MSEGO2)
o For each unit of measure in the main core table MSEG that is
not initial a line item, has to be present in the additional
quantity appendix table (Table MSEGO2) and the corresponding
packed format quantities have to be identical.
This way, inconsistent stock level updates can be prevented.
System Response
The system stops processing.
Procedure
If the error is reproducible, contact your system administrator.
Procedure for System Administration
The inconsitency can have several reasons, for example:
o Incorrect postings from external systems using function module
MB_CREATE_GOODS_MOVEMENT
o Handling errors
o Application programming errors
Technical information about the message:
Message class....... "O3"
Number.............. 359
Variable 1.......... 3000000234
Variable 2.......... "US01"
Variable 3.......... 0001
Variable 4.......... "BPMNG"
Please let me know,if you want some other details.Problem Issolved
-
Rejected material sent back to Sub-contractor.
Friends,
Scenario.
Finished Goods : X
Components: X1 and X2
Received X from subcontractor After assembly.
101 Mvt for X
543 Mvt for X1 and X2
X is recived in Quality stock and put them in blocked stock and later rejected and sent back to Subcontracting Vendor with 122 Movement.
X: Mvt: 122
Now my question is what will happen to component X1 and X2 which logically should effected with 544 Movement. It says insufficient stock and it says the value is negative..
Can you please guide me if my process is wrong anywhere and what is the right solution for this.
RegardsYou are absolutely right Csaba. Thanks for your response.
When the Finished Assembly is rejected and sent back with 122 Mvt, even the child components will have to be ticked and it has to do a 544 movement right ?
In my case it is not happening and the system shows the following error.
The goods movement value is negative
A subcontracting order contains negative components ( by-products). The value of these by-products is sufficiently high that the goods receipt value value of the material ordered is negative.
Reduce the quantity of the negative components until the goods receipt value is positive. Then enter a subsequent adjustment for the remaining by-products using transaction MB04.
In the case of negative delivery costs:
It would be great if you can help me understand this and resolve the issue.
Thanks -
We had a sub-contractor from ATT come to our Business Builiding. They were to drop cable in the right a way on the property for a business located behind us. The sub-contractor interferred with our telephone communication that was on the building. The contractor was abusive. The contractor use vugar names to the owner of the building when the contractor was asked to keep his hands off of the equipment. The subcontractor became beligerent. He was told to leave the propeerty. It took severl neighboring business to get the subcontractor off our property after amost 20 mintues of heated exchange. This contractor keeps coming back, and we have told him he is not allowed on the property and to notify ATT for an new sub-contrator. Its there a number we can call to have some assistance with this issue. We do not want to involve the police. Thank you.
See if ATT Customer Care can help. Click the ATT Customer Care link in my signature below, send the PM, explain your bad subcontractor situation.
Include your name, account #, email address and a good phone # (land or cell) and time to contact you on.
Check the blue PM envelope, upper right on every page, for their reply. Good luck
Chris
Please NO SD stretch-o-vision or 480 SD HD Channels
Need Help? PM ATT Uverse Care (all service problems)
ATT Customer Care(all other problems)
Your Results May Vary, In My Humble Opinion
I Call It Like I See It, Simply a U-verse user, nothing more -
Problems getting print-out of Sub-contracting challan
Hi all,
we,ve had real problem getting the print0out of sub contracting challan.
System wouldn't show any print-preview of the sub contracting challan.
but at assign forms and procedures in customizing of Inv management, at 51IF FOR SC challan, the system does show a print-preview of the sc challan form.
but, after creating a SC challan and trying to view the print-preview of sc chalan, the system would neither show print-preview nor get a print-pout of the sc chalan.
please do help in this regard,
thanks and regards
Nabilsolve with other thread
-
Error:subsequent adjustment in subcontracting
While posting subsequent adjustment for a subcontracting P.O,getting the error "The system could not copy the sub-items in this line".The quantity field for the main item is having a default value 0 and it was disabled for input.
I have maintained a BOM of the main item with usage 1.What is the transaction are you using for susequent adjuments.While receiving intitial GR you might have entered some differences for sub line items.If yes then use MB04 to settle the same.
Maybe you are looking for
-
When I go to "checkout" on Borders.com, I get an error message. The message is as follows: [ServletException in:/ConsumerDirectStorefrontAssetStore/ShoppingArea/ShopcartSection/body.jsp] null' I have tried refreshing, clearing cookies, and everything
-
Adobe Acrobat 8 Prof - PDFs will not open in Adobe automatically
I have a workstation that has Adobe Acrobat 8 professional installed. I was first notified that the user complained that each time he opened a PDF in an Email, it would open in Explorer. I had him save a document to his c; drive and did a view file t
-
Login as sysdba problem...
Hi, I've created my own database to make tests on Oracle and directly after that I've changed the passwords for all the users (sys and system users included). When I try to login without the sysdba role, Oracle applies the password verification fine.
-
Effect of Force use of non-existing index in program
Hi, What is the Effect of Force use of non-existing index in program? We have forced the use of a custom index in our program, i want to know the effect in the program if in the future this index will be deleted or removed from the database? Thanks a
-
Calculated column in pivot table
How can I add a calculated column (Daily Average) in a pivot table like this? "Product" in row and "Date" in column and a "Daily Average" column to the right. Date1 Date2 Date3 +Grand Total Daily Average+ Product