Subcontract challen

When we issue materials to a subcontractor,Under excise law 57AC, when we send materials to a subcontractor for processing, we are not required to pay any excise duty, even though the materials have left your premises. However, if the materials have not been returned to we within a given length of time specified by the law (in 2000, 180 days).what will be happened??? please explain in detail

We will have to reverse  excise credit that we posted when we purchased the materials ( Completion, Reversal, and Recredit). In the case of materials that we have manufactured in-house,we will have to post credit entries to the extent of the CENVAT rate of the assessable value of the materials.
You use this function to close a challan completely after all the materials have been accounted for. If a challan's return date has elapsed, and thus your right to the CENVAT credit, you use it to reverse the excise credit u2013 or, should your subcontractor return the goods subsequently, to recredit the excise credit.
Completion
You can complete a challan if you have accounted for all of the materials in it (and it thus has the status Fully Reconciled). This prevents you from making any more changes to it.
Reversal of CENVAT Credit
If the allotted number of days elapses and the subcontractor has not returned some or any of the materials in the challan (status: Posted or Assigned), you must reverse the excise duty that you have credited to your CENVAT account. The scrap has to be returned by the subcontractor. If it is not returned, the excise duty for the scrap has to be reversed.
This function sets the status to Reversed. From here, you have two options:
If you do note expect the subcontractor to return the materials, you can
complete it. If you do expect the subcontractor to return at least some of the materials, you can leave it as it is for the time being. Then, when the materials arrive, you can recredit the excise duty to the account (see below).
Recredit
If a subcontractor returns materials after the return date, you can recredit the excise duty credit that you have reversed.
J1IF13-complete,reverse and recredit a subcontractor challan
J1IFQ- Reconcile quantity of subcontractor challan
If S/C challan crossed the 180 day limit..Follow the procedure as below---
1) First Reverse the Excise Duties in T.code J1IF13 by reversing the challan
2) If the material is returned as it is from Subcontractor,then do the transfer posting by 542 movement type.Then reconcile the challan w.r.t. 542 Material Document Number.Then complete the challan In J1IF13 if total quantity is received against the challans.
3) If u r doing GR for the subcontracted item . then give the reference of Challan in GR against Excise Tab.Refer the GR material Document No. for Reconcilling the Challans in T.code J1IFQ .Complete the challan in J1IF13
Regards,
Edited by: GAURAV MITTAL on Nov 29, 2009 4:54 PM
Edited by: GAURAV MITTAL on Nov 29, 2009 4:56 PM
Edited by: GAURAV MITTAL on Nov 29, 2009 5:00 PM
Edited by: GAURAV MITTAL on Dec 3, 2009 6:18 PM

Similar Messages

  • Subcontracting challen po net value not come in challen

    Hi
    While I taking print of subcontracting challen po net value not come in challen
    any reply
    Regards
    Kailas ugale
    Edited by: Csaba Szommer on May 9, 2011 10:36 AM

    Hi
    check this link it may helpful to you
    same question was put by me in forum some day ago
    [net value not coming in subcontracting challen|subcontracting challen print;
    Regards
    Kailas ugale

  • Subcontracting Challen

    Hello
          I am facing some problem in Subcontracting
    i have created one subcontracting PO to vendor , materail is provided to him
    with 541 movement type , after that iam creating subcontracting challen
    T. code J1IF01 , then  did MIGO , after that i go for J1IFQ for reconcile
    the challen , then go for complete the challen J1IF13 IS valid for 180days as per indian standards,
    1)if he did not send materail within 180days then what to do?
    2)if he send ful materail then some of them are rejected how u can manage  with excise and all plz clear me on this issuse
    Regards
    Sapman

    Hi sapman
    As per excise regulation, you can remove material from plant and keep outside with out reversing excise credit, for max 180 days only. If the material lies more than 180 days outside the plant, you have to reverse the excise credit previously credited.
    As we use the subcontracting challan with out excise duty reverse, we have to monitor the number days the components lying in subcontractor's premises with out processing/consuming.
    If some material rejected, then take back the marerial to your own stock and reconcile the challan against the material document. Similarly for scrapping also, make transfer and reconcile.
    warm regards
    sairam akundi

  • Subcontracting challen print

    Hi
    While I taking print of subcontracting challen po net value not printed in challen
    any reply
    Regards
    Kailas ugale

    Are you printing standard subcontracting challan or Customized one ?
    Normally in subcontracting challan total net value  = Sum of all line items (Assesable value * Quantity issued),Since
    it is excise document which need to show total excisable material value sent outside.
    Why you need to print p.o net value which may include processing charges + cost of all bom components
    for which you were giving subcon. purchase order.
    Tell us actual business requirement if above mentioned is not true.

  • Reconsilliation of Subcontracting Challen

    Dear Experts
    In j1ifq
    Whenever we r reconcile the Mat Doc. Of Subcontracting PO GRN.
    System is showing with Some Material That Material Qty is not assigned Fully,short by  qty.
    if possible answer then pl reply .
    Rgds
    Pankaj Agarwal

    As you have created the S/C for each line item need to be reconcilled as per the the qty you have actually consumend batch wise in the GR through 543 movement type, check it and try to reconcile with the same qty that you have consumend...
    That is to say if in challan you have 100 qty for one line item and while consuming the material in MIGO for the same line item had been broken into several batches, int that case need to be reconcilled for the same qty in J1IFQ.
    Regards,
    Sujoy

  • Reconcillation of subcontracting process

    hello gurus
    in susubcontracting when i reconcilled gr quatity through j1ifq
    system is giving error massage that
    challan material is different from material document. so where could be the problem

    Hi,
    In J1IFQ transaction are you mentioning the Material document number (i.e GR 101 for PO)
    and doc year.
    Also mention the Subcontracting challen number and year with line item.
    Just check what u r entering the Material document number (It should be 101 GR document not 541 mvt type document number)
    rgds
    Chidanand

  • Standard O/P Type for Subcontract Challan PO

    Hi,
      For Subcontract Challan print out we have a made a seperate transaction code , but i want to know which is the std. o/p type for Taking the print out of Subcontract challan, like for po NEU is there   , so which is the o/p type is for taing the subcontarct challan print out  can u give the program name and form which is use for it.
      regards,
        zafar

    Hi,
    Standard Output type for SUBCONTRACT CHALLAN is J1IF
    You can give the Print for the subcontract challen in J1IF01 transaction, enter the Excise group and series group
    In the next screen you can find print parameters
    regards,
    santosh

  • How to take printout of Subcontact challen

    Hello,
    How to take Printout of Subcontract challen, Which T.code?
    Regards,
    Ramesh

    You can take Printout in J1if11 t.code.you have to select print immediately checkbox in Posting tab.

  • Subcontracting from EOU

    All SAP Gurus,
    We are having two plants under same company code
    One plant (1000) is an Export Oriented Unit
    Other plant is a domestic plant : 2000
    plant 1000 is needed to give certain material for subcontracting, but being an Export Oriented Unit it can not give material for subcontracting directly to subcontractor.
    So plant 1000 is giving the material to 2000 plant, which then passes on to the subcontractor.
    So two subcontracting challens are created for the material being subcontracted.
    STO betwwe plant 1000 and plant 2000 is not possible. as plant 1000 is Export Oriented Unit.
    How, this scenario can be mapped.
    Regards,

    Hi,
    You can transfer the materials (subcontracting components) from 1000 to 2000 through sales process (sales order, develivery and billing etc). After completion of subcontracting process at 2000 you can receive the material (finished product) through purchasing (Just like normal domestic purchase). Here you need to create plant as vendor and customer.
    Subrahmanyam

  • Plant A supplying material to plant B, plant B supplying it for subcontract

    All SAP Gurus,
    Here are two plants: A and B
    Plant A is EOU (Export Oriented unit)
    Plant B: Domestic Plant
    Plant A is providing material to Plant B,  57 F 4 challan is created.
    Plant B simplying passing on this material to subcontractor, and creating one more subcontracting challen.
    Subcontractor supplying material to plant B.
    Plant B supplying the material back to plant A.
    How this scenario can be mapped.
    Please help.
    Regards

    Please do not create a challan from Plant A to B, Instead create a STO & if necessary an EI while transferring the material from A to B. A subcontracting challan can be created when the material is sent from B to the Vendor because reconciliation can take place here.
    Then another EI can be created when the material is eventually sent from B to A again via stock transfer.

  • Sales with Subcontract process

    Hi experts,
    Please provide your valuable inputs on the below scenario :
    We sell material Y to our customer, but material Y is processed by our subcon vendor and we send material X to our subcon vendor for this purpose.  After processing material X into Y, our subcon vendor directly despatches the same to our customer.  Both the materials X and Y are excisable.
    How to map this scenario in SAP.
    Please help ASAP.
    Regards
    Radha Krishna

    Hi
    I think its more legal that technical
    If both material are excisble then what about subcontracting challen? if you not complete your challen in 180 days then?
    second if subcontracting vendor supplying material to customer ,then which duty your vendor will send to your customer it own?
    from where he will collect duty for material Y? because he producing Y material from X which is your material not his.
    better way sale your material X to vendor with excise ask him to produce material Y ,
    create Po for material Y as procure and show third party sale from Vendor
    Regards
    Kailas Ugale

  • Subcontracting material rejected at vendor location

    Hello,
    My client has sent material to subcontractor.he has created subcontracting challen with respect to material document.at vendor location two materials has rejected.How to reduce these materials in already issued challen.please do the needful.

    Hi
    Lets say by 541 movement you have sent the material to vendor and if it got rejected at vendor end then you ask vendor to send it back and in system by MB11 use movement type 542 to book the rejected qty first and then move to block stock.
    Please check
    Kishor

  • We are subcontractor

    All SAP Gurus,
    I'm aware of the subcontracting cycle, which includes:
    1. creation of subcontracting PO
    2. transfer posting using 541 mvt. type
    3. creation of 57 F 4 challen
    4. Receiving goods against PO
    5. Reconcilation of subcontracting challen
    6. closing subcontracting challen
    Now, I have the reverse scenario:
    We are the subcontractor, receiving material and providing subcontracting services.
    How this scenario can be mapped?
    Please helpu2026..

    Hi,
    Here u r selling "SERVICE" to ur customer.So u can try following process
    1.To tracks customer material , you can create materials with UNBW(Nonvaluated materials ) Materila type.
    2.Create "SERVICE" materil with "DIEN" material type in MM01
    3.Cretae SO (VA01),
    4.Billing(VF04/VF01)
    Regards,
    Biju K

  • One subcontractor different Plants/Addresses

    Dear All,
    I'm supplying a perticular material for subcontracting (one one material code).
    Is it possible to maintain different addresses for same subcontractor because it is send to different plants depending upon avaibility.
    This is required for creating subcontracting challen for different addresses.
    Thanks,
    Edited by: Rajan R. on May 12, 2008 1:15 PM

    hi Rajan
    Say you have a vendor or subcontractor VN(XXXX), who is having plant at different address, In this case create a seperate vendors as "delivering plant" and assign it to main subcontractor VN in XK02..
    then transfer items to plant of subcontractor
    then create PO for the main subcontractor and in "partner" tab enter the name of delivering plant from where subcontractor is supplying goods
    hopes this will solve ur problem
    reward points if helpful
    regards
    chetan

  • Sub-Contraction challen creation.

    Hi ,
    While creating sub-contracting challen . i am geeting below error.
    Please specify the number of line items for the challans.
    Message no. 8I802
    Please Guide me
    SAM

    Hi,
    Check whether you have maintained the following settings.
    SPRO - LG - Tax on Goods Mov's - India - Business Transactions - Subcontracting - Subcontracting Attributes
    Thanks & Regards,

Maybe you are looking for

  • Best Practice to implement row restriction level

    Hi guys, We need to implement a security row filter scenario in our reporting system. Following several recommendations already posted in the forum we have created a security table with the following columns userName  Object Id U1             A U2   

  • How do I get firefox to show weblink to my current page so I can copy it?

    The new firefox doesn't show the weblink to the current page. I need to copy the link to send it but I can't do that if it doesn't display it.

  • Working with a batch of measurements

    Recently switched to Diadem 9 and finding the new navigator layout with it's data portal. I'm often Working and analyzing many measurements with the same signal names in View. In the new portal I can load all the measurement. After looking on the fir

  • Adobe Form From Excel Has Excel File Location in Form

    I took an excel sheet that we use as a form and used the adobe form wizard to convert it to a pdf form and it has the excel files location at the bottom of the form C:\Documents and Settings\My Name\Desktop\stsform.xls. How can i make it so that this

  • Apps are not downloading on my I phone

    Hi,there my phone is not downloading any apps from App Store.What Should I do?