Subcontracting Delivery (LB) split through ME2O

Hi Folks,
When I try to delivery multiple materials from the same PO through ME2O, they get split into multiple deliveries. Lets say I have selected about 10 materials in one transaction, I see that 3 materials go into one delivery, 2 each go into two seperate deliveries while the rest into individual deliveries. This way I now have about 6 deliveries for a single PO.
I want to understand how this split is working and how to avoid?
Thanks in advance!

Hi Sajesh
I have come across same problem which you have mentioned here .
Could I request you to brief me how did you solve this problem .?
Also,  could I request you to interpret your words u201C Requirement date seems be to be reason for the splitu201D.
Which requirement date are you referring to .
I will reiterate that ship to party , schedule line , shipping point are same . but still delivery split has happened  while creating delivery in ME2O.
I appreciate if you reply soon on this .
Thanks in Advance .
Jayapala S.H

Similar Messages

  • Delivery Split through ME2O

    The subcontract order creates multiple deliveries instead of one delivery through ME2O. The PO has 3 to 4 sub components for the main material. The header data are all the same but still multiple deliveries are created. I have glanced through the SAP notes and found details related to partner data mismatch, delivery date backlog but these didnt help.
    If anyone has come through such scenarios let me know.

    Probably the components have different planned delivery dates.
    even you cannot see this in ME2O.
    But that was the answer I got recently from SAP with the rocommendation to look into  OSS note 377501 and 386340,

  • Delivery created through ME2O without PO number

    As you are aware , you will not see PO number in Delivery if it is created through ME2O transaction. Could any one tell me how to get PO number in Delivery which is created by ME2O by some enhancemets/user exits etc.

    ME2O is able to create deliveries to your subcontractor even when there is no PO, further you can deliver more quantity than the PO component quantity, and you can create one delivery to deliver components that are needed for more than one PO.
    We often deliver a full truck load of components to a subcontractor, to save as much freight costs as possible. The subcontractor does not just a one-time subcontracting for us, he does it on-going.
    because of this functionality SAP cannot establish a link between a PO and a delivery of components

  • Delivery split through VLSP along with JIT Calls with AW Partner profiles

    Hi SAP SD/LE Guru's,
    I have one critical issue to resolve immediately in my implementation of SAP 4.6C system in multinational automotive industry. It's in the area of Delivery split along with AW - Duns number partner profile and JIT calls.
    Here is the scenario:
    1. JIT(Just In time) calls will be created through EDI based on the ship-to, PO Nos, Duns number.
    2. The requirements will be updated in Scheduling Agreements JIT Delivery schedule.
    3. Picking is done based on the requirements.
    4. Packing, Deliveries and Handling units are created: Note: Each handling unit is linked to one JIT Call.
    5. Based on the Shipments, Deliveries needs to be split into further sub-deliveries.
        Ex. One Delivery has two HU's. This needs to be split into another delivery so that one HU need to be detached from original and attach to new delivery. At the same time corresponding JIT call also need to be detached from original delivery and attach to new delivery. This can be done through VLSP : Subsequent split(Outbound delivery). Split profile: 003 - split based on Quantities.
    The issue: When executing delivery split using VLSP and split profile: 003, the system is terminating and giving short dump.
    The error analysis says that AW - Duns number is creating the problem. The short dump occurs in SAPLV05I in Function module: SD_PARTNER_UPDATE.
    There is an SAP note: 154766 related to this problem says that Partner header should be used only once in copy control.
    But in customization of copy control from Sales order to Delivery, there is no VBPA Partner header.
    I appreciate if you can provide solution for delivery split and resolve this short dump issue.
    Thanks,
    Murali Chintakunta

    In reference to this change in the Custom Reports... Better experience when exporting data - to prevent customer confusion when exporting data from Mac computers, we have removed the export to excel option and exporting in CSV format by default.
    What is the customer confusion we are trying to stop here? I've got even more confused customers at the moment because all of a sudden they can't find the export to excel option but know it exists if they log in on a PC?
    Mark

  • Why some times delivery  will created through vl10c even sale order stock is not available?

    Hi,
    why some times delivery  will created through vl10c in batchmode even sale order stock is not available?
    Thanks,
    Kalyan.

    the correct english name is : Replenishment leadtime
    Check with Replenishment lead time - Supply Chain Management (SCM) - SCN Wiki

  • FM to create subcontracting delivery lines

    Hi Folks,
    We are using one custom function module to create subcontracting delivery lines. Inside this custom FM, we are using ME_COMPONENTS_MAINTAIN function module first to maintain the components and then ME_UPDATE_SCHEDULES_DISPO to create delivery lines for the schedule agreement. Actually the ME_COMPONENTS_MAINTAIN is displaying a screen where you have to maintain the material, wquantit etc. manually. But we dont want that. We need to create subcontracting delivery lines without manual intervention. Is there any FM available for this requorement? Or else can I use ME_UPDATE_SCHEDULES_DISPO directly to create subcontracting delivery lines? I know this query is more functional than technical. Kindly provide your inputs.
    Thanks,
    Mani

    http://scn.sap.com/thread/175138
    (about halfway down, Stefan Berger's post)
    I've not completely tested this yet, but whilst investigating a similar problem, I came across the above thread. ME_COMPONENTS_MAINTAIN has a paramater "I_FCALL" which if you set to 'X' doesn't call the screens, and just runs in background.
    You can also see the variable population by putting a breakpoint in the top of this fm, and then running the frontend transaction.

  • EKET-FIXKZ set after partial goods receipt of subcontract delivery schedule

    Dear all,
    when booking a partial goods receipt (via MIGO) of the finished product of a subcontract delivery schedule the schedule line becomes fixed (EKET-FIXKZ = 'X'), which hinders the next MRP run to modify the delivery schedule according to the new requirements.
    I have tested to change the fixing indicator via SE16 and the next MRP run will then replan the sub contract delivery schedule correctly. But this is no solution.
    Is there a way to modify this setting via an EXIT or BADI in MIGO ?
    Many thanky for your help
    Rabanus Diehl

    Dear all,
    when booking a partial goods receipt (via MIGO) of the finished product of a subcontract delivery schedule the schedule line becomes fixed (EKET-FIXKZ = 'X'), which hinders the next MRP run to modify the delivery schedule according to the new requirements.
    I have tested to change the fixing indicator via SE16 and the next MRP run will then replan the sub contract delivery schedule correctly. But this is no solution.
    Is there a way to modify this setting via an EXIT or BADI in MIGO ?
    Many thanky for your help
    Rabanus Diehl

  • Return delivery transportation charges through VT01N

    Dear All,
    I want to capture return delivery transportation charges through transportation model. Can anyone tell me the process step by step.
    Thanking you in advance.
    Sumeet

    Hi Sumeet
    Check the following links
    http://help.sap.com/saphelp_47x200/helpdata/en/92/c0dab4b45911d3b2ae0050045571f7/frameset.htm
    http://help.sap.com/saphelp_47x200/helpdata/en/a8/b9920f452b11d189430000e829fbbd/frameset.htm
    Thanks
    G. Lakshmipathi

  • Unable to create delivery through ME2O in subcontracting process

    Hi,
    I am trying to create delivery for the subcontracting order in ME2O, but it was giving the error. Stock also exist for component material.
    The error messange is:
    "An item with no delivery quantity is not permitted. Item will be deleted".
    Please let us know the reason.
    Thanks in advance!
    Thanks,
    Jana

    Hi
    Please check the Stock overview MMBE of the material, in the stcok overview check the stock qty click on
    details and check if any stock qty is reserved for any delivery.
    Usually the delivery is created but PGI is not done , in such cases systme reserves the stock for that delivery, in the sytem it shows that stock is availble but that may be reserved.
    Thanks & Regards
    Kishore

  • Delivery IDOC Split

    Issue:
    We could observe that the error coming in the Idoc XXX; are errors involving the financial postings that occur as a result of the inventory movement associated with a goods issue.
    Error Message:
    Maximum number of items in FI reached
    The above error in IDOC is due to max. number of items for an FI Document(999) is exceeded.
    As per my understanding, I think we have to split the delivery document into two parts and post to FI accordingly
    As FI documents is getting posted through IDOC, how can I limit my IDOC to process just 50% of line items(How to split my Delivery though IDOC)

    Refer below note:
    Note 1353827 - AC interface: Document split in FI for goods movements
    Regards
    Sreenivas

  • Subcontracting: delivery of components directly to subcontractor

    Dear experts,
    I have the following process at my client:
    Via a purchasing process, my client orders components at a vendor. This vendor delivers the components directly to the subcontractor who performs certain activities before sending the new assembled goods towards my client.
    The problem I have with this process is how to handle the good receipt of the purchase order and how to make sure the stock is afterwards issued towards the subcontractor?
    The subcontracting process is set up as a specific purchase order.
    I'm sure you have come accross a similar process in your past. Could you please shed some light on this topic?
    It's much appreciated!
    M

    Regarding your query, " Consequently, the above means that when setting up the subcontracting order, that this order will only contain the parts that are to be shipped from stock (and not the parts that are ordered at another vendor and delivered at the subcontractor). Correct?"
    This is not correct as You will make a subcontracting order with all the components tht part to be shipped from the stock and the parts that are ordered at another vendor and delivered at the subcontractor.
    1. You have two purchase orders one Normal Po with delivery to subcontracting vendor and other subcontracting PO.
    2. On doing Goods Receipt for normal Po it will take movement type as 101 O that is stock provided to vendor.
    3. For subcontracting Po you will do MB1b or ME2o for the parts to be provided to the vendor that is 541.
    4. On doing Goods Receipt for subcontracting PO the part provided by  the vendor will get consumed with 543 O and that provided from your own stock with movement type 543.
    Regards
    Sangeeta

  • Issue in Delivery Line Item through VL01N

    Hi,
    During Delivery creation through VL01N, in Line Item details under Financial Processing Tab, Cost Center is showing as non-changable... We cann't enter any value in this field..
    We have two options--
    1. By make the field as changable, so that we can enter the related cost center.
    2. Automatic Cost center should should according to Profit center...
    Please provide the best solution...
    Thanks..

    hi
    cost center its comes from setting related , it related with business area , it delivery its not possible to enter cost center ,
    it is totally related with fico ,
    so first you maintain the cost element , it cost element you can check previous delivery document accounting , goto delivery goods issue document document( mb03), click on display document , ofter click on accounting document , her double click on accounting document , system sows , accounting for debit and credit here g/l account and cost element  account you can find,
    goto okb9 , and select your company and cost element ,click on valuation area/business area based , here you plant and business area ,cost center find,
    in delivery no need direct enter the cost center , its automatic picking when you click on PGI,Updating at mb03,
    please check this , and also you contact your fico consultant

  • Unable to get delivery to split

    Hi all,
      In the sales order, i have 3 line items where 2 items go to Plant 100 and  1 item go to Plant 200.  I need to create split delivery as the plants are different.  When i ran VL10A, it show me just one line for that order with the first item for plant 100.
    Q1: Can anyone let me know if VL10A suppose to show 1 line or 2 lines as there are 2 different plants ?
    Q2: I want to create  2 deliveries from that one order since there are 2 different plants.  Would anyone be able to provide any suggestions ?  The following are the same at each item in the order:
         - ship-to party, shipping point, delivery date, quantities are confirmed
         - unloading point,  receiving point are blank
        - item category are TAN
      The only different among the item are plants.  Then why delivery cannot be split based on plant ?
      I forward to getting your suggestions. 
    Thank you.
    Joyce

    Hi,
    You can check the set for the items. Here you can check the subroutines, here you have the VOFM subroutine 001 (report FV50C001) where:
    Fill field ZUKRL with combination criteria
      LIKP-ZUKRL(2)      = CVBAK-VTWEG.
      LIKP-ZUKRL+2(2)    = CVBAK-SPART.
    So you can copy it with tcode VOFM (search in google a document with this string: inside vofm ext:pdf, I don't tell you the adress by copyright reasons) or check this notes, so you will know how to do your own VOFM (remember the naming conventions for VOFM, call it 901 e.g.). Well, check Note 327220 - VOFM function and its objects and related notes.
    Copy 901 (ie: FV50C001, you will need register in SSCR) and in the before coding write this:
    Fill field ZUKRL with combination criteria
      LIKP-ZUKRL(2)      = CVBAK-VTWEG.
      LIKP-ZUKRL+2(2)    = CVBAK-SPART.
      LIKP-ZUKRL+4(4)   = CVBAP-WERKS.      "write a comment for maintanence
    To set a break-point, write the sentence break-point or break username (it will work only for the username), or in other coding click on the stop icon in SE38 (ABAP editor).
    I hope this helps you
    Regards,
    Eduardo

  • Req Help to Update LIKP-LIFSK,Delivery Header block through custom program.

    Hi everyone,
    Can you please suggest a FM or BAPI to update the delivery header block field, LIFSK, in LIKP table through FM or a BAPI.
    I tried using 'BAPI_OUTB_DELIVERY_CHANGE' as below to update the LIKP-LIFSK, but it is not working.
    DATA : ls_likp TYPE likpvb,
           ls_dlv_header  TYPE bapiobdlvhdrchg,
           lt_dlv_items_control TYPE STANDARD TABLE OF bapiobdlvitemctrlchg,
           ls_dlv_item_control TYPE bapiobdlvitemctrlchg.
    DATA : ls_dlv_hdr_control   TYPE bapiobdlvhdrctrlchg,
           ls_dlv_techn_control TYPE bapidlvcontrol,
           lt_bapireturn TYPE STANDARD TABLE OF bapiret2,
           ls_bapireturn TYPE bapiret2,
           lt_bapiext2 TYPE STANDARD TABLE OF bapiext,
           ls_bapiext2 TYPE bapiext.
    DATA :  BEGIN OF ls_mns_of_del,
                 vbeln TYPE likp-vbeln,     "delivery number
                 lifsk TYPE likp-lifsk,     "means of transport
           END OF ls_mns_of_del.
    CONSTANTS : lc_del_blck           TYPE bapiext-param VALUE 'LIKP-LIFSK'.
    PARAMETERS : p_dlv TYPE likp-vbeln OBLIGATORY."  OBLIGATORY.
    SELECT SINGLE *
      FROM likp
      INTO ls_likp
      WHERE vbeln = p_dlv.
    CHECK sy-subrc = 0.
    CLEAR : ls_bapiext2.
    ls_mns_of_del-vbeln = ls_likp-vbeln.
    ls_mns_of_del-lifsk = 'BX'.
    ls_bapiext2-param = lc_del_blck .
    ls_bapiext2-value = ls_mns_of_del.
    APPEND ls_bapiext2 TO lt_bapiext2.
    CALL FUNCTION 'MAP2E_LIKPVB_TO_BAPIOBDLVHDRCH'
      EXPORTING
        likpvb          = ls_likp
      CHANGING
        bapiobdlvhdrchg = ls_dlv_header.
    CALL FUNCTION 'BAPI_OUTB_DELIVERY_CHANGE'
      EXPORTING
        header_data           = ls_dlv_header
        header_control        = ls_dlv_hdr_control
        delivery              = ls_likp-vbeln
        techn_control         = ls_dlv_techn_control
      TABLES
        extension2            = lt_bapiext2[]
        return                = lt_bapireturn[]
      EXCEPTIONS
        communication_failure = 1
        system_failure        = 2
        OTHERS                = 3.
    IF lt_bapireturn[] IS INITIAL.
      COMMIT WORK AND WAIT.
      MESSAGE 'Success' TYPE 'I' DISPLAY LIKE 'S'.
      LEAVE LIST-PROCESSING.
    ELSE.
      MESSAGE 'Error' TYPE 'I' DISPLAY LIKE 'E'.
      LEAVE LIST-PROCESSING.
    ENDIF.

    Hi ,
    After seeing your code, you are not passing any parameters to header control data. once check the below code, it might useful.
    DATA: h_data like bapiobdlvhdrchg,
             h_control like bapiobdlvhdrctrlchg,
            delivery like bapiobdlvhdrchg-deliv_numb,
            item_data like bapiobdlvitemchg occurs 0 with header line,
            item_control like bapiobdlvitemctrlchg occurs 0 with header line,
             return like bapiret2 occurs 0 with header line.
            CLEAR: h_data, h_control, delivery, item_data, item_control,
                   return.
            REFRESH: item_data, item_control, return.
           h_data-deliv_numb = gst_alv_table-c6_vbeln.
           h_data-dlv_block  = p_new_del_blck.         "the new delivery block
           h_control-deliv_numb = gst_alv_table-c6_vbeln.
           h_control-dlv_block_flg = 'X'.
           delivery = gst_alv_table-c6_vbeln.
              CALL FUNCTION 'BAPI_OUTB_DELIVERY_CHANGE'
                  EXPORTING
               header_data                   = h_data
             header_control                = h_control
              delivery                      = delivery
               TABLES
                return                        = return .
             "Check if return table got an error.
             READ TABLE return WITH KEY type = 'E'.
                IF NOT sy-subrc IS INITIAL.
               CALL FUNCTION 'BAPI_TRANSACTION_COMMIT'
                   EXPORTING
                  wait = 'X'.
                 ELSE.
             ROLLBACK WORK.
                            ENDIF.
    Regards,
    Parupelly

  • BAPI for Inbound Delivery Batch Split

    Hello Friends,
      I need any BAPI/BADI to assign batch split items to inbound delivery.  In out scenario, we generate transfer posting in MIGO with split batches and during inbound delivery generation in background, system generates seperate line items instead batch split items.  Now we need any BAPI/BADI to assign the batch split items during inbound delivery creation/change.
    Appreciate your support
    Best Regards,
    Goutham

    Hi Goutham,
    Please trt to use the BADI LE_SHP_DELIVERY_PROC - methods FILL_DELIVERY_ITEM and CHANGE_DELIVERY_ITEM when VB_CREATE_BATCH is called.
    As per note 317531 it is not possible to create bacthes in an SAP standard system via VL31N. There's no update on table MCHA even if you enter a new batch in the inbound delivery.
    I hope this information helps you.
    Kind regards,
    Fábio Almeida
    MM Consultant

Maybe you are looking for