Subcontracting return/rejection process

Hi experts,
My client is using subcontracting process in one of the plant which is excisable one .Some materials (assembly) gets rejected  in quality and is to be return to subcontractor with some challan and after rework from the subcontractor, the same comes back.
My question is How this return/rejection process can be mapped in SAP ( with excise challan and reconcillation etc). If sent back to subcontractor, what abt components?
secondly, is there any report available where  subcon PO wise stock can be seen ( receipt/issues of components and assembly as well)
I have to streamline the rejection process. Kindly guide. reply ll be  very well appreciated
regards
N Kumar

U have the following option for the Rejection return process,
1. u make return document with movement type 121 for GR Base return , after QA Person reject the qty & post the same to the Blocked storage location.
2.if the MIRO is done for the GRN document , then Create return PO, Post the doument with movement type 161, Use T code j1iv for excise ivoice creation.
for Rework process use following option,
1. make good receipt for the Ok qty only, remaining qty should be return
2.After GRN for the material & QA person posted the qty to Blocked, then use movement type 941 in mb1b so that material post to the vendor, send the material with manual challen,After receiving rework qty use movement type 942 to reverse the qty.
3.create return PO for the rework qty & debit the vendor with rquire amount.
Regards,
Deven

Similar Messages

  • Subcontracting return process

    Hi,
    Any one can tell me  Subcontracting Return Process.
    a) I done Return Delivery against the Subcontracting PO
    b) in J1IF01 I plan to create a Challan, its showing err..like " Document already exists for material document XXXXX"
    Please guide me.
    Rgs,
    Priya.

    HI
    Follow the below steps:
    Creation of Subcontracting PO (ME21N)
    Transfer Posting of Components to Subcontractor (Mvmt Type - 541) (MB1B/ME2O/MIGO)
    Creation of Subcontracting Challan w.r.t. Transfer Posting Doc (J1IF01)
    Goods Receipt w.r.t. Subcontracting PO and Refer Subcontracting Challan at the time of GR (MIGO) {GR with 101 and auto consumption of components with 543 movement}
    Reconciliation of Subcontracting Challan (J1IFQ)
    Completion of Subcontracting Challan (J1IF13)
    Generation of Annexure IV (J1IFR)
    Note: - In this case, you have to maintain the Assessable Value for the Components to be supplied to Vendor in J1ID and also Excise Tax rates for the Chapter IDs linked with these components. So during J1IF01, system will take the Assessable Value as Excise base Value and calculates the Excise Duties by taking Excise Tax Rates.
    Regards
    Prasanna

  • Subcontracting Returns process

    Hi Experts,
    Need you help on below scenario of subcontracting returns.
    I procure a material (X) from Vendor (A) in units of Meter, example rod. Later I send it to Vendor (B) for subcontracting (cutting) and get material (Y) in units of PC.
    At the time of quality check of material Y, I observe cracks in the raw material supplied by vendor A and plan to return to him.
    What would be your suggestion here, because I've to add up all the pieces to arrive to meters and return to Vendor A.
    Example: 200 pcs x 0.21 meter = Total return is 42 meters.
    Should I use a returns PO with material X OR returns PO with material Y and alternate UOM OR any other process which you think is better.
    Please note this material is excisable
    Thanks in advance
    Rajoo

    Hi,
    As per my understanding here, you have done GR for material Y from vendor B. And in background material X from vendor A is consumed in order to confirm receipt material Y. In this case you can not return material X as which is consumed. And if you try to return X there will not stock.  Best possible option is that, you have to return the material Y from vendor A.  This is you end/ finished product. And as per your input material is Excisable. Now from vendor B you can create one more return PO. to send material back to vendor A. But when you returned the PO & subsequently reversed the Excise using J1IS & Credit Memo to reverse the Amount if yet you have not posted the vendor invoice. in this case you can return the material.
    Rg

  • Return PO Process

    Hi Friends,
    In which scenario we can make use of Return PO process(Me21Nà MIGO) compared with normal reversal process (MBST or MBRL),
    Thanks and regrads,
    Chalaa,

    Hi
    You should make returns PO (movement type 161) when you don't know from which PO or GR your received that material or if invoice verification is done. This is called line rejection. When you make GR for returns PO system takes 161 movement type automatically. With reference to returns PO you can create credit memo for vendor. PO from which material received will not be open.
    If a material is rejected in Quality inspection and you know PO and GR details of that material and invoice verification is not done then you can use 122 movement type to return material to vendor. You can use MBRL for that.PO from which material received will become open.
    In case if you want to reverse the GR immediatly due to some error in data, you cancel GR using MBST. System takes automatically 102 movement type to reverse the GR. PO from which material received will become open.
    This is SAP standard
    Regards
    Antony

  • Subcontracting Returns

    Dear Gurus,
                         can you explain me the subcontracting return process along with T-codes. Thank you

    hi,
    Subcontracting Returns:
    Case 1) sending material back to vendor for rework FOC.
    Step 1) Create PO for rework matrial. change the BOM to recursive in component tab.Tick for FOC
    Step2)  send matreial through MB1B 541.
    Step3)  create s/c challan J1IF01
    Step4)  GRN against s/c PO.
    Step5)  Reconcille Challan J1IFQ
    step6) Complete challan J1IF13
    Case2) sending material back to vendor for rework with changes.
    Step 1) Create PO for rework matrial. change the BOM to recursive in component tab.
    Step2)  send matreial through MB1B 541.
    Step3)  create s/c challan J1IF01
    Step4)  GRN against s/c PO.
    Step5)LIV for s/c charges.
    Step6)  Reconcille Challan J1IFQ
    step7) Complete challan J1IF13

  • Return delivery process with excise in MM module

    Dear Friends,
                        this is chandu working as a consultant-mm , please any one can give the clear information regarding return delivery process for excise material , i'm following one process that is after invoice verification
    1) reverse excise invoice with MR8M
    2) return delivery with MIGO
    3) prepare outgoing excise invoice with J1IS  for print out J1IV
    4) preparing credit memo in MIRO with reference to original po
    the second process
    1) create return po with selecting return po check box in po
    2) GR with reference to the return po
    3)then J1IS  and J1IV  same process
    4) credit memo for return po in MIRO
    this 2 ways i'm doing the process  in the registers part1 that is qty updating (i.e qty is reducing)  but in the case of part2 that is the value it is not updating (i.e value has to reduce in the register right i'm working first time on CIN plz guide me the correct procedure if i'm doing wrong , in this my problem is only value not updating part2 register plz give me solution with clear explanation .
    regards
    chandu

    Hi,
    Follow the below mentioned procedure;
    1. ME21N - Create a Returns PO (Activate "Returns" indicator for PO line item)
    2. MIGO - Goods Receipt > Purchase Order (Returns PO) (Here system will hit Mvmt type "161" and you can also select Un-restricted/blocked stock from where you want to return the stock)
    3. J1IS u2013 Excise Invoice Other Movements
    Here click on u201Ccreateu201D button to create an outgoing excise invoice and reverse the CENVAT Amount.
    Here put all details as below and Press u201CEnteru201D.
    Ref.doc.type - MATD, Doc Number - Material document No of 161 mvmt, Doc Year, Series Group, Excise Group and Vendor
    Here check BED, ECS and SECess values to be reversed and click on u201CSaveu201D button to post the excise invoice.
    4. J1IV - Post and Print Outgoing Excise Invoice.
    5. MIRO - Credit memo w.r.t. Returns PO.
    Regards,
    Mahesh Wagh

  • CIN: Return STO process

    Hi All,
    I have the scenario regarding to Return STO process.
    Step1: Creating the return STO process.
    Step2: Negative goods receipt through MIGO. The movement type is 161.
    Step3: Creating delivery through VL10B. When iam doing the Post goods receipt (Negative post goods issue) through VL02N iam getting below error.
    Error: Purchase Order XXXX does not contain items for a stock transfer
    CIN related issue: How to handle the CIN ACTIVITIES. What transactions we have to use for updating or adjusting the Cenvat accounts. And what documents we have to use as references.
    Please help me to solve these issues.
    Thank you
    Regards
    Lakshmikanth

    Hi All,
    Any ideas please?
    Regards
    Lakshmikanth

  • Error in Return STO Process(Plant to Plant within company code)

    Hi All,
    I am doing the return STO Process(Plant to Plant within same company code) .
    Scenario:
    STO from Plant 1300 to 1400
    STO Process: ME21N->VL10B->PGI-> VF01(Proforma)->MIGO
    Return STO from Plant 1400 to 1300
    STO Return Process: ME21N(item with return indicator)->MB01(MT 101 w.r.t Return STO PO)->VL10B->PGR(Error)
    It is giving me the following error.
    Deficit of PU GR quantity 5 KG : 20027183 1330 2000 16
    Message no. M7021
    Kindly help me
    with regards
    Azeez.Mohd

    Dear,
       Please go through this link,
        [Deficit of PL Stock in transfer 10 EA : 100100051 IBM2;
        [Accept material in MIRO without any limitation?;
        [migo-return delivery-credit memo;
    Regards,
    Sandip

  • Issue in returns PO process- Third party

    Hi All,
      We have an issue in returns PO process -Third party
    Customer Forward Processp flow as below
    OR (US Sales Order) -> US Purchase Requisition (NB) -> US Purchase Order  (NB) -> MIGO (Mvt 101) -> MIRO (Vendor Invoice) -> F2 (Customer Invoice)
    Customer Return Process:as below
    ZREP (with US customer) -> US Purchase Requisition (NB) -> US Purchase Order Return (NB) -> MIGO (Mvt 161) -> MIRO (Vendor Credit Memo) -> ZRE (Customer Credit Memo)
    When the user raises Return purchase order , it is taking  the price from Inforecord  for current validity date.
    But ,Our user wants , it should select the same price from the  initial purchase order( as in forward process) even though the price changed in Inforecord for the current validity date when the Return purchase order raises .
    Please advise how to achevie this reqmt. Any user exits available.
    Regards,
    Amara.
    Edited by: AMARA LAKSHMANA RAO on Dec 3, 2008 4:01 AM

    Hi ,
    Thank you for the answer .  Actually the user wants to capture the  same price from the initial PO (forward cycle) into the returns PO(return cylce) .
    For example  initial PO (forward cycle) raised on 01.11.2008 at price $100 , then Inforecord changed at  price from $100 to $200 on 20.11.2008.
    User raised  the returns PO(return cylce)  on 21.11.2008 , then price is taking as $200 . But the user wants to capture the old price ($100) from the initial PO in to the return PO .
    How it can acheived.
    Regards,
    Amara

  • Returnable packaging process-Vendor-Company-Customer

    Dear SAP Gurus,
    I have searched through the internet as well as on this forum but I was not able to find the information I am looking for.
    I have the following issue concerning the Returnable packaging process in SAP:
    I need to gather overall information concerning the returnable packaging. The info concerning returnable packaging in relation 'my company' - 'customer' is quite accessible, however what about the process from vendor's side?
    The process is as follows:
    My vendor provides me with some materials that come with returnable packaging (e.g.Pallet01) -> Assuming I am just a middleman, I sell the goods to my customer and also send them on Pallet01 (one day my customer must return the pallet to me and I must return it to the vendor).
    - What are the settings I must set in customizing and in material master?
    - How would the process look like in the system?
    - In what report I can see how many Pallets I owe to the vendor and how many Pallets each customer should return to me (is there one report that would show everything or do I have to use separate reports)?
    - How do I proceed if the vendor decides to invoice me for the pallets or I decide to invoice my customer (I would like to know the best practices)?
    If there is an existing topic here (I was no able to find one) or any materials on the net I would be also grateful for the links.
    Thank you in advance!

    Dear kevinthai ,
    ex- create a po for 100 material send to vender then vendor send 100 materials to u then u migo finally stock is in ur plant ,
    then u sold that material to customer that is SD come to the  picture  if customer send faulty material to you then u receive that material to send faulty store , that material u will check ur system it will track all movement , then u will get to know which vendor u procured the material then go to migo  return to vendor put that po no which po u procured the materials ,enter it will display all material what ever material u procured at that time  then select the material & quantity and save ,it will goes to vendor
    before u should have customize MM-SD-FI  integration
    hope it will help you
    Regards
    shiv

  • Return against Process Order

    Hi Gurus
    I have a problem while posting a return against process order. When I am returning the process order the order quantity is not coming into the unrestricted area and it is showing in the reserved area. Because of this other process orders are not picking the right batch. The process order is not closed.
    Early response is highly appreciated.

    I check the problem and found that the process order line has reopen once we post the return. I don't know why this is happening. Could anyone tell me the standard practise and process flow of process order return.

  • Returnable Packaging - Process

    Hi Gurus,
    What is the process of returnable packaging in MM??
    We bought a drum full of 40 Lt of chemicals. We have paid the price of chemical and the material has also been consumed. But now the vendor demands the container back. How to capture stock of these containers in SAP?
    Please help!

    if you are asking for complete process in general..i would suggest searching SDN forum - it will give you lots of good answers
    for this time - i have done search for you...check below threads
    returnable packaging
    Returnable packaging process-Vendor-Company-Customer???
    and
    read SAP documentation @ help.sap.com
    http://help.sap.com/saphelp_470/helpdata/en/dd/560051545a11d1a7020000e829fd11/content.htm
    yogesh
    Edited by: Yogesh Lohiya on Feb 6, 2012 11:41 AM

  • How to map operation subcontracting in a process order.

    Dear Gurus,
    How to map operation subcontracting in a process order.
    there are five operations in a process after three operations the material is send to a subcontract for further processing(i.e the fourth) then it comes to the plant and the fifth operations completed
    How can i map this process .
    Thanking you in advance
    Regards
    Ram

    Hi,
    have you tried external operations in  receipe.  There you need to maintain all the procurement realted data for that particular operations that is done outside,  and system creates PR for every process order that you release.  However the material goes and comes in without any material number  (as WIP).
    If you want to have more control,  create a part number before SC operations  and afer SCoperations   and then use subcontracting process in procurement. 
    The need determines which option you can go with.
    cheers
    Rav

  • Return STPO process

    Hi All,
    We have received the material from our supplying plants through STPO ( different co code) process, and done MIGO with ref to outbound delivery. 
    Now, I want to return the material to supplying plant .  Anyone can please tell me what i need to config and what process i need to follow.
    Thanks & Regards
    Chandrashekar R

    hiii
    Return STO process is same like STO process only.
    But in master data ,what are things uhave maintained in regular STO process, it has to maintained in reverse manner.
    SO consider this points and maintaine the same in ur Customer master data, and vendor master ..etc,
    do below steps
    PLease check all end user manuals at your location, or the best practise notes for STO for Tcodes.
    Plant to Plant Stock Transfer ) Process with delivery
    STO cycle:
    1. Me21n - Create STO in receiving plant (Order Type UB ) Supplying plant - receivable plant - qty - material etc.
    2. Vl10b - Create replenishent delivery - collect sales document no from layout screen.
    3. Ref. to that sales doc no do the PGI in supplying plant - post delivery goods not save --- check mov type is 641 in po.
    4. J1IIn if excise invoice for supplying plant or if depot then do the j1ij for the same.
    5. VF01-create STO invoice in supplying plant - without a/c doc (select order type excise invoice india).
    6. Migo-Do GR in receiving plant w.r.t the outbound delivery made in supplying plant.
    Revert any clarification
    Thanks
    SAP-mm

  • RETURN PACKAGING PROCESS

    HI ALL ,
       CAN ANY ONE  LET ME KNOW  RETURN PACKING PROCESS I.E  RETURN PACKAGING PICKUP & ISSUE.
    THE MOVEMENT TYPES  FOR RETURN PACKAGING STOCK 2B POSTED .

    Hi sidi ,
    well , thanks for the response & link ,
    ERROR " NOT ALL PACKAGING MATERIALS ARE AVAILABLE .
    posted return PACKAGING MATERIAL (LEIH ) stock with movement types 561 v & 562 v ,AND THE STOCK IS AVAILABLE IN MMBE  AGANIST CUSTOMER . but STILL THE SYSTEM  PROPOSES a msg in delivery  " ERROR " NOT ALL PACKAGING MATERIALS ARE AVAILABLE .
    would u pl lt me know the movement types FOR RETURN PACKAGING  .
    Thanks & Ragards ,
    Jerry