Subcontracting same material same vendor different operations

All SAP Gurus,
I'm providing components (in this case these are tools) for subcontracting.
Accourding to the condition of tools, subcontractor will perform different opertions (eg. sometimes sharpening of the tools, some times chipping) over these tools.
I don't want to create different material codes for components (as my material which I'm supplying to subcontractor and material which subcontractor is supplying to me against components are same).
But processing charges are varying each time accourding to operations performed by subcontractor.
Subcontracting PO picks up same price each time from Purchasing Info record (subcontracting).
Is there any any out to pay different charges depending upon operations performed by the subcontractor.
(We can not create service PO, as material is going out of factory on subcontracting challan).
Please suggest,
Regards.

Hi
Try changing the Price in the PO In the Conditions Tab of the PO line item.
Or if the Prices are being adopted from the Inforrecord , update the Price there.
Thanks & Regards
Kishore

Similar Messages

  • Same material and vendor, but different prices

    Hello All,
    I want to keep two different prices for a material that is supplied by a single Vendor. The price of the material will be different when supplied by Sea and when suppplied by Air. hence, there is need to maintain 2 difffernt prices based on how the material is shipped.
    I had tried it with Subrange, but I have to make 'VSR' field manadatory in PO creation, which I want to avoid. I had tried with pricing conditions based on shipping instructions, but could not find 'shipping instructions' field in any condition table.
    Can some one help me on this?
    Regards,
    Amit G

    create freight condition and accordingly value ( by sea or by air) would be loaded on inventory. what you will achieve by maintaining different prices? MAP would be adjust accordingly.
    or if in inventory if you want to differtiate thet then activate split valuation and create valuation type as per shipping instructions.

  • Sale of same material from two different storage loactions

    hi,
    how can i configure to sale same material code from two different storage loactions?
    for eg if material code is 15000 and it is extended in two storage location A and B.My requiremnet is i want to sale from both storage loction at same time A and B both.How can i map it?
    thanks
    Nakul

    Dear Nakul Raj,
    If you want to sale same material from different storage locations it can be done.
    First raise the sales order enter the material code and quantity as a first line item and give the storage location "A" in item shipping tab.
    Then give the same material code and quantity (how much you want to send) as a second line item with storage location "B".
    Then save the document, do the delivery, the storage locations will be copied from order to delivery, if you want to change you can do so.
    Do the PGI.
    Hope it will resolve your issue.
    Please reply if any further clarifications
    Kindly try and let me know the result
    Thanks&Regards
    Raghu.k

  • Auto GR for the same material and with different routings to diff stor loc

    Hi All,
              I have a semi finished material having 2 different routings line 1 and line 2 and with respective 2 different storage locations but need to have Auto GR.

    I'm not sure what you are asking; to cause an operation to do auto GR, you need to choose the right operation control key. The auto GR is controlled via the operation control key.
    Then for the Slocs; on the production version (MRP 4 view) you have a field "receiving location". Maintain for each of the two versions the right location.
    Next, create a new production order, and choose one of the production versions. Release, and do CO11N for the operation with the auto GR control key. See that it is received in the desired Sloc..

  • Two different tax calculation for same material/plant/vendor key combination

    Hi all,
    My requirement is that in PO client needs two different percentages of calculation of VAT for same plant/vendor/material.
    How can this be incorporated?
    regards,
    vins

    Hi Vinda,
    Can't you use Tax Code in Purchase order and enter as the case may be
    If not, please ellaborate with example
    Thanks
    Nishu

  • How to handle same material number but different condition?

    In our industry(aerospace aftermarket), we can have inventory for one material in different conditions, e.g new, overhauled, scrap, etc. We use batch management and store the condition at the batch level. This probably was not the best way to handle this and now we're wondering how we can run MRP for a specific material, but only for certain conditions.
    From what I understand MRP only occurs at the material level, not the material-condition level. Is my assumption correct? Obviously, we would not want to include scrap inventory in any MRP or forecasting calculations. So if we had 10 for material 1234 in inventory, we'd want to exclude the amount that's scrap or any other condition we don't want to include in a forecast/MRP. 
    Is there a best practice that someone can share to handle this type of inventory management issue? Thanks!

    Hi,
    I've never used this but please have a look at it:
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/c6/126422bd9c11d1b54f0000e82de178/frameset.htm
    Planning startegies for variants:
    This section describes how to plan products that have a practical limited number of possible combinations of characteristics and characteristic values. Technically speaking this section describes the use of variants to sell configurable materials.
    Regards,
    Csaba
    Edited by: Csaba Szommer on Feb 5, 2009 10:46 PM

  • Weight discrepancy per pallet for same material, same qty and same pallet s

    Hi Gurus
    The issue is that in a delivery document only one item line having 75 quantites(it maens same meterial)and that has been packed and in system its showing for few handling units weight is 150 kg and for few handling units its showing as 120kg though the packaging material is same with net weight as 3 kg and one material is packed by one packaging material only so there has 75 handling units in that delivery doc.Can you tell me why this discrenpancy.

    Hi Ram,
    Please check wheather the split valuation is activated  or not for this material.
    if it is activated,
    go to mm03.
    select accouintg view, enter the valuation type ; in your case  BATCH1.
    then you can see the value of this batch material.
    again go to mm03,
    enter second batch in the valuation type.
    you can see the batch2 material value.
    regards
    srinivas

  • Same material with Different qualities

    Dear Experts,
    Please give me the solution for mentioned issue ....
    I have to maintain the same material which has different qualities (grades) and according to these qualities, the material rate is different. i have near about 50 different qualities for the same material and 50 different rates.
    My every vendor is supplying this material for 50 different qualities and rates. So in this case to maintain the individual material prices is big challenge.
    If i will maintain Info records, i have to maintain 200000 info record. and also there is possibility of price change for every three months.
    So please give me any other alternative solution for the problem.

    Hi Vijay,
    Variant Configuration may work in your case. I collected some links, please go thru the links:
    http://help.sap.com/saphelp_47x200/helpdata/en/92/58d455417011d189ec0000e81ddfac/plain.htm
    http://help.sap.com/printdocu/core/Print46c/en/data/pdf/LOVC/LOVC.pdf
    http://sap-img.com/sap-sd/steps-for-sd-variant-configuration.htm
    http://www.slideshare.net/arun_bala1/variant-configuration-overview
    http://www.sap-topjobs.com/VARCONFG%5B1%5D.pdf
    Purchasing:-
    1. MATERIAL MASTER
    Create Material with material type as HALB – Transaction code MM01
    Enter Material code as ZMAL.
    Select the following views – Basic data1, Basic data2, Purchasing, MRP1, Storage1, Storage2, Accounting1, Accounting2, Costing1, Costing2.
    Basic Data1 – Select General Item Category Group as “0002”
    Basic Data2 – Activate the field Material Configurable
    Remaining fields data is as applicable.
    2. VENDOR MASTER
    Create Vendor Master – Transaction code XK01
    Enter Vendor code as ZVEN
    3. Classification Characteristics
    Create Characteristics – Transaction code CT04
    Characteristics created as
    i) ZMALCOLOURRED after entering the description click on the tab Addnl data & then fill up the data in Table name = MMCOM & Field name = VKOND then save the characteristic.
    ii) ZMALCOLOURBLUE enter the description & save the data, do not enter any data on Addnl data tab strip.
    Save the data
    4. Classification
    Create Class as ZMALCLASS – Transaction code CL01
    Class as ZMALCLASS, Class Type as 300
    Assign the above two characteristics ZMALCOLOURRED & ZMALCOLOURBLUE to class ZMALCLASS.
    Save the data
    5. Configuration Profile
    Create Configuration Profile – Transaction code CU41
    Enter the material code as ZMAL,
    on the next screen enter Priority – 10, Profile Name – ZMALPROFILE, Class – 300. Select the line & click on the push button Class Assignment, assign the class ZMALCLASS come back to main screen
    Select the profile line item & click on the “Profile Detail”
    then click on the push button “dependency assignment”
    on the screen input dependency as “ZMALDEPENDANCY” &
    then click on the push button “Dependency editor”
    input the syntax as
    $self.ZMALCOLOURRED = 'RED' IF ZMALCOLOURBLUE = 'BLUE'
    save data
    6. Pricing Procedure ( SPRO )
    Pricing condition types like VA00 - Variants/Quantity & VA01 – Variants % is included in the pricing procedure with following settings
    Sr. No. DATA VA00 CONDITION VA01 CONDITION
    Control Data 1
    Condition Class A A
    Calculate Type C A
    Condition Category O O
    Changes can be made
    Manual Entries C C
    Item Condition Active Active
    Delete Active Active
    Amount / Percent Active Active
    Scales
    Scale Basis C C
    Control Data 2
    Variant Condition Active Active
    Access Sequence Variants Variants
    These conditions will appear in the pricing when variant configuration is made active in vendor Info Record.
    7. Vendor Info Record
    Create Vendor Info record – Transaction code – XK01.
    Input Fields like Vendor, Material, Purchasing Organisation and Plant.
    Click on the push button “ Variant Configuration “ In the pop-up window input the variant condition.
    Select the line & click on push button “ choose “ the pop-up window will display the two condition “VA00 “ & “VA01”, select the relevant condition, click on “choose” then save the data.
    Input all other relevant data for creation of vendor info record
    8. Purchase Order
    Create Purchase Order – Transaction Code – ME21N.
    Input all relevant like Vendor, Material, PO quantity, price etc.
    Select the Material Data tab strip in Item & click on the push button “configuration” the characteristic of variant configuration will appear input the required value,
    Go to the condition tab you will find variant configuration condition has appeared in pricing condition.
    Save the purchase order.
    Reg,
    Ashok

  • How to create Inpection Lot Z01 & 04 Type for same Material different Plans

    I am trying to create an Inspectoin Lot for two different Inspection Types.  One for (Z01) Incoming Inspection via MIGO and the other for (04) GR Inspection for Production via MFBF.  The problem is I have the same Material for two different Inspection Plans.  The Z01 Inspection Type was copies from the 01 Inspection Type only difference is I activated the Multiple Specs feature for Z01.
    1st Plan = Materia Group....BM206014,  Group Counter....1  (GR Incoming Inspectoin Z01 type)
    2nd Plan = Material Group....BM206014,   Group Counter....2    (GR Inspection for Production 04 type)
    A)  When I do the (Material Backflush) MFBF for the 04 type, the Inspection Lot gets created OK.  I then can go into QA32 and assign the correct Inspection Plat by clicking the Inspection Lot button.
    B)  When I do the MIGO via the Purchase Order (type Z01), it will not create the Lot if I have the Multiple Specs selected in the QM Material Master MM02.  If, I turn off the Multiple Specs in the QM Material Master and create a new PO and MIGO, it will create the Lot, however, it automatically assigns the lot to the wrong Inspection Plan (2nd Plan see above)  I need to be able to select the plan like I can with the 04 type.
    Is their some setting that can be changed in Config or somewhere that acts the same way as example A above?

    >
    dhayes12 wrote:
    > A)  When I do the (Material Backflush) MFBF for the 04 type, the Inspection Lot gets created OK.  I then can go into QA32 and assign the correct Inspection Plat by clicking the Inspection Lot button.
    >
    > B)  When I do the MIGO via the Purchase Order (type Z01), it will not create the Lot if I have the Multiple Specs selected in the QM Material Master MM02.  If, I turn off the Multiple Specs in the QM Material Master and create a new PO and MIGO, it will create the Lot, however, it automatically assigns the lot to the wrong Inspection Plan (2nd Plan see above)  I need to be able to select the plan like I can with the 04 type.
    >
    > Is their some setting that can be changed in Config or somewhere that acts the same way as example A above?
    For case A, create insp plan with usage "1- production" If you have one IP with this usage for given material then system will assign Plan to lot automatically. In your case for second plan update usage as 1.
    For case B, system should assign 1st plan make sure for both plan udage is correct. for 1st plan usage should be 5 while 2nd plan usage should be 1. Now if your 1st have status 4 and key date before lot date then system will assign plan auto.
    Thanks!!!

  • Single planned order for different sales order of same material

    hi frnds
    my client want that if there is two  or more sales order of same material in a specific period than he require single planned order during mrp run for that material or when if he enter same material in two different line in single sales order than mrp doesnt considered it line item aand produce single planned order for both sales order
    please help me out its very urgent
    thanks

    Hi,
    In Mrp 3 view set the availability check as 01 and in Mrp 1 view
    Keep the lot size as periodic lot size and try the same.
    Thanks,
    S.Nandhakumar

  • How to restrict the entry of same material twice on the order

    HI,
    How to restrict the entry of same material twice on the order before saving the Order ?
    I do not want my users to enter the same material as two different line items in the order.
    Any inputs wud b appreciated

    Hi Vam,
    For this you need to take the help of an ABAPer . Ask him to modify the user exit and add the logic.
    For user exit please go through the below link it will help you to resolve your issue.
    http://help.sap.com/saphelp_46c/helpdata/en/1c/f62c7dd435d1118b3f0060b03ca329/content.htm
    Regards,
    Krishna O
    Edited by: Krishna O on Jun 3, 2010 12:29 PM

  • Same material in diff material type

    Can we maintain the same material in two different mat types, In my client case same material they want to maintain in two mat types.
    Ex : If the purchase qty of steel is 20 tonnes, they will treat it as Capital &
    if it is 1 tonne or few kgs, they will treat it as consumables.
    If we cant maintain, then what i need to do ? pls help me out
    B/regds,
    CB

    Hi,
    For your questiton : - If we cant maintain, then what i need to do ? pls help me out
    Answer: - Create two different material code for same material one for counsaption and second is for non counsaption.
    Otherwise create single material code and prepaid both type of transaction on single material code.
    Regards,
    Mahesh Wagh

  • Split valuation for  material with two different price indicator S and V

    Hello Gurus,
    Is it possible to maintain split valuation for same material with two different price indicator S and V.
    For Ex. Material A is manufactured can be manufactured in house ,  procured from outside vendor and can be purchased from subcontracting vendor by providing raw material.
    We want to keep  Price control V for same material " A"  which is procured from outside vendor.
    And price control S for inhouse produced same material " A".
    Besically this material is semifinished and having BOM for subcontracting.
    Please advice.

    Hi
    When the material is split valuated, you maintain the accounting view for the material 1st with valuation category, here the price control should be V.
    When you will extend the material to valuation type "Inhouse mfgd" maintain the price control as S, for valuation type "Procured form outside vendor" maintain it as V.
    Regards
    Prasad

  • Material group in material master for different plants

    Warm greetings Masters of Material Management
    We have one material master for three different plants example  1000, 2000 &3000 with same material group  with different valuation class
    If we change material group in plant 2000 it is reflected in 1000 & in 3000
    My question is  this the standard practice that material group changed in one plant will be reflected in other plants
    Regards
    shamul heq

    Thank u Amola  
    The current situation, if user change  material group for plant 2000, it is effected in plant 1000 & in 3000
    the impact of this is in purchase requisition
    As the release statergy  is triggered from material group    to different department
    How can we solve this issue
    regards
    shamul heq

  • One material extention to different sales areas and Act .***.grps?

    Hi,
    I have one material for which i need to extend the material to different distribution channels,divisions and account assignment groups in this case can i extend one material to different sales areas as mentioned above or i need to create one more material with same material master data except the sales view data?
    thanks.

    I have extended the same material to 2 different distribution channels and divisions but when iam checking in display view of MM for different distribution channels divions should be different as i have given divisions also different but in my case the last saved division only appearing for both different distribution channels.
    Second thing in MVKE table iam not able to find the division field(SPART)?
    Is iam missing any setting?
    Thanks!

Maybe you are looking for

  • Auto Clear History/Start in Private Browsing?

    I have been using Firefox, but with the release of Lion it just does not look as good as Safari. The full screen mode and scroll bars are much more appealing in the Safari browser, so I am considering switching. My only hitch is that I am unsure of h

  • Multiple RMI servers in single JVM

    Hi, I have a RMI server listening to requests from internal network as well as external network. RMI returns the hostname as part of the stub. So to ensure that the subsequent RMI calls work fine I need to ensure that jama.rmi.hostname is set to corr

  • H:outputText value="#{bean.something}"

    Hello togehter! I want to get all the outputtexts from a bean. (I want to offer to change the language.) The problem is for my header.jsp and footer.jsp it doesn't work. It just shows nothing. I have the same code (h:outputText value="#{bean.somethin

  • Is it bad to use a non apple charger to charge my macbook air?

    I just ordered a replacement charger on eBay and realized that it was a non apple charger, is it bad to still use it?

  • Adjust resolution in parallels

    I have parallels on macbook when i go into windows the desk top looks acceptable but when i open internet explorer the web page is huge that you have to scroll back and forth to view. intially the desk top was so small unable to read so when I got th