Subcontracting with external service / non-stock material

Hi,
I have a scenarion in subcontracting when i provided the components / raw materials to the in-house workshop (workshop treated as an internal vendor) and further more our workshop required some external services / non-stok material from third party... now how i will incured this service / non-stock material cost on finished product.
(PP moudule is not implemented on project)
Regards,
Ali

Hi,
Please refer the following links ..it may help you...
Subcontracting service to a FERT material.
http://books.google.co.in/books?id=LDyarcerUu0C&pg=PA571&lpg=PA571&dq=Subcontractingwithexternalservice/non-stockmaterialinsap+mm&source=bl&ots=vj5kUO9dto&sig=vrlCpSZ0-V0BseN96Qw9rTVhsQ0&hl=en&ei=cJKRTs5_0MmsB6rrgIsB&sa=X&oi=book_result&ct=result&resnum=10&ved=0CG4Q6AEwCQ#v=onepage&q&f=false
Regards,
Udaya

Similar Messages

  • Plant Maintenanc External Service Requirement & stock material combination

    Hi Experts,
    We are implementing SAP Plant maintenance. In the external service requirement, the requirement is that there are some stock items which should be send to vendor with this service item. These items will be used in the service item for repairing the same.
    I have created maintenance order with control key PM03 and by this we are selecting the service from service master. In this way we are creating the service pr but we are unable to put the material in that maintenance order which will be sent for this service item. If we are putting this material in component tab, a reservation is created with 261 movement which is not solving our purpose.
    Please suggest me how to move forward on this issue.
    Thanks in advance.
    VT

    Thanks for your reply,
    But I am creating service PR through selecting the check box for sub contracting. After that I am putting material against Operation of External service. Reservation is generated for 543 movement but not allow to save and giving error message "Op. 0010 must have exactly one component as 'Rework Material to Subcontr.'"
    Please suggest what should we do ?
    Thanks
    VT

  • Non-stock material and service material

    What is
    1) The difference between non-stock material and service material? and
    2) The difference between text material and service material?
    Give the example and how to configure it into sap.

    hi
    1) The difference between non-stock material and service material?
    1.A.  non stoc material goes with NLAG Eg: Office supplies such as stationary & service materials goes with DIEN material type
    2) The difference between text material and service material?
    2.A. there is no any text material as a seperate master data in MMR &  DIEN (services).
    please chec the sap liabrary in it SAP has explained it very well.
    regards
    balajia.
    Edited by: balaji timmampalli achari on Nov 14, 2010 3:10 PM

  • PP-MM-FI integration for Non-Stock material consumption

    The client is expecting a simple solution for a Std SAP process which is LIKE subcontracting....but actually not.
    The requirement is to set up a process of external operations using a NonStock (NLAG) material ( which will have no physical stock updation when GR is done). This material is a part of BOM with item category N. The material will have S price control. ( Must from business requirements). PR gets created from process order --> converted to PO --> then 101 and simultaneous automatic consumption gets debited to order. (with a price = PO price). PO has a account assignment F and item category blank Standard).
    Question - This behaviour is not desired. The "Std cost" should be used in posting a consumption posting..& the rest ( PO price less Std price) should be shown as purchase price variance in a different acount. How to customise this break up ? Is there way in MM pricing conditions or something else ?.
    Pl note that there is no stock entry...only consumption will be debited with GR offset at PO price. Also at invoice verification, the price if different should be posted to price difference account ( which is not assigned to process order...it is directly going to COPA).
    Might be a very simple SAP solutions / answers from MM /PP......so that we avoid the ABAP development for reposting..
    Could somebody help pls ?
    Regards
    Ram

    Hi,
    Since Material is Non-Stock Material so it is must to maintain the Account Assignment Category in PR or PO for this Material. And once you maintain the Account Assignment Category in PO and do GR w.r.t. this PO then it will not consider the Material Master Price (Standard Price) since there is not any Stock Account Entry during GR, it will hit the Expense Account. And Price Difference Account will get debited only if Stock Account will come in picture.
    So following Accounting Entry will get generated;
    During GR (MIGO);
    Expense Account - Dr
    GR/IR Clearing A/c - Cr
    During LIV (MIRO);
    Vendor Account - Cr
    GR/IR Clearing A/c - Dr

  • PS subcontracting with external activity

    Hi,
    I have a couple of questions about "PS subcontracting with external activity" I have not found any information about this for PS subcon flow, I was looking for a subcon PS Wiki but no succeed.
    The scenario is to use a  external activity to a subcontractor and put the material components to deliver in the  external activity and check the subcon check box. Then use the valuated project stock for holding the materials.
    For material components there is an option in tab "Proc. Param" and fiel "Mat. Prov. Ind." = "Material Provision Indicator", do you know if this option can be use or be available in PS? This field is grey so I can not do anything with it, so my guess is that option use only by a BOM, could you confirm that for me?
    Right now I have a problem in the system so I can not save a project when creating a external activity and use the subcon check box, this is at OSS right now. But I was wondering if I put the material components in a external activity, how will it be represented in the PO?
    Will it be only one item in the PO, the service from the external activity? and inside this item will hold all my material components? this can be found in tab "Material data" -> "Components".
    Please share if you have some information about this,
    Regards
    Jose
    PS Note that this scenario is not a MM subcon

    abdul,
    I'm talking what you can do in the system, there is 3 posibilities I have in mind:
    Alternative 1 
    Is when I will send all the parts, thats right separated parts to be one. The material which will be the final material, is not in my stock/company. It is a new material Im manufacturing with the help of a subcontractor.
    In PS I want to create a subcontracting external activity, create a PR from PS, create a PO and deliver it to the receiver in other words the subcontractor who will put it together to the final material.
    For this alternative I think I have to create the material which the subcontractor will put together and have it as a head material in a BOM. The BOM will represent the parts Im sending for assembly, so when the material is deliver back to me, I will do a goods receipt of the head material.
    My question is in this if I have thought this right, if you have experience of this please contact me.
    Alternative 2
    Is when I will send a existing material and all the parts which will be use to maintain/repair this particular material from my stock/company to a subcontractor who will do the work. This material will have the same material no. when I do the goods receipt.
    In PS I want to create a subcontracting external activity, create a PR from PS, create a PO and deliver it to the receiver in other words the subcontractor who will maintain/repair the material.
    For this alternative I think I can use a BOM, create a BOM of this existing material which will be maintain/repair with the parts I will send.
    My question is in this if I have thought this right, if you have experience of this please contact me.
    Alternative 3
    This alternative is almost the same as alternative 2 with the exception that the material Im sending will change the material no when its back from the subcontractor. So I will send a existing material and all the parts which will be use to maintain/repair this particular material from my stock/company to a subcontractor who will do the work. This material will get a new material no. when I do the goods receipt.
    In PS I want to create a subcontracting external activity, create a PR from PS, create a PO and deliver it to the receiver in other words the subcontractor who will maintain/repair the material.
    For this alternative I think I can use a BOM, create a BOM of this existing material which will be maintain/repair with the parts I will send. Then I have to put the new material in my external activity as a material component with negative quantity as part of the subcontracting delivery
    My question is in this if I have thought this right, if you have experience of this please contact me.
    I hope my question is now clear for you, we are using the defence and aero solution so what I know I do can use the subcontracting with valuated project stock

  • Unit Cost of non stock material - Hubwoo Catalogue

    Hi Team,
    There is one requirement to transfer the the cost of matrial from SAP PM to ArcFM. Here the materials are assigned to the operations in the PM order. Here we want to transfer the service cost and material cost of the particular operation to the ArcFM ( ie an external design tool) to estmate the total cost involved for the particular operation.
    Here the unit cost of the stock material can be get from the material master. But for nonstock material, a hubwoo catalogue is maitained. How do we get the unit cost for the this material?
    There is an interfece we have to develop to transfer the service cost and material cost from the SAP to ArcFM. Hence we have to get the unit cost of the non stock material here.
    Thanks in advance.
    Regards,
    Shyjith

    Hi,
    Yes, you are right but in material master price is not updating, many times I have been assigned the same material as a non stock and at every time I have maintained the planned price on order level but it is still maintained as "0" value in material master,
    what is the standard process?
    what settings need to be made to get automatically planned price or last purchased price for a non stock material?

  • In case of Non Stock Material - Different GL for projects from WRX

    Hi Gurus,
    While doing MIGO for non stock material in case of projects, system is crediting account from WRX in OBYC with blank valuation class. but how can we give different GL for projects in this case.
    Please revert asap.
    Thank you

    >
    sapmm99 wrote:
    > For non valuated material, material  master is required or?
    >
    > As per my knowledge material master is mandatory only for stock materials. not for not valuated and non stock materials usually we never maintain master data for non stock and non valuated materials
    >
    > if i am wrong please advise me
    Its upto you if you want maintain material master record or not for non valuated material. With material master you have a material code to input in the field of PO, without material master you put in short text.

  • During creation of NON stock material PO from where system will pick price

    Hello All,
    While creating PO for non stock material from where system will pick the price?
    If info record is there from where it will pick, if info record is not there then from where it will pick like that...
    If existing PO is there or not
    if existing contract is there or not
    For non stock material should we maintain the material master or ?
    Please advise me
    Thanks in advance

    >
    sapmm99 wrote:
    > For non valuated material, material  master is required or?
    >
    > As per my knowledge material master is mandatory only for stock materials. not for not valuated and non stock materials usually we never maintain master data for non stock and non valuated materials
    >
    > if i am wrong please advise me
    Its upto you if you want maintain material master record or not for non valuated material. With material master you have a material code to input in the field of PO, without material master you put in short text.

  • Automatic PR to PO conversion for non stock material

    Hi,
    Can  Automatic PR to PO conversion be done for non stock material (with account assignment category and no material master).
    We are presently doing only for stock material with transaction ME59N.
    Thanks and Regards,
    Pratap

    Some of the pre-requisites for automatic generation of PO from PR are
    1. The system selects only those requisitions for automatic PO generation for which the indicator Automatic purchase order has been set for both the material and the vendor.
    2. It can only generate purchase orders from requisitions to which a unique source of supply has already been assigned.
    So material master is mandatory if you want to create PO automatically from PR and you need to activate this option both at vendor and material master.

  • Purchase of non stock material

    Hello MM experts,
    We use the non stock material type for material we purchase on cost centers. Those materials do not have any price in the master data because they are generic. For example, we have one material code for office furnitures.
    Now we want to use the RFQ functionnality after a PR is created but we can't link the RFQ price wihout updating PIR.
    For example, i have to PR with different RFQ price
                     material nb      description               long text    qty                      RFQ                price
    PR 1        123456            office furniture           chair         1                           11                  50
    PR 2        123456            office furniture           desk         1                           12                  100
    Is it possible to link a RFQ to a PR without maitaining a PIR?
    Is it the right way to purchase generic materials?
    Thanks a lot

    I didn't know that to link a RFQ to a PR and a PO, you have to select the RFQ in tcode me21n.
    You can create a PR with reference to RFQ or create a RFQ with reference to PR. Usually it's PR - RFQ - PO. If you create a RFQ and maintain the quotation through ME47. Now if you create a PO with reference to RFQ, system will automatically pick the price to PO even without inforecord. you enter the RFQ number in ME21N item overview tab. or with the help of document overview.
    Do you know why when a RFQ is pending for a PR, the PR is still available for PO conversion in me21n ?
    RFQ - PR - PO is not a regular process either it's not a invalid process. Usually it's PR( this is where the demand created) and the PR is converted into PO if we know the vendor already and if we dont know the vendor we create RFQ. RFQ is just aid to get the quotation and I dont see logic to restrict the creation of PO. Only restriction you can make is.. restrict PO without reference to PR or RFQ through OMET

  • Using a Non-valuated, non-stock material in an STO

    Created a planning material with UNBW material type in ECC 6 to use to help manage shipping capacity at the mill.  Added to a sales order and it decremented the plan as expected.
    Half of the mill's deliveries are STO's so now trying to get this to work on an STO.
    Does anybody have advice on how to get a non-valuated, non-stock material (ideally, a planning material, but we could work around this) that we don't plan to deliver, to work on an STO?

    Thx for replying.  I need the material to be accepted by the STO but also to work with planning so it decrements a planned shipping capacity for the mill.  So I am trying to figure out how to get it on the STO and be differentiated from other, normal materials that have $ value, inventory, and account assignment,  This material will only have a planned quantity that can be decremented by demand coming from either sales orders or STO's.

  • Serial number for non stock material

    Hello,
    I would like to create a serial number for a non stock material  (material type NLAG) (PO with account assignment catergory K) and I receive the following error message during the goods receipt (transaction MIGO) :
    *Movement type 101 does not currently support serial number management*
    *Message no. IO306*
    *Diagnosis*
    **With the help of * under the business operation, the entry in table T156S used here under movement type 101 defines that no serial numbers are supported here.**
    *System Response*
    *Termination of the transaction called up.*
    Is there somebody who can help me with this problem please ?
    Thanks a lot in advance for your help.
    Kind regards,

    Hi,
    I'm not familiar with Serial Number Management but I guess you can apply it only to materials with stock.
    http://help.sap.com/saphelp_47x200/helpdata/en/dd/f8c814b3f911d1896e0000e8284931/frameset.htm
    (no non-stock materials are mentioned...)
    BR
    Csaba

  • Moving Average Price for non stock material

    Hi All,
    We are looking at loading a large number of material masters for items that will not be stocked - i.e. an account assignment will always be provided during purchasing.
    When we load these materials - what should the moving average price on the accounting tab be set to? If we put an estimated price in - then when we purchase we will get a warning if the variance between the purchase price and the moving average price is too great. And then when the material changes in price (in lets say a year because the vendor has increased prices by 10%) we can no longer update the moving average price.
    What is the best practice in this scenario?
    Kind Regards,

    non stock material (standard material type NLAG) does in general not have accounting views, hence it has no fields for moving average prices.
    however it can be customized to have an accounting view, we did it too. This  servers the requisition process, with accounting view the price defaults to the requisition. without accouting view, the valuation price needs to be entered manually by a user in the requisition.
    The MAP gets only updated if the stock is posted to inventory, which will never be the case for non-stock material, because of this you should always be able to change the MAP directly in the material master with MM02, or if not possible in MM02 with MR21.

  • Non Stock Material related

    Hi
    In our company we do not create masterial master of Non Stock Material. If I create Sales Order for suppose 20 chairs, it doesnt pick pricing procedure. More over the quantity field also goes blank every time the order is created.Can i also create invoice for this. Pleasae guide.

    why pricing procedure is not determining when its maintained in OVKK for this document type,customer and sales area?
    - Sales Area (determines from Sold-to Party Sales Area)
    - Documnet Pricing Procedure (determines from Sales Doc Type in VOV8)
    - Customer Pricing Procedure (Customer Master - Sold--to Party - Sales Tab)
    whether we can run a sales cycle for a material with no Material Master
    No, we can't run a SD process cycle for Non Stock Material without Material Master.
    If you want to have SD process cycle without creating Materaial master then you can use Text item (TATX)
    Normally, we don't create a material master these kind of item.
    So, if you enter a material in the Sales Order just with description without giving the material number, then system will determine material with Text item (TATX)
    Make sure the system have following kind of item cat determination for Item Cat TATX for your order type in VOV4
    Sales Doct Type
    Item Cat Group
    Usage
    High level Item
    OR
    <blank>
    TEXT
    <blank>
    Regards
    JP

  • Non stock material info record

    Hi SAPERS,
    Please let me know the difference between the stock material and non stock material info records, Is there any difference in creation of both records.
    Thanks in Advance,
    D Prasad

    Hi,
      When the IDoc for purchasing info records of a stock material is posted, if the purchasing info record for the material and the appropriate supplier does not already exist in the receiver system, the number of the purchasing info record is copied from the central system. Otherwise, the existing purchasing info record is updated.
    ·        For purchasing info records for non-stock materials, the purchasing info record number is always copied from the central system. If a purchasing info record with the same number already exists, the system checks whether it has the same supplier and material group as the info record from the central system.
    Regards,
    Pardeep Malik

Maybe you are looking for