Subcontracting with PP /PS

question 1: we have project stock in store and we issue the raw material (project stock) to production .so 1st operation is done in house and now for the second operation we are sending the material to subcontractor for machining but the problem is same material is sent and received back and since the stock is already issue to production the current stock in MMBE is zero.
however i need to issue the child material that is raw material to vendor from MB1B but the quantity is already consumbed by production order in first operation . Please advise the solution.
question 2: I am not able to issuse the project stock material to subcontractor in MB1b since a material cannot fall in two special stock category.
i have found a link to use 311 Q movement type to solve the issue. but please advise if any other solution is there
all child componenet are excisable.
Question 3: can we mention the assesable value of material in 57 F4 challan .
question 4:  some child component is sent to subcontractor and same are recieved back along with finished product.
they are not consumed in process . advise how to adress in sap.
question 5: we receive finished material from subcontractor but in side company we splitt the material in componenets in certain cases . please advise how to increase the stock of componenet and reduce the stock of parent material.

HI,
question 1: we have project stock in store and we issue the raw material (project stock) to production .so 1st operation is done in house and now for the second operation we are sending the material to subcontractor for machining but the problem is same material is sent and received back and since the stock is already issue to production the current stock in MMBE is zero.
however i need to issue the child material that is raw material to vendor from MB1B but the quantity is already consumbed by production order in first operation . Please advise the solution.
Please take your semifinieshed material in stock like we did for finished material which we take in stock and then sale to customer take PP help for same
question 2: I am not able to issuse the project stock material to subcontractor in MB1b since a material cannot fall in two special stock category.
i have found a link to use 311 Q movement type to solve the issue. but please advise if any other solution is there
all child component are excisable
It is not possible to send special stock to vendor,you have to move your special stock to unrestricted stock first then you can send it to vendor ,transporting from project stock to unrestricted
check following link
[Movement Type 411 and 412;
Regards
Kailas Ugale

Similar Messages

  • PS subcontracting with external activity

    Hi,
    I have a couple of questions about "PS subcontracting with external activity" I have not found any information about this for PS subcon flow, I was looking for a subcon PS Wiki but no succeed.
    The scenario is to use a  external activity to a subcontractor and put the material components to deliver in the  external activity and check the subcon check box. Then use the valuated project stock for holding the materials.
    For material components there is an option in tab "Proc. Param" and fiel "Mat. Prov. Ind." = "Material Provision Indicator", do you know if this option can be use or be available in PS? This field is grey so I can not do anything with it, so my guess is that option use only by a BOM, could you confirm that for me?
    Right now I have a problem in the system so I can not save a project when creating a external activity and use the subcon check box, this is at OSS right now. But I was wondering if I put the material components in a external activity, how will it be represented in the PO?
    Will it be only one item in the PO, the service from the external activity? and inside this item will hold all my material components? this can be found in tab "Material data" -> "Components".
    Please share if you have some information about this,
    Regards
    Jose
    PS Note that this scenario is not a MM subcon

    abdul,
    I'm talking what you can do in the system, there is 3 posibilities I have in mind:
    Alternative 1 
    Is when I will send all the parts, thats right separated parts to be one. The material which will be the final material, is not in my stock/company. It is a new material Im manufacturing with the help of a subcontractor.
    In PS I want to create a subcontracting external activity, create a PR from PS, create a PO and deliver it to the receiver in other words the subcontractor who will put it together to the final material.
    For this alternative I think I have to create the material which the subcontractor will put together and have it as a head material in a BOM. The BOM will represent the parts Im sending for assembly, so when the material is deliver back to me, I will do a goods receipt of the head material.
    My question is in this if I have thought this right, if you have experience of this please contact me.
    Alternative 2
    Is when I will send a existing material and all the parts which will be use to maintain/repair this particular material from my stock/company to a subcontractor who will do the work. This material will have the same material no. when I do the goods receipt.
    In PS I want to create a subcontracting external activity, create a PR from PS, create a PO and deliver it to the receiver in other words the subcontractor who will maintain/repair the material.
    For this alternative I think I can use a BOM, create a BOM of this existing material which will be maintain/repair with the parts I will send.
    My question is in this if I have thought this right, if you have experience of this please contact me.
    Alternative 3
    This alternative is almost the same as alternative 2 with the exception that the material Im sending will change the material no when its back from the subcontractor. So I will send a existing material and all the parts which will be use to maintain/repair this particular material from my stock/company to a subcontractor who will do the work. This material will get a new material no. when I do the goods receipt.
    In PS I want to create a subcontracting external activity, create a PR from PS, create a PO and deliver it to the receiver in other words the subcontractor who will maintain/repair the material.
    For this alternative I think I can use a BOM, create a BOM of this existing material which will be maintain/repair with the parts I will send. Then I have to put the new material in my external activity as a material component with negative quantity as part of the subcontracting delivery
    My question is in this if I have thought this right, if you have experience of this please contact me.
    I hope my question is now clear for you, we are using the defence and aero solution so what I know I do can use the subcontracting with valuated project stock

  • J1IS in subcontracting with full payment of excise duty

    hi
    Can u tell me please
    In subcontracting with full payment of excise duty I have created PO,sent material to stock provided to vendor (541).while creating outgoing excise invoice with referance to material doc.(MATD)
    i am getting following error.
    GL account has not been assigned for MSUSP in customization
    Message no. 8I447
    Diagnosis
          GL account has not been assigned for the excise a/c in customization
    I am not getting where to assign G/L
    Reg
    Roc

    hi
    please check this customization setting
    Logistics - General --> Tax on Goods Movements --> India -->Account Determination
    Specify Excise Accounts per Excise Transaction &
    Specify G/L Accounts per Excise Transaction

  • Subcontracting with full payment of excise duty

    Hello friends,
    Can u plz give the complete configuration details for setting up Subcontracting with full payment of excise duty, Cenvat, Edcess.
    Purushotham

    Hi,
    Process Flow for Sub contracting with Excise duty
    1)The purchasing clerk creates a subcontract order for the subcontractor’s srvices.
    2)The warehouseman creates a transfer posting for the materials that you want to send to the subcontractor.
    3)The excise clerk creates an outgoing excise invoice for the materials.
    4)You send the materials to the subcontractor, together with the excise invoice.
    5)The subcontractor processes the materials and returns them to you, together with another excise invoice.
    6)The excise clerk captures the subcontractor’s excise invoice, using the purchase order as the reference document.
    7)The warehouseman enters the goods receipt.
    8)The excise supervisor posts excise invoice.
    The accounts payable clerk posts the subcontractor’s invoice.
    For this one only u require Account dtermination for ETT for OTHER in Logistic general-Tax on goods movement-India-Account determianation.
    Raghu

  • Subcontract with full payment of excise duty

    hi gurus
    Can any one provide me itutor link of subcontract with full payment of excise duty,import cycle,import under custom bonded ware house
    Thanks in advance
    Roc

    hi
    This is a subcontracting under full payment of duty scenario.
    Refer this link
    http://help.sap.com/saphelp_erp60_sp/helpdata/en/09/ebf138cdd78a4be10000000a114084/frameset.htm
    Subcontracting Under Full Payment of Duty
    Purpose
    This procedure illustrates how you use the system to send materials to your subcontractors for processing using normal excise invoices.
    Prerequisites
    You have created a condition type for manually entering excise duty in the subcontract order. In the standard system, you can use condition type JEXC, maintain in pricing procedure.
    Process Flow...
    1. Create a
    tract order for the subcontractoru2019s services.Enter excise manually in the condition type JEXC & take a tax code for VAT calculation.
    2. Do the transfer posting for the materials that you want to send to the subcontractor.
    3. Create an outgoing excise invoice for the materials by J1IS & J1IV.
    4. You send the materials to the subcontractor, together with the excise invoice.
    5. The subcontractor processes the materials and returns them to you, together with another excise invoice.
    6. Captures the subcontractoru2019s excise invoice, using the purchase order as the reference document.
    7. Do the goods receipt & refer excise invoice in excsie tab.
    8. Posts excise invoice.
    9. The accounts payable clerk posts the subcontractoru2019s invoice.
    for imports
    Import scenario
    To map Import procedure into SAP , follow the following steps :
    1.Create material master of import goods.
    2.Create vendor master record of import vendor and Customs clearing vendor.
    3.Maintain CIN settings.
    4.Maintain J1id.
    5.Maintain Pricing procedure SAP standard JIMPOR..,maintain required conditions..JCDB,JCV1...
    6.Assign the schema to respective import vendor in Purchasing view of VMR.
    7.Create import PO ,check in conditions of JCDB, JCV1 the customs clearing vendor(Indian vendor) and percentage is assigned..This can be done by In condition tab select condtion then click on display,then enter.
    Save the PO.
    8.MIRO --Capture Bill Of Entry.(Commercial Invoice No.,).Customs clearing first .Here CVD will b converted to BED.
    9.Capture Excisse invoice--j1iex.
    10.MIGO.
    12.Post Excise Invoice.
    13.MIRO...Payment to vendor(import vendor)
    http://help.sap.com/erp2005_ehp_01/helpdata/en/95/3ca40a110511d4b5ae006094b9ec21/frameset.htm
    regards
    kunal
    award if helpful

  • Subcontracting with pay of Excise Duty

    Dear All,
    In Subcontracting with pay of Excise Duty,
    How much % i have to maintain in Condition Type JEXC & how could i get the accounting entry mention below in MIGO & Excise flow in BED,ECS & SECS fields.
    CENVAT Input BED - Dr
    CENVAT Input ECS - Dr
    CENVAT Input SECess - Dr
    CENVAT Clearing A/c - Cr
    Plz suggest...........
    Thanks

    Hi,
    Indeed, in subcontracting process u donot need to pay any excise despite the material sending to the vendor is excisable one. Here in this process:
    1. U have to create a subcontract  challan with J1IF01 and take a print out of the challan with j1if13 and send with subcon material.
    2. Transfer the material from our stocks to subcontractor vendor with 541 movement type.
    If the material is not received from  the vendor with in 180 days u have to pay the CENVAT credit amount taken at the time of  purchasing.
    And, u can take the credit again after receiving the material again using J1IFQ.
    If it is of  inventorised excise type, u donot need to think of it as the values r gets added to the material at the the time of purchasing itself.
    Regards,
    Bhuvan

  • Subcontracting with delivery

    Hi,
    Can anybody send me step by step configuration of subcontracting with delivery to my mail id:[email protected]
    The following is my scenario.
    We are sending raw materials to one vendor in batches.And in turn that vendor will send back the finished goods to the company.It is an urgent please.
    Thanks in advance
    kumar
    Message was edited by:
            MANUPATI KUMAR

    Hi,
    First Create BOM in Transaction code: CS01, for your Finished product which you want to procure from the SC Vendor........in items you can give the Raw materials you are providing to SC Vendor.....Very Importanly, for the component you want to send to SC Vendor also should have the Sales view....then only the Shipping point determination and all takes place...
    Then in Transaction code ME11, create Sub Contracting Inforecord
    Then in OLME-->Purchase Order>Set up Sub Contract Order--
    > For your Plant from where you are shipping the material to SC Vendor,  Assign Delivery type LB....
    Then for your Suppling Plant Sales Area, Create one Customer master and in that customer master assign your SC Vendor in General Data->Control Data Tab>In Vendor Field  and In Sales Area Data-.> Shipping Data tab--
    >Maintain entries in  Delivery Priority,Shipping Conditions,Delivering Plant fields.
    Then Create SC Purchase Order with Item catogary "L"....In Item details--->Material Data Tab--
    .>Components,  you can view the details of the material you have to send to SC Vendor.... then save the PO
    Then Goto, Transaction Code, ME2O, choose the component and choose create Delivery....then Delivery no will be created.....then you goto VL02n and do the PGI...The components will be automatically transferred to SC Vendor in  541 movement type...
    After completion of work, you can do GR Normally...
    Hope I have explained in detailed manner
    Reward if useful
    Regards
    S.Baskaran

  • Node missing - subcontracting with chargeable components

    Dear Experts,
    Our system is ERP EHP5 SPS05.
    In SPRO under MM - Inventory Management and Physical Inventory -
    the node Subcontracting with chargeable components is missing
    Please help.
    Thanks.

    Dear Kotakonda,
    In the IMG activity Activation Switch for SAP R/3 Enterprise Extension Set, activate Extension Set
    EA-SCM.
    Then carry out the IMG activities for Subcontracting with Chargeable Components in Customizing for
    Materials Management (MM), by choosing Inventory Management and Physical Inventory ->
    Subcontracting with Chargeable Components.
    See also
    SAP Note 641298
    and link http://help.sap.com/saphelp_47x200/helpdata/en/cb/2f26455c59a046a37e58dc3f1ae85e/Chap_09_MM.pdf
    Hope it helps
    Thanks & Regards,
    Amit Barnawal

  • Subcontracting with chargeable components Node missing

    Dear Experts,
    Our system is ERP EHP5 SPS05.
    In SPRO under MM - Inventory Management and Physical Inventory -
    the node Subcontracting with chargeable components is missing
    Please help.
    Thanks.

    Try Transaction code SCC.
    It will take you to the config for sc with chargable components
    Rajesh

  • Subcontracting with Chargeable Components

    Hi All,
              Please tell me configartion steps of Subcontracting with Chargeable Components.
    what is the business process to map in SAP.
    Regards
    Pavan

    I actually found this one in help.sap.come:
    http://help.sap.com/erp2005_ehp_04/helpdata/DE/15/318debd36f6348ab711dd588f9ec54/frameset.htm

  • Subcontracting with slaes order

    hi i want to know
    how can we do the subcontracting with sales order
    i got a process using 311 e movemnt when i search on SDN
    plz let me know if this process is correct how can i  have subcon challan
    Subcontracting scenario(Sale Order wise)
    Subcontracting For Sales order.
    Subcontract Account assigned PO
    how can i create storage loc as vendor
    plz help
    regards
    raj

    Hi,
    Subcontracting for Project Stock: -
    Purpose: - Subcontracting is also possible in conjunction with Project stocks. The subcontracting orders are account-assigned to a Project. Thus, the components are not transferred (using a transfer posting) to the "stock of material provided to vendor" but are directly withdrawn from the Project stock the time of the goods receipt. The material manufactured is also posted to the Project stock.
    The cost of subcontracting is then debited to the Project.
    Since the components are not transferred to the "stock of material provided to vendor", it is recommended that you use a transfer posting to transfer the provided components to a new storage location (for example, 9999). This enables you to obtain an overview of those stocks that are physically located at the subcontractor. This information is particularly important when you carry out a physical inventory of the Project stocks.
    Features: -
    Withdrawal from Stock of Mat. Provided for Project: -
    For components that are managed in Project stock, you can define whether the components are to be withdrawn directly from each Project or from the stock of material provided to vendor. You manage this via the dependent requirements indicator for individual customer requirements and collective requirements (MARC-SBDKZ).
    You can maintain this indicator in the following places:
    In the MRP view of the material master record (MRP 4)
    In the explosion types for the BOM item (in Customizing for Production in the step Basic Data -> Bill of Material -> Item Data -> Define explosion types)
    Configuring the explosion types has priority over the configuration in Inventory Management.
    If the indicator is set at Collective requirements only (2), the materials are withdrawn from the stock of material provided to vendor. If this indicator is set any other way, the system withdraws materials from Project stock.
    Regarding Subcontracting Challan: -
    Go to OMJJ, select the field "movement type" and press enter
    Enter movement type "311" and double click on "Field selection (Enjoy)" under Dialog Structure on left side.
    here "New Entries" and add field "LIFNR" (Vendor)
    Now in MIGO, at the time of transfer posting of components using movement type "311 Q", specify the vendor code of the Subcontracting PO (i.e. Subcontractor)
    Now create Subcontracting Challan in J1IF01 for material document of 311 Q movement type.
    Also check in SPRO > Logistics - General > Tax on Goods Movements > India > Business Transactions > Subcontracting > Maintain Movement Type Groups > here for Movement Type Group "0001", Movement Type "311 Q" should be maintained.
    Then do GR against PO and refer the Subcontracting Challan here.
    And then do reconciliation in J1IFQ for the GR Document against Subcontracting Challan.
    Also check in SPRO > Logistics - General > Tax on Goods Movements > India > Business Transactions > Subcontracting > Maintain Movement Type Groups > here for Movement Type Group "0002", Movement Type "543 Q" should be maintained.
    Follow the below mentioned process;
    Process Steps: -
    1. OX09 - Create Storage Location as "9999" for Subcontractor Location
    2. MB1B - Do Transfer Posting of material from RM Warehouse to this Storage Location via movement type "311 Q" (Instead of doing 541)
    3. Now go to J1IF01 - here use material document of movement type "311 Q" and create Subcontracting challan. (If required)
    Prerequisite: - In SPRO > Logistics - General > Tax on Goods Movements > India > Business Transactions > Subcontracting > Maintain Movement Type Groups > Here for Movement Type Group "0001" (For issues), maintain movement type "311 Q" also along with 541.
    Rest all, refer subcontracting challan during GR and then reconciliation and completion, etc... will be same as usual.
    Note: - At the time of GR, consume components from storage location "9999" (for 543 movement type)

  • Subcontracting with LE

    Hello,
    Can anybody explain me the reasons of using the subcontracting with LE outbound delivery
    Regards

    HI,
    Check the link
    http://help.sap.com/saphelp_dimp50/helpdata/EN/43/e1ba42e2e0c611e10000000a1550b0/content.htm
    Regards
    KK

  • Subcontracting with mat type UNBW

    hi
    system ask me for the gl acct in one scenario and i want to know why
    scenario is as follows
    this is make to order scenario
    using sales order with job work money
    now i am giving the mat for sub subcontracting  with out price (free)
    mat is unbw fin and raw
    acct assignment E and item cat L
    system now asks me for the gl account
    now my question is why sys asks for the gl account as its a free order

    Hi,
    If you are sending the material for subcontracting with account assignment "E" , G/L account is mandatory even though it is free goods  issue. In Automatic Accoutn determination(AAD) system SAP std configuration.
    Please give the G/L account and proceed.
    (or  )
    please raise a service order
    G.Ganesh Kumar

  • Subcontracting with STO

    Hi all,
    can any body give the details of Subcontracting with STO process. what are the difference to be maintained in the below process.
    1. Intra STo - Sub contracting
    2. Inter STo - Sub contracting
    Thanks in Advance.
    K. Praveen

    Dear Praveen,
    Check the  below link. it will be usefull to u.
    cross company code subcontracting process

  • Subcontracting with chargable items

    Can anybody explain me "what is subcontracting with chargable item?"
    what are its effects after activation?

    Hi Krishna,
    During PO creation for subcontracting, u have to give atleast one item to the vendor in order to get the final product, however there are situation where apart from ur item vendor also uses some of his items in order to manufacture the final product. These items which he uses from his side are chargable items (For which u need to pay, apart from the services rendered from him).

  • Vendor subcontracting with outbound delivery without reference

    Hi Experts,
    please do you know if it is possible to manage subcontracting movement (541) using an Outbound Delivery without reference to any Sales Order nor Purchase Order?
    Can you send me please the detailed description of settings in master data and customizing?
    Thank you very much
    Kind Regards
    Andrea
    Edited by: Andrea on Jul 21, 2008 12:46 PM

    Hi,
    With ME2O, it's necessary to have a subcontracting PO in selection for your materials. From this selection, you have the requirement and the vendor stock for these materials.
    If the stock is negative, you can create a outbound delivery.
    For your information, this outbound delivery is as a delivery without reference. But, with ME2O, it's necessary to have PO in selection.
    Then, another solution is to update vendor stock with MB1B but not connection with LE.
    But, i tried to add item category LBN for LO delivery type.
    But, i have a error message during the GI (message M7 071).
    I'm not on real test environment.
    Can you try ?
    Regards,
    Lionel

Maybe you are looking for

  • How to measure the phase shift using AC analysis?

    Hi, I have a simple RLC circuit consisting of no more than 4 components. If i hook up the network analyser function to the circuit and read the S11 values, i can see a change in the input impedance and a phase shift when i run it across a range of fr

  • Multiple users for the Authentication ?

    Hi Guys, we have multiple users who process their credit card requests through xi and we need to issue certificates which will be unique for every user. where i need to maintain all these certificates and how a particular user is validated when he se

  • Weird.. package does not exist

    I know this is a common question and i searched the forum but nothing there is what I need. First of all I have the 'main' source file under a directory: d:\Model1_SecurityService\ There is a subdirectory securityservice, under which there are severa

  • Apple Web Site Default Icon, Gone..

    Hi There, I seem to have tossed my Apple Web Site Default Icon.. I remember seeing the puff of smoke which means I moved it a little to far, and now I'd like to get it back. You know the one, it looks like an A, or an @ on a spring or something.. Any

  • Home v Office functionality?

    Hi... I have another issue which never was answered when I posted last year... My MBP works fine at home, but at work Mail does not connect, nor can I use MobileMe to update my iWeb website. What is up with the work setup that causes this to happen??