Supply Side Change STO Delivery Date

Hello,
I apologize in advance as I suspect this has been asked somewhere, but the search terms are very generic...
Every implementation I've been at we've had the request to have the delivery date adjusted on STO's to match the actual availability of material in the supplying plant when known.  Using Scheduling Agreements (LP or LU) I can get close to the desired functionality, but it's still not they are looking for. 
Plant 1 orders 1000 EA a week for 10 weeks from Plant 2.
Plant 1 has MRP type P3 non-fixing with time fence, EX lot for lot buckets.
Plant 2 has MRP type P1 auto-fixing w/time fence, EX lot for lot buckets.
Running MRP generates the schedule lines in Plant 1 (source list with '2' in MRP field) which transfer demand to Plant 2 via special proc. key 40.
MRP creates  P. req. in Plant 2 for supply from external vendor
Over time, some of the PO lines from the vendor get pushed out or pulled in.  Using V_V2, we can adjust the deliveries as required, but we'd like to know if adjusting the delivery date on the vendor PO line items in Plant 2 can reschedule the schedule line on the STO/SA from Plant 1 so that their ATP for sales is always as accurate as possible. 
SAP documentation implies that it can do this, but aside from checks on manually created items at the time of creation or change (existing POLI) there seems to be no option to do this, but instead the default requested date remains. 
We're basically asking that the supply side drive the PO LI delivery date instead of the PO demanded date remaining firm. 
I suspect confirmation control may bring some of that functionality, but we'd like to avoid that step of processing if there is a way. 
thank you in advance.

Thanks for the quick reply.  I'm not sure this completely solves the request, but the couple lines near the end on rescheduling infer the results we are looking for, but are not able to produce the results as explained by SAP. ATP works perfectly at creation time or change of the items mentioned, but the schedule line rescheduling seems not to work as expected. 
I'll re-read with my SD team and make sure we're not missing something in the checks. 
thanks again

Similar Messages

  • STO delivery date should not be in weekend.

    Hi expert,
    i just want to make sure the STO delivery date should skip weekend or give a warning message in case it is calcuated based on planned delivery time to be the weekend. Now I know that the calendar in receiving plant configuration can reach this request. but what i concern is, if i change this config, the impact is too big. Does any one have better idea?
    also, it looks like that the calendar in unloading point in ship-to master data doesn't work for this.
    Thanks!

    Dear Srinivas,
    Change the check as follows from
    Check: BKPF-BUDAT>SYST-DATUM
    to
    BKPF-BUDAT <= BKPF-CPUDT
    add  BSEG-KOART = 'K' in prerequisite
    Regards,
    NCC  Talluri

  • STO delivery date and VL10B delivery

    I'm trying to run VL10B to create a delivery for a STO item that is in stock, but no  delivery is created.
    The STO item, however, has a delivery date prior to the current date.  If I change this delivery date on the STO to a future date, the VL10B then picks up the item and creates a Delivery.
    I suspect this is related to an availability check not being performed by VL10B.  Surely I should not have to go back to STO items each time and change the delivery date.  Thoughts??

    Hi Chad
    when you try to create run VL10B, system will check with STO (Purchase Order)  delievry date. If date is falling within Delivery creation date, it will allow you to create.
    regards
    Srinivas

  • User exit or BADI to change the delivery date in ME51N  transaction

    Hi Gurus,
       I need a user exit or a BADI where I can change the delivery date in the item overview  tab for each material. I need to calculate the date according the vendor contact details.
    Please let me know if there is any BADI or a user exit for the same
    Thanks a lot!!!
    Sharath

    quick search for exits/badis: get package name and supply it into se80
    or
    se15
    thanq

  • Changing proposed delivery date in sales order for one specific sales org

    Hi All,
    I want to change proposed delivery date in sales order automatically for one specific sales org only without changing lead time in VOV8.
    For that can I use MV45AFZZ. But it is asking access key to make changes. Is there any other user exit for the same. And how does exactly change it.
    Thanks in advanced.
    Points will be awarded.
    Regards,

    EXIT_SAPFV45E_001 has nothing to do with this - it is meant to update the purchase order from a sales order. It might not even be triggered if the sales order has no link to a purchase order.
    USEREXIT_SAVE_DOCUMENT is not really good for this either, because the delivery date has to be changed before that. If memory serves, it also influences the schedule lines and probably the ATP check and such. I would strongly advise against it. One of the other routines in MV45AFZZ should do just fine, USEREXIT_MOVE_FIELD_TO_VBAK for example.

  • STO Delivery Date is not copy from Allocation Table Site Date

    Hi,
    I have a problem when Stock Transfer Order created based on the Allocation Table, the delivery date is not copy from Allocation Table. E.g. In Allocation Table delivery date is 26.09.2009, but in STO delivery date is 06.11.2009.
    Check the configuration and also check the stock, there is stock available to be delivered on 26.09.2009.
    Can someone please give me a hint to find out what is missing or wrong, and how to fixed this?
    Greatly appreciate for your suggestion and sharing.
    Kind Regards,
    2tea

    I found the problem finally.

  • How to cancel the second ATP after changing the delivery date in the SO

    Hello,
    our solution creates automaticly a production order accorting to sales order.
    The system calcule ATP for each items at the creation of the sale order.
    Sometime, we change the delivery date on the scheduled line and SAP do another ATP. If the composants are not available we get an TSUP status on the order production.
    How can we cancel the second ATP ?
    Is it possible to cancel it when we change delivery date ?
    Thanks
    Regards
    Pierre

    I think its not possible to skip the atp during change of the sales order.  All these determinations will trigger before saving the order
    regards,
    Ramana

  • MRP for STO Delivery Date Issue

    Dear Gurus,
    We are using MRP to generate STO purchase requisition for a specific material.
    We have entered planned delivery time in the receiving plant. The supplying plant is 1000 and receiving plant is 2000.
    We have entered planned delivery time in plant 2000 for 10 days . MRP is run at mid night. System is generating PR . But the delivery date is same as current date.
    E.G: Material A planned delivery time 10 days in plant 2000
    Planning date is 20/07/2014
    in PR : Delivery date is 29/7/2014
    and PR release date is 19/7/2014.
    The release date is appearing in the past. Kindly help me to resolve this issue.
    Thanks in Advance.
    Sreedhar

    Hi Dev,
    When i create STO PR manually all the dates are appearing as per standard calculation considering the planned delivery cost.
    The issue is in MRP run.
    Thanks & Regards,
    Sreedhar

  • Changing Required Delivery Date to the Existing Purchase Order date In VA01

    Hi All
        My requirement is while creating a sales order I want to know Is there any exit to move the PO date in Header details of VA01 to the Req Delivery Date in Sales tab or change the Req. Delivery date to the existing PO date in sales tab of VA01. And also please note that it should be triggered on save of VA01 transaction.
    Thanks in advance
    Shivakumar

    hi
    Hope this helps
    DTRM001            Reschedule schedule lines without a new ATP check
    45A0001            Determine alternative materials for product selection
    45A0002            Predefine sold-to party in sales document
    45A0003            Collector for customer function modulpool MV45A
    45A0004            Copy packing proposal
    45E0001            Update the purchase order from the sales order
    45E0002            Data transfer in procurement elements (PRreq., assembly)
    45L0001            SD component supplier processing (customer enhancements)
    45P0001            SD customer function for cross-company code sales
    45S0001            Update sales document from configuration
    45S0003            MRP-relevance for incomplete configuration
    45S0004            Effectivity type in sales order
    45W0001            SD Service Management: Forward Contract Data to Item
    46H0001            SD Customer functions for resource-related billing
    60F0001            SD Billing plan (customer enhancement) diff. to billing plan
    Regards
    Atul

  • STO Delivery date

    Hi,
    I have issue in STO as below,
    Stock transport orders - when you create a delivery on a Stock Transport Order the date on the delivery becomes the date the Stock Transport Order is due to arrive at the receiving plant.  This is creating issues for planning.  Example:  STO 1234 has a receipt date of 7/10/07 and the Rel Order (demand side) has a ship date of 6/31/07.  When you create the delivery the date on the delivery becomes 7/10/07. 
    Thanks in advance,
    Suresh

    Hi Suresh,
    Did you solve this issue? 
    How did you solve it?
    Best Regards
    -Italo

  • Unable to change requested delivery date in the sales order at item level.

    The issue is when I create order with one material (linked to network and project is created automatically in the background), I am able to change (in change mode) req delivery date for an item, but when I create order with 2 materials (linked to network and project is created automatically in the background), I can not change (in change mode) the req delivery date of any item. Req delivery date is then copied from the header req delivery date.
    Is this a standard SAP functionality or a defect?

    Req del date is the date requested by customer and  can be changed at item level. Probably the confirmed date in the schedule line is derived from the network scheduling after ATP check. (ATP check is not activated in this case)
    I am able to change the req del date at item level if there is only one item (Linked to network) and not when there are two line items (Both are linked to 2 diff networks belonging to same project)
    I tried to change the date in the network, scheduled and saved but that didnt change the date in the sales order. On the contrary, if I run ATP check, netowrk dates get back to original dates derived from sales order.

  • Pricing after change of delivery date in sales order

    Hi,
      When i change delivery date in a sales order prices are not recalculated automatically .
    I want the prices to be calculated automatically .
    thank you.
    Ashok

    hi,
    i have this problem, can anyone suggest me, is there any user exit or anything relevant for the solution.
    When we attempt to remove the Rejection flag (for any Reason) The system is changing Dates in sales order like Delivery date , Shipping date, GR date  to current date this needs to be stopped and client wants to retain old set of dates when rejection flag is removed
    waiting eagerly for this solution. if you find send me mail to my id [email protected]
    bharadwaj.

  • SID change during system data import

    Hi,
    We are palnning to install a new SAP system with SID PRN by importing the data which was earlier exported from an existing system with SID PRO.
        As the data to be imported belongs to the old system with SID PRO, will the system create any problem when importing the same data to a system with different SID(PRN).
           Please clarify whether do we need to do any additional steps regarding the SID change. Please help in this regard.
    Thanks,
    Abdul

    Hello Abdul,
    No issues. Just make sure you run BDLS after assigning logical system. Otherwise you are bound to face issues with certain kind oof master data.
    Regards.
    Ruchit.

  • InterCompany STO Delivery Date

    I have one Intercompany STO with four line items. Two deliveries are getting created. Transportation Group, receiving plant are same. Delivery date in shipping tab is also same. Delivery date in OBDs are  different. Kindly help.
    Regards,
    Ram.

    Hi,
    When you create the ourbound the delivery, the system checks the existing schedule line under "delviery schedule" tab.  and SD scheduling will recalcualte all date in function SD_SCHEDULING.
    Please check your "delviery schedule" tab, also, please check document http://service.sap.com/sap/support/notes/1469092
    BR

  • How to change proposed delivery data in a SO

    Hi Gems,
        I am new to SD.
    I am creating SO with order type OR.
    The system is proposing Delivery date (and some other date like goods issue date, loading date etc.) as 2 days ahead of the current date.(these dates can be changed manually)
    U can find all these date in schedule line/Shipping.
    I want to change the proposed date to current date.
    beside this there are 2 other date in Availability control.
    1) Complete delivery (Dely/Conf. Date)
    2) Dely Proposal (Dely/Conf. Date)
    these are also proposing dates 2 days ahead and not giving permission to change it manually to current date (u can able to change it to any future date but not to any past date of proposed date).
    There is no problem while creating SO. But when I am trying to create delivery it's giving error as 'Dely/Conf. Date' is in future.
    Now, how to change these dates?
    Please help me to solve this problem.

    Hi Surajit
    As you have maintained 2 days , so go to VA02-> item data->schedule lines tab->check the delivery date
    If the delivery date is 14.02.2009 then go to VL01N and give manually the delivery date as 14.02.2009 ,
    then you can do  delivery
    Example :
    Today's date : 12.02.2009 ;
    Maintained days : 2 days
    Delivery date : 14.02.2009 ;
    Check the following parameters wheather you have maintained or not :
    In shipping point details check pick, pack , goods in transit  time
    In VOV8 check the Lead time in days
    In MMR check the GR time , In house production time
    Regards
    Srinath