Synching of Item and Project definition status

Hi There
Currently, I would like to know 2 things as below. (Using PPM 5.0)
1) Project Definition status to 'On Hold' and synch to item (Decision point status) to set 'on hold'(created in SPRO -> Proftfolio Management).
   - Is this possible? I am not able to find the on hold in the drop down or the standard DFM
2) Existing project definition status can be set to Lock or unlock. Can this be synch to the item (Decision point status) to
on hold  or project in progress status (created in SPRO -> Proftfolio Management). Do we need to set in the DFM.
If there is any clarification required, please let me know.
Thanks.
Kannan

Hi Lashan.
I have done the testing with the recommended steps provided it is working fine. However, now I am trying to do from portfolio Item to project management. So if the project is set to project on hold, the project definition need to change to Lock.
Change statue to on hold at item.
Project definition. It didn't change.
Configuration  as below.
1) Map Business Transaction for Synchronisation.
2) Map portfolio Management Status to DFM business Transaction.
3) Map DFM Business Transaction to Portfolio Management Status.
Is there anything else I missed. Hope you can shine some light on my configuration. Thanks.

Similar Messages

  • Short Dump while using BAPI_PS_PRECOMMIT to set Project Definition Status

    Hi All,
    I am getting a short dump while using BAPI_PS_PRECOMMIT for setting the Project Definition status..
    The requirement is to create a Project Definition and then set its status to REL from CRTD. For this purpose i am using the BAPI's in the following sequence :
    1. BAPI_PS_INITIALIZATION
    2. BAPI_PROJECT_MAINTAIN
    3. BAPI_BUS2001_SET_STATUS
    4. BAPI_PS_PRECOMMIT
    5. BAPI_TRANSACTION_COMMIT
    The Proj Def creation is happening successfully in step2. Interestingly, when I debug the program and stop at PRECOMMIT BAPI the program does not give a dump. I have also tried to give COMMIT WORK / WAIT FOR n SECONDS after BAPI_BUS2001_SET_STATUS, to give BAPI sometime for DB update but nothing seems to be a permanent solution.
    Please give your views on a solution for this problem..
    Thanks & Regards,
    Somil

    Can you please check how to post code in SDN ...
    I cannot read your code properly

  • How to populate WBS element and Project definition in Additional Tab

    Hi,
    I have a 2 requirements
    1) we need to populate WBS element and Project definition of an order in PM
    IW 32 trasnaction (Additional data tab).
    2)Also i need to program settlement rules in CJ02 for WBS elements .
    How do i approach ?  when i do manually it is taking the values in IW 32 when the status is released.
    So i think first we need to chnage the Status from Created to released and then start working on step 1 and Step 2
    Kindly suggest.
    Thanks,
    Pradeep.

    Problem one solved ......
    Basically we need to put the status of WBS elememnts and then write a BDC for additional data tab.
    Looking into issue 2......

  • Status Synchronization in Portfolio Item to Project Definition

    Dear Gurus;
    This is my first time in custom the Synchronization andi need help to make this "Status Synchronization"in Portfolio Item to Proyect Definition.
    I know that i can make this in the follow SPRO:
    1. Maintain DFM Business Transactions
    2. Map Business Transactions for Synchronization
    3. Synchronous and Asynchronous Status Synchronization
    4. Map DFM Business Transactions to Project / Initiative Business Transaction
    5. Map Portfolio Management Status to DFM Business Transaction
    6. Map DFM Business Transaction to Portfolio Management Status
    I made all of this configuration but still not work.
    Please help.
    Regards,
    Mariano

    Hi Santhosh;
    First of all, you have to know that the function of Portfolio Status (Item or Decision Point) are "User Status" and in Project Status (Project definition and Phases) are "System Status", you can't configure Portfolio User Status to the Project User Status.
    For Example: I have been setting the Item User Status "Suspended" that are synchronized to the Project System Status "Canceled", and it's worked fine.
    Do this steps:
    1) Maintain DFM Business Transactions -> don't touch this (SAP standard)
    2) Map Business Transactions for Synchronization -> don't touch this (SAP standard)
    3) Map Project / Initiative Business Transaction to DFM Business Transaction -> Here you have to map the source bus transaction to  the DFM bus transaction (are the same).
    PDCP PPO DX05 DFM5
    4) Map Portfolio Management Status to DFM Business Transaction -> It's the same as point 3, but in reverse.
    PDCP PPO DFM5 DX05
    5) Map Portfolio Management Status to DFM Business Transaction -> Here you have to set the old status to the new status (i used to define the Item Status to he DFM Business transaction).
    PPO Item PDCP 185 190 DFM5
    6) Map DFM Business Transaction to Portfolio Management Status -> It's the same as point 5, but in reverse.
    PPO Item PDCP DFM5 190
    Hope this help you.
    Best regards.
    Mariano

  • No inquiry items and project assignment to sales order

    Hi Friends?
    I am using DP81 to create sales pricing but getting error message when entering project number that
    No inquiry item exist for project
    There are no inquiry items for project A1
    Message no. VPK1111
    Diagnosis
    A project-assigned inquiry is a prerequisite for sales pricing.
    To access sales pricing, choose Logistics or Accounting -> Project System  -> Controlling -> Planning .
    Procedure
    Check your entries.
    If required, create a customer inquiry and assign it to a WBS element for your project definition.
    *Further we assign the the project in sales order via( VA01-->account assignment tab here we can assign the WBSE to sales order).*
    Is there any other way to assign project to sales order?
    Regards

    The error message clearly states that you have not created any sales inquiry...You wanted to carry out sales pricing, for that you need an enquiry from customer...So first create inquiry in VA11, there you assign WBSE and then do DP81

  • Due to deleted Sales order line items and Archived Sales order is still showing as Incomplete in BW as Open Order reports because of Incorrect SAP R/3 Rejection Status("A") in VBUP table.

    In a archived saler Order user had deleted Line Item and completed overall sales order. Now this sales order is archived, but it is stll appearing in BW report as open order because of deleted item  with rejection Status is maintained as “A” (Not yet Processed).
    We want to change this status from "A" (Not yet Processed) to "C" as completed.
    I have tried to reload Archive data but due to some limitation I was not able to do it. Also I feel this will like this s not the proper way to do it.
    Could you please help me to correct way to do it???
    Thanks in advance....

    Hi Vaibhav,
    If you can get the list of Sales orders which has deleted line items and force completion status. You can manage them in BI via lookup  or navigation attribute.
    Just my views I am sharing .
    Thanks,
    KDJ

  • CADO Report - Missing Project Definition and WBS elements

    While running CADO (time sheet data) report for employee, data is not being pulled up for the WBS Element and Project Definition. What could be the reason? Here time is entered against a network activity but for some entries WBS element and project definition is dispalyed and for remaining it is not.

    Yes....these activities are assigned to the WBS element in the project. As I mentioned earlier for the same activity in some cases WBS element is populated.

  • XRPM, cProjects and Project Systems link in BI

    Hi Guys,
    We are implementing a RPM solution in our BI 7.0 system. We have a requirement where we need to link RPM data with cProjects(Project, Task) and Projects Systems (Status, WBS Elements, so on) data.
    Could some one give me the links/documents related to linking the above objects.
    Thanks in advance
    Srinivas.

    Hi Neelam:
    Check Project system tables like PROJ etc and create a View for the fields you want.
    Use this View as your datasource to extract data.
    Thanks,
    Jagadish B V

  • BAPI/FM for setting the user status for the Project definition and WBS elem

    Hi,
    I have to set the User Status for the Project Definition and the WBS elements in that project.
    The User status to be set is the same for the project and wbs elements.
    Please let me know if there is any BAPI/FM to set the user status..
    Thanks in advance.
    Regards
    Shiva

    Hi Shkithija,
    There is a dump encoutered in the form "PS_FLAG_GET_GLOBAL_FLAGS" for 'chk_precommit_ok' in the "BAPI_PS_PRECOMMIT".
    But it is showing SY-SUBRC = 0 when used along with BAPI_TRANSACTION_COMMIT.
    May i know what are input parameters we need to pass it to "BAPI_PS_PRECOMMIT".
    Do you have any idea.
    Please let me know
    Regards
    vishnu

  • Project Profile Status Definition

    Hi,
    I would like to understand the impact and difference on the below 3 options for specifying status profile for Project Definition:
    1. if it is left blank
    2. if PS000001 is specified
    3. if 00000001 is specified
    Thanks!
    Regards,
    Vivian

    Hi
    1. if it is left blank- There will not be any user status for PD. Hence all the transaction control will be by the system status.U can add profile later.
    2. if PS000001 is specified- User status control for PD will be from profile PS000001.
    3. if 00000001 is specified- User status control for PD will be according to the profile  00000001
    For details of status profile check T code OK02.
    Regards

  • Data Transfer Not Up-To-Date  and To Be Archived at Project definition ?

    Hi All,
    I want to know about the statuses "Data Transfer Not Up-To-Date and To Be Archived at Project definition level?" In documentation Flagged for Transfer  and  To Assign are only mentioned.
    Thanks and Regards,
    Arti.

    Hello Arti,
    the system sets this status when there is a problem with the replication. For example, in the customizing of your project type (accounting area) you have defined the type of transfer as 'Automatic as of release of project'.
    Now, for example, you have a project that has status 'Created - Transferred - Data Transfer Not Up-To-Date - Assigned', this means that the replication is not yet complete because according to the customizing setting you need to release the project first.
    Hope this helps!
    Best regards,
    Silvia

  • System Status Change for Project Definition

    Hi,
    I am working on a requirement to notify the Project Manager when the Project Status changes to REL.
    I couldn't find any user exits where I can add the code to send an e-mail notification at the time of status change of the Project Definition or the WBS elements within the Project.
    I checked for events in Business Objects BUS2054(WBS) and BUS2001(ProjectDefinition) which might get triggered at the time of status change. I couldn't find any events relevant to Status Change.
    Any ideas how to handle this requirement ?
    Regards
    Bhooma

    I found a solution to this issue.
    Regards
    Bhoooma

  • How to block reusage of archived Project definition and WBS element numbers

    Dear All,
    We have archived our projects using the TC SARA and the Project definition and WBS elements numbers no more exist in tables PROJ and PRPS etc.. When I now try to create a new project, the system proposes the next open number or allows to enter a number which is the same as one of the archived projects. But in our organization we cannot reuse the Project definition and WBS element numbers (even if it is archived) as a rule.
    Can anybody guide me what are the possibilities to block or avoid the reusage of the numbers of archived project definition and WBS elements in a fool-proof way? 
    Thanks and regards

    One Workaround:
    Use T code OPSJ and lock the project coding mask. Doing this you can not use this mask any more.
    But you want to continue using the mask but with different numbers. Not sure how this can be acheived. lets wait for others view
    Regards
    Sreenivas

  • Creation of project definition and wbs element

    I want creation of project definition and wbs element upto 4 level using bapis.
    i am using transaction cj27,cj01,cj02
    which function module to use for this??

    Hi,
    to create project definition with customer fields the BAPI you should use is : BAPI_BUS2001_CREATE
    to create WBS elements with different levels and specific fields the BAPI you should use is BAPI_BUS2054_CREATE_MULTI
    these bapi must be used in the sequence of call :
    BAPI_PS_INITIALIZATION
    BAPI_BUS2001_CREATE / BAPI_BUS2054_CREATE_MULTI
    BAPI_PS_PRECOMMIT
    BAPI_TRANSACTION_COMMIT
    before using the bapi, you must apply OSS note :
    637345 - Syntax error with enhanced PS tables
    i sent you the oss note to your mail
    please reward points if helpfull.

  • Status Sync between Portfolio Item and Initiative doesn't work!!

    Hi,
       Does any body have a procedure to synchronize the status between Portfolio Item and Initiative.
    i have done all the configurations, but still sync Item -->initiative not happening but working fine with in Reverse direction Initiative --> item.
    My requirement is to have status Sync from Item to Initiative.
    You can take an Example: REL from Item --> Initiative and send it across.
    correct answer will definately get rewarded...
    We are on PPM 5.0 SP level 6.
    Rgds
    Reddy

    Hi All,
           Nobody has any idea on this or not even a clue?
    Rgds
    Reddy

Maybe you are looking for

  • How to use search feature in my JSP?

    Hi all, In my struts application, there is one Jsp page which receives some keyword and based on that keyword it searches the local file system(all diskslike C:\,D:\,E:\.....). how to implement this feature and should display only the latest 10 recor

  • LOOP_IN_MESSAGE_ROUTING

    Hi All, - Scenario : BPM <-> Abap Proxy on R/3 (synchrone) In the SXI_MONITOR (on both XI and R/3), I have the following message : "Code : PROTOCOL.LOOP_IN_MESSAGE_ROUTING Loop discovered in message flow: System is.00.sap001, pipeline IS with inbound

  • Is there a way to link the x-axis of multiple graphs in a report? Using DIAdem 12.0

    Is there a way to link the x-axis of multiple graphs in a report?  Using DIAdem 12.0

  • Paul and Kate in the real world?

    Do any of you use the text-to-speech voices for Cp4 in the published versions of your projects? I've been using them in my most recent projects, thinking in the back of my mind that I'll go back and re-record human narration to replace them. But, I h

  • Repairing an HP 2175xi cartridge holder

    While installing a new cartridge in our old HP 2175xi, my wife snapped off the plastic spring-loaded cover piece that keeps the cartridge in place.  Can that be fixed?  Is it a matter of replacing the cover?  Is it worthwhile to spend money to replac