Table for cost center / activity type prices
Can someone give me the table name where cost center/activity type prices are stored?
Regards,
Manohar
hi,
for cost centers
table name = CSKSZ
field name = KOSTL
Activity prices
table name = RKPLN
field name = TKF
HOPE IT HELPS
regards
sayeed
Similar Messages
-
Master record for cost center/activity type
Hi all;
How create a master record between an cost center and activity type?
Thank youHi
You can create master data between cost center / activity type.
You can link the two by planning for activity qty the combination of a cost center / activity type in KP26. Then you do a detailed planning for costs for the cost center / activity type / cost element in KP06.
I hope it is clear..
Regards,
Suraj -
Actual activity price does not exist for cost center / activity type
Hi,
We are trying to upload the time sheet related data(number of hours an employee workred on a project) ect from Non SAP to SAP.
We have used a customized program and have loaded the data from se38.
All this HR data will be saved in CAT2
Later we transfer the time related data into SAP FI/CO using CAT7.
+When tested with a couple of employees time sheets, they got uploaded in SE38 proerly and when transfered it through CAT7 it was properly taking the hour*rate is cost and was reflecting in the respective cost element.
For a few time sheets in SE38 we were getting an error saying that the cost center(100501)/ activity type(EAT001) does not exist for 2010.
Hence we have taken, FY 2010, the cost centes and activity types in KP26 and have given the planned Activity as 1. No planned cost in KP06.
We have run the price calculation forr the FY 2010.
Then we were able to uplaod the time sheets, but when we tried to transfer the data through CAT7, it throws an error saying no activity price exist for cost center 100501/ activity type EAT001. If I ignore the warning an proceed, no amount is being calculated.
When uploaded employee time sheets before, all the cost were getting claculated and were entering into the respective cost elements, but now no amounts are being calculated and it is taking Zero.
When checked the previous years data i.e, 2009 all amounts are fine, in KSII I can see the activity quantity filled with some numbers in 2009, where from are they comming? I have checked KBk6 nothing was mentioned.
PLease assit
Regards,
shilpaHi
I never used CAT* though, but the error means that you need to maintain a activity price in KBK6 (Actual price)
Regards
Ajay M -
KSPP error: Plan/SOP order &: Reference to cost center/activity typ
Dears,
I need to know how to correct the error: "Plan/SOP order &: Reference to cost center/activity typ" that I received when I run the KSPP.
Error code kp603.
Thanks in advance
KR
VincentHi everbody,
I found that when we have a formula in Resource -> Costing view but no quantity ( zero ) in Standard Value for operations (Master recipe) then we face the error.
Other tips could be found in sapnote 1770587 and sapnote 380282.
I hope this help to solve the issue.
Regards -
Table for cost center plan/actual data
Hello gurus,
What are the tables to get for cost center wise plan/ actual data? The data which was entered through KP06 was sitting in whcih table?
regds
ramachandraHello Ramachandra,
Actual and Plan Data can be found in COVP view.
1) For Actuals, you should use the values 04 and 11 to the field WRTTP;
2) For Plans, you should use the values 01 and 10 to the field WRTTP.
If you need to get the totals, you should use tables COSP and COSS.
Hope this help you.
Cheers,
Daniel. -
TAble for cost center group in 3.0 F transaction.
hi,
i need to develop a report to extract cost center data from r/3 in 3.0 F version.
can u guys help me that which table has got entries for cost center group.
waiting for your replies,
Regards,
Rachanahi ,
I have checked in csks, cska, cskb, and cssk as well, but i didnt find a field which holds the cost center group information ..please help me as this is a bit urgent ..
Thanks in advance ,
Regards,
RaAchana -
Table for Cost Center and WBS Element.
Hi Experts,
i done the creation of Servcie Contract with account assignment category as Cost Centre "K" & Project "P". Now i'm trying to take the report for this document.
Plz help me, in which table the Cost center data and WBS Element data is stored.
Regards,
sudhakarhi!
check the table T163K and the field is KNTTP.
Reward if useful.
Yuvi. -
Hello Experts,
We are customizing a financial report and having a strange requirment, where we need to sum up the total value(Debit+credit) of a particular cost element from cost center report S_ALR_87013611.
For example, Cost element 600000 is having debit value 5000 and credit value 2000 in the report S_ALR_87013611, so we need to bring the value of 3000 (Sum of debit and credit value) in customize financial report for cost element 600000.
I have checked the table COSS with value type 4, but I am getting there 2000 debit and 2000 credit, 3000 debit is got missing.
Please can any one tell me which table should I check for getting the proper data?
Your early feedback will be highly appreciated.
Regards,
Mohammed KalimHi Ajay,
Thanks for your prompt response.
COSS and COSP are not serving my purpose.
COSSA & COSPA are the structure table.
I am not able to find cost center field in COEP table.
Hi Mahesh,
Thanks for your valuable inputs.New GL is not active in our client.
Hi Raman,
Thanks for showing interest in this issue. COBK is Document Header table.
Regards,
Mohammed -
Resource - cost center - activity type
Hello,
I can see the link Resource - Cost center (in the resource master data)
I can see the link Activity type - cost element
I can see where the activity type's planned cost is done, for such or such cost center
I cannot see the relationship Resource - Activity type
isn't there any direct link or is it only an indirect link, through the cost center
Thanks for your help
KR - LoïI need to post 2 diferent type of costs to 2 different accounts (cost elements) my question is what impact is if I mantain in one resource with cost center 1000 2 activity types, one is also linked to CC 1000 but the 2nd is linked to CC 2000
In the costing tab at the Resource there is a field for the cost center so my question is what are de implication with this cost center and the link between the activity types and the cost centers
you can maintain 2 cost element for two activity.
But you can't combine two cc in one resource
then you need to create two resource, one with cc 1000 and other with cc 2000,
the second question is, I have to maintain these 2 different cost at the time of confirmation, Is it correct that I mantain the cost of an HOUR in KP26 so when the confirmation happens I just have to say in COR6N that 15 hours were used so based on rate given in KP26 system will calculate and allocate that cost properly, Is this how it works?
as per the formula in OP54, assigned in resource with respect to activity.
at the time of actual booking, system will calculate the actual cost of the activity ( as per the formula maintained in resource)
Also I want to ask if like the activity described before I can have 2 of these attached to the same work center and same phase? I know I can have up to six per Resource but how is the confirmation done, in one step at COR6N you give the 6 parameters to each of the activities or you have to go one by one and saving in this transaction??
In resource for each activity ( parameter) you need to assign formula and activity type, while creating process, system will copy all the parameter and formula in process order, while booking in cor6n system will copy all the parameter. -
Res all,
how to define cost center for work center ?
and how to define activity types for SETUP , MACHINE , LABOUR etc activity?
plz send details with TCODES
regardsHi Ajay
For defining Activity types T code KL01
Then you have to plan the activity by using T code KP26
Here you assign the activity type to particular cost center
To define cost center T code KS01
Then in CR01 (work center) u will assign the cost center and activity type
to that cost center
Thanks
Ansuman -
Table for Cost of Goods Manufactured price
Hi Gurus
I want to find out the cost of manufacture price for the item number
eg
if we go tcode ck11n , enter the material number and execute twice we get the total cost of the manuafactured which is ppc3
so could anyone tell me which table can I see the cost of manufacture total price
regards
PirozHi Srimanta
I check all the tables KEKO ,CKIS AND KEPH
but did not find the cost of goods manufactureed Total costs in that table could you tell me which field it is ?
CK11N - Enter the material press execute twice and you will see the costs componet view I need that field
regards
Piroz -
hello,
what table i can found the cost center i createdin tcode KS01.
thanks.
donnaHi Donna,
Check the tables
A026
A061
A062
A063
CSKB
As these are related to controlling area in which you are working -
Table for Cost center plan data by version
Hello,
I need to find out which tables in sap hold the cost centre and profit centre plan data by version.
I am having trouble finding the tables if anyone can help?
ThanksCOEP CO Object: Line Items (by Period)(costing document line item information)
Orders, sales document items or cost centers can be described as object types. The connection of an object to its CO data is given by the general object number (OBJNR field in the CO tables, such as COEP-OBJNR). This field provides you with information about the object type and, if needed, about the object key (such as the order number).
GLPCP EC-PCA: Plan Line Items -
Activity Type set up for cost center
Hi All ,
While creating a task list i m getting a message
Activity type is not set up for cost center in the year 2008
Message no. CR062
How could i set the activity type for cost center? Plz tell the procedure.
regards
sunil
Edited by: sunil gupta on Sep 19, 2008 10:12 AMDear Sunil,
Check out this,
1.Create a Cost center using T code - KS01.
2.Create an activity type using T code - KL01.
3.Assign the Rates for an activity type & cost center combination using T code KP26.
4.In the input screen of T code KP26 ,enter version as 0, from period 1 and to period as 12 and the Fiscal
Year as 2008,enter the cost center, activity type click on overview screen (F5)---> enter the per hour Rate
under Fixed price and set value as 2 for distribution key and plan price indicator as 3.
5.After performing this ,while creating the work center ,this combination of activity type & cost center
should be assigned.Then while creating routing/task list this work center can assigned for performing
operations.
Check with this & revert back if you need any further help.
Regards
Mangalraj.S -
KP26 activity type / price planning
Hi ,
After giving cost center , activity type , fiscal year and period ,
1) How system automatically proposes plan activity , capacity , Priced fixed etc values ? From where it gets data ?
2)How values entered in plan activity , capacity , fixed price , variable price , price unit , plan price indicator etc affect /calculate activity cost ?
I know SAP help is available , If some one can explain with examples it would be great help .
Let us say I have work center WKCN and I have maintained capacity , scheduling and costing tab . I have maintained plan activity as 102 , capacity as 108 , price fixed as 80 , price unit as 00001 ....Please explain how the next chain of events happen .
NPIn KP26, activity pricing will done for the combination of labor cost center & activity type assigned in work center. Here activity price will be maintained on hour basis or day basis.
In task list or order, work hours will be given for the internal activity. Here for the internal operations, work center & activity type will be defined.
If work hours is 15 hrs & fixed price is 80 INR (as per your example), the total activity cost will be 1200 INR for order (15 x 80).
Price Unit
The price unit is 10 for activity type "Drilling" with unit "Hours".
The price applies to 10 hours of drilling.
The price unit is 1 for activity type "Drilling" with unit "Hours".
The price applies to 1 hours of drilling.
Plan Price Indicator
001:
The price of the activity type is determined automatically based on the planned activity and the planned costs required for this plan activity quantity.
002:
The variable portion of the price is calculated based on the plan activity quantity. To determine the fixed portion, the system uses the capacity and not the plan activity quantity.
Maybe you are looking for
-
Partitioning 1.2T External Hard Drive for Time Machine and PC backup?
We have a 1.2T Seagate external hard drive. I partitioned it so that I could use part of it for my Time Machine backups and want to be able to use the rest of it for the PCs in the house. I formatted the rest of the space using the Disc Utility and t
-
Live TV buffering in Media Player filling up SSD?
Hi all: I have a HTPC with a SiliconDust HDHomeRun DUAL 2-Tuner ATSC DLNA/UPnP Compatible Streaming Media Player, HDHR4-2US. This is a network tuner that can stream live tv over the network to multiple computers. It is supposed to work with Wind
-
I have a macbook and im kind of unhappy with the built in iSight. I think it is awsome idea for location but the quality is not that great. Ive seen many pictures on apples website showing confrences but unfortunatly my iChat conferences are always b
-
Where can I download acrobat XI all I can find is pro version
Where can I download acrobat XI standard all I can find is pro version
-
ITunes 10.4.1 (10) - The control to connect to my airports missing.
I stream music to two airports expresses which have additional speakers connected to them, on the upgrade yesterday the control on the bottom right of the iTunes screen is missing. This also shows my Computer and Apple TV connections, where did this