Table for Gnerated work schedule
Hi Seniors,
Can any body guide me where to check the work schedules those are already been created.
I have created the work schedules mannually in QA and want to check them,but wondering where to,which is the table.
Please guide.
Hi Antonie,
Thanks for the quick update.the table ids for work schedule what i want to know is that,
i have already generated work schedules for 4years week on week basis,
Now i want to check the periods that have been generated lets say,once you generate the payroll period for a certain period you can chek it in the same NOD Payroll>>Basic Settings>>Payroll Organization>>Genarate Payroll Period & in that you can check the table for Check Payroll Period.
Like this i want to check the work schedules that have alredy been created.
Please guide.Thanks.
Edited by: srssaphr09 on Mar 29, 2011 9:27 AM
Similar Messages
-
T-Code to update condition table for delivery & transport scheduling to SCM
Hello,
Could you tell the T-code to update condition table for delivery & transport scheduling to SCM system
These are the some SAP fileds
/SAPCN1/KOTABNR (Condition Table)
/SAPCND/KAPPL(Application)
/SAPCND/KSCHL(Condition type)
/SAPCND/KOLNR(Access sequence)
Thanks in Advance
RK
Edited by: RK on Jun 9, 2009 5:58 PMHI
The TCODE for this is /SAPAPO/ATP_GCM.
Regards
Anurag. -
Updation Error in "Group Personnel Subareas for the Work Schedule "
Hello everyone,
While trying to assign a PS grouping code to my Personnel Area here, I am facing a problem.
I can't see them in the table mentioned above .
Already checked the previous steps in Enterprise structure i.e creation PA and PSA, they are displayed properly in respective tables but I can't find them here in grouping for work schedule.
Could any one of you be kind enough to throw some light on possible errors and their solutions.
Thanks & Regards,
VibhuHi,
Just now I am able to sort out this problem, Actually we need to carry out "Maintain User Parameter" activity under 'Personnel Administration'
IMG Steps are as follows :
SPRO => Personnel Management => Personnel Administration => Basic Settings => Maintain User Parameters
Following screen will come up
here select the country you like to work on (in my case it is India)
Select Continue
A pop up will come stating "Parameters created for India"
Select Continue
User profile screen will come up
Save it
Now go to time management section of IMG
Go to "Personnel subarea grouping"
Personnel areas belonging to your country grouping will be displayed on screen.
Thanks,
Vibhu -
Adding recurring but sporadic events to iCal for my work schedule???
I am trying to add my husband's work schedule to my iCal but there's no pattern to his schedule and I'm trying to avoid adding each work day separately.
For example for March he may work 15-17 days mixed of all days of the week . Some nights some days but usually two weeks of each. That part isn't a problem.. Even If I could add one or two weeks at a time that would be great. one week is M, T, Fr, Sun the next could be Wed, Th, Fri...,etc. No set pattern.
I tried highlighting several days at once to add an event to those specific days but that didn't work. Thanks if you have any suggestions!If there is no pattern to it then all you can do is add one day at a time. Life must be very confusing with no pattern.
AK -
Alarm clock app for different working schedule
I'm looking for an alarm clock app or some sort of app that will allow me to schedule reminder/alarm at different week. For example, I want to set an alarm on week1 at 3AM on M, T, W, Th and then week2, 3AM on M, W, Th, F, Sa and repeat this pattern. Does anyone know anh app that will allow me to do this?
Many thanks!Maybe this app can help
https://itunes.apple.com/au/app/worktime-work-schedule-shift/id594764457?mt=8 -
Break timings for Flexible work schedules
Dear All
I am trying to configure the breaks for Flexible working time. (For example :- 24 hour clock, the employee can log in any time for fixed 9 hours). what is the procedure in configuring such breaks and since the break times also vary, how do we maintain the same ?
Thanks in advance
Best Regards
MohammedDear Sehgalji
By using the table v_t550p, we can define only the breaks with fixed times,but i am trying to define breaks with flexible timings, since the working timings are flexi timings
example :- breaks are not defined and employee can take a break anytime for fixed duration of 20 minutes.
Regards
Mohammed -
59 sec Begin tolerance for Daily work schedule
Dear Experts,
I need to give begin tolerance as 59 sec to DWS, but when i tried to give in DWS table, it is not taking seconds, its only taking minutes.
Kindly let me know any other way of doing the same, if a PCR needs to be written, which function/operation can be used to for the same and how to derive it.
Your valuable suggestions will help me a lot.
Regards,
SrinivasHi,
In DWS you cannot account for the Time Unit ' SECONDS'.
But for your solution, check the function 'DPTOL'
"Times are rounded in the personnel calculation schema of RPTIME00 using function DPTOL."
Thanks & Regards, Swapnil Mishra -
Dear Experts,
how can i set a default value for work schedule rule (Infotype 0007) ?!
Thanks in advance.Hi
After configuring the required tables for the work schedule rule, ensure that you also generate the same using the T code PT01.
once the work schedule is generated, use the TCode PE03 to access the feature.
Work on SCHKZ feature in whci the return value is the work schedule rule that is created.
This will appear by default in IT0007 when you click on create the IT0007.
whenever you change the WS rule ensure that you generate the same using PT01 and chnage the return value in the Feature.
Your problem will for sure be solved
All the best to you
Regards
RR -
Error "No entry in table T551A" while creating set work schedule rule.
Dear Team,
I am getting following error while creating set work schedule rule.
Error "No entry in table T551A" for key 22 BBB [ here BBBB is my period work schedule]
The actual prob is i configured all the necessary steps but when i tried to create work schedule rule im getting this error. Also, in the same screen there is one field DWS grouping initially value in this is 00 and gread mode. But after giving ES grp, holiday calander ID etc etc when i try to save that screen that value is chainging to 22 from 00.
My ES grop=2 and PS grop=2 . Is that value is my ES and PS grouping..?? or some other thing.
Request you to please help me out.
Regards
Shab.HI, there are 8 steps you need to do below:
1. Group Personnel Subareas for the Daily Work Schedule
2. Group Personnel Subareas for the Work Schedule
3. Define Break Schedules
4. Define Daily Work Schedules
5. Define Period Work Schedules
6. Define Employee Subgroup Groupings
7. Define Groupings for the Public Holiday Calendar
8. Set Work Schedule Rules and Work Schedules
All of them belong to TIME MANAGEMENT. I think you miss some steps above.
Please check it again.
Regards!
Minh -
Planned working time changed and we need to change work schedule for multip
Hi All
I have 2 senarios on time mgmt
1.We have a transfer absence quota where this can be used in day off but it count day offs.It has to show the Calendar days and absence days equal.I am not getting this when i tried
I have a scenario that company management wants to cahnge the planned work timings due to whether for multiple work schedules which already exsist and running.How we can change these new timings and can generate work schedule in single shot/config change?
Can any one through light on these two?
Thanks in advanceAny body plz give me a clue.
Final Out put should be
"Finally check the Abs Days and Calendar days are diff, but the requirement is both should be same." -
Reg:picking work schedule satrt time and end time
Hi gurus,
I am wrkng on overtime report in hr abap.in pa0007 we will have work schedule rule,
for that they will assign timings.i nedd to pick up the start time and end time for that work schedule rule.
can any one help me from which tables i can pick that.
thanks & regards.I think best way is to have your 10.00 or 11.00 as Date objects in the database, and to use methods of Date or Calendar to compare them.
-
Define Work Schedule Rule when Period Work Schedules are created
Experts:
I am trying to configure a DWS and PWS for a given plant. I am aware from a different network thread that this is a 11 step process. I have created the following:
PSG= 03
DWS = 1
Breaks were defined
Created DWS of 1stI, 2ndI, and WNDI (ist shift, 2nd shift, and weekend shift)
Verified day types are correct
Created the following period work schedules:
WK 1 2 3 4 5 6 7
1STI 1 1STI 1STI 1STI 1STI 1STI FREI FREI
1STI 2 1STI 1STI 1STI 1STI 1STI FREI FREI
1STI 3 1STI 1STI 1STI 1STI 1STI FREI FREI
1STI 4 1STI 1STI 1STI 1STI 1STI FREI FREI
2NDI 1 2NDI 2NDI 2NDI 2NDI FREI FREI FREI
2NDI 2 2NDI 2NDI 2NDI 2NDI FREI FREI FREI
2NDI 3 2NDI 2NDI 2NDI 2NDI FREI FREI FREI
2NDI 4 2NDI 2NDI 2NDI 2NDI FREI FREI FREI
WKDI 1 FREI FREI FREI FREI WNDI WNDI WNDI
WKDI 2 FREI FREI FREI FREI WNDI WNDI WNDI
WKDI 3 FREI FREI FREI FREI WNDI WNDI WNDI
WKDI 4 FREI FREI FREI FREI WNDI WNDI WNDI
How do I define the rules to determine variant for monthly work schedule rule generation??
I am aware that X stands for that it is relevant to the calendar and that 1 = Monday - 7 = Sunday.
Can someone help define the work schedule rules I need and what each code means??
Thanks,
BobbieHi Bobbie,
1 . By Using variants you can make changes in normal working timings.....and these changes made in Table V_T550X...conditions can be applied by using
......... Holiday Class
......... Holiday Class for the next day
......... Weekday
......... Variant
Holiday Classes :
Blank stands for -
Not a public Holiday
1 stands for -
Public Holiday
2 Stands for -
Half day Holiday
3-9 stands for -
Customer specific Public holiday Classes
Variants of daily work schedule Selection rule 01 stands for :
--- Standard variant Blank
--- variants A for work on Fridays
Variants of daily work schedule Selection rule 01 stands for :
--- Standard variant Blank
--- Variant A Work on Friday
--- Variant B work on Public Holidays of Public Holiday Class 2
--- Variant C work on days preceding Public Holiday Class 4
For ex: if ur company wants to treat second week of Saturday is half day holiday for employees..then u can do this by fulfilling the fallowing conditions..
... Select holiday class 2 in Holiday Class field by putting X
... Holiday Class for the next day select each holiday class
--- Weekday - select workday as Saturday (6)
......finally create daily work schedule and attach the daily work schedule variant to Daily work schedule (V- T550X to V-T550A)..then u assign ur daily work schedule to period work schedule,period work schedule to work schedule....
.......You can configure these rules for any type of weekdays or weekends ...its depends on the requirement of client to client
........X represent applicability of holiday class in Holiday class and Holiday class next day & weekday...
2 . Come to selection rule.....In selection rule u can treat ur holiday class by using day type...ex ....if u want ur managerial category people won't get paid if they work on public holidays or Sunday...u can do this by using selection rules...
3 . Personnel Time Management :
--- Work Schedules
--- Define Public Holiday Class
Personnel sub area grouping for the work schedules and daily work schedule
daily work schedule .... Break schedule , Define rules for variants & daily work schedule
Define Period work schedule
Day types - Define day types,selection rules & Special days
Work schedule rules and work schedule
.... Define employee sub group grouping and groupings for public holiday classes
.... Set work schedule rules and work schedules
.... Generate work schedules
Please take care of the grouping...
i think now u could the understand the concept now ....
Thanks & Regards,
Avanthika.k -
Transaction Code of Work Schedule
Hello,
Please let me the Transaction Code how to update the Work Schedule Scenrio or let me know the steps how to update the Work Schedule.Follow the below steps to generate Work schedule:
1 Define Holiday Class SAP Customizing Implementation Guide (IMG) ® Time Management ® Work Schedules u2192 Define Public Holiday Classe (Change Public Holidays) Tcode-OY05 Table view-SFC_DISP
2 Personnel Sub area Grouping SAP Customizing Implementation Guide (IMG) ® Time Management ® Personnel Subarea Groupings ® Group Personnel Subarea for Work Schedules & Daily Work Schedules. Tcode-SPRO Table view-V_001P_N
3 Define Break Schedule SAP Customizing Implementation Guide (IMG) ® Time Management ® Work Schedules ® Daily Work Schedules ® Define Break Schedules Tcode-SPRO Table view-V_T550P
4 Define Daily Work schedule SAP Customizing Implementation Guide (IMG) ® Time Management® Work Schedules ® Define Daily Work Schedules Tcode-SPRO Table view-T508Z
5 Define Period Work Schedule SAP Customizing Implementation Guide (IMG) ® Time Management® Work Schedules ® Periodic Work Schedules ® Define Periodic Work Schedules Tcode-SPRO Table view-V_T551A
6 Define Day types SAP Customizing Implementation Guide (IMG) ® Time Management® Work Schedules ® Day Types ® Define Day Types Tcode-SPRO Table view-V_T553T
7 Define Employee Sub group groupings SAP Customizing Implementation Guide (IMG) ® Time Management ® Work Schedule Rules & Work Schedules ® Define Employee Subgroup Grouping. Tcode-SPRO Table view-V_T508T
8 Define Grouping for the Public Holiday Calendar SAP Customizing Implementation Guide (IMG) ® Time Management ® Work Schedule Rules & Work Schedules ® Define Employee Subgroup Grouping à Define Groupings for the Public Holiday Calendar Tcode-SPRO Table view-V_001P_M
9 Set Work Schedule Rules & Work Schedules SAP Customizing Implementation Guide (IMG) ® Time Management ® Work Schedules ® Work Schedule Rules & Work Schedules ® Set Work Schedule Rules & Work Schedules. Tcode-SPRO Table view-V_T508A
10 Generate work Schedules Manually. SAP Customizing Implementation Guide (IMG) ® Time Management ® Work Schedule Rules & Work Schedules ® Generate Work Schedules Manually. Tcode-SPRO Table view-PSHFT
11 Set Default Value for the Work Schedule IMG à Time Management à Work Schedulesà Planned Working Time à Set Default Value for the Work Schedul.(Feature:SCHKZ) Tcode-PE03 PE03 -
How to create and implement a new work schedule rule successfully?
Dear Community,
How to create and implement a new work schedule rule successfully?
In other words, what are all the basic steps to create and implement a new work schedule rule successfully?
Thanks in advance.Hi,
Follow the below steps to create Work Schedule:
Holiday Calendar
Transaction Code: SCAL
Holiday calendar comprises of list of paid holidays to be given to employees on festivals by the company.
Personnel Area/SubArea Groupings
Go to SPRO --> Time Management --->Work Schedules --> Personnel SubArea Groupings
Maintain perosnnel area/Subarea groupings for work schedule.
i.e. Suppose in Mumbai you have WS = GEN ( 10 to 6) and in Chennai you have WS = NORM ( 8 to 4 )
Work Schedule
Go to SPRO --> Time Management --->Work Schedules -->Daily Work Schedules
Go to SPRO --> Time Management --->Work Schedules -->Period Work Schedules
Daily Work Schedule is actually your office timings with breaks (paid /unpaid) i.e. Planned Working Time which is then included
in Period Work Schedule to make a week ( M T W T F S S )
Daily Work Schedule (i.e. Day) -
> Period Work Schedule (i.e. Week)
Work Schedule Rules
Go to SPRO --> Time Management --->Work Schedules -->Work Schedule Rules and Work Schedules
After doing above mentioned configurations,maintain employee group/subgroup groupings in which you have to define which calendar is applicable for which type of employees for which work schedule.
You will maintain this work schedule in infotype 0007 - Planned Working Time of employee via transaction code - PA30 -
Please help me about Work Schedule.
Dear all,
On my client have schedules are below :
- Form Monday to Friday: Is working day for all employees except IS department and Driver Group and Saturday, Sunday are Holiday.
- IS Department : Employees work 5 days a week with rotating basic service on Saturday, compensated by one weekday off.
- Driver group have 6 working days on a week (Mon-Sat). Sunday is holiday.
I have not solution to config . Please help me to define and config to solve my problem.
Thanks for your help.
Huyen NguyenDear Arun Sundararaman,
Thanks for your anwers. But can you help me more for creating a specific Personnel Subarea Grouping for Daily Work Schedules for drive group. I can't create this because I use Personnel Subarea Grouping to define Branch Office, Head Office,On-site Abroad office,. . . so is there solution else ?
Thanks for your supports.
Huyen Nguyen
Maybe you are looking for
-
At a loss at how to solve this prompt!.....
Hi, have a MacBook OS X, V 10.7.5, recently had to install Google Chrome to access on-line course on USA website, in this website I had to click on link to read document in PDF format, screen appears saying 'before viewing PDF document in this browse
-
Error During Import: File Could Not Be Imported
I am trying to load some .AVI movies from my digital camera into iMovie; most of them will, but 1 or 2 for some reason will not. I have played some of these videos on my old G3, which I replaced with this new computer; most loaded in OK. The clips th
-
Problem with Advanced Security Manager
Hi I am using the advanced security manager to migrate security from Essbase 7 server to Essbase 11 server. The users who are externally authenticated on essbase 7 server are under native security mode on the Essbase 11 server after security import.D
-
Problem with Access policy Provisioning on AD
Hi, I have created an access policy, which will trigger the provisioning the user to AD when the user is added to group 'abc'. Its without approval. We have object form and process form. Process form is autosave. But, the problem is, as soon as the u
-
an ssl error has occurred and a secure connection to the server cannot be made cant backup to icloud