can anybody tell me what tables do we use for budget compensation for infotype 1000, 1001, 1500, 1520.
I dont know how to go on, how should i proceed?

Hi sia,
Check standard report - RHECM_BUDGET_RPT
Check tables - HRP1000 / HRP1002 / HRP1001
Check out this process this could be perfect solution from Functional Consultant point of view.
For Personal Administration Infotypes.
Goto..T-code......PM01->Enter Infotype No-> like 0000->Click on Tenichal Attributes Button->Select Infotype No->Click on Details or CtrlShiftF2 and you can see Database Tabe and Just Double Click on the Table Name you can see all details.
For Org Management Infotypes.
Goto..T-code......PPCJ->Enter Infotype No-> like 1001->Click on Check Button->a popup window will show the detail information table, structures & Functioan modules involved & which can be used to retrie data .

Similar Messages

  • Tables for Budget data

    Hi,
    Please provide the base tables for Budget data
    thanks

    hi Arun,
    check these
    BPGE (overall budgets),
    BPJA (annual budgets) and
    BPPE (period budgets).

  • Table for "Budget planning : Cost Center"

    Hi Gurus,
    can anyone pls tell me table for "Budget : Cost Centre" . We create budget with respect to cost center in KPZ2/KPZ3 but i am unable to find out in which this data can be found.
    Pls tell me the table to retrieve the data.
    Regards

    You can do it yourself.
    goto transaction St05. activate the trace. then execute the transaction. after execution goto st05. click deactivate trace.
    then click display trace...hit enter button. a list will be displayed. goto menu bar choose first menu then choose option "Summarice sql statements"...a list will be displayed from which you can know what all tables were affected by the transaction.

  • GL tables for budget information.

    GL tables for budget and expense information.
    What database tables I should consider looking at if I want to generate a report that would list the actual to budget balances.
    I know we can achieve what I want with FSG, however, I am looking for other alternatives.
    Thank You,
    Merloza.

    Following are the major tables that stores the budget information:
    • GL_BUDGET_ENTITIES
    • GL_BUDGET_ASSIGNMENTS
    • GL_CODE_COMBINATIONS
    • GL_BUDGETS
    • GL_BUDGET_VERSIONS
    • GL_BALANCES

  • Table for budget distribution undet project system.

    hi,
    do any one know the table for budget distribution under a project system?
    i need to get the data of budget assigned to a WBS level with the position ID, for a project. the transaction code to distribute the budget is by using transaction code - IM52.
    i posted this question in here before, but the answer i get is incorrect, as i need the table for budget under porject system. thanks

    Check these tables:
    PRPS  WBS (Work Breakdown Structure) Element Master Data
    IMPR  Investment Program Positions
    IMPS  Assignable Operative Objs for Capital Investment Positions
    IMAK  Appropriation requests - general data

  • Table for Budget Structure - FM9k

    dear All,
    I need to write the bdc for the fields in fm9k.
    I have the select the tick mark through my bdc in the tcode FM9k.
    Is there any table for this where i can directly modify this.
    please guide me..
    Regards,
    Vidhya

    please check the link below
    Re: Table for line items of budget document posted through FMBB transaction.
    Dont try to update standard table manually... sap handles it using standard transactions and reports..
    Regards
    Satish Boguda

  • Table for Budget Data

    In which table the Budget figures stored
    thanks in advance

    Hi,
    You will find it in COSS/COSP tables (value type 1).
    The lines are stored in COEP tables if you have integrated planning.
    Regards,
    Eli

  • Tables for budget supplement,return and transfer

    Dear PS experts,
    Would appreciate if you could help me to identify which table should i use to capture/calculate project budget supplement, return and transfer.
    Thanks in advance!
    Best regards,
    Eila

    Pass Objr of WBS  to this tables
    BPEG  Budget revision header 
    BPEJ  Budget revision header 
    BPGE  Overall/annual budget 
    BPJA  Overall/annual budget 
    Regards
    Nitin

  • Table for Budget

    Hello All
    In the Budgeting Component of Compensation Management. I am involving the developers for making a custom report which would show which all managers have exceeded/completed the budgets in the compensation adjustment process.
    So where can I get the technical information related to the reporting ?
    I know Budgeting would involve the table HP 1520. Is there any other critical information I am missing out that the developers need to know ?
    Thanks

    the table is HRP1520 & the Developers need to be made aware that the Budget Unit is tied to an Org Unit via the Relationships table HRP1001..
    ~Suresh

  • Tables for Budget allocated and spent for a WBS element

    Dear experts,
    I am new to PS domain, kindly tell me the table names where I can find the Budget allocated to a WBS element and Open budget for a WBS element.
    Thanks & Regards,
    Murthy.

    Hi,
    I think by conversion cost you mean Production cost of the turbine.
    Since you do both the actvities Material procurement and production under the same WBS. The budget cannot be tracked separelty.
    Have 2 different WBS strucute one for procurement and one for production. However you can add the existing Nwk activities to these WBS.
    Regards,
    Ramesh-

  • Tables for  BUDGET & ACTUAL - COST CENTER

    Hi
    I want to know what are the table in which the actual and the budget for the COST CENTER are stored....
    Regards
    SAP4ME

    Hi Eli,
    Thnx for the reply.i have already checked those mentioned by u.
    My req is  that i want to pull the DATA for developing a report of ACTUAL and BUDGET for a particular cost center o range of cost cost centersfor a range of period.
    But in the table mentioned by,how can i will come to know,to which cost center ,what is budgeted and the actual .
    Please give some details.
    Regards
    SAP4ME

  • Need tables for Budget

    HI All,
    I need  tables regarding Cost Center and its CC Budget amount & Internal Order and its IO Budget Amount.
    Could you please give some tables to fulfill my requirement
    Thanks in advance
    regard
    Vishnu

    hi check this
    BPIG                       
    BPIJ

  • HR Compensation: Where to define configuration for Budget

    Hi all,
    When doing HR Compensation Planning (include Merit and KEIP planning for e.g.), we will have the budget total for each org unit, the amount distributed and remaining ...
    I found the FM HR_ECM_UI_GET_PROC_PREP_DATA which gets data for budget total into the internal table BUDGET_TAB.
    I have a requirement to modify the columns in this budget table.
    I would like to know where we can do the configuration for the budget total information???
    Thanks,
    Khanh

    Hi,
    We have a issue: we have employees with daily payments (instead of hourly rate for example). These employees are flagged as "hourly" in SAP grouping.
    Now the budget information is not updated correctly when we increase the daily rate of an employee: SAP calculates: increase * Annualy woring hours from IT0007. which is not correct for daily rates.
    Are you sure that all the calculation logic is made in the JAVA coding? is it in any way possible to change this without changing JAVA code?
    Many thanks for yiur help!
    Lucas

  • Components to be activated for Budget check in the table TRWCA

    hi,
    I want to know the components to be activated for budget check in the TRWCA table. I want to check the budget at the time of  PO creation , Goods reciept/Invoice receipt creation  using Network account assignment in PO  which is having WBS element and Project in its higher level.
    Thanks
    Rao

    ok well!
    Brother system will only check the budget, when your availability control is active.
    Further, as per your configuration, system will only prompt error  message when your budget exhausted 100%. ok
    please follow the same then  let me know
    check your WBS status is there avaiablity control active, when you entered the amount for budget/release.
    also check the transacion "CJBV - Activate Availability Control "
    Note: when ever you change the setting of your budget profie, must reconstruct the availability control transaction code is :CJBN/CJEN
    Thanks

  • Table for WBS project status and budget.

    hi,
    i am being requested to have a report with project details with the PO and PR.
    but i were unable to find the table for the project status (TECO, REL) for a WBS element. may i know want table and what field they were being link?
    aside, may i know under what table does the "budget assigned" to a WBS element located at?
    thanks

    Hi Ben,
    in order to retrieve the status of a WBS element, please select into table JEST by object number (JEST-OBJNR = PRPS-OBJNR). This will give you an internal status code (JEST-STAT). Then go to table TJ02 with this internal code and select field TJ02-TXT04: this will give you the external status code.
    For the budget, go to tables COSP and COSS, selecting by object number (OBJNR).
    I hope this helps. Best regards,