Target Cost not captured in the production order.

Dear All,
I have created cost estimate for the FG material and moved the standard cost to FG material and created the production order.
In the production order ,I could see the Actaul cost & Plan cost,but the Target cost is ZERO.I have checked the entire and PP & CO settings ,it is OK.
Please let me know that what could be the reason for not capturing the Target Cost.
Regards
Subbu

Hi Subbu
1. Have you released the cost estimate from CK24 before GR from prod order? Check if field Current price in Costing 2 view is not Zero
2. If your contr area currency is different than comp code currency, then your costing variant should allow you to release the cost in contr area currency as well.. T code OKKN ("assignments" tab)
3. Check if target cost version 0 is defined properly and assigned to your contr area
4. check if variance key is there in your prod order.. you can assign default var key to plant in OKVW
5. Execute Variance calculation KKS1/2/6
Regards
Ajay M

Similar Messages

  • Sales Order Schedule line not populating in the Production order

    Queation: Is there a way to tell the system to look at the sales order, line item AND schedule line. It is displayed in MD04 but it doesn't carry over to the Production Order. We are a MTO and this information is relevant in a number of ways. 
    Please Help.

    Vickie,
    If you are using MTO scenario then when you run the MRP for the material, it will create a planned order for that sales order based on the dates calculated from the sales order schedule line (Shipping tab)...
    So now when you convert the planned order to production order, all the sales order details will get copied.
    try and revert back.
    Swapnil

  • Field "GR Non-valuated" in tab "Goods receipt" of the production order

    Hi,
    When creating a production order, the field "GR Non-valuated" in tab "Goods receipt" is checked by default, due to my assessment customizing.
    This field indicates to the system that it should not create any accounting document, whereas I would like to create one. Does anyone know how to withdraw this automatically check?
    FYI, I do not use COPA and the very basic of CO-PC and I would like to create automatically a default assessment rule (cost center).
    Thanks for your help.
    Ronan

    Hi,
    please note that this is not an MM, but a PP-SCF related issue. It does not belong to the forum ERP MM.
    The indicator AFPOD-WEUNB is set automatically as soon                  
    as you do not settle your production order to category 'MAT' (see                    
    settlement rule). If the order is not settled to a material, then the                
    Goods Receipt will not be valuated and the flag G/R Non-valuated (WEUNB)             
    is set. Only when you settle to a Material is the G/R Non-valuated not              
    set, and you will  receive FI postings in the case of such a movement.               
    This is standard system behaviour.                                                   
    Please review the following notes relating to settlement rules: 518496,              
    400400.                                                                               
    To make sure that the GR-Nonvaluated flag is not set in the                          
    production order, field KZBWS must already be filled with 'M' in the                 
    customer requirement. For that, please set the field KZBWS='M' for the               
    requirement class that is used (see 'General Customizing' in note                    
    459734). PLAF-KZBWS (indicator:valuation of special stock).  
    Regards,
    Edit

  • Target cost Not updated in Production order

    Dear All,
    when I save & release the production order system is not showing tgt cost. But once GR thas been done it is showing target Cost.
    How can system should will show target cost without doing GR.

    Dear Sainath,
    It is the standard behaviour of SAP,that only making a GR for a production order you will be able to see the target cost in CO03 -
    -->Goto >Cost-> Analysis.
    IF the order is only created or released you will be able to see the data under cost --->itemization or else cost component
    structure.
    Under Analysis you will not be able to see any data.you can see the data's after making GR.I dont think some option to make the
    data's visible before this.
    Correct me if I'm wrong.
    Regards
    Mangalraj.S

  • Material costs not captured in production order

    Hi all,
                After clicking 'Cost order' (Ctrl+F7) in production order header screen, if i am checking the cost component structure(Goto->Costs->Cost comp. structure) of production order, only the operation costs are captured. The materials costs are not captured here. Please suggest me in this issue.
    Regards,
    Krishna Chandra.

    Hi everybody..thanx for the replies..i want to clear the following things to u,
    1. Costing variance key is PPC1 for planned and PPC2 for actual.
    2. I have maintained the prices in the material master - MAP for child items & Std for the header item.
    3. This is happening for all the production orders
    4. I have kept the costing relevancy for all the materials in the BOM.
    Apart from these please give me the possible inputs to solve the problem.
    Regards,
    Krishna Chandra

  • GR for production order post to cost center and not to the production order

    Hi all,
    when we post the goods receipt for the finished product against the production order (mov. type 101), the order is not credited with the corresponding stock value. Instead of this, the value accounts to a cost center.
    We specified this cost center in OKB9 (Default account assignment), because if not, we get an error when posting the goods receipt cause of lacking accounting object.
    I can't see why the system does not credit the production order?
    Any ideas?
    Thanks for your time
    Daniel

    Hi Daniel,
    This is the first time i am coming across an issue like this.
    neverthless from a logical front,
    1. Remove Cost center as a valid receiver in Settlement Profile.
    2. Your OKB9 setting are pretty much good. No need to worry about it.  Becasue, OKB9 only will work if the system doesn't identify any other cost object. In this case Production Order is an automatic cost object which system should have taken.
    3. Check the Settlement rule when you have created Production Order. It should have been MAT.
    4. I hope you are creating Production Order with Material (using CO01 and not CO07)
    5. Make sure in OPL8, the default rule in controlling tab is PP1.
    Once all these are fine, i do not see any reason why you will get your probelm.
    Please check and revert back to me if the problem still persists.
    Best Regards
    Surya

  • Rework cost not capturing in production order

    Hi Experts,
    I'm not getting rework order cost in the main production order while settlement of the production order. I maintained settlement rule in the rework order as ORD (Main production order number).
    Please help me.
    Naren

    Hi
    If settlement is done properly i.e. w/o test run indicator and the rework order has values posted to it - Then KO88 or CO88 must be successful. If not, system would tell you the error #
    br, Ajay M

  • Cost analysis not showing up in production order

    Hi All
    Preliminary cost analysis is not showing up in the production order...can anyone suggest what could be the possible reason for this

    Hi,
    Once you issue goods(GI) to order then only you can see actaul cost in cost analysis in Production order.
    if you are looking for target cost in cost analysis,you have to post goods receipt(GR) from order to inventory.
    hope this helps you.
    Thanks,
    Rau

  • Target cost not appearing in process order

    Hi All,
    Please let me know the reasons for target cost not appearing in process order.
    Thanks,
    SAP PQ

    Two more scenarios:
    1. You have co-product.
    2. You reverse the variance calculation.
    It will show the target cost only after you run variance calculation.

  • Costing the production order for the configured material

    We are trying to cost the production order for a configurable item.  But the system is not calculating any cost in the production order.  Sales order related to this configurable material is costed.  What additional setting I need to cost the production order for the configured material ?

    Hi Niki
    If your SO is costed, thats enough from a System's perspective... Planned cost will be the sales order cost estimate because SO saves the Chars required for the Configurable material
    Planned cost in Prod order depends on the Costing variant you have assigned in the order type... Check the error log if there is any error in cost calculation in prod order
    br, Ajay M

  • In the Production Order, Sales Quotation is displayed not the Sales Order

    Hello to All,
    I need a kind help from you.
    My scenario is as follows
    There is a Configurable Material (Finished Product)
    Sales quotation (VA21/2/3) were made for this material.
    Sales Order (VA01/2/3) with reference from the Sales Quotation were made for this same material.
    Now when I run the MRP (MD02) for this material, Planned Orders were created.
    Planned orders were converted to the Production Order.
    In the Production Order (say in Display mode), under the 'General' tab, there is a segment called 'Sales order'. In this segment, the sales order is being displayed if the Production Order is created for a sales order (MTO scenario).
    But, in my case, the Sales Quotation number is being displayed instead of the Sales order.
    My Issue which need your answers:
    Is it a standard SAP scenario?? I mean, if the production order is created for a sales order and again if the sales order is created earlier with reference to a sales quotation, then in the production order, the Sales quotation is displayed. Is it a standard?? Or it is showing wrongly? I mean, is it like that, always the sales order should be displayed in the Production order and not the sales quotation??
    Please suggest so that I can overcome this problem, if at all it is a problem.
    Some More Inputs (For your analysis/research):
    1. After the MRP run of the material the Planned Order is created. I have checked the planned order, and found tha the assignment of sales document (in this case Quotation) is done in the Planned order itslef. It is visible wthin the "Assigmnet" tab of the Planned Order.
    2. For the analysis purpose, I created one stand-alone Sales Order for the same material. I mean, without reference from any Sales Quotation. Then, when I run the MRP (md02), the Planned Order and then production order were created normally, with reference to the Sales order. This just for your kind information.
    3. I have checked the pegged requirement of the Production order in the MD04. It is showing the Sales order itself. But, if I see the production order (CO02/O03), it shows sales quotation.
    User Requirement:
    Evenif, the sales order is created with reference to a Sales Quotation, after MRP run, in the Planned and thereby subsequent production order, the Sales Order should display and not the Sales quotation.
    Please suggest.
    Thanks and Regards,
    Supriyo

    Hi
    Since your scenario is configurable material,  the system takes the reference of sales quotation only. Because the in case of configurable materials the sales quotation is the base and based on the sales quotation the sales order is created and subsequent production order.
    This is std SAP and for configurable materials the sales quotation is deciding factor
    Krishna

  • Partner details are not getting captured to the purchase order from the ven

    Hi,
    Issue : ( ECC PO)
    Partner details are not getting captured to the purchase order from the vendor master.
    We found that the partners are not getting captured in ECC PO's automatically from the vendor master. We checked for all the config and everything seems to be o.k, but could not figure it out.
    Any suggestions are highly appreciated.
    Regards
    Sudhakar

    Hey Sudhakar,
    I believe what is happening here is that the ECC PO document type has not been assigned to the partner determination procedure.
    If this is working properly for standard POs, then,
    Go to Partner detrmination under Purchasing>  Partner Settings in Purchasing Documents> Assign Partner Schemas to Document Types.
    and enter teh appropriate document type and refer it to the procedure you have for NB Pos

  • S_ALR_87013532 report -plan cost not rolling upto the WBS/Project level

    Dear All,
    Plan cost from production orders is not rolling up to the WBS/Project level in S_ALR_87013532 ( Plan/Actual Variance report).
    Where as plan cost from network is properly rolling up to the WBS/Project level in the above report. 
    Please suggest what could be the reason for this issue. Is any configuration needs to be done for this.
    Thanks & Regards,
    Vishal

    Dear sir,
    Thanks for the reply & sorry for late response from my side.
    OPSV settings are already maintained in our system.
    Some how i realized  later that cost are actaully getting rolled to the WBS level, but we have observed one more discrepancy.
    Example -
    Production order "X" value - 100 (  as seen through co03)
    Production order "X"value- 40 ( as seen through report s_alr_87013532).
    We found that  in report  s_alr_87013532 , although my total  producton order value of 100 is represented at the WBS /Project level, but at the production order level , it is showing value of 40. 
    On further analysis we found that for production order X
    Materail cost- 60
    Labour cost-40
    The material cost of 60  is not getting fetched against production order "X" in report " S_ALR_87013532".
    There are very few cases , where such discrepancy is seen.
    Kindly suggest.
    Regards,
    Vishal

  • Activity price not getting updated at Production order

    Hi All,
    I have made activity dependent planning at cost centre and calculated the activity rate. The activity rate is showing correctly for the cost centre in KP26, but while confirming the production order (CO11N) the the activity price is not getting updated in production order. But material price is getting properly updated at production order.
    Plz help me in identifying the possible areas of mistakes.
    Regards,
    BKD

    Hi,
    Please check the Period for which you have created the ht activity price is same as the period in the conformation. In the workcenter in which you are confirming please check whether the activities are assigned to the work center.
    Bye,
    Ramesh

  • Balance sheet G/L account posting is not captured in the SLR budget report

    My case:
    While posting a schedule agreement ( which is account assigned to "project make to  order"), to G/L account, the following warning  message comes.
    " G/L account  is a balance sheet account".
    Although I am able to post the scheduled agrrement to that G/L account,  but my slr budget report does not capture this commitmnet cost  (commitment management is active for present financial year).
    Further for the cost to be captured in the budget report the G/L account should exist as cost element ( as from my observation).
    I observed that , that particualr G/L account ( which is a balance sheet account)  is not present as a cost element .
    My  CO colleagues  says that it is not advisible to create cost element for a balance  sheet G/L  account as it may lead to mismatch in the  cost  flow.
    Now , how can the cost be captured in the  budget report for this G/L posting.
    Please suggest  some feasible and correct solution.

    Hi Vishal......
    As I think ...here we have to take P & L account ...becouse cost can be booked only in P & L with revenue...for that we can see commitment too..balancesheet account are direct account ....like Bank account ..........
    please rewards the points if useful
    Regards
    Rama Shanker Sharma