Targets days supply

Hi Gurus,
Please let me know on targets days supply in PP DS and the effect of it on planning. what are the necessary settings to be maintained for achieving the same ?
Thanks,
Prasanth

Hi Prasanth,
In APO the requirements is rolling that is if you have Forecasting then the forecast for a month it is
disaggregated into days or weeks hence if you plan to have a safety stock planning done by APO this method
of maintaining Target days helps to maintain the stocks at the location all the time so if you define 4 days
as the Target days of supply then at all time Heuristics run or optimizer run will ensure that stocks are
there to meet the requirement of next 4 days as is in your case. In case of shortfall system will generate
a requirement on the Source plant based on the transportation lane.
Settings are maintained in Product Master under Lot size tab (Quantity and date Determination).
Please let me know if you need any further information on this
Thanks,
Harsh

Similar Messages

  • Target Days Supply in SNP Heuristics and Deployment

    Dear Experts,
    Does the Target Days supply only define the minimum and not the maximum stock levels?
    Example: consider a Period P1
    The target dayu2019s supply is 20 days, and the Days Supply in Period P1 is more than 20 (suppose 35)
    The Total Demand in that week is not big enough to bring the Days supply < 20
    Question:
    Does the system still create a Distribution Reciept (Planned) in this case and keeps increasing the day's supply of dest location? Or does it create stock transfers only if Days Supply is threatening to fall below the Target Days Supply?
    In other words:
    Does Target Days Supply only come into picture when Days Supply < Target Days Supply, in which case the system adds the difference (Target Stock Level u2013 Current Stock Level) to total demand while creating stock transfers.
    When Days Supply is >> Target Days Supply, does the SNP Heuristic still create a Stock Transfer even though there is enough stock to cater to the current total demand and not fall below Target Stock?
    Hope you can help in understanding this concept.
    Regards,
    Rimjhim

    Thanks for your reply.
    Please correct if I have misunderstood:
    While calculating the net requirement during SNP Heuristic run, the system will apply Target Stock Level into consideration and will only create a Pur Req if the stock is falling below the Target stock.
    Thanks,
    Rimjhim

  • How to calculated "Target days' supply" in SOP Planning

    Hello all
    after input "Target days' supply" in SOP. then run "Create Product Plan"
    there will create production plan in screen. thus i used "Target days' supply" strategy.
    there have one quesion, how to calculated product quantity?
    Thanks.

    Dear,
    System calculate days supply automaticly, this that no of days required to maintain that stock level,
    In the standard planning table, choose Edit-Create production plan-and the desired strategy (either Synchronous to sales, Zero stock level, Target stock level, Target daysu2019 supply, or Plan externally).
    Please refer this link for help,
    http://help.sap.com/saphelp_47x200/helpdata/en/a5/631fdf43a211d189410000e829fbbd/frameset.htm
    Regards,
    R.Brahmankar

  • Target Days of Supply in PPDS

    Hi All,
    I am trying to use the Target Days of supply with PPDS.
    The documentation says it works but on my tests
    it does not.
    IN SNP it does work.
    Any ideas ?
    Thanks,
    T

    Hi Mike,
    I have setup the Target days supply settings in the material
    master and I am using the planning of standard lots heuristic.
    It works perfectly in SNP ... just not in PPDS.
    Any other ideas ?
    Thanks,
    T
    Edited by: TonyG on Dec 21, 2007 11:03 AM

  • Target day's supply vs day's supply

    Hello all,
    Can anyone help me explain the exact diff between target day's supply and day's supply? I would appreciate the help.
    Thanks,
    Neha

    Hi Neha,
    Day's supply:is to determine for how long the available stocks and receipts will cover your requirements.
    http://help.sap.com/saphelp_ewm70/helpdata/en/39/24a037f11cff7fe10000009b38f889/content.htm
    Target days' supply: is maintained in product master to determine the safety stock that has to be produced to cover the number of target days demand.
    http://help.sap.com/saphelp_46c/helpdata/en/35/b58ff68f0e05e4e10000009b38f983/content.htm
    Regards,
    Manimaran M.

  • CTM - Safety days Supply

    Hello all,
    I'm working with CTM and I found a problem that I can't solve. If I set the profile to consider for example 8 safety days supply  (I tested with all settings) the system do not consider the safety days of supply for the first 9 days. The system creates the supply with no difference between demand and supply and at the 10th day it start to create supply with 8 days difference from demand. Did anyone know what is happening? I tryed with fixed and time-dependent safety days of supply and I'm working with the SCM 5.0.
    Thanks in advance,
    Marcelo

    Thanks a lot for your help.
    This setting seems to be a very good suggestion. The early demand fulfillment specifies the time that the system have to build up safety stock, but I tested it and this setting seems that doesn't work for safety days of supply. Do you know if there is another setting like this for the days of supply?

  • Safety days supply not followed due to change in Means of Transport in SNP

    Hello All,
    I am facing a strange issue regarding the SNP heuristics and means of transport. We observed that the system was not respecting the safety days supply. For example if we had a receipt in bucket 'N' and there is a violation of safety days supply in bucket 'N-1'. When we un a heuristic ideally system should delete the receipt in bucket 'N' and create a new one in bucket 'N-1'.
    But we observed that the system is retaining the existing receipt in bucket 'N' and also creating a new one in bucket 'N-1'. This is making the available days supply to increase manyfolds and the whole plan looks inconsistent from Safety Days point of view.
    After analyzing the issue i observed that if we have existing receipts using a Means of Transport 'X'. Now if we run the heuristic using a Means of Transport 'Y' then the system doesnt touch the existing receipts. If I run teh heuristics using the existing Mean of Transport then it works absolutely fine.
    Kindly suggest.
    Regards,
    Abhi

    Hi,
    when you check all products flag it means the means of transport is available for all products and not product specific, to select the MOT for SNP you need to check the aggrgtd plng flag.
    Also safety stock has nothing to do with MOT, SNP heuristic plans based on checks the quota arrangement if its for multiple MOT it will distribute the PR based on the ratio in quota if both MOT are able to meet demand on time, otherwise it will violate quota till the time both MOT are not capable of meeting the demand on time.
    If no quota is defined it will check for which lane is able to meet on time n if their are multiple lanes which can fulfill demand on time then it will choose MOT with less cost.
    Have you got multiple MOT for a source destination combination to be considered for SNP heuristic?
    Just check your design again and explain the problem again as this is not the standard expected behavior.
    Thanks,
    Sanjog

  • Customizing of the days' supply in MD04/MD06

    I don't see any difference with the first receipt days' supply and 2nd receipt.  We need for the 1st days supply more binding information, like the PO or process order,
    for the second we need assigned purchase requistions or firm planned orders. Could you please check.
    *Please set the indicator for consumption based planning not on safety stock or reorder point.
    Can some one give me steps how to implement the above requirement . I have gone thru the configuartion but need further help .
    Regards,
    SHD

    Shahid,
    You need to get your users to clarify their requirements.
    I don't see any difference with the first receipt days' supply and 2nd receipt. We need for the 1st days supply more binding information, like the PO or process order,
    This requirement is not explicit enough.  Tell the users you need an explicit list of the items they wish to include in the calculation for first days supply.  They can select from the list found in configuration (these are the only options available):
    Production/Process orders
    POs, shpg notifications, sched. lines, dely scheds
    QM inspection lots
    Firmed purchase requisitions
    Firmed planned orders
    Assigned planned orders
    Receipt reservations
    Shipping notifications
    for the second we need assigned purchase requisitions or firm planned orders
    This is explicit enough, but not possible.  Assignment of a purchase req is not adequate to delineate.  Unfirmed (but assigned) PuReqs will not be considered.
    Please set the indicator for consumption based planning not on safety stock or reorder point.
    Receipt days supply is configured at the plant level.  It will be same whether you are using consumption based planning, or demand based planning.  It is possible to have the system calculate days supply "until stock falls to Safety stock level" or "until stock falls to zero"
    Once you have your lists of items that are to be included in 'first day' and "second day', go to OMIL.  For items to be considered only in 'first day', enter a 1.  For items to be considered only in 'second day', enter a 2.  For items to be considered in both, enter an 'X'.  
    If you wish for the system to ignore safety stock (calculate days supply until stock falls to zero), enter 1 in the safety stock field.
    Rgds,
    DB49

  • Fixed Days Supply , Oracle E-Business Suite Planning

    Dear Sir/Madam,
    With regard to using fixed days supply on item attribute level, we are not yet sure what the effect is on the planning.
    We know that demand over a certain period of time (FDS) will be aggegrated to one orderline.
    However, if in week 10, demand has been aggegrated for let say quantity 10, and during that week (and thus in the weekly MRP RUN), additional demand of 2 in that same timeframe is needed.
    Will Oracle include that extra demand and make one orderline for 12?
    We currently think that FDS frames are frozen after one MRP Run. is this true, and can this be ignored?
    What I mean is:
    For item XB we have the following planned orders
    -5 need by date 10-03-2015
    -7 Need by date 10-06-2015
    -10 need by date 10-08-2015
    If we set FDS to 365 days, for item XB, Oracle will aggregate total demand of 22 in one orderline.
    But what happens if suddenly a new planned order enters O_MRP
    3 need by date 08-08-2015?
    Will the planning , unless we haven't released the orderline of 22, make a new orderline for 25 units for need by date 10-03? We currently think it generates a rush order.
    Many thanks in advance!

    OracleE-BusinessSuiteR12AdvancedSupplyChainPlanningConsultantCertifiedExpert wrote:
    Hi All,
    I work as demand planner(supply chain) and my company use oracle.
    I would like to know would above course would help me to do my job better ?
    The short answer is probably. 
    The long answer:
    - You have mentioned a certification and then referred to it as a "course".
    - To achieve certification you need to pass two exams: (Ref: Oracle EBS R12 Advanced Supply Chain Planning Certified Expert Consultant )
    - Associated training courses are recommended ... though not mandatory in this case ( See recommended training on exams from the above link).
    - It is almost certain that whatever training one undertakes that should increase knowledge ... and if job relevant it should help you get your job.
    - You will need to look at exam topics (or training course topics) and make a self assessment of how much you stand to gain; and how much it will gain it in future.
    ---- You should know more about yourself than anyone else, and if you are honest with yourself should be able to work out your own cost/risk/benefit.
    ------ Remember cost may not only be monetary ... it may be time you could have spent doing something else ... perhaps with your family.

  • Fixed Days Supply & Fixed Order Quantity

    Hi,
    in certain cases we use the Fixed Days Supply & Fixed Order Quantity attributes in the Item Master to influence our ASCP plan calculation (size of planned orders etc.)
    We need this because we do discrete production (semiconductor industry) and with the fixed order quantity we to ensure that the system plans with full Lots.
    However I am not sure what the impact of the Fixed Days Supply is, especially in combination with the Fixed Order Quantity.
    Unfortunatly the Manuals do not tell very much about this. Does anyone have experience with this and wants to share some knowledge? I would like to know what these parameters really do and maybe there are better ways for our setup...
    Thanks,
    David.

    Hi,
    thanks for the reply. I found the detailed explanation in user guide you mentioned.
    I am not sure that we made the setup in an optimum way.
    We use for example fixed days supply = 5 for many buy items, because we place weekly Purchase Orders for these items and want to have the planned orders combined instead of having a planned order for every day.
    And we use the fixed order quantity to prevent two things:
    1) The size of the planned order gets below a typicall Lot size and the calculated leadtime for this planned order is too short. We define item based resource usage rates so it will calculate the exact lead time for the small planned order, but in reality our production has to run the full Lot which takes more time of course.
    2) without the fixed order quantity the planned orders might become too big, which makes scheduling of them more difficult, because finding a free time-slot on the machines for a huge quantity must be more difficult than for a smaller planned order.
    But unfortunatly Oracle does not provide some business cases, especially for our semiconductor industry so it is more trial-and-error what we are doing...
    regards,
    David.

  • Use of Calendar in Days Supply Calculation in APO

    The Days Supply is R/3 is defined as - The range of coverage is then the number of workdays between todayu2019s date and the date of the requirement that causes the shortage minus one day
    The Days of Supply in APO defined as - The days' supply tells the planner how many calendar days the receipts and stocks will cover the current requirements for.
    In our case we have a factory defined in R/3 as 5 days working, so R/3 display Days Supply it displays only number of Working days till stock/receipt last while APO displays number of Calendar Days ( including non working days)
    Is there any way..i can make these 2 number same in R/3 and APO. Both System has same configuration for considering stock, receipt 7 requirement elements.
    Thanks in advance !!!

    Hi,
    Normally APO should consider the working days.
    could you check that the macro "Determine workdays" is properly executed; and that "Days' supply " is based on the workdays key figure.
    Please note that by default the relevant calendar is the shipping calendar; please ensure that it is maintained in the location master.
    If you want to based it on another calendar, you need to adapt the macro.
    Thanks and Regards
    Julien

  • Days supply is not populating in the planning book

    Hi Experts,
    When I select multiple products in the planning book, the value is papulating as total but if I drilled down to individual product then days supply(Key figure) values are not populating in the planning book.
    Please let me know if any idea.
    Regards,
    Hrishi

    From what you mention it looks like you do not use the standard SNP Planning Book. Was the macro inactive so that you had to regenerate?
    When you move a macro from workbench to level change it should not require to be regerated.
    Please check if following macros are active (green) under level change in sequence
    Determine Workdays
    Layout Attributes
    Drill (Level)
    Else compare the macros and sequence in the standard SNP Planning Book with the Planning Book you are using.
    The Day's Supply (All: Day's Supply) and Determine workdays macros are essential for populating the day's supply keyfigure.
    Thanks,
    Somnath

  • Can't Find the fixed days supply in the collected items.

    Dear All,
    after running the collection process , i can't find the fixed days supply item attribute in the collected data (from the table MSC_SYSTEM_ITEMS).
    Regards.
    Ahmad.

    Ensure that you have defined fixed_days_supply at the org-item level.
    If you have, then check if the collection is working properly by making some other change to an item (such as description change and change of the fixed lot multiplier).
    If those changes are not coming over, the problem may be with your Data collection. Can you run a full DC? Make sure that the snapshots have been refreshed properly.
    Hope this helps,
    Sandeep Gandhi

  • Stock Days' Supply Without Receipts - Negative despite ample stock?

    I am reviewing the MRP list for a material and find the following situation in MD06 as well as the stock / requirements list:
    SEALING WASHER;                                             3.0-     3.0-     3.0-     22.02.2011     216,071      PC     25,000
    Where the values are StckDS, 1st RDS, 2nd RDS, MRP date, plant stock, UOM and safety stock respectively.
    The plan situation considering only requirements and stock is as follows:
    22.02.2011     Stock                                                                                216,071
    22.02.2011     SafeSt     Safety Stock               25,000-     191,071
    05.12.2010     OrdRes     B445.112.261-00               6-     191,065
    05.12.2010     OrdRes     B445.112.275-00               6-     191,059
    22.12.2010     OrdRes     B445.119.578-00               40-     191,019
    17.02.2011     CusOrd     0041725938/000120/0001               350-     190,669
    02.05.2011     ----->     End of Planning Time Fence               0      0
    With more than enough stock to cover all current and future requirements, why would the stock days' supply go negative? I do not understand the calculation from the online help, where negative values are not explained.
    Edited by: Sriram N A on Feb 23, 2011 11:33 AM

    I overlooked th fact that there was a separate "project stock" segment that was being planned, for which the requirement was past due.  Hence the days' supply was negative.
    The coverage for use of normal unrestricted stock would be 999 as per the data.

  • QM Lot in Receipt Days Supply

    Hi All,
    We done the config for Receipt days supply as QM Lot to be considered for both 1st and 2nd Days receipt. But it is not considering. What would be the reason? Whether the issue is in QM or PP?
    Is there any possibilty that a particular status of QM lot will not considered as stock?
    Regards,
    Sureshbabu G.

    Hi
    In OPJJ - Availability Check control for the combination of checking group & checking rule ..check whether incl.quality insp stock option is ticked or not.
    Regards
    Brahmaji

Maybe you are looking for

  • Write Back Capability in Essbase

    Dear All, I read some where BSO has a direct write-back capability which is not possible in ASO, correct me if i'm wrong. Now my doubt is What is write back capability.

  • Improvements for z1

    So recently the z2 and the tab z2 hav been released with impressiv enew features so the other just passed flagship z1 sud hav these features so through a software update the z1 sud b made able to capture 4k ultra hd videos like the z2 both feature th

  • Help with LR4 trial download

    I'm trying to dowload LR4, but nothing is working!! Help!!

  • Migrating from Git to TFS 2013

    Hi, I have TFS 2013 and want to migrate GIT source code to TFS. I was able to migrate the code with history but want to ask for a way where by I can keep branches also intact. I want to give away from GIT and want to use Git support from TFS itself.

  • Migrating from PSE 5.0 on Windows XP to PSE 8.0 on Windows 7

    I am running PSE 5.0 on Windows XP on my old computer.  Half of my images (about 55GB--or about 15,000 images) are on the C drive under My Pictures  (lots of folders under there).  The other half are on an external  USB drive which I will be moving t