Task column not editable in Project Server 2013 (PWA)

Hello,
is that possible that Project's task column which are published on PWA cant be editable for any Project Manager, Team members?
We have  a scenario where my management team wants that after creating project from MS Project Professional 2013 (where we have provided standard template for projects to chose from ) needs to published on PWA. After publishing it, no one can't modify
task name in Projects but can add task if required.
Is it possible??

For the field:
Go to server settings, enterprise custom fields and lookup table,
Click on Create
Select task type, then formula,
Click on the field selector button and pickup the [task name] field under the text group,
Save.
For the view:
Go to the server settings, then manage views,
Select the view in question under "project" (for example tasks details)
In the field section, select your new field from the left side and add it to the right side,
Select the default task name field from the right side and remove it (it'll go to the left side),
Validate.
To validate:
Go to the project center and open your project,
Navigate to the schedule PDP and select your view tasks details)
Click on "edit" to open the project schedule,
Publish the project plan and check that your field is there and cannot be edited.
Hope this helps,
Guillaume Rouyre, MBA, MVP, P-Seller |

Similar Messages

  • Notification to Manager if task/Time sheet not approved in Project Server 2013

    is there any option if any user(Resource) updated his/her task & sent to his/her Manager for approval
    and Manager is not approved ( say in said timeline or days) then some notification should go to one step up (as Reporting Manager of that Manager who not approved task update & time sheet) in Project Server 2013?

    A solution could be to create email subscriptions on an SSRS report containing the non-approved task updates by manager.
    See reference here:
    http://bhushan.extreme-advice.com/email-subscriptions-for-ssrs-reports/
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, MCP |

  • How to make the 'Finish Date' field Editable in Project server 2013

    Hi All,
    In Project server 2013 on premises deployment, When I try to create a new enterprise project [Also in case of new custom project type], Only the 'Start Date' field is available. The 'Finish Date' field is by default taking the value of the 'start Date' itself.
    I am unable to make this 'Finish Date' field editable.
    Any pointers on this would be very helpful,
    Thanks
    Shanky

    Shanky --
    When you create a new project in either Microsoft Project Professional or Project Online, the system does not allow you to enter both a Start date and a Finish date for the project.  Here is how the software works:
    You enter the Start date of the project.
    You completely plan the project with tasks, task dependencies, task Durations, and assigning resources to tasks.
    Based on the Start date you provide, plus all of the task information, the software calculates the Finish date of the project for you.  So, you cannot provide both the Start date and the Finish date, nor is they any way to force the system to allow
    you to do this.  Hope this helps.
    Dale A. Howard [MVP]

  • Project Serial Number column in Project Server 2013 (PWA)

    Hi All,
    Whenever any new projects are created on Project Server 2013, they are arranged automatically by Alphabetical order. So i would like to know or need support through which i can create serial number column in Project Center so that projects are aligned. as
    per numbers.
    Kindly help..

    Hi,
    It is actually 2 questions. 
    First you want to create a unique ID for projects? Here is an excellent
    blog about this subject.
    Then you want to sort projects along a number? It could be a custom number field or the unique ID above. You just have to go to the server settings, manage views and go to the "sort by" section and select your number field.
    Note that the field used to sort the project center view must be in the view to be used as a sorting criteria.
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, P-Seller |

  • Project server 2013 - PWA: My Tasks page is not loading and disabled

    Hi
    i had an issue that suddenly occur for one of my users (just to him).
    My Tasks page is not loading, it shows "Loading" in the middle of the page and stuck that way, and also the Ribbon buttons are disabled.
    Anyone knows what could he had done to make this happen?
    The print screen is in Hebrew but i described what appears.
    Ofir Marco , MCTS P.Z. Projects

    Hi Ofir,
    I've had a similar issue in a previous version of Project Server. A corrupted assignment was causing this in my case. I found the corrupted assignment using the following procedure:
    Retrieve all published assignments & related projects for the user (in the database)
    Open each project one by one in MS Project & set the 'Publish' value to 'No' for the user's assignments and publish the project
    Everytime after publishing a project, retry to open the Tasks page
    At a certain moment your Tasks page should work again and you know now which project/assignment is causing the error, just replace the corrupted assignment by a new one and it should work again
    Hope this helps

  • Project Server 2013 PWA resource view

    Hi all, 
    Is there any way to see the detail information of a resource in PWA? In Project Professional 2013, we can check all the task\project the resource is assigned and all the planned work for the resource under resource usage view. However, we can not find it
    in PWA. Any suggestion?
    Regards,
    Anna

    Hi Anna,
    From the resource center, you can select one or more resources and check for their availability. You'll have a graph will all resources assignments by time periods and projects with a grid for the details.
    http://office.microsoft.com/en-us/project-server-help/view-resource-availability-HA010059812.aspx
    Hope this helps,
    Guillaume Rouyre, MBA, MCP, MCTS |

  • Project server 2013 PWA - Can't open project in PWA

    When attempting to open a project in PWA the following message is generated:
    An error occurred while opening your project. Give us a few minutes and try again. If this happens again, contact your administrator.
    It happens in all PWA sites.
    In addition you can open and edit the projects using Project Pro without any problem.
    Any suggestions?

    Can you run the below command in SharePoint Management shell:
    set-spprojectpcssettings -maximumworkerscount 260
    Once done restart the Project Services and then check the behavior.
    Cheers! Happy troubleshooting !!! Dinesh S. Rai - MSFT Enterprise Project Management Please click Mark As Answer; if a post solves your problem or Vote As Helpful if a post has been useful to you. This can be beneficial to other community members reading
    the thread.

  • Custom Column for Project Code Number & Search Box to search Content in Project Server 2013

    Hi all,
    I want to add a custom column in Project Center view for showing some Numerical Projects codes like 4523, 5248,8956 like that... Each code will represent Project assigned with that code in Project Server 2013. Also let me now if i can add some search box
    in Project Center page through which i can search Project Code or Project Name. Currently, provided search bar not working in Project Server 2013.
    Need it urgent..Kindly help

    Hi,
    If you want to add this column in a project center view, be careful to choose a project view in the "manage views" views' list. Also it must be a project custom field and not a task field. As Paul said, we assume that the field with the code exists
    and has been previousky created by you.
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, MCP |

  • Project server 2013 csom save and publish

    Hi,
    In Project server 2013 PWA when you edit project custom fields and save the queue job execute the following jobs: 
    - "Project Update from PSI"
    - "Project Publish Summary"
    - "Reporting (Project Publish Summary)"
    In my code (CSOM)  i can only use : " QueueJob Job = projChechedOut.Publish(true);"
    which is creating all these jobs:
    Project Update from PSI
    Project Publish Notifications
    Project Publish
    Project Checkin
    Prepare Project Web App Permission Synchronization For Projects
    Reporting (Project Publish)
    Project Workflow Check-in
    Synchronize Project Web App Permissions to Project Web App
    Synchronize Project Web App Permissions to Project Site
    Reporting (Project Sync)
    Is there way to "simulate" the save from PWA instead of fully publishing the project using CSOM,  because it is a lighter solution since my code is supposed to only set custom field value (if i only update, not publish it is written to the
    Draft) and secondly performance (less jobs) is better ?
    Thx in advance !!

    Hi,
    as an update to my post:
    - In PSI the method is project.queuepublishsummary(guid jobid, guid projuid)
    http://msdn.microsoft.com/en-us/library/office/gg200290.aspx
    the description says: Publishes the stage summaries of the specified project, in a partial publish operation.
    I am wondering if the equivalent method exists in CSOM. There is this method: PublishedProject.UpdateVisibilityCustomFields() but it seems doing exactly the same thing as publishing a DraftProject.
    Any ideas ?
    Thx

  • Access Project Server 2013 from personal mobile device

    Dear All,
    This is something great about Project Server 2013 (PWA) where users can view theirs task & other information on their personal mobiles, tabs etc. But i not able to access my company Project Server 2013.
    Is that i am missing something to install or configure PWA 2013 as i am admin for this application?
    Kindly let me know 

    That means your PWA site collection in not published externally so your mobile device can't resolve the DNS. If you connect your mobile device to the same network your Project Server environment is on, it will work as the DNS would resolve. You probably
    want to look at publishing PWA externally if you want to use it on mobile devices. Here are some links for you / your IT department, the process is the same for PWA and any other SharePoint site collection:
    http://www.brightstarr.com/sharepoint-technology-and-application-insights/securely-publishing-sharepoint-externally-using-web-application-proxy
    http://blogs.msdn.com/b/sambetts/archive/2014/04/02/setting-up-a-reverse-proxy-for-sharepoint-with-tmg-server.aspx
    http://www.isaserver.org/articles-tutorials/installation-planning/Planning-SharePoint-Publishing-TMG.html
    Paul
    Paul Mather | Twitter |
    http://pwmather.wordpress.com | CPS

  • Project Server 2013 licenses in use

    Is there any way to retrieve the exact number of PWA and Project Pro licenses in use for a Project Server 2013 instance?
    In older versions you had the 'About Project Server' page and for 2010 there was a SQL script. But this script does not work for Project Server 2013.

    Thank you Paul! That query works just fine.
    I reworked it a bit to suit my needs: take into account DENY and the fact that a PWA CAL is included in the Project Pro license.
    My query to list the licenses in use is below:
    SELECT
    PERM.Username,
    CASE WHEN PERM.LogonProDeny = 1 THEN 0 ELSE PERM.LogonProAllow END AS [ProLicense],
    CASE WHEN PERM.LogonPwaDeny = 1 THEN 0 ELSE
    CASE WHEN PERM.LogonProDeny = 0 AND PERM.LogonProAllow = 1 THEN 0 ELSE PERM.LogonPwaAllow
    END
    END AS [PwaCal]
    FROM (SELECT
    RES.RES_NAME as Username,
    MAX(LOGON_PRO.WSEC_ALLOW+0) AS LogonProAllow,
    MAX(LOGON_PRO.WSEC_DENY+0) AS LogonProDeny,
    MAX(LOGON_PWA.WSEC_ALLOW+0) AS LogonPwaAllow,
    MAX(LOGON_PWA.WSEC_DENY+0) AS LogonPwaDeny,
    CASE WHEN RES.RES_TYPE > 100 THEN 0 ELSE 1 END AS UserIsActive
    FROM pub.MSP_RESOURCES AS RES WITH (NOLOCK)
    INNER JOIN pub.MSP_WEB_SECURITY_CLAIMS AS SC WITH (NOLOCK) ON SC.ENCODED_CLAIM = RES.WRES_ACCOUNT
    LEFT JOIN pub.MSP_WEB_SECURITY_GROUP_MEMBERS AS GM WITH (NOLOCK) ON GM.WRES_GUID = sc.SECURITY_GUID
    LEFT JOIN pub.MSP_WEB_SECURITY_SP_CAT_RELATIONS AS CR WITH (NOLOCK) ON CR.WSEC_SP_GUID = GM.WSEC_GRP_GUID AND CR.WSEC_CAT_UID IS NULL
    LEFT JOIN pub.MSP_WEB_SECURITY_SP_CAT_PERMISSIONS AS LOGON_PRO WITH (NOLOCK) ON LOGON_PRO.WSEC_REL_UID = CR.WSEC_REL_UID AND LOGON_PRO.WSEC_FEA_ACT_UID = 'D2F88263-31C5-4FF5-BEAE-B98B26C5C116'
    LEFT JOIN pub.MSP_WEB_SECURITY_SP_CAT_PERMISSIONS AS LOGON_PWA WITH (NOLOCK) ON LOGON_PWA.WSEC_REL_UID = CR.WSEC_REL_UID AND LOGON_PWA.WSEC_FEA_ACT_UID = '7C40A2C2-FD15-44E3-8FD3-11B3E0A4E441'
    WHERE RES.RES_TYPE IN (1,2,101,102)
    GROUP BY RES.RES_NAME, RES.RES_TYPE
    ) PERM
    WHERE PERM.UserIsActive = 1

  • Project Server 2013 - Approved Tasks not applied to Project Schedule

    Environment Details: Microsoft Project Server 2013 SP1
    When an Resource completes a tasks within the Task or Timesheet page at the end of each day, the tasks is routed to the Project Owner for approval. The Project Owner (Project Manager) approves the task. During this process no errors are displayed.
    When the Project Owner (Project Manager) goes into the Project Professional 2013 client to view how the project is progressing, and update the project completion date, the updates is not applied to the project. 
    This worked for some time, but has recently stopped working with no changes made to the environment. Any help would be great, as our project manager's are manually updating the tasks prior to approving them so they can report back on the project each week. 

    Hello ProjMgrMatt
    Sounds pretty serious, but I think something is missing somewhere.
    Make sure that the Status Manager field is the same as the Project Owner. 
    Check to queue to be sure that nothing is stuck and waiting.
    Create a new project, publish, submit, approve, etc and see if it still happens.
    Cheers!.
    Michael Wharton, MVP, MBA, PMP, MCT, MCTS, MCSD, MCSE+I, MCDBA
    Website http://www.WhartonComputer.com
    Blog http://MyProjectExpert.com contains my field notes and SQL queries

  • Task custom field and formula custom field don't correspond Project Server 2013

    Hi people, I have an interesting case in Project Server 2013 SP1 CU Apr:
    I have a custom task number field called AM. This field get's filled by a PSI action with actual material costs from an external system.
    I also have a custom task cost formula field that is called AM*. This field is a formula field that has the formula [AM]. And summary tasks use the formula field as well.
    As soon as I create a project, assign costs in the external system and let PSI fill the values within AM I get correct values in AM. But nothing is calculated on AM*. If I edit the project in the browser and publish, check in and revisit the project
    AM* still isn't filled.
    If I open the project in MS Project Pro the calculation comes through nicely, however I do not want to use MS project Pro to see correct data in browser.
    Some tests I have already done:
    I have noticed that when I create a new calculated task field AM2*, this get's calculated correctly on the already existing task.
    I have also noticed that opening the custom field in server settings and just saving the field creates correct values on AM*.
    What is going on? I don't want to save the custom formula field every day... There are 11 custom formula fields in the environment at the moment.

    Hi Gary,
    Thank you for the quick response. Please note that the fieldnames are [AM] and [AM*]. There is a difference in field name due to the astrix. However I did think about the situation and changing one of the field names all together didn't do anything for the
    situation at hand.
    It looks like some kind of refresh thing, because without changing anything in the custom field just saving the field in server settings will turn op good values. However, values already turned up good in Project Professional 2013. And that suggest
    that there is a calculation error on the PWA side wouldn't you say?
    Anyway, thank you for taking time to look into this matter.
    Erik

  • After Migrating to project server 2013 some of my Mpp are not opening in project professional

    After migrating to project server 2013 from 2010. my some of mpp are not opening in project professional. 
    project professional taking some time and then showing checkin error. There are no logs on project server to this issue.
    but you can see these project in project server 2013 without issue. I have also tried the EditLink function. but result is same project professional not able to open. Check in error.

    Hello,
    Can you try this:
    Open one of those Projects in PWA to edit in the browser
    make a slight change (new dummy task etc.)
    Save and Publish from the web
    Close and check in from the web
    Wait for the jobs to complete
    Open project professional
    try and open the same project again from there
    Paul
    Paul Mather | Twitter |
    http://pwmather.wordpress.com | CPS

  • Project Server 2013: Project progress task available to only assigned resources.

    I have a project in project server 2013. In that I am preparing the project plan. Now I want that only the respective person to whom I have assigned the task can modify the % complete. Not even the owner can edit it.
    Shruti Vyas
    Advaiya Solutions Pvt. Ltd.
    Associate Development Services.

     Project owner can modify the the plan either from PWA or from MPP.
    As far as % complete is concerned for assignment only Resource who will be assigned to the task can fill the actual for the task either from Task page or from Timesheet page if Single Entry Mode is enabled. No one else can fill the actual for the task from
    Timesheet page and task page. AS assignment will be available to the only that resource who is assigned to the task.
    But Project owner can do the modify the project plan any time either from MPP or from PWA you can not restrict him/her. But as far as % complete is concerned do the setting 
    To prevent the project manager from updating a team member's actual time worked, select the Only allow task updates via Tasks and Timesheets check box. it will be
    available on server setting --> Task setting and display
    http://technet.microsoft.com/en-us/library/gg982960(v=office.14).aspx
    kirtesh

Maybe you are looking for

  • How to restrict number of rows display using ig:gridView

    Hi All How to restrict number of rows display using <ig:gridView datasource="{mybean.mylist}"> i am getting 10 rows using data_row . i wanna show only first 5 rows . pageSize ="5" will be ok . but it displays remaining rows in next page. but i want t

  • Anchor tags not working in FF

    Hello, I am new to website design and creation and I am having a rather weird problem. I originally designed my website using Google Chrome (which I will not do again). My website works fine in Chrome but certain links do not work in Firefox or Inter

  • How to merge DAC Analysis RPD with my existing RPD

    Hi all, I need to build OBIEE load completion report. So I need merge DAC Analysis RPD with my existing RPD.. Used following RPD ((http://rnm1978.wordpress.com/2009/07/23/mark-rittmans-obiee-repository-for-dac/) In my existing RPD ,I am using Oracle

  • Missing products.jar

    I downloaded the 815shipstd.tgz file. I read and followed the PDF file. I had to buy some extra MBs of Ram. I set up the oracle8i user and oinstaller and dba groups. OUI started up real nice. Then... the "Source" field wants a products.jar file. It d

  • T510 models NTF39RT and 4349R73

    Hi, I am looking at these two models: Lenovo ThinkPad T510 4349R73 Lenovo ThinkPad T510 NTF39RT having no idea on how to select one. Descriptions are identical except for video card, but the price is significantly different. Are there any other techn