Task Status in Project Server 2013

Hello,
I was wondering if someone could give me an overview of the Task Status options in Project Server 2013? I am a current 2010 user but we have not been able to use this feature in the past. Specifically, I am wondering:
1. Can I assign an entire task to a user? In 2010 I had to assign resources to a task and then update each assignment. I want to be able to assign the entire task and have the user tell me the Physical % Complete, Actual Start, and Actual Finish at the task
level. 
2. Is there any kind of built in what-if analysis feature? Can a program manager review the impact of the submitted status before accepting?
Thanks,
Jessica
Jessica Hancock

Hi Jessica,
Basically, task statusing and timesheeting has not changed between 2010 and 2013 versions. The first would be about the need (or not) to activate the Single Entry Mode, meaning a single interface for task statusing and timesheet. This DO matters since in
case you activate it, the task tracking method will be forced to "hours of work done per period". See in this
blog the others methods.
1- From the PM's point of view, you can in MS Project Pro or PWA assign one or more resources to a single tasks, creating then the corresponding number of assignments. From there, each single user assigned on this task will have to enter his own tracking
on his assignment. As you'll see in the blog, the % physical cannot be entered by the team member, only the % complete if the 1st method is chosen.
2- About this what-if analysis, the PM can click in the approval center on the "preview updates" before accepting or rejecting. He will be able to vizualise what will his project plan look like in case he approves the task updates versus what does
his plan actually look likes. See reference
here.
Hope this helps,
Guillaume Rouyre, MBA, MVP, P-Seller |

Similar Messages

  • Import Task progress in Project Server 2013

    Hi,
    Import task progress feature in Project Server 2013:
    I have updated actuals in tasks page in PWA 2013, and saved it. I tried to import it to timesheet page but the value already exists and the import task progress option is greyed out. i mean, when i enter actuals in tasks page and save it, the value automatically
    comes in timesheet page, then what is the use of Import task progress.
    Am i understood correctly?
    Please help.
    K.Gokulraj

    Hi,
    In my environment SEM is not enabled, i want to know how this option "import task progress" will be help full in time sheets.
    Once i enter task hours or task % complete  from My tasks then the actual hours in time sheets  are
    automatically filling. 
     Can anyone tell me
    what is the use of the  "import
    task progress" How this option is use full & in which scenarios we can use this option.  
    Thank You, Kumar KSV

  • Need to create a TASKS page with a filter default in PWA Project Server 2013 (Online)

    Never done this so, I am wondering How to go about or what I would need to create a simple PWA page like "Tasks" in Project Server 2013 online where it default to a filter that is set to not equal to the user that is logged on?
    \Spiro Theopoulos PMP, MCITP. Montreal, QC (Canada)

    Hi Spiro,
    The "my tasks" page or "my timesheet" are automatically filtered on the user currently connected. Unless you are using workarounds such as status manager or delegation, I see no way to bypass this.
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, P-Seller |

  • How to handle PSW approval task in project server 2013 through declarative workflow VS 2013

    Hello,
    Plz explain in detail handling PSW approval task in project server 2013 through declarative workflow VS 2013
    bcoz when using am posted on with this error when i try to approve the item
     "This list item  has not been created by the workflow.you cannot apply this content type"
    any help would be appreciated!!!!
    Thanks regards, Vignesh.

    I am also experiencing issues with this.  After the approval task is completed, the Workflow gets cancelled with the following message
    RequestorId: 60d96368-4cb4-b059-8086-604972a92e60. Details: System.Collections.Generic.KeyNotFoundException: The given key was not present in the dictionary. at Microsoft.Activities.Hosting.Runtime.Subroutine.SubroutineChild.Execute(CodeActivityContext context)
    at System.Activities.CodeActivity.InternalExecute(ActivityInstance instance, ActivityExecutor executor, BookmarkManager bookmarkManager) at System.Activities.Runtime.ActivityExecutor.ExecuteActivityWorkItem.ExecuteBody(ActivityExecutor executor, BookmarkManager
    bookmarkManager, Location resultLocation)
    All other desired workflow actions work as expected.  Emails are sent, project is moved from stage to stage, however as soon as the workflow approval task is completed, either Approved or Rejected, the Internal Status is changed to Canceled and the
    workflow fails.
    What is interesting is when the Approval task is completed, the approver will receive an email notification that the task was CANCELLED or DELETED....
    not COMPLETED, which is what would be expected.
    Has anyone seen this - any potential resolution?

  • Project Server 2013 - Approved Tasks not applied to Project Schedule

    Environment Details: Microsoft Project Server 2013 SP1
    When an Resource completes a tasks within the Task or Timesheet page at the end of each day, the tasks is routed to the Project Owner for approval. The Project Owner (Project Manager) approves the task. During this process no errors are displayed.
    When the Project Owner (Project Manager) goes into the Project Professional 2013 client to view how the project is progressing, and update the project completion date, the updates is not applied to the project. 
    This worked for some time, but has recently stopped working with no changes made to the environment. Any help would be great, as our project manager's are manually updating the tasks prior to approving them so they can report back on the project each week. 

    Hello ProjMgrMatt
    Sounds pretty serious, but I think something is missing somewhere.
    Make sure that the Status Manager field is the same as the Project Owner. 
    Check to queue to be sure that nothing is stuck and waiting.
    Create a new project, publish, submit, approve, etc and see if it still happens.
    Cheers!.
    Michael Wharton, MVP, MBA, PMP, MCT, MCTS, MCSD, MCSE+I, MCDBA
    Website http://www.WhartonComputer.com
    Blog http://MyProjectExpert.com contains my field notes and SQL queries

  • Task custom field and formula custom field don't correspond Project Server 2013

    Hi people, I have an interesting case in Project Server 2013 SP1 CU Apr:
    I have a custom task number field called AM. This field get's filled by a PSI action with actual material costs from an external system.
    I also have a custom task cost formula field that is called AM*. This field is a formula field that has the formula [AM]. And summary tasks use the formula field as well.
    As soon as I create a project, assign costs in the external system and let PSI fill the values within AM I get correct values in AM. But nothing is calculated on AM*. If I edit the project in the browser and publish, check in and revisit the project
    AM* still isn't filled.
    If I open the project in MS Project Pro the calculation comes through nicely, however I do not want to use MS project Pro to see correct data in browser.
    Some tests I have already done:
    I have noticed that when I create a new calculated task field AM2*, this get's calculated correctly on the already existing task.
    I have also noticed that opening the custom field in server settings and just saving the field creates correct values on AM*.
    What is going on? I don't want to save the custom formula field every day... There are 11 custom formula fields in the environment at the moment.

    Hi Gary,
    Thank you for the quick response. Please note that the fieldnames are [AM] and [AM*]. There is a difference in field name due to the astrix. However I did think about the situation and changing one of the field names all together didn't do anything for the
    situation at hand.
    It looks like some kind of refresh thing, because without changing anything in the custom field just saving the field in server settings will turn op good values. However, values already turned up good in Project Professional 2013. And that suggest
    that there is a calculation error on the PWA side wouldn't you say?
    Anyway, thank you for taking time to look into this matter.
    Erik

  • Project Server 2013 Task Reassignment Privileges Off? (Works in Timesheet)

    Version: Project Server 2013
    I'm trying to give our users access to reassign tasks.  I turned on "Reassign Task" on the Global Permissions and gave them security to "Assign Resource" on all their categories.
    I've tested this, and the "Reassign" feature is available and working then they are on the "Timesheet" page, but it is grayed out and gives the message:
    "This control is currently disabled.  You might not have the right permission level to use this, you might need to select an object or item, or the control might not work in this context."
    Again, the same task is available to be reassigned in Timesheet though.
    My guess is that this is a Security Permission issue, because my account which I am the Administrator and Owner of the project, I can reassign tasks on both pages.
    Any suggestions?
    Thanks,
    Justin
    It's me

    Hi Justin,
    Just for your information, as far as I know, the "assign resources" is not necessary for using the "reassign task" feature. The "reassign task" global permission is enough.
    To be sure to understand your issue, the "reassign task" button is available for you as admin or project owner, but not for users which you granted the "reassign task" permission to? Am I right?
    You are talking about global permissions but did you add the "reassign task" to the
    groups permission the users belong to?
    Silly question, but do the users have select a task before trying to reassign it?
    Hope this helps,
    Guillaume Rouyre, MBA, MCP, MCTS |

  • Creating Task in a Project of Project Server 2013 - Exchange 2013

    Hi,
    We have made an integration between Project Server 2013 and Exchange 2013 for the tasks of user.
    It's working fine but I've got a little question. Is it possible from Exchange to create a task in a specific project of Project Server ? Because when I create a task, even if I'm in the Exchange folder of the project, the task is created as a Personal Task.
    So, how can I, with Exchange, specify where I want to create my task ?
    Thanks,
    Patmol

    Hello Patmol,
    I was able to reproduce it. Any tasks added in exchange folder get added as personal task. This turned out to be the design behavior. A Task created in Exchange is considered to be a personal task. It can be added to the project plan from personal task by
    clicking on it and then selecting the Project Name.
    There is document which contains information on "My Tasks Aggregation in SharePoint Server and Exchange Task Integration". You can download it using below link
    http://www.microsoft.com/en-us/download/details.aspx?id=38799
    Hope this helps.
    Thank you,
    Kiran K.

  • Workflow status web part gives error when going back to previous stage (using GO TO) in Project Server 2013 workflow

    Hi,
    Workflow status web part gives error when going back to previous stage (using GO TO) transition activity  in Project Server 2013 workflow.
    Please guide how to create a workflow which restarts from a desired stage.

    Thanks for your prompt reply....
    It gives following error
    Workflow Status
    This Web Part was unable to load.
    Information that may be useful in solving this problem was written to the Unified Logging Service (ULS) log on the Project Web App with the following ID: e95a9c9c-1f68-90d7-0a3e-5951df70fec6
    For more information, contact your Project Web App administrator.
    what do you mean to restart the Project Server 2013 with different project name, please elaborate....

  • Create template for a task in Project Server 2013

    Hi everyone,
    I've got a little question, yes, again :-)
    Some user of Project Server haven't scheduled tasks, so they need to create their tasks by the "My Tasks" page, "Add a row" then "Add a new task".
    Unfortunatly, these users create a lot of little tasks but which are the same excepted for an information (like number of the bug ticket) and my bosses want to create a template of a task for create this kind of tasks very quickly but I do not find a way to
    do that.
    Is it possible with Project Server to do something like this ?
    Thanks to you,
    Patmol

    Patmol6 --
    There is no default functionality in Project Server 2013 that would allow a team member to create a new task from some kind of custom template.  It MIGHT be possible through custom software development, however.  Hope this helps.
    Dale A. Howard [MVP]

  • Project Server 2013 Tasks differ in project site and plan

    I have an Project Server 2013 enterprise plan that I created with an associated project site. The plan has tasks added to the timeline. The project site has a timeline webpart but the problem is the tasks added to the timeline differ.
    Does anyone have any ideas what could be the problem here? I checked the timeline webpart and it's correct.
    Thanks!
    [Images below].
    The following image is taken from the schedule PDP.
    This image taken from the project site depicts what is out of sync.

    Hi Guillaume,
    Yes, I've checked the queue while publishing the project. It's successful without any errors. I don't remember if I checked the ULS logs, but what I suspect is that it will say something along the lines of orphaned tasks in the project site.
    Anyways I've tried a number of things and I think the only 2 options I have are:
    Re-create the project site then sync the plan to it
    Ask MSFT for a script to resolve the orphaned tasks
    For the same of time, I'm going to assess how long it would take to re-create the project site.
    Thanks,
    Roland

  • Project Server 2013: Project progress task available to only assigned resources.

    I have a project in project server 2013. In that I am preparing the project plan. Now I want that only the respective person to whom I have assigned the task can modify the % complete. Not even the owner can edit it.
    Shruti Vyas
    Advaiya Solutions Pvt. Ltd.
    Associate Development Services.

     Project owner can modify the the plan either from PWA or from MPP.
    As far as % complete is concerned for assignment only Resource who will be assigned to the task can fill the actual for the task either from Task page or from Timesheet page if Single Entry Mode is enabled. No one else can fill the actual for the task from
    Timesheet page and task page. AS assignment will be available to the only that resource who is assigned to the task.
    But Project owner can do the modify the project plan any time either from MPP or from PWA you can not restrict him/her. But as far as % complete is concerned do the setting 
    To prevent the project manager from updating a team member's actual time worked, select the Only allow task updates via Tasks and Timesheets check box. it will be
    available on server setting --> Task setting and display
    http://technet.microsoft.com/en-us/library/gg982960(v=office.14).aspx
    kirtesh

  • Project Server 2013 Workflow Task Permissions Breaking Inheritance and Causing Workflow to Cancel

    I have an on-premise instance of Project Server 2013 with a workflow that includes an
    Assigned Task to assign users to Approve or Reject a WF phase. The workflow successfully assigns the task and notifies the user of the task. However, after (or possibly just prior) the user Approves the task, the workflow is automatically
    cancelled. 
    By default, the WF Task List is set to inherit permissions. After Approving an item, it appears that the list permissions automatically breaks inheritance, causing the workflow to cancel. This occurs somewhat regularly after resetting permissions to inherit
    from the parent site. Although there are stretches where the issue doesn't occur. I'm not sure what's causing the list permissions to change. 
    This issue occurs in both our Dev and Prod environments. Has anyone experienced this issue with permissions breaking inheritance automatically?

    Hi Vic,
    According to your description, my understanding is that the workflow was cancled when you created a workflow with Impersonation Step to break inheritance permissions.
    After breaking inheritance permissions, make sure the workflow initiator (the creator) still has least edit permission on the list.
    In addition, please check the workflow history list to find more information about this issue.
    I hope this helps.
    Thanks,
    Wendy
    Forum Support
    Please remember to mark the replies as answers if they help and unmark them if they provide no help. If you have feedback for TechNet Subscriber Support, contact
    [email protected]
    Wendy Li
    TechNet Community Support

  • Notification to Manager if task/Time sheet not approved in Project Server 2013

    is there any option if any user(Resource) updated his/her task & sent to his/her Manager for approval
    and Manager is not approved ( say in said timeline or days) then some notification should go to one step up (as Reporting Manager of that Manager who not approved task update & time sheet) in Project Server 2013?

    A solution could be to create email subscriptions on an SSRS report containing the non-approved task updates by manager.
    See reference here:
    http://bhushan.extreme-advice.com/email-subscriptions-for-ssrs-reports/
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, MCP |

  • Help needed Regarding Project Server - 2013 Workflow

    Hi All,
    I am new to Project server 2013 Workflow, hence please help me regarding this. Pardon me if this question is too trivial. 
    I have created a project type associated with a workflow and my workflow is as follows :
    So I am not doing anything here, I am just testing the workflow as mentioned by technet site : http://technet.microsoft.com/en-us/library/dn458865(v=office.15).aspx
    But it is mentioned that, after a minute or 2, the workflow state will change, also they have mentioned to press the Submit button.
    But in my case, the workflow is not moving to next stage [It just says 'The workflow is still processing - which never changes after hours] or I am getting the submit button (Submit button is disabled on the ribbon). Below is the state of my workflow :
    PS : I have made the user added to Portfolio managers group as well. But still I am having this same issue. 
    The Workflow manager is installed properly, and it is working fine in case of List workflow. I am facing the issue only wrt Site workflow for Project server 2013.
    Please help me to solve this issue.
    Thanks,
    shanky

    Hi Kiran,
    I am now facing issue while assigning a task to a person in the workflow.
    I am having a person named say 'John' , who is included in Project Manager as well as Portfolio Manager.
    And I am using a workflow as :
    Stage : Conceptual
    Assign a task to John (Task outcome to Variable: Outcome5 | Task ID to Variable: TaskID3 )
    Transition to stage
    Go to Approval
    But this is again giving issue as :
    Workflow Internal status : Cancelled
    Details: System.ApplicationException: HTTP 401 {"error":{"code":"-2147024891, System.UnauthorizedAccessException","message":{"lang":"en-US","value":"Access denied. You do not have
    permission to perform this action or access this resource."}}}
    PS : I have used the same Sharepoint admin account for 'Account Name' in ‘User Profile Sync' , Is this causing the issue? Please let me know.
    Thanks,
    Shanky

Maybe you are looking for

  • Satellite C850-1G2 can't upgrade Win 8 to 8.1

    When I try to upgrade Win 8 to 8.1 I get a message that says update Win 8 first. When I try to update Win 8 I get 132 updates. I have spent many hours trying to perform this task but the updates are not installed. I tried using the troubleshooting to

  • BBS function

    how can i wirte a bbs with email function using jsp/java servlet, anyone one give me example. e.g. the user can write a new post or reply to other user's post.the user can format the text by clicking button such as itial, underline, set color of text

  • IDOC_OUTPUT_ORDRSP - Multiple Issue Output

    Hi All, I have problem issuing multiple output for a Sales order Confirmation. BA00 is configured as: 1> I have assigned reqmnt 2 to the output BA00 2> Multiple Issue flag is checked 3> In Change Section, I have assigned FORM ZZ_ITEM_CHECK for progra

  • Advanced Adapter Engine

    Hi Guys ,          can u please tell me.hat is the use of Advanced Adapter Engine in 7.1 Regards Syed

  • Image related problem.

    Hi, I have created html report with type plsql anonymous block. my same application is running offline as well online. my code is working well online. image is displaying in html report. but when i run same code in off line application.image is not a