TECO Status on WBS Element

Dear Experts,
We have set the status to TECO for a WBS Element.
But it is allowing CAT2 Entry for the Activity Attached to the WBS Element.
I would like to know if there is a Status to Block costs , but not Revenues
Regards,
Shareeq
Edited by: K M AHAMED SHAREEQ HUSSAIN on Jan 26, 2010 12:55 PM

Hi Gurus,
I have a problem also with my WBS Element's status... maybe you can help me...
We have some cost orders related to some WBS Elemetns. We want to be able to close first the WBS Element, and leave the cost order available for new postings, only in the COST ORDER, and when necessary, close the cost order. But SAP does not allow to close a cost order if it's WBS element is close. It gives CJ656 message, but i can't make this message only as a warning.
Do you have any idea or clue about how to avoid this problem?¿?
Thanks a lot!!
Regards

Similar Messages

  • TECO Status in WBS ELement not allowing DP91 transaction for RRB

    Hi Team,
      I would like to look if DP 91 will not allow to Bill a  particular cost once the project is in TECO Status.
    Please confirm if this is configurable.
    Regards
    Vignesh R

    Thanks for your clarification.
    I have one more query which is not related to the Project status.
    When a Dynamic item is being populated in DMR after DP91 transaction,the summarisation of material or activity takes place and If there are A(50$),B(25$),C(25$) are the materials posted and grouped to form Dynamic Item "Material" and E(100),F(50$),G(50$) are the activity posted and grouped to form Dynamic item "Labor" based on grouping set in material determination,
    the DMR will reflect as
    Line               item 10
    Material         Material
    Price             100$
    Line                item 20
    Material          Labor
    Price              200$
    My client need a report which would give a detailed list of Dynamic item along with quantity and value by just entering the Billing document number.
    Like
    Material
    A   50$
    B   25$
    C   25$
    Labor
    A  100$
    B  50$
    C  50$
    What are the tables I need to refer to bring up a report as stated above.
    I couldnt get these details in AD01DLI and AD01DLIEF
    Regards
    Vignesh R

  • PS-Relationship between the system status in wbs elements and activities.

    Relationship between the system status in wbs elements and activities.
    We have the following requeriment with the system status in PS. We have a project with complete technically status and we want to undo the complete technically status in one activity without changing the complete technically status in the WBS element or the project.
    The reason is that after putting the complete technically status, users have to change the values in the P.O. We don´t want "open" all the project and we only need to "open" the activity where the P.O. are in.
    Is that possible? How is connected the system status between activities, wbs elements and the project son I can change the status in the below step without changing the higher steps?
    Thanks in advance.

    Hi Bala
    Yes, you have put it rather correctly.
    We use WBS elements for booking and posting time (client requirement). So what I am looking for is WBS Elements with the system status TERL (Time and Expense Released).
    I talked of the deletion flag also, because a WBS element flagged for deletion can't be used. It's one of the criteria to screen the WBS elements.
    I hope it's clearer now.
    Vinitha.

  • Function module to get the status of WBS elements IN Project Systems

    Hi,
    I am suppose to delete the WBS elements in PS depending on certain conditions. WBS elements that are to be deleted should satisfy the following conditions:
    1.     Status of WBS elements should not be  ‘AUC’ construction
    2. WBS element, which have cost association, like PO association or internal order association      shouldn’t be deleted WBS element does not have confirmed activities.
    3.     WBS elements, which have confirmed activity in association with their networks, should not be deleted.
    Either I can check for status of WBS for the above mentioned conditions or if u can suggest me some diff way I shall be grateful
    Need help in this regards.
    Thanks

    Hi
    Use the FM:
    <b>JV_GET_WBS_ATTRIBUTES</b>
    Regards,
    Sreeram

  • How to retrieve the User Status on WBS Elements

    Hello,   could someone please tell me  how to retrieve the User Status for WBS Elements using ABAP?  Which table stores this information.
    Thanks.

    if you have the OBJNR there was also another FM status  in Se37 [link>>|http://sap.ittoolbox.com/groups/technical-functional/sap-dev/changing-status-620444]
    also look in the similar requirement [discussion|http://sap.ittoolbox.com/groups/technical-functional/sap-bw/wbs-user-status-262089]

  • How to find out System Status of WBS Elements?

    Hi PS Experts!
    Please help me on my query.
    I want to get a list of WBS elements whose status is Released and can be used.
    If I try to search the table PRPS, it can only help me in finding WBS elements without deletion flag, with RA Key and so on.
    But the System status (such as Blocked for use) etc. is not present in the table.
    The one way I know is to get Object Number of WBS element from PRPS Table and insert it in JEST Table to get system status.
    Or alternatively, I give the WBS element no. in CJ20N t-code, and then check for System Status.
    These 2 methods work, if I do it one WBS Element at a time. If I need to get thousands of WBS elements in such a fashion, it's tedious.
    So could anyone help me on this issue?
    Thanks in advance,
    Vinitha.

    Hi Bala
    Yes, you have put it rather correctly.
    We use WBS elements for booking and posting time (client requirement). So what I am looking for is WBS Elements with the system status TERL (Time and Expense Released).
    I talked of the deletion flag also, because a WBS element flagged for deletion can't be used. It's one of the criteria to screen the WBS elements.
    I hope it's clearer now.
    Vinitha.

  • Cannot change Status of WBS Elements

    Hi Guys,
    I am trying to change the status of a WBS element. When i try to change the status of the WBS element, I get the message that " THere are still open down payments for the WBS ". What does this actually mean??
    I found the downpayment GL and looked for the open items. In the open items i was able to find a line item to which this WBS is attached. Then i tried to go to the document, in which this line item exists. Now in order to clear the open line item with the WBS, how should i clear that line item?? I want to know how to clear the down payment for this WBS or the found out line item.
    Thanks.
    Kris..

    Hi,
    Run the report S_ALR_87013536 - Plan/Actual/Down Payment as Expense for the particular WBSE that was showing in the error. Here you would see the value of down payment against the WBSE.
    Run FBL3N for the down payment G\L by selecting the WBSE from dynamic selection. Here you can get the open line items with WBSE and relavent PO.
    For clearing the down payment discuss with your concern MM  and FI dept.
    Hope this could help you.
    Regards,
    Nag.

  • Status of WBS element triggering confirmation of network activity ?

    Hello,
    Can you please let me know if the following requirement could be solved using workflow in PS module :
    Setting of 'Fully invoiced' status (FNBL) on WBS element in CN02 transaction should trigger the confirmation of network activity (transaction CN25).
    How this possibly could be done using workflow ?
    Regards, Wieslaw

    Hi,
       its possible to raise a workflow on Setting of 'Fully invoiced' status (FNBL) on WBS element in CN02 transaction .
      BOR: bus2054
      Do status managemnet to raise a  evnt of this BOR  ( BSVW  ).
      In the work flow in one of the method of extended BOR,
        do the confirmation of network activity thru  some bapis,etc.
    For confirmation:
       BOR: PSAFRU method:    NetworkConfirmation.Create
       check if this is helpfu
      create an instance of this nd check if this method helps.

  • Change user status for WBS Elements

    Hi All,
    I am working on a workflow related to PS milestones.
    When a milestone is achieved the user status has to be set for that WBS element and to all the WBS elements that are next to it.
    I have tried to use the FM (ran FM independently as standalone), CJDW_INTEGRATED_USRSTAT_CHANGE with PROJECT NUMBER as input, but it throws an error NOT FOUND.
    I have gone through the documentation of it also, which says that user has to prefil the structure PROJ before this FM is called, which i could not understand.
    So can please anyone tell me, about the usage of this FM and how to run it so as to change the user status.
    Thank you all in advance,
    regards,
    vijay

    it is possible to have status with radio button and check box, by keeping status with status number and without status number.
    But I doubt about your requirement whether it is possible in standard or not.
    Please search SDN forums for some exit / BAdii which you can modify status profile.

  • U00BFMultiple user status for WBS Element?

    Hello,
    I need to create multiple user status for a WBS element.
    I'm using the BAPI: BAPI_BUS2054_SET_STATUS
    CALL FUNCTION 'BAPI_BUS2054_SET_STATUS'
         Importing
           return = ls_returnbapi1
        TABLES
    I_WBS_SYSTEM_STATUS =
            i_wbs_user_status = it_wbs_user_status"--> This table contais 2 record, with the same WBS elements and diferent status
           e_result = it_result.
    I put several rows (two)  in the table it_wbs_user_status., I put two rows,  the WBS elements for the same item with two different status, but I get error because it says that the WBS  element is repeated.
    ¿Can you have multiple user status for the same element PEP? I try it in the transaction CJ20N too, and I don't Know.
    Thanks.

    In transaction CJ20N you can change user status for each WBS elements.
    Menu --> Edit --> Status --> User Status --> you can choise betwen "Set" or "Set & Pass On".
    I want BAPI, function , etc.... that do the same thar "Set" , not "Set & Pass On".
    BAPI_BUS2054_SET_STATUS = "Set & Pass On"
    Thanks

  • CJ20N - status release WBS element

    In transaction code CJ20N - projects, when you release the status of an WBS element, which BADI is called ?
    I need to transfer fields from the WBS element to the screen assets under construction, and especially to the tab 'allocations'.
    Regards,
    Alex Glorie

    HI
    Welcome to SDN
    [ Click This|Re: User Exits and Badi]
    Regards
    Pavan

  • To get system status of WBS Element in run time

    My requirement is to call a Z prorgam when the std transaction CJ20N is saved.
    The Z program should be called only when the system status is set as closed. I am using the BADI workbreakdown_update to call the Z program. Inside the BADI I need to check if the system status is closed or not. How can I capture the screen field value of System status ? Can any one help me?

    Hi,
            table TJ02 dont contain the updated record. this process should be triggered before saving. So I need to get the changed system status in screen. The table contains the status as Released but the screen field has the status as closed.I need to fetch the screen value.

  • Costs posted through FB01 to General Cost Element in TECO Status

    A general cost element whose system status was changed to TECO on 10/16/2009 has had costs posted from our Travel System in PR1 and also tested posting from FB01 to the same general cost element in a test client sucessfully.  Costs were posted on 12/5/2009  (PR1) and 12/10/2009 (test system).  This seems inconsistent with the logic that PS typically follows, that TECO does not allow cost postings.  The environment is ECC6 with Enhancement pack 4.
    Edited by: Rebecca Poling on Jan 11, 2010 11:11 PM

    Only system status CLSD (Closed) and account assignment locked don't allow actual post against WBS
    Here's the explanation on TECO status from SAP Help
    You use this status for WBS elements that are completed from a technical point of view, but where you still expect costs to accrue.

  • System status change of WBS element

    Hi everyone,
    We need to change system status of WBS element programmatically.
    So can anybody suggest me which function module can I use?
    Thanks & Regards,
    Anirban

    system stauts is set when some function is executed e.g.
    REL is set when WBS is set to REL - CJ20N edit->status-> release
    SETC ise set when settlement rule on WBS is creaed
    BUDG is set when you carry out budgeting via txn CJ30
    so it depends on what system status you want set, then execute the following business transaction manually or via program/ development.
    However for setting REL or TECO you might be able to use some function modules
    For WBS elements I would check out the following
    CNIF_STATUS_2054               Set/Read Status for BUS2054                                     
    BAPI_BUS2054_GET_STATUS        Read Status for BUS2054 (Work Breakdown Structure)              
    BAPI_BUS2054_SET_STATUS        Set/Reset Status for BUS2054 (Work Breakdown Structure)         
    CNIF_STATUS_2054_CANC_AALK                                                                     
    CNIF_STATUS_2054_CANC_CLSD                                                                     
    CNIF_STATUS_2054_CANC_DLFL                                                                     
    CNIF_STATUS_2054_CANC_LKD                                                                      
    CNIF_STATUS_2054_CANC_MDLK                                                                     
    CNIF_STATUS_2054_CANC_TECO                                                                     
    CNIF_STATUS_2054_CANC_USER                                                                     
    CNIF_STATUS_2054_SET_AALK                                                                      
    CNIF_STATUS_2054_SET_CLSD                                                                      
    CNIF_STATUS_2054_SET_DLFL                                                                      
    CNIF_STATUS_2054_SET_LKD                                                                       
    CNIF_STATUS_2054_SET_MDLK                                                                      
    CNIF_STATUS_2054_SET_REL                                                                       
    CNIF_STATUS_2054_SET_TECO                                                                      
    CNIF_STATUS_2054_SET_USER

  • How to Control authorization for users with certain status for level 2 WBS Element

    Dear All,
    Is there any standard way or enhancement available to control authorization for users with certain status for WBS Element i.e. for example
    Pre-requisite:
    There is only 2 level of project i.e.
    Lev_ WBSE_______Description
    1___ 7-14.E_______summay outage controller
    2___ 7-14.E.2310__ Plant/unit # 2310
    2___ 7-14.E.2310__ Plant/unit # 2220
    Project Controller  (authorization role assigned "Z_PS_OP7_OTGCON_C") have all project level authorization
    Plant/Unit Controller (authorization role assigned "Z_PS_OP7_PLNTOTG_C_2310") have only level 2 authorization with enhancement that we did in system by Z table.
    User ID_ Plant #
    123345_ 2310
    122455_ 2220
    Issue:
    After System Status released and User Status approved the WBS basic date for Plant/Units should be restricted from updating/changing by Plant/Unit Controller level and only project controller should have this authority.
    Solution required: 
    Can any one tell how to control this scenario either by standard or enhancement available to control authorization
    BR
    Saqib Usman   

    Hi,
    Did you explore SAP Enhancement CNEX0002 Using Transaction CMOD?
    Thank you and regards,
    Varshal Kachole
    The SCN Rules of Engagement

Maybe you are looking for

  • Executing BPM's in sequence

    Hi Gurus, Is there a way that we can execute different BPMs in sequence? Like as a workflow. Please input your views. We have developed different BPMs and need to integrate them together in sequence. 1) We have to make it as a huge BPM with all the s

  • Error installing oracle 10g in centos5.3

    Hi, i got this error while installing oracle 10g in centos... Checking Network Configuration requirements ... Check complete. The overall result of this check is: Not executed <<<< Recommendation: Oracle supports installations on systems with DHCP-as

  • Related to business partner

    hi, i want to assigne   balance of one business partner to another  but when i am going to journal entry and press the tab key then G\L account is open  so  what is the solution for this problem  regards   sandip

  • Is it possible to convert characters to movieclip symbols?

    I want to do something like when ppl type in some texts, the program will convert every character of the text to a movieclip symbol, so I can animate individual characters. Is there a way to do something like that? Thx in advance~

  • How do I find out if I can download music from South Africa? iTunes does not have a Music or Video department on my screen

    How do I find out if I can download music in South Africa.  iTunes does not have a logo for Music or Video when I open it - oly for App store, Podcast and iTunesU.  I am doing something wrong?