Terms of payment with odd days

I need to set up a new payment method that Due on 2nd working day after 45 days from baseline date .
I try to first config "Due on 2nd working day after 30 days from baseline date ."
in payment term tab.
Term1. I define no.of days as 2. additional months: 1, but I can't save it.it shows error:
No set day has been specified for condition 1
Message no. FC117
how to solve this? I find I can't input 1.5 month in additional months field. any solution? thanks

No. I already mentioned that 2nd working day, it is not fixed day. if you use fixed day, if the second day is Saturday. you fail my basic requirement.
my second requirement is after 45 days.
anyway, thank you for reply

Similar Messages

  • Terms of Payment with Working days

    Hi SAP GURUs,
    I am new to SAP ISU...I need to create a terms of Payment where a payment will be made in say 15 working days and not in 15 calender days.
    Require your help on the same
    Regards,
    Pradeep

    Financial Accounting (New)->Contract Accounts Receivable and Payable->Basic Functions->Postings and Documents->Maintain Payment Termsu2026Double click on the payment terms...
    We can assign factory calender id over there.
    Regards,
    Siva

  • Payment terms in OBB8 with 50 days with two day of payment.

    Hi Experts,
    We need some helpu2026. We have to create a payment terms in OBB8 with 50 days with two day of payment, day 05 and 20.
    Requisites:
    If the bill expire date is between the days 01 and 15 from month X, the pay is realized the day 05 from month X.
    If the bill expire date is between the days 16 and 31 from month X, the pay is realized the day 20 from month X.
    Any idea
    Best Regards,
    Driss,

    Hello Driss
    In the payment terms , where you define cash discounts .
    You can configure the requirement you specified .
    Maintain as follows :
    Term ,    Percentage     ,        No.of days      ,     Fixed date   ,   Additional month
    1         ,       0.00%            ,        15              ,            05           ,           0
    2         ,       0.00%            ,       31                 ,         20             ,         0
    I think this should work fine
    Let me know if this is ok
    Ravindra Kumar

  • Terms of payment- 2 additional days are considered for giving discount

    Hi All,
    I am facing a problem with Terms of payment.
    I have configured a new terms of payment as "34 days -2% and 35 days net due".
    Surprisingly it is giving discount even if i pay on 35 and 36th day also. In OBB8, i have taken Document date as default date for calculating days and i have not given any additional days.
    This is text displayed at OBB8 "Within 34 days 2 % cash discount         Within 35 days Due net".
    Eg: I post doc on 01.04.09 and bline date is 06.05.09.
    Even when i pay this on 06.05.09 or 07.05.09, it is giving 2% discount.
    Please let me know why system is considering 2 additional days. This problem is there even in other payment terms also.
    Ours is a US based project.
    Regards,
    Rajanikanth.

    Hi Rajini,
    In your case, system allows due date + 2 days for grace days. Therefore the actual due date in your case is  05.05.2009 + 2 days = 07.05.2009. System will not calculate cash discount @2% on or after 08.05.2009.
    I think you are maintainin "Tolerance Group for Customers/Vendors.
    Please go to Transaction Code: OBA3. In OBA3, there is a field for "Grace days due date". I think you have given 2 days as grace days there. You have to remove grace days there and try it. Now system will not give 2 days as grace days while calculating cash discount.
    Hope this helps you.
    Regards,
    Kannusamy S

  • Terms of Payment with Posting key 09

    Hi,
    My client is a construction company which undertakes customer projects. Scenarios of retention amounts are very common in construction industry. We have a scenario where in at the time of sales invoiceing the amount of the invoice gets divided in three parts;
    1. Billing amount to customer
    2. Retention amount 1 (Due after 1 year from invoice date)
    3. Retention amount 2 (Due after 3 years from invoice date)
    We are using payment term to split these amounts. Client want the retention amount to get debited to a customer special GL. The accounting entry will be-
    01  - Customer Dr - 8000
    09R-Customer Dr - 1000
    09R-Customer Dr - 1000
            Revenue Cr -           10,000
    The issue is, payment term is not getting populated with posting key 09. I tried changing the field status for both posting key as well as for GL field status.
    Requesat to please let me know how the payment term can be displyed with posting key 09.
    Thanks & Regards,
    Ajay Gupte

    Dear Ajay,
    To make the field You need ready for input for posting
    with special G/L indicator, the following Customizing setting is
    necessary:
    Financial Accounting -> Accounts Receivable and Accounts Payable ->
    Business Transactions -> Outgoing Payments -> Automatic Outgoing Payment
    -> Payment Method/Bank Selection -> Configure payment program -> All
    company codes -> double-click on corresponding company code -> under
    Vendor -> 'Sp. G/L transactions to be paid' you should enter the special
    G/L indicator A,B,C, etc.
    As explained in note 4683, the only standard possibility to get the
    field payment terms on creating a posting with a special G/L indicator
    is by setting in the payment program configuration (trans. FBKP) for
    'All company codes' for customers/vendors 'Sp. G/L transaction to be
    paid'.
    Mauri

  • Payment term thread continuation with that

    Thank you all.for your  reply to previous thread of mine.
    So in relation to above my requirement is that Cash discount is based on payment term and differs from material to material.
    Suppose i maintain a cash discount of 1% for material x and the payment term is payment in 7 days then this 1% should be active on the receipt of payment from the customer within 7 days only otherwise the cash discount does not apply.
    Please guide .as no percentage is maintained in payment term because it will be applicable for all the material for that particular customer.

    Suppose you have payment term
    0003 :
    Within 14 days 3 % cash discount
    Within 20 days 2 % cash discount
    Within 30 days Due net
    If you use the condition type SKTO, the payment terms will be activated in the billing document and when the customer makes a payment if the payment date is within 14 days 3% gets activated automatically, within 20 days then 2% and from 20-30 days no cash discount.
    Regards
    AK
    Hope I was able to explain properly

  • Terms of payment in MM

    Hi:
    Our client has two types of terms agreed with their vendors, only one of this term is applied on PO creation in MM. One is for Day based payment terms like payment after 30 days etc, other payment term may be 50 % advance 20 % on delivery (GRN) and remaining to b settled after invoice verification. For payment term like 30 days net, 60 days etc i-e day based payment terms it is right to have them created in OBB8 and assign them to vendor master,PO or invoice but what about the terms like 50 % advance , 50 % after invoice etc. I do not want them to create in OBB8 , is there any way in MM to cater this.
    Thanks
    subject was edited by: Jürgen L

    there is only one customizing transaction to create payment terms, no matter if they are used for customers, vendors or both (this is just a flag)
    the terms are stored in table T052, the central place used by SAP to control its processes based on payment terms. And this table is maintained through OBB8.
    MM does not have anything independent. Of course something can be entered as text. but this cannot be used to control anything

  • Change term of payments in Documents

    Hi
    Can the terms of payment be changed to the documents which are already posted.
    Say i posted documents with 30 days grace, now i changed the terms of payment to 20 days. But the changes did not effect documents already posted. Is there any why by which  i can change those documents to 20 days grace
    Regards
    KM Naidu

    no i dont think u can change the paymentterms in posted document
    if u have posted GR and iv is not done then u can change payment terms in IV
    but not in posted IV
    reward if usefull

  • Displayment  of terms of payment

    Hello,
    I need to create different terms of payment but I have a problem.
    If I create the same term of payment with two different limit days when I display the list where appear all the terms of payment, the system duplicate each term.
    I want to see each term of payment only once, how can I do it?
    Than you very much
    Best regards
    Beatriz Amezua

    Hi....
    Adding to the above, if you would like to see the terms of payment with some identification you can have your own narration in the sales text filed of payment terms.
    For example two terms of payment
    0002 and Z002 are to be created and identified separately with narration as per the day limits:
    for 0002--sales text field you can enter PT 0002-Day limit 10.
    Z002-PT 0002 -Day limit 15.(with this kind of narration in sales text you can relate both PT)
    Codes for payment terms need to be created separately as Ashok narrated above.
    Assign points if this is useful.
    Regards
    Aravind

  • Payment term key with limit days in Extended Classic Scenario

    Hello,
    We have an SRM 4.0 implementation (SRM Server 5.0 with Support Package
    9) using the Extended Classic Scenario.
    When a shopping cart is created, it must be approved, and then a
    purchase order is generated (first locally at SRM, and then is
    replicated to the backend).
    The problem is that the payment term key (field at header level EKKO-
    ZTERM) of the backend purchase order is empty, only in cases when we use a payment term key which have several different values for the
    field "limit days" (T052-ZTAGG in backend, BBP_PAYTERM-ZTAGG in SRM).
    Example:
         ZTERM     ZTAGG
          K180           09
          K180           19
          K180           31
    If the payment term key selected has no several values for the field "limit
    days" (one single entry), the payment term key arrives correctly at the backend purchase order.
    Example:
         ZTERM     ZTAGG
          E000           00
    In SRM table BBP_PAYTERM we have upload the backend payment terms
    (using report BBP_UPLOAD_PAYMENT_TERMS). In other threads it is said that you must copy the entries generated by the report with the logical system of the SRM system, but in extended classic scenario it seems to be not necessary.
    We have already implemented note 846009, in order to use always the backend payment term, but the error didn’t get resolved.
    We have our vendor business partners mapped to the local and backend
    purchasing organizations, but it is only necessary indicate the Payment term key for the Backend Purchasing Organization.
    Regards

    hi,
    Pls see the foll notes:
    Note 576349 - Terms of payment in the ECS
    Note 541934 - Modification note: Copying base date from T052
    Note 953999 - ECS: Terms of Payment values not in PO header
    <b>Note 940453 - Backend payment term data not updated in the extended PO
    Note 945018 - Incoterms data not transferred to the back end</b>
    BR,
    Disha.
    Pls reward points for useful answers.

  • Multiple payment term with different day limit

    We have three payment terms with multiple day limit. for example: ED11 (day limit 10),  ED11 (25 day limit) and ED11 (32 days).
    User enter just ED11 but i dont understand how system understand which out of the three is the require payment term.
    Users feel that due date calculated is wrong. In most case it calculate the due date exactly based on the days mentioned in the payment term. In all cases, days mentioned are 90 days.
    In one case, due date if it is (just 90 days) 30/04 but user feels it should be 10th May in the following (obviously he is reffering to ED11 daylimit 10). In this case, SAP calculate 90 days. Is it because of too many payment terms which same name.
    Best,
    Bala

    Hi,
    Please go and check the following path.If teh user wants no. of days as 10, then it should be maintained as 10 in the no. of days field in Payment terms. I think in your case it may be maintained as 90.
    IMG->Finacial Accounting->General Ledger Accounting->Accounts Receivable and accounts Payable->Business Transactions->Outgoing Invoices/Credit memos->Maintain Terms of Payment->Check No. of days in Payment terms.
    Assign points if u consider this to be useful.
    Thanks,
    Prithwiraj

  • Payment term with fixed day but exclude weekends and holidays

    Hello,
    our customer has a requirement to have payment term that is like this:
    Due date: fixed day 15th next month.
    If due date falls in weekend or holiday due date will move to next business (working) day.
    We have working payment term which is always the 15th on next month but it falls to weekends.
    I was searching SDN found something but not working.
    Could you please send me a step-by-step configuration how to exclude the weekends and holidays?
    Thank you a lot.
    Best regards,
    Lubos

    Dear Lubos,
    unfortunately waht You need to have It is impossible into the SAP Standard System.
    Please be aware that the vendor invoice has two relevant dates:
    Baseline date   > INVFO-ZFBDT
    Due on   > INVFO-NETDF
    The Baseline date is managed by the "Term of payment",  transaction obb8, frame
    "Baseline date calculation" where You can put for example :
    Fixed day            30
    Additional months     3
    This means that if You put as Document date 01.01.2009, the baseline date
    will be 30.04.2009 (fixed day 30, additional months 3).
    The "Due on" date will start ALWAYS from "the Baseline date"
    (that in my example is 30.04.2009) and according to the below
    "Term of payment" , the System will add
    31 days, so the Due on date will be 31.05.2009.
    Term      Percentage   No. of days  /  Fixed date  Additional months
    1.               %      31
    2.               %
    3.
    You could think to use the FI substitution to reach Your goal.
    Mauri

  • Terms of payment - More lines in Terms, %of Discount & No. of Days

    I am facing the problem of defining more than 3 cash Discount rates while defining Terms of payment in OBB8,
    the requirement is 90 days credit with following discount rates:
    Days                %of Discount
    0-5                    6
    6-20                  5
    21-35                4
    36-50                3
    51-65                2
    66-80                1
    net 81 days
    Is there any standard settings to be done for this, or any work around can be done
    Immediate help will be appreciated.
    thanks
    Rakesh
    Rakesh

    Hi Rakesh,
    this is only a suggestion not a solution which I am  specifying. I could have tried on my own but today I dont have access to SAP.
    Check whether we can devide one terms of payment(TOP) in to three TOPs by using day limit field
    When you create a TOP, say RAK, in the day limit field provide 10,20,30 like this and try
    Regards
    Prastiksha

  • Terms of payment in sd module along with the fico interface

    Explain breifly abou the terms of payment in sd module along with the fico interface?

    Hi,
    See the the SAP documentation of Daylimit.
    For terms of payment which depend on whether or not the baseline date is
    after or before the 15th of the month, you can define a two-part payment
    term under the same terms of payment key. The terms of payment key is
    expanded by the day limit entered here. Thus there are two entries in
    which different terms can be specified.
    In your case,
    if rbkp-bldat is between 1st and 5th of the month, extract
    data related to t052-ztagg = '05'.
    If rbkp-bldat is between 6th and 20th of the month, extract
    data related to t052-ztagg = '20'.
    if rbkp-bldat is between 21st and end of month, extract
    data related to t052-ztagg = '31'
    Regards
    Vinod

  • How to Create payment term for -Net Due 1st Day of Second Month Following

    Hi,
    We need to add a payment term for "Net Due 1st Day of Second Month Following Delivery". We need this to be in the system as soon as possible as we just were told of a change in terms for our client effective May 1st.
    Kindly advice me how to select the dates in OBB8?
    Thanks
    Supriya

    Hi Supriya,
    In OBB8, create a new payment term with the following settings -
    Default for baseline date = No default
    Payment terms/Term 1/Fixed date = 1
    Payment terms/Term 1/Additional months = 2
    This payment term will ask you for a baseline date on document entry. You can give the delivery date as the baseline date. If required, this date can be changed after posting the document also.
    Hope this helps.
    Regards,
    Mike

Maybe you are looking for

  • Little stuttering on 3e monitor

    After installing a 2 videocard to play the 3e monitor and some help from the forum this works principally. One problem in this setting stay's. It looks if ones or twice per seconde the picture on the monitor "freezes" shortly, or plays back two frame

  • BAPI for Posting Asset Documents

    Dear All, I have a requirement where I have to post Asset Accounting Documents. The purchase is done from the Vendor. I need to pass the Vendor code, Special GL Indicator and reconciliation Account in one line item and Asset Number in another line it

  • Pushbutton

    Hi friends, I need to display two pushbuttons and two parameters on the selection screen, when I click one push button I have to display one parameter and hide the another parameter,same with the second pushbutton.Please give me some sample code. sat

  • SAP DB connect errors

    Hi      We have an SRm 7.0 running on windows 2003 64 bit the database is MS-SQL 2005. We keep getting the connect and disconnect errors. DB-error 11 BVV BVY BV4 etc. I dont see a place to attach the screen shot here.

  • Ipad 3 Sound won't work in games