The delivery schedule lines don't get created automatically on MRP run.

Hi All,
The delivery schedule lines don't get created automatically on MRP run for subcontracting material.  I have maintained source list as follow eg.
Valid from | Valid to | Vendor | Porg | PPI | Agreement | Item | Fix | MRP | MRP area
02.11.2009 | 31.12.2999| XYZ | XY01|     |AA0000XYZE |10 | X |2 | ABC
Could you please help me about this issue
Thanks in advance.

Hi Amit,
Please ensure the value of Special procurement key in the MRP2 view for the material. It should be maintained as 30 - subcontracting.
Thanks and Regards,

Similar Messages

  • Schedule lines are not coming for HALB after MRP run

    Dear All,
    I am not getting schedule line after mrp run, inspite of all required setting only purchase requisitions are coming.
    Material type is HALB and involve a subcontracting process (30). For raw material I am getting the schedule line but in the case of HALB, it is not coming.
    Pls let me know if I am missing something and guide me further on this.
    Thanks & Regards
    Kundan Kumar

    Hi,
    In transaction OMDT you have to enable the indicator create schedule lines
    In MD02 MRP control Prameter here select the Delivery schedules -3- Schedule line. Processing Key as NETCH and Planning Mode - 3 delted and recreated.
    Maintain source list ME01, in that put MRP indicator as '2' i.e. schedule lines via MRP.Put your agreement no in that.
    If u run MRP properly u will get schedule lines automatically in ME38.
    Make the schedule agreement, make it source relevent in the source list make is FIX and MRP indicator as 3.

  • Regarding the Delivery schedule item in Production order

    Hi Gurus,
    Kindly can you let me know what are the settings to be done for getting the delivery schedule line number in the production order along with the sales order and item number for a MTO scenario.
    Regards
    Anand

    If you're working with stg. grp 20, it should do what you're looking for.
    If you're not sure, do this in your sandbox -> assign the stg. grp in material master, create a SO for this material, run MRP, convert the planned order to production order & verify the results.
    To know more about this stg. grp you can go thru SAP help or just do a search in this forum or maybe wait for someone to paste the links for you.

  • SCHEDULE AGREEMENT-DELIVERY SCHEDULE LINE ITEM PRINTING

    Scheduling agreement is created in ECC.
    Delivery schedule line items are generated using APO and CIFed over to ECC.
    Upon displaying in ME38 in ECC, the delivery schedule line items are appearing as required. The problem is that no output type is displayed for condition type LPET even though the settings are done & condition records are maintained.
    Can someone throw some light on this?

    Hi Anil ,
    Goto Transaction NACE , Select Application EL and then Click on O/p Types.
    Select your o/p and click on Processing routines.
    Make a copy of medium 1 and change it to 5. The program , Form , Form routine would remain the same.
    Maintain condition records with medium 5 in MN10.
    Ensure that email address exists in Vendor Master.
    Check with ur Basis to make sure that the setting are done in Transaction SCOT for sending document via PDF.
    Create a new Agreement and test it.
    Regards
    Ramesh Ch

  • Scheduling agreement, unnecessary delivery schedule lines

    Hello
    We use Scheduling agreements for purchasing spare parts. The MRP run checks the warehouse requirements and creates delivery schedule line to scheduling agreement.
    Now the MRP run creates unnecessary delivery schedule lines to scheduling agreement if the earlier created delivery schedule line's delivery date has been changed manually.
    For example,
    Today the MRP run finds requirement for one article  and creates the delivery schedule line, where delivery date is 2.9.2008 (determined from articles basic data).
    The Vendor confirms the delivery date as 3.10.2008 and the purchaser changes manually  (transaction ME38) the delivery date to delivery schedule line accordingly and prints the created message.
    The next MRP run creates new delivery schedule line, where delivery date is again 2.9.2008.
    now there are two open delivery schedule lines for this article with delivery dates 3.10.2008 and 2.9.2008.
    Why the MRP run does not notice the existing delivery schedule line with the new delivery date 3.10.2008?
    we have changed delivery dates manually several years and this has never happened before.
    could you please help me to resolve this.
    Thanks in advance,
    Srikanth

    In addition to the above post,
    as you changed the date manually from 2nd to 3rd....
    so there are was no report for 2nd generated ulitmately...and if generated it was changed...right...
    so when you again run the mrp...the system will generate one more pr for the same article....
    this ultimately happens because of the set del dates in the MMR as i told above..
    Hope it helps..
    Regards
    Priyanka.P

  • Delivery Schedule line date customer receiving day dependant

    Hello Experts,
    We are working with transfers between plants with STO UB. Tha availability check is activated at storage location level and it works correctly. Now, some plants have a special day for receiving goods. Say, Plant A receives on monday, plant B receives on tuesday, Plant C receives on wednesday.,...
    We want to influence the delivery schedule line based on the goods receiving day of the requesting plant?
    ex : if the system determines delivery schedule line date on 31/01 but the receiving day of the plant is monday, so the system have to update this date to the next receiving day (04/02 = monday)
    Thanks for your help.
    Regards.
    A.

    Hello Experts,
    We are working with transfers between plants with STO UB. Tha availability check is activated at storage location level and it works correctly. Now, some plants have a special day for receiving goods. Say, Plant A receives on monday, plant B receives on tuesday, Plant C receives on wednesday.,...
    We want to influence the delivery schedule line based on the goods receiving day of the requesting plant?
    ex : if the system determines delivery schedule line date on 31/01 but the receiving day of the plant is monday, so the system have to update this date to the next receiving day (04/02 = monday)
    Thanks for your help.
    Regards.
    A.

  • Why GR performed on MRP generated delivery schedule line (unconfirmed)?

    Hi Gurus,
    Need some advice from you all, I have a scenario here which MRP generated the delivery schedule lines for material A on 10.08.2011 - 124 KG.
    User review the MRP result and didnt confirm the line, but she added in manual line on 11.08.2011 - 124KG.
    On 11.08.2011, warehouse performed GR on the delivery schedule lines. It's found that GR was actually updated into the delivery schedule line generated by MRP (10.08.2011) and not the manual line confirmed by user. (11.08.2011).
    User is questioning now why the GR able to be performed on MRP generated line which had not been confirmed? Any guru can share with me the fact and good note regarding this on MRP? Thanks!
    Michelle

    Hi,
    Since we are talking here about schedule lines, these are open for GR when the delivery schedule is send to the vendor.
    In your case you had a quantity open for 10/08/2011 generated by MRP, then the user added manually another line on 11/08/2011. After this the user will have transmitted the delivery schedule which makes that both the items where marked as transmitted and thus open for GR.
    Now when the goods come in the system will post against the first open schedule line that is found until this is fulfilled and then switch to the next open line at the moment of GR. So this is why the GR was put against the MRP generated schedule line as this one was the one with the earlier date.
    Regards,
    Peter

  • VL10G is not creating delivery for some of the confirmed scheduled lines

    Hi, I was trying to find the reason why we are getting a very generic error message (Message type V50R ID 036 - The document could not be delivered.) for some of the confirmed schedule lines when executing VL10G in batch and no delivery document is created. Those orders have confirmed scheduled lines and inventory has confirmed to have stock. However, when the VL10G is executed in background, the sales order line items will be captured into the list but when creating delivery, the systems is showing the above error message.
    From debug, found out the message is generated from LV50R_VIEW43.
    We went through lots of OSS notes but nothing seem to ring a bell here. We are using ECC6, list type = index list.
    The error message is very inconsistent. The same documents will be dropped for delivery after several days without any change to any of the sales document or inventory level.
    Some of the note mentioned the parallel processing lock on ATP check for the material may be the reason for the error however we are not using any parallel processing in VL10G. We also checked the index table VEPVG has all correct entries and all the entries are being selected into the delivery due list. Error happens when the delivery is trying to be created.
    Any advice is appreciated.
    Thanks.

    Hi ALL,
    Any suggessiton on the below issue.
    We have batch jobs to process the DDL for the STOs, but some of the line items of the same STO is not picked up by batch job, (VL10B is assigned in the batch job, i checked the variant and configuration, everything seems to be fine, when i try to process the DDL through VL10B manually by giving the STO number only, the VL10B program is not picking the STO, but the same STO can be processed through VL10D, what could be the problem and why the VL10B program is not recogonizing the STO for the delivery creation.
    We are using ECC 6.0
    Regards,
    Rajesh.R

  • *MRP unable to create Delivery Schedule Lines in MM Scheduling Agreement*

    Hi Experts,
    I need your help...
    The issue is, in-spit of maintaining Source List with an u201CScheduling Agreement with item No.u201D & u201CSource List Usage in MRPu201D as 2 (Record relevant to MRP. Sched. lines generated automatically), MRP run does not generate Schedule Lines, instead PRs are created.
    Please help me to understand such behavior and fix the issue as the requirement is to generate Schedule Lines only.
    Thanks,
    Pratap

    Hello
    Please check
    1) Source List maintained properly in terms of Material # ; plant # ; proper POrg ; Schd Agr # and line item# ; proper validity date & MRP relevant indicator
    2) Please also check Quata arrangement if you are using. whether % is maintained correctly against the vendor
    3) MD03 , Delivery schedules- should be 3
    4) check your planning horizon whether it is NETCH or not
    5) check material master -MRP2 view, Procurement type is F- external procurement, schedule margin key if you are using
    if everything above is set, then I feel it should work
    Also please verify-
    lot size, safety stock and the corresponding prod volume for MRP input v/s the stock available in MMBE
    example.
    MD04, we can see the open del lines.
    if SS = 50 , prod volume is 150
    1) if MMBE shows 200 then it wont generate any schedule.
    2) if MMBE is 180 and your lotsize is 40, then after MD03, you will have a schedule line of 40 (provided if everything is set properly)
    Please ensure there are NO open delivery lines . if you find such in MD04, then please close open delivery lines
    in calculation of MRP, system considers such open delivery lines are going to receive and no additional schedule line generated even after MRP run
    thanks

  • MRP creating multiple delivery schedule lines in PR

    Hi,
    We have activated MRP (type PD) where Purchase requiesition is auto created by system for requirement quantity. We require to optimize delivery schedule in such a way that entire PR quantity is broken into various delivery schedule based on planned delivery time and requirement.  Scenario can be further explained with following example.
    Material Requirement for a month is say 1,25,000 units
    Closing Stock say 25,000 units
    PR Generated by system for 1,00,000 units. The entire quantity is schdulled with only one delivery schedule line as per planned delivery time. 
    The requirement is to generate multiple delivery schedule lines automatically in Purchase requisition based on planned delivery time so that Purchase orders can be placed with system generated delivery schedule lines.
    How can it be achieved ?
    Regards,
    Nirav Kinkhabwala

    Dear
    Are you dealing with Single vendor  where you want Multiple Schedule Line item through single PR  which should be generated through MRP run ??
    What you will have to do is to set up the Outline Agreement or Info Record for your vendor and material and then create the source record for this vendor- material relationship and make sure that this source record is set as MRP relevant. Once MRP is run, the vendor is automatically defaulted to your PRs. If in your material master, you have defined the same purchasing group for various material numbers, then with Transaction ME59, it is feasible that you can combine various PRs of the same purchasing group by flagging onto the 'Per Purchasing Group' indicator checkbox. Make a trial test and let me know how it goes.
    Or you can use Qouta arrabgement in that case for different vendor .Please refer : Multiple Requisition  line itme for Quota arrangement
    Just check and revert
    regards
    JH
    Edited by: Jiaul Haque on Dec 25, 2010 1:52 PM

  • Link between Delivery schedule line counter from PO and the material docume

    Dear Gurus,
    I have one PO with single line item having delivery schedule -
    Material 1 -
    delivery schedule 01.01.2009     2000
                                                         01.03.2009    5000
    I have received quantity against this Po
    I want to know where I can find the link between Delivery schedule line counter from PO and the material document
    Best regards
    Sar

    There is no link from the MAterial document line item (Table Mseg) to the PO Schedule Line (EKET).
    If this is for Evaluating an on time delivery or GR, you may consider the following approach.
    PO details Po Date  QTY
    Sch1   01Jun2009   200   
    SCH2  08Jun2009   100
    GR Details
    GR1   01Jun2009   180
    GR2   07Jun2009   110
    GR3  09Jun2009      10
    Calculate a *** total qty for the PO Line.
    PO details Po Date  CUMUL QTY
    Sch1   01Jun2009   200   
    SCH2  08Jun2009   300
    Calculate a *** total qty for the ontime GR.
    PO details Po Date  CUMUL PO QTY  CUMUL GR on time
    Sch1   01Jun2009   200                180
    SCH2  08Jun2009   300                 290 (180+110)  the 3rd GR was too late
    Evaluate the PO SChedule Lines as follows:
    Po SCL qty + CUMUL GR QTY - CUMUL PO QTY = ADJ GR ON Time Qty
    SCH1 01Jun2009
    200 + 180 - 200 = 180 on time for 01Jun2009 date ( 90% fill rate)
    SCH2 08Jun2009
    100 + 290 - 300 = 90 on time for 08Jun2009 date (90 % fill rate) the first 20 of the GR on 07Jun2009 went to fill the late, early date.
    Best of luck !
    SCH2 100 +290 - 300 = 90 on time for 07Jun2009 date

  • Schedule lines are not getting generated during MRP Run

    Schedule lines are not getting generated during MRP Run. I have maiantained source list for the material with proper validity date and also maintained scheduling agreement . MRP relevvant Indicator , I have marked - 2 which means -Record relevant to MRP. Sched. lines generated automatically.
    Still I am not able to get schedule lines and instead of that *Purchase Requisitions* are getting generated.
    Can any one help me and suggest me what to be done in this case .
    Thanks & Regards ,
    Nirmalya

    Dear,
    Welcome to SDN,
    In transaction OMDT you have to enable the indicator create schedule lines
    In MD02 MRP control Prameter here select the Delivery schedules -3- Schedule line. Processing Key as NETCH and Planning Mode - 3 delted and recreated.
    Maintain source list ME01, in that put MRP indicator as '2' i.e. schedule lines via MRP.Put your agreement no in that.
    If u run MRP properly u will get schedule lines automatically in ME38.
    Make the schedule agreement, make it source relevent in the source list make is FIX and MRP indicator as 3.
    Regards,
    R.Brahmankar

  • Order of delivery schedule line counter at schedule agreements from MRP run

    Currently we are using schedule agreements for our long term external suppliers, but we are facing a problem with the order of new delivery schedule lines created during MRP run.
    Because of master data settings like, lot size, rounding value, plan delivery time and planning time fence to set as firm new requirements, multiple schedule lines are created with no order for schedule line counter.
    Does anyone is aware of a BADI, user exit or customizing control to have this schedule line counter in order?
    Thank you
    Daniel Guillen
    IT
    Skyworks Inc.

    Hi,
    Pls put this query in SD fourms  and get immly help because this is technical fourms.
    Anil

  • Schedule lines are not getting generated through MRP

    Hello Experts,
    While running MRP, we observed that the system is creating PR instead of schedule lines, although all the necessary prerequistes to generate schedule lines through MRP are maintained. For e.g.
    1. MRP Schedule line relevant indicator '2' is maintained in the Source List.
    2. Sch. Agreement dates and Source List validity dates are same.etc...
    Further after some analysis, we observed that if we change the source list validity from date to some back date then system is creating correct schedule lines.
    Example: Material M1; Planned delivery time 7 days; GR processing time 5 days; MRP Type PD; Lot Size WB;
    SA validity dates - 07.09.2011 to 31.12.2011
    Source List validity dates - 07.09.2011 to 31.12.2011
    If MRP run on 12.09.2011 and source list dates are retain same as mentioned above, system creates the PR.
    If MRP run on 12.09.2011 and source list dates changes to 05.09.2011 to 31.12.2011, system creates the schedule lines.
    Could you please let us know, why the system behave like this?

    Dear,
    Welcome to SDN,
    In transaction OMDT you have to enable the indicator create schedule lines
    In MD02 MRP control Prameter here select the Delivery schedules -3- Schedule line. Processing Key as NETCH and Planning Mode - 3 delted and recreated.
    Maintain source list ME01, in that put MRP indicator as '2' i.e. schedule lines via MRP.Put your agreement no in that.
    If u run MRP properly u will get schedule lines automatically in ME38.
    Make the schedule agreement, make it source relevent in the source list make is FIX and MRP indicator as 3.
    Regards,
    R.Brahmankar

  • Forecast delivery schedule lines consumption

    Hi,
    I cannot fully understand what is the logic behind the consumption of the forecast delivery schedule lines. This is how the problem can be exactly defined:
    - scheduling agreement with delivery orders (LZM)
    - JIT delivery schedules are not used and no delivery schedule is maintained... just a forecast delivery schedule
    - the whole process is manual, there is no EDI implied
    - the cumulative received quantity is updated by an ABAP development that is triggered at delivery goods issue
    The rest, happens normal - forecast schedule lines are updated weekly, the customer send pick-up sheets, a TAM delivery order is created, then delivery, GI...
    The problem: not always the MRP requirements generated by the forecast delivery schedule lines are consumed by the delivery order/GI. If the delivery orders / deliveries are made on the exact quantity of the schedule lines everything works fine. It is also ok when there are two successive delivery orders with a cumulative quantity that matches exactly the forecast line. As soon as a over-delivery is made, everything turns upside-down: older delivered schedule lines appear again in planning as if nothing was delivered until now...
    I suspect that the problem is related to the fact that the whole process is manual and updating the cumulative received quantity is not the only parameter that is counting... is it so? Or the forecast delivery schedule has to be respected 100% in terms of quantities and timing?
    I would really appreciate your help.
    Regards,
    H.

    Also please clarify whether delivery schedule lines in ME38 (even it is created automatically), in Planning time fence, will get affected by MRP run.