The Stage Gate Workflow get suspended in project server 2013

Hi,
Getting following error when i am trying to create an stage gate project/workflow in project server 2013. The submit button in
the ribbon gets disabled and when i see the workflow status it is suspended. and getting following error message. 
RequestorId: d5f04432-bd27-3da1-0000-000000000000. Details: RequestorId: d5f04432-bd27-3da1-0000-000000000000. Details: An unhandled
exception occurred during the execution of the workflow instance. Exception details: System.ApplicationException: HTTP 401 {"x-ms-diagnostics":["3001000;reason=\"There has been an error authenticating the request.\";category=\"invalid_client\""],"SPRequestGuid":["d5f04432-bd27-3da1-bc57-8ce72d9f5e43"],"request-id":["d5f04432-bd27-3da1-bc57-8ce72d9f5e43"],"X-FRAME-OPTIONS":["SAMEORIGIN"],"SPRequestDuration":["153"],"SPIisLatency":["0"],"Server":["Microsoft-IIS\/8.0"],"WWW-Authenticate":["Bearer
realm=\"2a5d48f2-f71d-4589-a6ae-ab6c0d30fafd\",client_id=\"00000003-0000-0ff1-ce00-000000000000\",trusted_issuers=\"00000005-0000-0000-c000-000000000000@*,[email protected]0d30fafd\"","NTLM"],"X-Powered-By":["ASP.NET"],"MicrosoftSharePointTeamServices":["15.0.0.4481"],"X-Content-Type-Options":["nosniff"],"X-MS-InvokeApp":["1;
RequireReadOnly"],"Date":["Thu, 04 Jul 2013 11:20:43 GMT"]} at Microsoft.Activities.Hosting.Runtime.Subroutine.SubroutineChild.Execute(CodeActivityContext context) at System.Activities.CodeActivity.InternalExecute(ActivityInstance
instance, ActivityExecutor executor, BookmarkManager bookmarkManager) at System.Activities.Runtime.ActivityExecutor.ExecuteActivityWorkItem.ExecuteBody(ActivityExecutor executor, BookmarkManager bookmarkManager, Location resultLocation)
Could anyone help me to fix this issue and reason why the Stage gate workflow isgetting suspended.
Thanks,
Sunitha

Check your User Profiles and make sure that the user's domain is correct. We've seen workflows suspend with 401 errors when the User Profile Service syncs with AD and pulls the wrong domain name - for
example if your FQDN is corp.company.com and the user logs in with company\username, UPS might have corp\username instead. Hence a 401 error...
Here is a link that includes the steps to fix this:
http://social.technet.microsoft.com/wiki/contents/articles/18060.sharepoint-20xx-what-if-the-domain-netbios-name-is-different-than-the-fqdn-of-the-domain-with-user-profile.aspx
Neall

Similar Messages

  • Project Server 2013 licensing

    I was reviewing the Microsoft Project Server 2013 licensing terms and noticed the following:
    PPM solutions require a Project Server 2013 license for each running
    instance of the software
    (source: http://office.microsoft.com/en-001/project/microsoft-project-licensing-project-for-multiple-users-online-and-on-premises-project-management-software-FX103802201.aspx)
    The PUR mentions something similar:
    For each license, you may use one Running Instance of server software
    (source: http://www.microsoftvolumelicensing.com/ProductPage.aspx?pid=443)
    You have to install Project Server on each SharePoint server in your farm. In the past it has always been said that you need one Project Server License for each installed copy (so for every SharePoint server in the farm).
    Has anything changed for Project Server 2013?
    Is a Project Server License only required for the SharePoint Server where you activate the Project Server Application Service?
    Or does running equals installed when it comes to licensing?
    Anyone can shed some light on this? Thank you!

    I agree with Bernhard on this one....there's been no real change for on-prem licensing....you still need a Project Server license for each server in the farm.
    That being said, there was a significant change (and confirm with your local MSFT rep), but in some cases, the online subscription pricing may be used for on-prem installations, i.e. I can pay by user by month instead of buying the CAL.  I don't think
    this impacts the server licensing, but worth noting.
    The "Running Instance" terminology is maybe meant to capture the VM scenario where I have one physical server running multiple VMs, each one running Project Server?
    Andrew Lavinsky [MVP] Blog: http://azlav.umtblog.com Twitter: @alavinsky

  • Creating custom Category for Risk & Issue in Project Server 2013

    Dear All,
    How to Change Risk & Issue Category default as per business requirement when selecting them through drop down or radio button?
    I can do only Project wise from project site & then setting changes. But i want to customize it for all projects which are getting published in Project Server 2013. So doing manually every time project wise not making sense & consuming time also.
    Kindly help..

    I have created custom template but not getting as demonstrated in  blog
    post from Prasanna  specially
    end part where Risk, Issue n all content can be seen. In My case only simple 3-4 items can be seen apart from risk, issue etc.
    After that i saved this custom template to my
    one of EPT in Project Server 2013. But unable to customize my Risk & Issue Category options for all projects. However, i have gone through that post & unable to understand as described in 2010 & i am using 2013 version.
    Kindly let me know after saving custom Template
    to EPT how to move further to customize these risk & issue categories globally.!!

  • Workflow in Project server 2013 online not going particular stage after Approval

    Hi All,
    i have created workflow using sharepoint designer 2013 for project server 2013 online. and i have also set the approver after the first stage. when i create a project using this workflow, project is created successfully and the approval task also go for
    a approval to specific user. and i have set the property that after approval it has to go on specific stage. but the problem is when user approve the task it shows approved but my stage in workflow is remain same. it is not going to any stage. 
    i don't know why this type of problem is occur. 
    FYI, i have created same workflow for Project server 2013 on premise(Which is installed in my server) and
    it is working fine but when i want to deploy this workflow in
    project server 2013 online its giving error.
    so please help me to solve this type of issue.
    Thanks

    I am also experiencing issues with this.  After the approval task is completed, the Workflow gets cancelled with the following message
    RequestorId: 60d96368-4cb4-b059-8086-604972a92e60. Details: System.Collections.Generic.KeyNotFoundException: The given key was not present in the dictionary. at Microsoft.Activities.Hosting.Runtime.Subroutine.SubroutineChild.Execute(CodeActivityContext context)
    at System.Activities.CodeActivity.InternalExecute(ActivityInstance instance, ActivityExecutor executor, BookmarkManager bookmarkManager) at System.Activities.Runtime.ActivityExecutor.ExecuteActivityWorkItem.ExecuteBody(ActivityExecutor executor, BookmarkManager
    bookmarkManager, Location resultLocation)
    All other desired workflow actions work as expected.  Emails are sent, project is moved from stage to stage, however as soon as the workflow approval task is completed, either Approved or Rejected, the Internal Status is changed to Canceled and the
    workflow fails.
    What is interesting is when the Approval task is completed, the approver will receive an email notification that the task was CANCELLED or DELETED....
    not COMPLETED, which is what would be expected.
    Has anyone seen this - any potential resolution?

  • Workflow status web part gives error when going back to previous stage (using GO TO) in Project Server 2013 workflow

    Hi,
    Workflow status web part gives error when going back to previous stage (using GO TO) transition activity  in Project Server 2013 workflow.
    Please guide how to create a workflow which restarts from a desired stage.

    Thanks for your prompt reply....
    It gives following error
    Workflow Status
    This Web Part was unable to load.
    Information that may be useful in solving this problem was written to the Unified Logging Service (ULS) log on the Project Web App with the following ID: e95a9c9c-1f68-90d7-0a3e-5951df70fec6
    For more information, contact your Project Web App administrator.
    what do you mean to restart the Project Server 2013 with different project name, please elaborate....

  • What are the common errors we get in supporting project

    can any body reply what are the common errors we get in supporting project
    for abapers tickets will get or not.
    what type of tickets generally get regarding reports.

    <b>SAP Tickets</b> are nothing but problems or issues raised by the end
    customer in a company where end users are running SAP project.
    Once the SAP project is implemented, support phase begins. Support
    team is responsible for solving the tickets/issues in day-to-day
    business.
    For any support project, customer will set up Help Desk. If any
    problem occurs customer will call Help Desk and register the
    issue/Ticket.
    Different companies use different software products to manage SAP
    Tickets. Remember this software is not provided by SAP. It is third
    party software. There are many software products in the market like
    Manage Now et c. You can call these software products as tools.
    All tools will provide the common attributes which are listed below-
    1) Every user will be provided with user name and password to enter
    into the tool
    2) We can see the tickets assigned for a particular user name.
    3) You can list all open tickets by giving the Date Range
    4) You can list all closed tickets by giving the Date Range
    5) You can list out all the open tickets assigned for an User
    6) You can list out all the closed tickets assigned for an User
    7) You can see the description of the Ticket, by entering the Ticket
    Number. You can see who had raised the Ticket, what is the problem.
    What is the severity of the Ticket?
    There are lot many other attributes like you can transfer the Ticket
    to another user etc.
    <b>What is the severity of the problem Ticket?</b>
    When a Ticket is raised, it will be given severity. There are
    following severities. It may vary from company to company.
    Severity 1
    Severity 2
    Severity 3
    Severity 4
    The severity will be decided based on the business critical impacts.
    If there is large impact on the business it
    will be given 1 severity, if it is having least impact then it will be given 4.
    Severity 1 problem tickets should be solved in 8 hours.
    Severity 2 problem ticket should be solved in 16 hours.
    Severity 3 problem ticket should be solved in 15 working days.
    Severity 4 problem ticket should be solved in 30 working days.
    Again the no of days may vary from one company to another.
    All these things will be decided when giving the contract to the IT
    company. The agreement is called as "SLA".
    SLA stands for Service Level Agreement.
    What happens if a particular ticket is not solved by the IT company
    according to the SLA/Contract?
    The Customer imposes fine on IT company as per the contract/SLA.
    <b>Errors in Extraction</b>
    1) RFC connection lost.
    2) Invalid characters while loading.
    3) ALEREMOTE user is locked.
    4) Lower case letters not allowed.
    5) While loading the data i am getting messeage that 'Record
    the field mentioned in the errror message is not mapped to any
    infoboject in the transfer rule.
    6) object locked.
    7) "Non-updated Idocs found in Source System".
    8) While loading master data, one of the datapackage has a red light
    error message:
    Master data/text of characteristic ZCUSTSAL already deleted
    1)extraction job aborted in r3
    2) request couldnt be activated because theres another request in the
    psa with a smaller sid
    3) repeat of last delta not possible
    4) datasource not replicated
    5) datasource/transfer structure not active
    <b>Issues faced during the implementation :</b>
    1. Slippage of milestones
    2. Incorrect or wrong design
    3. Reporting format problems
    4. Data not matching or reconciling problems
    5. Issues discovered during testing leading to redesign
    6. Performance issues
    7. Requirements misinterpretation
    9)check the data same in source system and target system ( i mean
    suppose u are extarcting from r/3 after loading check ur data r/3 and
    bw same or not.
    10)that is abap code, i didnt understand ur question properly.
    11)
    12) generic extarction, if ur businees contect satisfy ur requirement
    u go for generic, suppose u need data from different tables go generic
    with view with 1:1 relation 1:M relation for function module.
    13)v3 update back groud job is in lo
    14)its superior info object, u can find this in master data tab .
    15)
    16)tuning we will go for improve query performance (compression,
    aggregates, partation, index, rollup, precalculated web tneplates.)
    17) rsa7(check with some one)
    18)bw statics for find data base time and olap time and frontend
    time(based on u can improve query performance create like aggra comp ,
    indices etc..)
    19) direct chain only one chain , meta chain if u have more than one chains
    load errors u can solve manually, other than load errors u can wait
    right click and repeat.
    20)
    21) u cn cteate other cube and traansfer, but data space waste.(bec
    structures will be deffi)
    22) u mean data source enhancement.or not(let me know)
    23)rsap0001( for customer exit variables) 001 for transaction data 001
    attributes, 003 text 004 hierchies.
    24)web application design , its like same bex, but report will execute
    in browser.
    25)
    26) arrangement of process are called process type and we can use
    varient and start process for back ground jobs.
    <b>Don't forget to asign points</b>
    regards
    ravish

  • Help needed Regarding Project Server - 2013 Workflow

    Hi All,
    I am new to Project server 2013 Workflow, hence please help me regarding this. Pardon me if this question is too trivial. 
    I have created a project type associated with a workflow and my workflow is as follows :
    So I am not doing anything here, I am just testing the workflow as mentioned by technet site : http://technet.microsoft.com/en-us/library/dn458865(v=office.15).aspx
    But it is mentioned that, after a minute or 2, the workflow state will change, also they have mentioned to press the Submit button.
    But in my case, the workflow is not moving to next stage [It just says 'The workflow is still processing - which never changes after hours] or I am getting the submit button (Submit button is disabled on the ribbon). Below is the state of my workflow :
    PS : I have made the user added to Portfolio managers group as well. But still I am having this same issue. 
    The Workflow manager is installed properly, and it is working fine in case of List workflow. I am facing the issue only wrt Site workflow for Project server 2013.
    Please help me to solve this issue.
    Thanks,
    shanky

    Hi Kiran,
    I am now facing issue while assigning a task to a person in the workflow.
    I am having a person named say 'John' , who is included in Project Manager as well as Portfolio Manager.
    And I am using a workflow as :
    Stage : Conceptual
    Assign a task to John (Task outcome to Variable: Outcome5 | Task ID to Variable: TaskID3 )
    Transition to stage
    Go to Approval
    But this is again giving issue as :
    Workflow Internal status : Cancelled
    Details: System.ApplicationException: HTTP 401 {"error":{"code":"-2147024891, System.UnauthorizedAccessException","message":{"lang":"en-US","value":"Access denied. You do not have
    permission to perform this action or access this resource."}}}
    PS : I have used the same Sharepoint admin account for 'Account Name' in ‘User Profile Sync' , Is this causing the issue? Please let me know.
    Thanks,
    Shanky

  • How to handle PSW approval task in project server 2013 through declarative workflow VS 2013

    Hello,
    Plz explain in detail handling PSW approval task in project server 2013 through declarative workflow VS 2013
    bcoz when using am posted on with this error when i try to approve the item
     "This list item  has not been created by the workflow.you cannot apply this content type"
    any help would be appreciated!!!!
    Thanks regards, Vignesh.

    I am also experiencing issues with this.  After the approval task is completed, the Workflow gets cancelled with the following message
    RequestorId: 60d96368-4cb4-b059-8086-604972a92e60. Details: System.Collections.Generic.KeyNotFoundException: The given key was not present in the dictionary. at Microsoft.Activities.Hosting.Runtime.Subroutine.SubroutineChild.Execute(CodeActivityContext context)
    at System.Activities.CodeActivity.InternalExecute(ActivityInstance instance, ActivityExecutor executor, BookmarkManager bookmarkManager) at System.Activities.Runtime.ActivityExecutor.ExecuteActivityWorkItem.ExecuteBody(ActivityExecutor executor, BookmarkManager
    bookmarkManager, Location resultLocation)
    All other desired workflow actions work as expected.  Emails are sent, project is moved from stage to stage, however as soon as the workflow approval task is completed, either Approved or Rejected, the Internal Status is changed to Canceled and the
    workflow fails.
    What is interesting is when the Approval task is completed, the approver will receive an email notification that the task was CANCELLED or DELETED....
    not COMPLETED, which is what would be expected.
    Has anyone seen this - any potential resolution?

  • How to import the Issues list from an Excel File in Project Server 2013

    Hi,
    I'm using Project Server 2013.
    A Project Manager has been playing with the Issues List, deleting some fields, creating new columns and modifying some columns name. The result of this is that I'm getting this error everytime the task
    Reporting (Project Sync) is executed:
    General
    Reporting Wss list sync failed:
    ReportingWssSyncListFailed (24018) - 1100. Details: id='24018' name='ReportingWssSyncListFailed' uid='4feafda7-f147-e411-940d-005056957f05' SPListType='a1efd9a9-bd03-4604-91f3-31a2cc5693ff' Error='1100'.
    ReportingWssSyncListFailed (24018) - 1100. Details: id='24018' name='ReportingWssSyncListFailed' uid='5deafda7-f147-e411-940d-005056957f05' SPListType='a1efd9a9-bd03-4604-91f3-31a2cc5693ff' Error='1100'.
    ReportingWssSyncListFailed (24018) - 1100. Details: id='24018' name='ReportingWssSyncListFailed' uid='69eafda7-f147-e411-940d-005056957f05' SPListType='a1efd9a9-bd03-4604-91f3-31a2cc5693ff' Error='1100'.
    ReportingWssSyncListFailed (24018) - 1100. Details: id='24018' name='ReportingWssSyncListFailed' uid='75eafda7-f147-e411-940d-005056957f05' SPListType='a1efd9a9-bd03-4604-91f3-31a2cc5693ff' Error='1100'.
    ReportingWssSyncListFailed (24018) - 1100. Details: id='24018' name='ReportingWssSyncListFailed' uid='81eafda7-f147-e411-940d-005056957f05' SPListType='a1efd9a9-bd03-4604-91f3-31a2cc5693ff' Error='1100'.
    ReportingWssSyncListFailed (24018) - 1100. Details: id='24018' name='ReportingWssSyncListFailed' uid='8deafda7-f147-e411-940d-005056957f05' SPListType='a1efd9a9-bd03-4604-91f3-31a2cc5693ff' Error='1100'.
    Reporting message processor failed:
    ReportingWSSSyncMessageFailed (24016) - RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.. Details: id='24016' name='ReportingWSSSyncMessageFailed' uid='5beafda7-f147-e411-940d-005056957f05' QueueMessageBody='ProjectUID='a1efd9a9-bd03-4604-91f3-31a2cc5693ff'.
    ForceFullSync='False'. SynchronizationType='Issues'' Error='RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.'.
    ReportingWSSSyncMessageFailed (24016) - RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.. Details: id='24016' name='ReportingWSSSyncMessageFailed' uid='67eafda7-f147-e411-940d-005056957f05' QueueMessageBody='ProjectUID='a1efd9a9-bd03-4604-91f3-31a2cc5693ff'.
    ForceFullSync='False'. SynchronizationType='Issues'' Error='RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.'.
    ReportingWSSSyncMessageFailed (24016) - RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.. Details: id='24016' name='ReportingWSSSyncMessageFailed' uid='73eafda7-f147-e411-940d-005056957f05' QueueMessageBody='ProjectUID='a1efd9a9-bd03-4604-91f3-31a2cc5693ff'.
    ForceFullSync='False'. SynchronizationType='Issues'' Error='RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.'.
    ReportingWSSSyncMessageFailed (24016) - RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.. Details: id='24016' name='ReportingWSSSyncMessageFailed' uid='7feafda7-f147-e411-940d-005056957f05' QueueMessageBody='ProjectUID='a1efd9a9-bd03-4604-91f3-31a2cc5693ff'.
    ForceFullSync='False'. SynchronizationType='Issues'' Error='RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.'.
    ReportingWSSSyncMessageFailed (24016) - RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.. Details: id='24016' name='ReportingWSSSyncMessageFailed' uid='8beafda7-f147-e411-940d-005056957f05' QueueMessageBody='ProjectUID='a1efd9a9-bd03-4604-91f3-31a2cc5693ff'.
    ForceFullSync='False'. SynchronizationType='Issues'' Error='RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.'.
    ReportingWSSSyncMessageFailed (24016) - RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.. Details: id='24016' name='ReportingWSSSyncMessageFailed' uid='97eafda7-f147-e411-940d-005056957f05' QueueMessageBody='ProjectUID='a1efd9a9-bd03-4604-91f3-31a2cc5693ff'.
    ForceFullSync='False'. SynchronizationType='Issues'' Error='RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.'.
    Queue:
    GeneralQueueJobFailed (26000) - ReportingWSSSync.WSSSyncMessageEx. Details: id='26000' name='GeneralQueueJobFailed' uid='98eafda7-f147-e411-940d-005056957f05' JobUID='9e937da7-f147-e411-940e-005056957f0d' ComputerName='b579360a-53ab-4fe0-bf9b-c62f5e8d3529'
    GroupType='ReportingWSSSync' MessageType='WSSSyncMessageEx' MessageId='1' Stage='' CorrelationUID='0945bd9c-0d6a-a0f1-47b0-68cdfcfbff9a'. For more details, check the ULS logs on machine
    b579360a-53ab-4fe0-bf9b-c62f5e8d3529 for entries with JobUID
    9e937da7-f147-e411-940e-005056957f0d
    What I'm trying to do is to create a new Project from the scratch, update the Issues List, not deleting or modifying columns, just creating new columns in order to match the names he (the Project Manager) put in his Issues List, then Export the list to Excel,
    and then create a datasheet view matching the Exported list, but here I don't know how to import the list (copy / paste or whatsoever it can be done...)
    Do you know how to do it, or do you know another/any method to solve this problem?
    Thank you in advance,
    José Espases

    Hi José,
    2 considerations: 
    The first one is that (as you experienced) one should not delete or rename any of the predefined columns in the risk/issue list. What you did is the right way, meaning keeping the native column as is and creating new ones based on the business needs. Finally
    you just need to create view with the appropriate fields.
    Then for importing risks from an Excel list, I can't test it right now, but you should have a datagrid view (MS Access type) allowing you pasting data from Excel.
    Hope this helps,
    Guillaume Rouyre, MBA, MCP, MCTS |

  • Project Server 2013 - Workflow Execution " Submit button is grayed out. "

    Dear All,
    As i was in progress to making workflows in sharepoint designer this is my first project of implementing project server 2013 and executing the workflows,in the continuation of this i followed below mentioned link to go through the process of WORKFLOWS but
    got some issue
    LINK: http://msdn.microsoft.com/en-us/library/office/jj163494(v=office.15)
    ISSUE: Is that the SUBMIT Button is grayed out after saving initial proposal plan. Snapshot is attached.
    I have checked in/out process along with this gone through re-executed the whole process same result occurred.
    Suggestion/Help needed... 
    REGARDS DANISH DANIE

    Hi Danish, 
    Its a common thing which users are experiencing.
    When you create project from workflow click on Submit it take time for transition before transition it check all the condition which you have set for workflow stage. As per your screenshot it is waiting for details in PDP (Provide details of the proposed project) 
    when you click on submit it push data into the database,sometimes it send e mails to stakeholder then it use exchange and take times to send e-mails and for transition too.
    When you/user face this issue ask them to wait for some time or close the file then reopen. 
    In the screen workflow is waiting for Project detail information in PDP that is why it is still in process and not going to next stage.
    kirtesh

  • Configure Workflow Manager 1.0 in Project Server 2013 with FBA

    Hi,
    Please suggest the ways to configure Workflow manger in Project server 2013 where PWA using FBA
    we have tried for below situation, but no luck!!
    The workflow manager configured using windows login account, we are associating a FBA site with workflow manager which is 
    Register-SPWorkflowService -SPSite 'http://FBAsite' -WorkflowHostUri 'http://workflowmanagerapplication:12291'
    Following steps are taken care while creating workflow.
    We have added users to the user service profile services
    User profile synchronization is started
    The user by whom we are logged is available in User Profile list
    we are not running workflow with share point system account
    Final step full synchronization of User Profile Application
    Below the error we are getting when workflow run
    Resume this workflow  
     RequestorId: 879e36f9-9db0-3c16-0000-000000000000. Details: An unhandled exception occurred during the execution of the workflow instance. Exception details: System.ApplicationException: HTTP 401 {"Transfer-Encoding":["chunked"],"X-SharePointHealthScore":["0"],"SPClientServiceRequestDuration":["440"],"SPRequestGuid":["879e36f9-9db0-3c16-a91c-356d29becb34"],"request-id":["879e36f9-9db0-3c16-a91c-356d29becb34"],"X-FRAME-OPTIONS":["SAMEORIGIN"],"MicrosoftSharePointTeamServices":["15.0.0.4605"],"X-Content-Type-Options":["nosniff"],"X-MS-InvokeApp":["1;
    RequireReadOnly"],"Cache-Control":["max-age=0, private"],"Date":["Sun, 15 Jun 2014 12:44:03 GMT"],"Server":["Microsoft-IIS\/7.5"],"WWW-Authenticate":["NTLM"],"X-AspNet-Version":["4.0.30319"],"X-Powered-By":["ASP.NET"]}
    at Microsoft.Activities.Hosting.Runtime.Subroutine.SubroutineChild.Execute(CodeActivityContext context) at System.Activities.CodeActivity.InternalExecute(ActivityInstance instance, ActivityExecutor executor, BookmarkManager bookmarkManager) at System.Activities.Runtime.ActivityExecutor.ExecuteActivityWorkItem.ExecuteBody(ActivityExecutor
    executor, BookmarkManager bookmarkManager, Location resultLocation)

    Hi Mafeer,
    Since this issue is related to Project Server, I would like to recommend you to post there for more effective support:
    Project Server General Questions and Answers
    Thanks for your understanding.

  • Unable to edit the Project details from PWA in Project server 2013

    I am Migrating the project from MS Project 2007 to MS Project 2013.In that i save the project as a file first in 2007 and then open that file in  MS Project 2013 And publish it.But in some Project when i am Trying to change the projects details from
    PWA in Project server 2013 and then trying to save then the projects are not saving and are generating the error as shown below
    •GeneralQueueException:◦GeneralQueueException (9131). Details: id='9131' name='GeneralQueueException' uid='f7bb5d93-20e9-e411-b302-005056ae159c' messageID='2' exception='System.TimeoutException: This request operation sent to net.pipe://localhost/pscalc_13c43af4a7d34a2c8145b776b325a865
    did not receive a reply within the configured timeout (00:05:00). The time allotted to this operation may have been a portion of a longer timeout. This may be because the service is still processing the operation or because the service was unable to send a
    reply message. Please consider increasing the operation timeout (by casting the channel/proxy to IContextChannel and setting the OperationTimeout property) and ensure that the service is able to connect to the client. Server stack trace: at System.ServiceModel.Dispatcher.DuplexChannelBinder.Request(Message
    message, TimeSpan timeout) at System.ServiceModel.Channels.ServiceChannel.Call(String action, Boolean oneway, ProxyOperationRuntime operation, Object[] ins, Object[] outs, TimeSpan timeout) at System.ServiceModel.Channels.ServiceChannelProxy.InvokeService(IMethodCallMessage
    methodCall, ProxyOperationRuntime operation) at System.ServiceModel.Channels.ServiceChannelProxy.Invoke(IMessage message) Exception rethrown at [0]: at System.Runtime.Remoting.Proxies.RealProxy.HandleReturnMessage(IMessage reqMsg, IMessage retMsg) at System.Runtime.Remoting.Proxies.RealProxy.PrivateInvoke(MessageData&
    msgData, Int32 type) at Microsoft.Office.Project.Server.Interfaces.ICalcService.OpenProjectRemappedProject(CalcServiceCallState callState, Guid realProjectGuid, Guid remappedProjectGuid, EngineSessionState& sessionState, EngineSessionType sessionType,
    PSError& psError) at Microsoft.Office.Project.Server.BusinessLayer.CalcServiceChannel.OpenProjectRemappedProject(CalcServiceCallState callState, Guid realProjectGuid, Guid remappedProjectGuid, EngineSessionState& sessionState, EngineSessionType sessionType,
    PSError& psError) at Microsoft.Office.Project.Server.BusinessLayer.CalcServiceProxy.<>c__DisplayClass2.<OpenProjectRemappedProject>b__1(ICalcServiceChannel calcServiceChannel, PSError& localPsError, EngineSessionState& localSessionState)
    at Microsoft.Office.Project.Server.BusinessLayer.CalcServiceProxy.<>c__DisplayClass6e`1.<RunCalcServiceOperation>b__6c() at Microsoft.Office.Project.Server.Base.IdentityUtilities.<>c__DisplayClass1`1.<RunWithAccessToAppTierServices>b__0()
    at Microsoft.SharePoint.SPSecurity.<>c__DisplayClass5.<RunWithElevatedPrivileges>b__3() at Microsoft.SharePoint.Utilities.SecurityContext.RunAsProcess(CodeToRunElevated secureCode) at Microsoft.SharePoint.SPSecurity.RunWithElevatedPrivileges(WaitCallback
    secureCode, Object param) at Microsoft.SharePoint.SPSecurity.RunWithElevatedPrivileges(CodeToRunElevated secureCode) at Microsoft.Office.Project.Server.Base.IdentityUtilities.RunWithAccessToAppTierServices[T](Func`1 action) at Microsoft.Office.Project.Server.BusinessLayer.CalcServiceProxy.RunCalcServiceOperation[T](CalcServiceOperation3`1
    func, EngineSessionState& sessionState, String scopeName) at Microsoft.Office.Project.Server.BusinessLayer.CalcServiceProxy.OpenProjectRemappedProject(Guid realProjectGuid, Guid remappedProjectGuid, EngineSessionState& sessionState, EngineSessionType
    sessionType) at Microsoft.Office.Project.Server.BusinessLayer.ProjectEngineUpdate.OpenProject() at Microsoft.Office.Project.Server.BusinessLayer.ProjectEngineUpdate.HandleUpdate() at Microsoft.Office.Project.Server.BusinessLayer.ProjectQueueDispatch.HandleProject2(MessageContext
    mContext, ProjectMain project, ServerEventManager sem, ProjectDataSet dataset, Guid projectUid, Guid sessionUid) at Microsoft.Office.Project.Server.BusinessLayer.ProjectQueueDispatch.InternalDispatchMessage(IPlatformContext context, Message msg, Group messageGroup,
    JobTicket jobTicket, MessageContext mContext)'. 
    •Queue:◦GeneralQueueJobFailed (26000) - ProjectUpdate.ProjectUpdate2Message. Details: id='26000' name='GeneralQueueJobFailed' uid='f8bb5d93-20e9-e411-b302-005056ae159c' JobUID='a6fa36de-1fe9-e411-b302-005056ae159c' ComputerName='1af8030b-7714-4c8f-8738-903b73e87a82'
    GroupType='ProjectUpdate' MessageType='ProjectUpdate2Message' MessageId='2' Stage='' CorrelationUID='0a4aff9c-dd6b-7015-87a8-29d876e1540c'. For more details, check the ULS logs on machine 1af8030b-7714-4c8f-8738-903b73e87a82 for entries with JobUID a6fa36de-1fe9-e411-b302-005056ae159c. 
    What will i do .Please help.

    Hi Jeremy,
    Thanks for the reply .I try the steps that is given in link above but its not working.Please suggest something.What
    should i do.

  • Can new PWA views be created whereby a filter can be set and associate to the view by default? (Project Server 2013 ONLINE)

    My main question is: Can new PWA views be created whereby a filter for that view can be set, and associate to the view by default? (Project Server 2013 ONLINE)? and can I have a filter set to filter on person logged on to...
    In previous versions of Project Server, when CREATING a PWA view, we were able to apply/ define a filter for that view.  Does not seem like it is the case in Project Server 2013 Online.  And if I remember, we could also use the URL Guid_view_id. 
    Please confirm; and / or tell me how-to.
    What I was hoping to do is the following... Given that our standard that we have adopted for reporting time is 'My Timesheets' (fyi, Single Mode Entry=ON), we have some resources who have others who do it on their behalf via 'My Tasks' (ie., accomplished
    by using the 'Assignment Owner' field, accordingly).  Therefore, when entering time on someone else's behalf within 'My Tasks', we like to present the user that is logged in only the tasks that they are are assigned to update on others' behlaf.
    I know that there is another more elegant approach to doing this which may be to use the Delegation feature. But since we are trying to stick to Sharepoint Security mode for now, this is not an option for the time being.
    Any help appreciated would be greatly appreciated.
    \Spiro Theopoulos PMP, MCITP. Montreal, QC (Canada)

    Hi Spiro,
    1- You still can define in Project Online a filter in the view settings, it is located just above the category setting. Here is a screenshot of the summary project center view:
    2- The view GUID is not anymore in the URL, since the URL triggers an action only on the webpart and not on the whole page. I agree this is annoying since it was great to send a URL with a specific view.
    3- Concerning the access to my timesheet versus my task, I'm not sure to get a full understanding but on a general way, it is much more easy to deal with those situation using categories which you cannot do with the SP permission mode.
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, P-Seller |

  • How to get timesheet information in a javascript (Project Server 2013)

    Hi all,
    In Project Server 2013, I'm trying to customize the Timesheet ribbon. This far, I've been able to add a new button and tie an event to it. All is working well. This is all done using elements.xml and a javascripts.
    Now the problem is that I want to get some informations about the timesheet (the Guid for example) and, for now, I've got no success. I know that there is an object called PS.TimeSheet, but when I try to use some PS.TimeSheet's methods I get an error.
    Note that i'm in the page http://servername/pwa/timesheet.aspx (there is not Guid in the address) and all the treatments should be done in the javascript (no call to another aspx page)
    Thanks !

    Finally, I've found the solution.
    My goal was to add a button in the timesheet ribbon to launch a special report showing some data about the timesheet. The report has the timesheet Guid as parameter.
    To customize the Sharepoint ribbon, you have to do it via an xml file and a javascript (a lot of explanation is available in the internet that explains how to do it). So I had to call a function in the javascript to launch the report (which is a SSRS report).
    When you are in a javascript you have access to many global variables. When the timesheet.aspx is displayed, there is a global variable called "timesheetComponent".
    Using this variable we can call the method :
    timesheetComponent.m_consumedApi.get_Impl()
    to get an implementation of the current timesheet. This implementation has an attibute that has a lot of nice stuff about the current user and the current time sheet. This attribute is 
    _headerInfo
    _headerInfo is a structure that includes tsUid which contains the timesheet Guid I was looking for.
    Finally, the function attached to the button goes like this :
    function _LaunchReport() {
    var tsUId;
    var rptPath;
    var tsImpl = timesheetComponent.m_consumedApi.get_Impl();
    try
    if (CONST_REPORT_PATH == null || CONST_REPORT_PATH == "" ) {
    alert("Constant CONST_REPORT_PATH is not defined")
    else {
    tsUId = tsImpl._headerInfo.tsUid;
    rptPath = CONST_REPORT_PATH + 'TimesheetDetails&rs:Command=Render&rc:Parameters=false&TimesheetUID=' + tsUId;
    window.open(rptPath);
    catch (Err) {
    alert(Err)
    CONST_REPORT_PATH is the path to SSRS defined elsewhere
    I hope this will help some other poeple !

  • Publication of the big-sized Enterprise projects from Project Professional 2013 to Project Server 2013 takes about 60+ minutes.

    Dear Sirs,
    I need your support over the following MS EPM 2013 issue:
    Publication of the big-sized Enterprise projects from Project Professional 2013 to Project Server 2013 takes about 30+ minutes. We
    need to reduce this total publication time down to acceptable working values 10+- minutes.
    Environment information:
    Single App Server (Virtual): 16 Gb RAM, x64 4xCPU, HDD > 50 GB free disk space, OS Windows Server 2012 Standard Edition x64 Service
    Pack 1, MS SharePoint Server 2013 and MS Project Server 2013 with CU December 2013 (KB 2850024) applied.
    Single RDBMS MS SQL Server (Virtual): 8 Gb RAM, x64 4xCPU, HDD > 200 GB free space, OS Windows Server 2012 Standard Edition x64 Service
    Pack 1, MS SQL Server 2012 x64 SP 1 Enterprise Edition.
    We have 1Gbit LAN between APP, DB server and 1Gbit LAN between APP and Proj Prof Client.
    Yes, we are on the way of migrating to the Prod environment
    with 3-tiered architecture (with SP1 slipstream and CU December 2014 applied), but this issue also
    presents there.
    Project’s file information:
    Tasks in the file: [~4900], resources in the file [~396] enterprise task’s custom fields used in the file [~23].
    Project save procedure for this new project would last about 7 minutes. Project publication would last about 47 minutes. We noticed that
    tasks synchronization process took about 1 second for each ~2,5 tasks, to add them to the sharepoint tasks list. So for all 5148 tasks it took about 5148/3/60 =  34 minutes. Other 13 min was used for reporting database publication and other tasks relevant
    for new sharepoint site creation.
    Case 1: Issue description:
    During the Enterprise project’s file save and publication we have the following sharepoint 2013 log messages:
    07.31.2014 12:43:17.22 Microsoft.Office.Project.Server (0x0358) 0x3D5C SharePoint Foundation Monitoring b4ly High Leaving Monitored Scope
    (Persisting list changes). performing time =376.068676326181 22dca99c-4696-70f1-e9e2-06851d0bcffd
    07.31.2014 12:43:17.69 Microsoft.Office.Project.Server (0x0358) 0x3D5C SharePoint Foundation Monitoring b4ly High Leaving Monitored Scope
    (Persisting list changes). performing time =361.652807828928 22dca99c-4696-70f1-e9e2-06851d0bcffd
    It shows that sharepoint spend at least ~350 milliseconds (or 0,35 sec*4900 tasks = 1715 sec, or 28,5 min) for each task update during
    project publication. And we also have another log file that shows that about 0,7 sec (or 0,7 sec*4900 tasks = 3430 sec, or 57 min) sharepoint spend for save each task in project file to project server. So total save and publication time more then 60+ minutes
    for that project file. The same result we have even if user didn’t do any changes at the project file.
    We use only enterprise projects (dbo.MSP_EpmProject_UserView.projectvisibilitymode = «False»), and do not use sharepoint tasks lists,
    but the synchronization between MSP Plan and SharePoint tasks list works at any case.
    Case 2: Issue description:
    - For the second test we created a new project with new sharepoint project’s site on basis of our «issue» project, with total amount
    of tasks in it of 5148 (yes, we increased the tasks list default limit at the sharepoint site up to 6000 items in it – standard limits for sharepoint view list – 5000 items).
    - Project save procedure for this new project would last about 7 minutes. Project publication would last about 47 minutes. We noticed
    that tasks synchronization process took about 1 second for each ~2,5 tasks, to add them to the sharepoint tasks list. So for all 5148 tasks it took about 5148/3/60 =  34 minutes. Other 13 min was used for reporting database publication and other tasks
    relevant for new sharepoint site creation.
    -Then we deleted the
    tasks list for that new test project from the sharepoint site and republish the project plan one more time. This time project save procedure took about 7 minutes, project publication about 2 minutes and 3 minutes for other relevant queue jobs. So total time
    is 12 minutes.
    As a conclusion: yes, we have determined
    the exact problem - during synchronization process (from Project Server to SharePoint) it perform copying all tasks and related data from Project to SharePoint in spite of fact that you changed only ONE task or ALL of them. At any case, synchronization will
    copy ALL of them from Project Server to SharePOint task’s list.
    Our workaround is to disable the task’s synchronization for such big-sized project plans:
    – to delete the SharePoint «tasks» list at the SharePoint site tied with project plan.
    - or deattach the SharePoint site from the project plan.
    Thank you for reading this topic, please if you also forced with such issue provide us any known workaround or maybe any official response
    \ feedback from MS about it.
    Thank you in advance,
    Best Regards, Andrey

    Regarding my topic, I also said that every time when sync works it updates All items from project’s plan at Project Server to corresponded task’s list at SharePOint server. Inspire of the fact that you changed only One task or group /
    all of them at your project’s plan.
    And it seems to me and my colleagues that it’s probably (maybe) a “bug” at the product. Here is what we have if looked a little bit closer to the code:
    Share Point determines what task to sync from Project’s plan to sharepoint list. To do that sharepoint needs to know was that task changed or not, based on the following fileds (check SQL stored procedure “[MSP_READ_TASKS_FOR_SYNCRONIZATION]”):
    TASK_UID    TASK_NAME    TASK_START_DATE    TASK_FINISH_DATE    TASK_PCT_COMP    TASK_PARENT_UID    TASK_OUTLINE_NUM   
    WSS_LISTITEM_UID   TASK_ID    TASK_IS_ACTIVE
    We noticed that at any case synchronization performs for all tasks, EXCEPT the ROOT one. Then we looked at the comparison of TASK_PARENT_UID field. So sharepoint compares TASK_PARENT_UID with ParentID (this is internal name for lookup
    field “Tasks” at the Sharepoint, and it stores their values at the format "ID;#Title").
    And comparison performs like following:
    SharePoint looks for Task at the Tasks’s list corresponded to Project’s plan with ID represented at the TASK_PARENT_UID field. Then it takes SharePoint ListItem ID (“int” type) and store it to the “num” parameter;
    num = this.GetCachedListItemByUniqueId(listItem.ParentList, nullable.Value).ID;
       2.Then it compares “num” with task’s “ParentID” at SharePOint as follow with operator “!=”:
    ((SPItem) listItem)["ParentID"] != (System.ValueType) num
       3. If comparison was success (true) – then it tell us that values (at the Project’s plan for tasks) was changed, then it need to be synchronized. Corresponded Method setup “true” flag, and then returns it.
    The “bug” is that this expression at the Step 2 will always return “true”, because in fact it compares “string” (see above – that this is lookup field at SharePoint side)
    with “number”. For example if the parant task ID is “55”, then we get:
    "55;#Task 1" != 55
    And by the rules of .Net the “string” will never equal “number”
    Furthermore this is approved by the SharePoint logs:
    In that case we always get the note “Setting ParentID to” at the logs (we see it if turns on Verbose for “Project Server” -> “Sharepoint Integration” category).
    So at any case of publishing project’s plan we always get that note at the logs for tasks that have Parent task, and we have Parent for all of them EXCEPT the ROOT one, exact logs represented further:
    10/15/2014 02:37:32.26    Microsoft.Office.Project.Server (0x07D8)    0x06E8    Project Server    Sharepoint Integration    ado0d   
    Verbose    Setting ParentID to 1    bf2fc29c-7727-b00d-fa4a-34f22ea9ec1d 10/15/2014 02:37:32.62    Microsoft.Office.Project.Server (0x07D8)    0x06E8   
    Project Server    Sharepoint Integration    ado0d    Verbose   
    Setting ParentID to 1    bf2fc29c-7727-b00d-fa4a-34f22ea9ec1d 10/15/2014 02:37:32.63    Microsoft.Office.Project.Server (0x07D8)    0x06E8    Project Server   
    Sharepoint Integration    ado0d    Verbose   
    Setting ParentID to 1    bf2fc29c-7727-b00d-fa4a-34f22ea9ec1d 10/15/2014 02:37:32.67    Microsoft.Office.Project.Server (0x07D8)    0x06E8    Project Server   
    Sharepoint Integration    ado0d    Verbose   
    Setting ParentID to 1    bf2fc29c-7727-b00d-fa4a-34f22ea9ec1d 10/15/2014 02:37:32.69    Microsoft.Office.Project.Server (0x07D8)    0x06E8    Project Server   
    Sharepoint Integration    ado0d    Verbose   
    Setting ParentID to 5    bf2fc29c-7727-b00d-fa4a-34f22ea9ec1d
    The following is the complete Method’s code from the corresponded reflector:
    private bool UpdateParentID(DataSet taskDS, DataRow row, SPListItem listItem, Dictionary<Guid, SPListItem> redoEntries)
    bool flag = false;
    int index = taskDS.Tables[0].DefaultView.Find((object) DataRowExtensions.Field<Guid>(row, "TASK_PARENT_UID"));
    if (index >= 0)
    Guid? nullable = DataRowExtensions.Field<Guid?>(taskDS.Tables[0].DefaultView[index].Row, "WSS_LISTITEM_UID");
    int num = -1;
    if (listItem.Fields.ContainsField("ParentID"))
    if (nullable.HasValue)
    try
    // STEP 1
    num = this.GetCachedListItemByUniqueId(listItem.ParentList, nullable.Value).ID;
    catch (ArgumentException ex)
    if (redoEntries != null)
    if (!redoEntries.ContainsKey(DataRowExtensions.Field<Guid>(row, "TASK_UID")))
    redoEntries.Add(DataRowExtensions.Field<Guid>(row, "TASK_UID"), listItem);
    //STEP 2
    if (num != -1 && ((SPItem) listItem)["ParentID"] != (System.ValueType) num)
    ((SPItem) listItem)["ParentID"] = (object) num;
    ULS.SendTraceTag(845443U, (ULSCatBase) ULSCat.msoulscat_PS_ProjectSharepointIntegration, ULSTraceLevel.Verbose, "Setting ParentID to {0}", new object[1]
    ((SPItem) listItem)["ParentID"]
    //STEP 3
    flag = true;
    else if (((SPItem) listItem)["ParentID"] != null)
    ((SPItem) listItem)["ParentID"] = (object) null;
    ULS.SendTraceTag(2495056U, (ULSCatBase) ULSCat.msoulscat_PS_ProjectSharepointIntegration, ULSTraceLevel.Verbose, "Resetting ParentID to null");
    flag = true;
    return flag;
    Any thoughts about it would be much appreciated!