Hi
We are using EBP 4.0
We are creating sales orders with item cat "Third Party Item", the purchase req's are created in R/3 but we have problems when we transfer the purch req's to SRM via BBP_EXTREQ_TRANSFER.
There is an errormessage in SMQ1   "<i>Partner not Found</i>". I have also checked SLG1 in SRM but there is no additonal info there.
I think the problem is related to the Customer (ship to), it looks like the Businnes Partner has to be created for that customer but I don't really understand how it works.
Any tip ?
Thx
Anders
PS we can transfer normal purchase req's created by MRP to SRM without problem.

Hi Andres,
I think this scenario is not supported by SRM. These requisitions will have eban-estkz = 'V' and  there is a check iin the plugin routines which exclude these requisitions from going to SRM. It will be a modification to make this go through SRM and will not be supported.
I hope this helps.
Thanks and Regards,
Vani

Similar Messages

  • How to configure purchase requesition in third party order

    dear expert
    can you explain how to configure purchase requesition in third party order.
    vicky

    Hi
    Kindly check the below
    Maintain the purchase requisition doc type in the  third party order  schedule line category  in the t code VOV6 as below
    Sched.line cat.        TP    Third party schedule                                                                               
    Delivery block                                                             
    Movement Type                                        Item rel.f.dlv.       
    Movement type 1-step                                                       
    Order type            NB    Purch Req                P.req.del.sched       
    Item category         5     Third-party                                    
    Acct.assig.cat.       X     All aux.acct.assgts.                                                                               
    Incompl.proced.       31    Sched.Line w/PurReq.                           
    Req./Assembly                                                              
    Availability                                                               
    Prod.allocation                                                                               
    Regards
    Damu

  • Cost center not populated in Purchase requisition for a third party order

    Hello,
    We are currently testing the Third party order flow which includes :
    1. Creation of a sales order with item category TAS
    2. A purchasing contract is maintained for a sales order item at the schedule line level.
    (In the purchasing contract, account assignment is already maintained for each contract item, meaning a G/L Account and a cost center).
    3. Automatic creation of the Purchase requisition when the sales order is saved.
    >> The account assignment is not copied from the contract to the Purchase requisition. Do you know why and how I can do that ?
    Thanks
    Best regards
    Benjamin

    Hi Palani,
    if i am not wrong This WBS in location or additional tabs are used for settlement purpose. For PR creation by maintenance Orders can have Order number as account assignment.
    Please reply
    Thanks
    Sunil

  • About third party order

    I would like to know the process of those third party order.
    1. Create SO with item cat is thrid party
    2. assign PR to PO
    3. MIGO   <------ I don't know whether need good received or not
    4. PGI
    5. Billing.
    Above steps is correct or not. Thanks!

    Hi,
    If the material is directly sent to customer,the following steps to performed.
    Order Related Billing.
    1.Create Sales Order (Purchase Req.automatically generated after saving the sales order.
    2.Release the PR for creation of Purchase Order.
    3.Purchase Order is sent to Vendor.
    4.MIGO or MIRO done as per requirement.
      (If MIGO is there then it's Stastical)
    5.Create Billing Document.
    Thanks & Regards,
    Hemant Patil

  • Third Party order in MM

    Hi
    I like to know about Third party order process followed in Material Management module and what are the documents will be generated in this process .Explain me the process in detail ?
    Thanks & Regards,
    senthil.

    Sales people will receive the order for which the company may carry the mateirals or not, in this case sales depaertment will enter the third party sales order which evantually create the third party Purchase requisition in the MM
    now MM department will convert the reqs in the PO.
    for this Po vendor has delivery address in the PO for custom
    so vendor will deliver the Goods to customer location and invoice to your company, once you get the invoice from the vendor your sales dept will bill to the customer
    so it customer pay and you pay to the vendor.
    In third-party processing, you place a purchase order with a vendor to deliver goods or perform a service for a third party (for example, for a customer).
    This means that your company does not deliver the material. You forward the order to an external vendor instead, who then sends the material directly to the customer and invoices you.
    Third-party processing is carried out in the components SD (Sales and Distribution) and MM (Materials Management). By creating a third-party item in a sales order, purchase requisition, or purchase order, you can request that the vendor sends the goods directly to your customer. A document can consist of one or more third-party items.
    Activities
    Entering a Sales Order
    You enter a third-party item in a sales order. The system automatically creates a purchase requisition item for each third-party item in the sales order.
    Entering a Purchase Order to Vendor
    You enter a purchase order with a third-party item with reference to the requisition third-party item.
    Delivering Goods to Customer
    The vendor supplies the goods to the customer. To document this step in the system, you can post a statistical goods receipt in Inventory Management. However, this is not compulsory.
    Entering a Vendor Invoice
    The vendor sends you an invoice. You enter the invoice receipt in Invoice Verification. The invoice receipt is necessary before a billing document can be created in SD.
    Creating a Billing Document for the Customer
    In SD, you create a billing document for the sales order. Depending on the Customizing settings (whether or not the billing-relevant indicator is set for the item category in SD), you draw up the billing document on the basis of the order quantity or on the basis of the quantity specified in the vendor invoice. If the customer is billed on the basis of the order quantity, you can create the billing document immediately after the sales order is entered. If the customer is billed on the basis of the quantity specified in the vendor invoice, you cannot create the billing document until the vendor invoice has been entered in Invoice Verification.
    If you do not use the SD component, third-party orders can be handled completely in Materials Management. Here you enter a third-party order (or a purchase requisition) manually with the item category S and account assignment category X. In this procedure, the activities Entering a sales order and Creating a billing document for the customer are eliminated.

  • Third Party Order Processing in CRM

    Hi,
    I need to create an item category in CRM which enables me to activate third-party order processing in ECC. So the process should be:
    - Create sales order in CRM, choose item category "TAS"
    - Save sales order
    - Order triggers purchase req. in ECC (or sales order with item cat. TAS)
    I read sap.help. where it says we need to use SCM etc. for this process. Actually we only have ECC connected. Is it still possible like that?
    Rgs
    Anke

    Hi Anke,
    1.Create a ztrans type and item category by copying TA and TAS in CRM.Maintain the same document type and item category in ECC.
    2.select the "Create PO Automatic" option in the ECC item category definition.
    3.Assing the Purchase order document type to Schedulines and assign schedule line to Item category.
    Hope it helps....
    Regards,
    S Reddy

  • Incompletion for third party orders

    Hi Everybody,
    I see that the incompletion procedure config is not useful to stop third party orders(TAS items) from creating a Purchase Req if an order is incomplete for pricing. I tried flagging the 'Pricing' check in the status group definition but that didnt help either. The only option I see that is the billing document gets blocked in case of incomplete pricing in the order but we would want to set up our system to stop the purchase req itself from getting generated like it does when there is a credit block for the order.
    Unfortunately OVB5 too has a requirement only for credit block and none for pricing.
    Any ideas would be appreciated.
    Thanks & Regards,
    Vidya Sagar

    hi,
    this is to inform you that,
    this cannot be achieved with standard configuration i think so because if you keep in LOG of incompletion in sales order it will not stop creating PR.
    so this is pure development
    where you can write in user exit USER_EXIT_SAVE_DOCUMENT_PREPARE that if the sales order item category is VBAP-PSTYV =  TAS  & schedule line category is VBEP-ETTYP then check the LOG whether the document is completed or not and if not throw an error message & stop triggering PR stating that document is incomplete.
    this triggers while saving the document.
    hope this clears your issue
    balajia

  • Third Party Orders - MRP

    Hi,
    I have a client who takes sales orders and fulfills those orders using third party purchasing functionality, with the vendor delivering directly to the customer. There is no sales stock involved and the item category on the purchase order is configured for no goods receipt.
    If they look at their stock requirements list for a given material, the sales orders appear, but the requisition created as a result of the SO schedule lines do not, nor do purchase orders created from these reqs.
    As a result, during MRP SAP is attempting to procure the material through a standard requisition for an external purchase.
    I've changed config so schedule lines with the schedule category relating to this type of purchase do not transfer requirements to MRP, resulting in no MRP activity at all, however the client wishes to see each component (Sales order, purchase req/order) when they view their stock requirements list.
    How is this handled in the standard system (ie what strategy group in the material master, what item category on the POs, etc....) so these requirements and replenishments are all visible on the stock requirements list?
    Thanks in advance,
    Mark

    Hi Mark,
    You can check below link for your process (Building Block 107).
    http://help.sap.com/bp_bl603/BBLibrary/Content_Library_BL_EN_IN.htm
    Regrads
    Ali

  • Third Party Order Planning with SNP - Forecast not Consumed

    Hallo SAP Gurus,
    I have implemented the solution "Third Party Order Planning with SNP" created by Abhay Kapase in our SAP APO System - please see http://scn.sap.com/community/scm/apo/blog/2014/02/26/third-party-order-planning-with-snp.
    But I have one problem that the forecast is not consumed.
    I have done the following things:
    1. I have activated the business Functions SCM_APO_DRS_PLAN in the APO System and  LOG_MM_OM_2 in the ECC System.
    2. I have done the customiznig in the ECC System: Created the schedule line category D1 and assigned it.
    3. I have done the customizing in the APO System: Created the planning strategy 21.
    4. I have created all the necessary master data in the APO and the ECC System
    5. I have been created a customer order.
    6. The purchase requisitionhas been transferred to the APO System. But the forecast is not consumed.
    Can anybody help me.
    Best Regards
    Dieter

    Someone must know!
    We have a similar requirement. We do have CRM but don't wish to implement it for this purpose.
    In the SNP planning boook, we want to be able at the SNP vendor location to see the total requirement for both materials to be delivered to our normal supply chain as well as those directly delivered to customers. The direct delivery sales orders are entered to R3 according to the standard process; the purchase requisitions and PO's for these do not go to SNP. The customer location is set-up in SNP. Is there a way to make the purchase req's and orders visible in the SNP Planning Book???
    Many thanks
    Chris

  • Third party order processing with GATP allocations and no CRM

    Hi,
    Does anyone know how to integrate third party order processing with APO product allocations, or know of some good references? We do not have CRM. We currently have APO 4.0, soon to be upgraded to 5.0 and R3 4.6.
    Thanks,
    Gigi

    Someone must know!
    We have a similar requirement. We do have CRM but don't wish to implement it for this purpose.
    In the SNP planning boook, we want to be able at the SNP vendor location to see the total requirement for both materials to be delivered to our normal supply chain as well as those directly delivered to customers. The direct delivery sales orders are entered to R3 according to the standard process; the purchase requisitions and PO's for these do not go to SNP. The customer location is set-up in SNP. Is there a way to make the purchase req's and orders visible in the SNP Planning Book???
    Many thanks
    Chris

  • Automatic po creation third party order

    Hello Gurus,
    In case of automatic po creation from third party order we have attach purchase organization and vendor to sales organization. This restrict only one vendor against sales organization.
    Is any BADI available which we can use which to change vedor dynamically ?
    Best Regards,
    Vasant

    Dear Vasant,
    For automatic PO at the time of GR following are the prerequisites:
    1) In Customizing
    a) Auto PO generation must be activated in Mov. Type 101 & 161
    b) the plant for which GR is entered must be assigned to standard Pur. Org.
    c) Default Document type for PO must be specified in GR ( MB 01)
    2) Application - Front end side
    a) material must be valuated material
    b) Purchasing Info record must exist for vendor , material & standard Pur Org.
    c) Conditions in Info Records must be valid.
    d) Applicable for stock items & not consumable items
    e) you cannot enter any movement in GR block stock
    f) Material Master & vendor master records must.
    If you ensure all above settings then it is possible to have auto PO during GR.
    Please try,
    Vivek

  • Third Party Order Processing

    Dear All,
    1.Can anyone explain me the term 'Statistical GR' in Third Party Scenario & also why & how we do it (also the Config settings required for the same).
    2. In third Party Scenario we have order acknowledgement & confirmations so how we do this ??
    Do we use the confirmations tab in the third party PO?? ( If yes wat we have to select - inbound delivery or rough GR)??
    Appreciate all the helpful answers.
    Regards,

    hai
    The account assignment category X in the Customizing system of Purchasing determines whether a goods receipt can be posted for a third-party item. Here you define whether a goods receipt is possible, not allowed or compulsory.
    If a goods receipt is possible, the GR indicator in the purchase order item is changeable. When you enter the purchase order, you decide if a goods receipt is to be posted or not.
    You can only enter a goods receipt for a third-party order if the goods receipt indicator is set in the order item
    we are specifying the account assignment category in the third party po as well as the itemcategory
    so the effect of the gr will be to just like consumption
    we will do the gre just like normal gr to post it to the gr/ir account to verify and to settle the invoice to the vendor
    you can use confirmation key as usual to have the confirmations and acknowledgements

  • Third-Party Order Fulfillment Process Scenario

    Hello,
    I would like to know if any of you have come across a use case where the Third-Party Order Fulfillment is  Not  based on the Supplier/Manufacturer shipping out the material directly But the Buyer (and in some cases even end User/customer) arranges this themselves. This is very common in International Trade where the Buyer/Business arranges the shipment themselves by using the services of a Freight Forwarder who Ships the material to the end user/customer after the Supplier/Manufacturer has made the Material available. In such cases the actual Shipment could take days or weeks from when Material is made ready by the Suppliers.
    Currently the Third-Party Order Fulfillment Process assumes only one scenario and that is the Supplier will ship the material and inform their Buyer of Delivery. But in International Trade this is not the case and the Incoterms in the Purchase Order can be different to the Incoterms in the Sales order example in the PO the incoterms could be Ex-Works and in the SO CIF.
    This leads to requirement of ASN and separate Inbound and Outbound Delivery and their separate Release in this Process as well.
    These are not currently supported in the Third-Party Order Fulfillment process thus the Third-Party Order Fulfillment process in ByD has a very limited use in its current form.
    If there are other users who have come across this as well then it would be nice to have your comments and possible workaround.
    Best regards
    Nick

    There is no standard SAP solution for this requirement.
    You can trigger output from inbound delivery document to generate EDI output and send delivery information to customer.
    You will require to define custom output type , partner profile and link with custom fucntion module.
    FM should have logic to pick information from 3rd party sales order and inbound ASN and generate IDOC
    Hope this solution will work for your requirement

  • Third Party Order processing in case of multiple vendors

    Hi,
    With the third party order processing; purchase requisition gets created automatically based on the scheduling item category. This process works fine when there is only one vendor. In case if we have multiple vendors for the same product; purchase requisition gets created with out any vendor reference. These orders needs manual intervention to assign the source of supply.
    In stead of this; we would like to automate the process of the selecting the vendor automatically? Is there any by means? Currently we do populate the corresponding vendor partner function in the sales order item level. Can this be used as reference vendor during purchase requisition creation process? Is there any configuration or customitization?
    Have any one come across this?
    Thanks for the answer..
    Regards,
    Nagarjuna

    There's a default vendor in source lists.

  • Third-party order processing issue

    Dear,
    In the Third-party order processing,i have finished  SO-PR--PO successfully.
    But when i  Posted Invoice Receipt  for the Purchase Order using T-CODE:MIRO after finishing  Posting the Goods Receipt,it could't work.
    It showed the message'Invoice document still contains messages'.
    I can't find the problem.
    Buy the way it is just in the IDES system,and the data is the std.
    How can i resolve it ?
    TKS!

    hi,
    When doing Miro , There is Tab on top named  Messages. Click on it and assigned to your output type and enter communication method.
    You ll be able to complete your MIRO.
    Revert if not resolved
    Regards
    Amit Gupta

Maybe you are looking for

  • Error when using "inlist operator" in the query filter of Webi 3.1

    Hi, We are currently in the process of migrating Deski to webi (BOXI 3.1). The problem is, Deski is using the "inlist" operator which is working fine but after migrating to webi the inlist operator in the query filter is throwing the below error, *Er

  • Check box creation

    Hi Experts, i hae to create a check box for account assaignment default value ticked, ifit is ticked out put should come other wise output should not come could any one help me, account assaignment field is ekpo-knttp. i am giving the code below REPO

  • Repeating dynamic table data in another table in the same document

    Greetings one and all: I created a dynamic table (for input) at the beginning of my form. I created a dynamic table (for display and printing) later in the same form. I wish to populate the second dynamic table with the contents of the first dynamic

  • HTTPS and client invocation of web service - how to?

    Got some web services that are document and document wrapped. Have generated the client stubs using <clientgen> ANT task from BEA. Time to run a test against the web services, but they have to run on HTTPS. When I invoked my web service using the HTT

  • Help:plzz tell me how to save template form without losing any attached lib