Hello Guys,
I have a scenario wherein time entered will go either to Project Manager (Person responsible in WBS) or to Supervisor maintained in HR for approval.
A person is assigned to an activity and he will book time against that activity and release for approval. It will go to either Project manager assigned in WBS element or if person responsible is not maintained in WBS element, it will go to Supervisor assigned in HR master data for approval.
My question is, in which report/transaction I can see the time is pending with whom, Project Manger or Supervisor.
Deepak

Thanks Sanjeev.
I checked in CAC1, where I have see if  user profile is enabled for this approval process?
I have checked both CADO and CATS_DA reports.
I think I am failing in telling my requirement, I want see with whom the time is pending with (User ID, Salary Code etc...) for approval. Is there any report?
I can see the status of time sheet on both above reports but these reports does not show with whom these timesheet are pending for approval.
Deepak

Similar Messages

  • How to get list of PO pending for approval with a Particular Approver

    Hi Experts,
    I have created a Workflow for PO Approval. So when a PO is created the Approver is notified via an emaill.
    This is working fine.
    But now in the mail i have to send the list of Purchase Orders that are pending for approval with that Approver.
    Kindly suggest an approach to achieve this scenario.
    Regards,
    Radhika.

    There are several standard solutions to your requirement.
    One is to lessen the frequency of the program rbbp_notification_offapp and tick the box collect workitems. This should create one mail for all pending workitems for that agent.
    Another one is to retieve the workitems sent to him / her with FM SAP_WAPI_WORKITEMS_BY_TASK and include that data in the email you send.
    You can influence emails throught the badi behind rbbp...etc.
    Called BBP_OFFLINE_APP_BADI
    Kind regards, Rob Dielemans

  • Purchase Requisition pending for approval

    Hi,
        How to find out the Purchase Requisitions that are pending for approval?
    Thanks and Regards,
    Pavan

    Hi
    Try with ME5A, with dynamic selection option release indicator - blocked or with selection option PReq. processing state- 03.
    Thanks

  • Pending for Approval Appraisals

    Hi,
    Is there anyway to cancle the process of an appraisl that is "Pending for Approval"?
    I've tried to cancle the workflow from the sysadmin, although its status is canceled i still can see the appraisal pending for approval in the Appraisals In Progress section.
    Any advice?
    Thanks

    As my understanding,
    Employee has submitted these appraisals and they are pending for approval for respective Managers.
    If this is case, Two Possible solution could be there
    1. Manager can revert back to Employee
    2. Using API you can update to APPRAISAL record to "Pending with Employee". This change will effect in PER_APPRAISALS tables.
    Respective Notification you can close them from wf_notification Table.
    Thanks.

  • SSHR: Leaves Still "Pending for approval" after last approver

    Hi,
    After Approving the absence through SSHR from the last approver , it still pending for approval and was not transferd to the Application.
    Is there any specific configuration i've to do to enable the Approval process to be completed.
    we use AME for Approval.
    Apps Version : 11.5.10.2
    waiting for your help, please.
    thanks
    Edited by: Smarteng on Mar 21, 2012 6:30 AM

    Hi,
    The issue has been resolved, the reason was rhat the profile option HR:Defer Update After Approval was set to No and the backgroun process was running with no parameters, it should be running with the following parameters in order to update the database with the SSHR transaction:
    Item Type = HR
    Process Deferred = Yes
    Process Timeout = No
    Process Stuck = No
    Thanks for all for your help.

  • Absnce status is pending for approval, but supervisor dont get request

    Hi experts
    If i apply for absence and sumbit it, dann staus = PEnding for Approval, but my supervisor didn't get my request to approve my holidy request.
    Question: Why he /sehe will not get any entry in his page (Action pending for approval).
    Any suggestion????.
    Thx

    Hi Mehdi,
    I think in this case the approver to whom you are expecting approval request will go, its not going to that person, instead of that it is going to someone else.
    To find from backend to whom it is going
    Give this query
    select * from HR_API_TRANSACTIONS
    find out the item_key (Make sure item key is of your transaction only)
    select * from WF_ACTIVITY_STATUSES where item_key = (as got from above statement)
    now under this find the username that is specified against 'NOTIFIED'..
    This is the username with whom the notification is pending,
    Approve from this user, transaction will proceed further.
    Rupali

  • CUP: Avoid requests to be pending for approval: Best approach?

    Hi all,
    We would like to receive inputs for the different approaches you are using to avoid requests to be pending for approval.
    What is to say, to provide provisioning for new users eventough the role owner of one role requested hasn't respond the request.
    Many thanks in advance. best regards,
      Imanol

    Hi Imanol,
    Suppose a request is pending for approval to an approver. You can do following things
    1 Send Reminder mail. You can configure reminder mails in Configuration-> workflow->Email reminder.
    From here you can configure the time period and the email contents.
    2 you can set escalation. You set escalation navigating to configuration-> workflow-> stage.
    open a stage, you can set wait time and escalation configuration
    you can escalate to next satge, alternate approver & to administrator.
    3 you can also configure stale request setting.
    Configuration-> requests-> stale request.
    you can define the time period of the stale request.
    All open requests will be closed after that period. you need to run the background job for that.
    proviosning will not happen in this case
    kind Regards,
    Srinivasan

  • PO pending for Approval   -   tobe sent as mail for Approver (intimation)

    Hi ,
    PO tobe relased tobe sent(Intimated )  as mail for Approver
    what are the options for configuring this .
    With Rgds,
    Krishna.
    Edited by: Krishna L on May 27, 2011 3:28 PM

    Hi Krishna,
    Standard SAP comes with the workflow WS20000075 for release of purch. documents. You have to activate its linkage to the event PurchaseOrder.releaseStepCreated. This is done in trs SWETYPV - locate the entry BO BUS2012 RELEASESTEPCREATED or create one if it doesn't exist. Then make sure the receiver type is WS20000075 and the column "type event linkage" is checked.
    In customising for MM > PO > Release > Release proc. > Workflow define the recipients of the WF for each release code. If you assign the WF to an organisational unit rather than to a user, you will have to allocate users to this org. unit in trs PPOME.
    Good luck!
    Raf
    PS. For more details, check this link in the [system documentation|http://help.sap.com/erp2005_ehp_02/helpdata/en/04/92775546f311d189470000e829fbbd/frameset.htm].
    Edited by: Rafael Zaragatzky on May 29, 2011 6:24 PM

  • UWL for Manager : Multiple work items for approval

    Hi Experts, We have a scenario when the line manager is approving the leave workitems in his UWL. And the UWL has multiple  leave workitems pending for approval. When the line manager click on any of the work item in the UWL, The UWL opens the items which was first creared in the UWL rather than the one which the line manager clciked. Then line manager has to navigate to the desired work item by clicking on next button. Is their any funtionality / customization available to get only the work item which is clicked in the UWL. Please advise. Regards, IFF

    I had the same issue and spent a long time correcting it including opening a OSS request with sap.
    It took a combination of all almost all the notes above (1807724 is included in our current release so we didn't have to install).
    But nothing worked for us until SAP directed me to the following note http://service.sap.com/sap/support/notes/1733095 that was the final fix to all our problems.
    One other thing to note is from the time we implemented the correction for note: 1946640 had changed from its original so if you implemented it before revision 3 came out you may need to update.
    Hope this helps,
    Martha.

  • Project Server 2013 timesheets not showing up for approval

    We're using Project Server 2013 and entering timesheets. I'm a team manager who is set up as the timesheet approver for a few people, including Nicole.
    Nicole opens her timesheet and fills it in for the week.  She applies time to four Administrative tasks and two project tasks.
    Nicole submits her final timesheet for approval.  (We have also tried having her save it first, then to the final submission, with the same results.)
    I go to my approval screen and see the four Administrative tasks listed as separate lines.  I do not see the project tasks.
    I select the four Administrative tasks and approve them.  They disappear when the screen is submitted.
    In previous weeks, and with some other employees, I would immediately see a single line item that said "My Timesheet" for Nicole which I could then approve.  But recently this stopped, and I do not see her timesheet.
    If Nicole checks the status of the timesheet it says it's submitted to me.
    On my Approval page if I go to History, Timesheets this timesheet is not listed under "approved by me" nor is it under "my resources unsubmitted timesheets."  It's in limbo.
    The only fix is for Nicole to recall the timesheet and resubmit it.  Then it shows up on my Approval page.
    Any suggestions?
    -- Paul

    We resolved this. The solution was as follows:
    Go to PWA Settings, and under Security choose Manage Groups.
    Click the Team Members group.
    Scroll to the Categories section, and in the Selected Categories area highlight (select)
    My Tasks.
    Click the box to allow the permission called Adjust Timesheet which is under the grouping for Resource.
    Now don't ask me how or why that works.  It's not a setting that intuitively matches what's going on.  But it fixed it for us.
    By the way, we had a number of other timesheet issues (view failures, etc.) that were all cleared up when we installed the April 2014 Cumulative Update for Project Server 2013, as well as SharePoint 2013 SP1.  I highly recommend both.
    -- Paul
    Paul LoSacco, Web Presence Team, Omnicare

  • CFolders Main Page - To show pending Tasks for approval

    Hi,
    When ever the user login to cFolders 4.5, they see the first page as My colloboration <User Name>. So from there they need to drill down to respective project and then to folders and then to documents to approve the pending drawings.
    So the above involves at least 3 or 4 screens for them to go for the approval screen.
    Is there anyway, when ever the approval user logs in, he/she should see only those pending tasks available for them to approve, so that they just approve and log out.
    Regards,
    Ani

    Hi,
    two methods to set task for approval as home page.
    1.From super user login, u can set what ever page as home page for all users. only at front end u can change these settings. at  right top corner settings tab provided.
    2. second option is, user can set his/her home page as from his login only. its is based on individual user settings and these settings for home page will be different from user to user.
    but in first case it wil be applicable for all users.
    thanks
    amit
    award points for useful answer

  • PWA : Timesheet Manager list not available when submitting TS for Approval

    I've set the Timesheet Managers users in PWA settings and unchecked ‘Fixed
    Approval Routing’.
    On
    submitting the TS for approval in the sending request the control to choose the TS manager approver
    is missing... as there was a fixed route, but it's not the case.

    Hi,
    Please refer to this
    article.
    When you uncheck the fixed approval routing, while submitting a timesheet, Project Server will popup the list of predefined timesheet managers so the user can choose who will be approving his timesheet.
    If you check the option, then Project Server will send the timesheet for approval to the timesheet manager of the user (as it used to be in PS2010).
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, P-Seller |

  • Timesheet keeps loading when saved or sent for approval

    Of late we are having issue with users while trying to save timesheet and send timesheet for approval. On selecting these buttons the timesheet keeps on showing 'loading' message and when user clicks on any other link in PWA page a pop-up comes up 'You are
    naviating away from this page, your changes will be lost'.
    Most the users facing this issue are either using IE 9 or IE 10 and for some users changing Browser mode to IE 9 in F12 Developer Tools worked but some users responded back saying issue still persists. But for the same users timesheet save and submit timesheet
    worked fine in Mozilla and Chrome browsers. Cache issue might not be present in IE as this issue happened even after clearing browser cache in IE.
    The similar is issue was faced by some PMs accessing Project Center. Also there is no entry for this behavior in ULS logs.
    Environment is Project Server 2010 SP2.

    For users in IE10 can you add the PWA site in Compatibility View and then Check.
    Go to Tools in IE > Compatibility View Settings. Add the Site.
    Cheers! Happy troubleshooting !!! Dinesh S. Rai - MSFT Enterprise Project Management
    Please click Mark As Answer; if a post solves your problem or Vote As Helpful if a post has been useful to you. This can be beneficial to other community members reading the thread.

  • Import quote sales order with 'Pending Internal Approval' status.

    Hi,
    I’m trying to import a quote sales order using the oracle Order Import request, the order was imported with status 'Draft'.
    Is there any way to import the quote sales order with 'Pending Internal Approval'?
    or any API to change the Quote Status from 'Draft' to 'Pending Internal Approval'?
    Thank You In Advance.
    Ali

    No in standard, there is no such TCodes.  You have to develop a zee report considering the tables VBBE (for open order quantity) and MARD (storage location wise stocks)
    thanks
    G. Lakshmipathi

  • PO pending for Release

    Here PO have been raised by the Stores incharge, and there is only one MD approval for every purchase
    How will he come to know the list of PO's which have to released
    Is there any Transaction which only shows the PO's which has not been released???

    Did you check transaction ME28.
    Since there is only 1 Release Code create a Variant for Release Code.Once the person executes the Transaction he can see the PO pending for Release.
    You can also activate workflow so that the person can get the mail notiification showing which PO are pending for Release.
    Regards
    Vaibhav Mahajan

Maybe you are looking for

  • Itunes Deleted My Music

    I updated ITunes to the latest version and I seem to have deleted my music. I asked my friend who also have the same issue but she said she found her music in one of her school folder after she searched for it. I have gone through my computer, by fol

  • White screen? Resetting doesn't work

    I've tried resetting like a million times! Still nothing, my screen is still white. I have the 160GB. I won't restore because thats over 24,000 songs gone. I dropped it today on the pavement, it wasn't even a hard drop. Can someone tell me how to fix

  • Can I upgrade from 10.3.9 to 10.4?

    I have a iBook G4 933MHz 256 SDRAM can I upgrade to 10.4? What problems might I encounter?

  • Photoshop tutorials

    Are there any free photoshop cs6 video tutorials with the photoshop files so that I can work on the file while following along on the video?

  • Poor resolution RAW import

    When importing a RAW fil to LR the quality become very poor, without Im doing anything.  I do not have the same problem when importing a JPEG in LR or a RAW file in Elements for example. Is there any setting that should be changed? The problem is ver