To exclude Storage location frm MRP run

Hi Friend s
In my secnario MRP should not consider the storage location  stock planning
i using stratgey 11 gross req planning ,
and  (SPRO), In MRP  -define storage location MRP  per Plant , i set the indicator 1 i.e storage location stock excluded frm MRP
But still i mrp considers  stoge location stk .
is there any setting ?
Regards
Sandeep

Sandeep,
For strategy "11" system automatically will not consider storage location stocks, so no need to define that in SPRO>MRP->Planning-->Sloc MRP/Plant as told by you.
Couple of checks....i would suggest.
1. Check whether you have maintained "2" - Mixed MRP indicator in MRP3 view.
2. Check whether the PIR you have created is having requirement type "BSF".
Regards,
Prasobh

Similar Messages

  • Excluding storage location from MRP run in Long Term Planning

    Hi,friends,
         In my scenario , i want to exclude storage location from MRP run in long term planning.When i set storage location MRP indicator "2" in SPRO and SLoc MRP indicator "1" MRP4 in material master, i can exclude the storage location after run MRP with MD01/MD02,and i can see the expected result in MD04.But in Long Term Planning scenario the storage location can not be excluded after run MRP with MS01/MS02,and the requirements list in MS04 include the stock in the storage location i want to exclude. i dont know if i miss something.Plz give me some advice.
    Regards
    Joey

    Hi,
    Refer the OSS Note 208017 - LTP: Long-term planning and storage locations
    ==========================================================================
    Symptom
    In long-term planning (Transactions MSBT / MS01 / MS02 / MS03), the MRP indicator of a storage location for a material is not taken into account (material master, view MRP 2 [up to and including Release 3.1I] or MRP 4 [as of Release 4.0A]).
    The storage locations excluded by MRP or planned separately are also planned in the plant segment.
    Additional key words
    LTP, MM01, MM02, MM03, master data, MRP indicator, LGORT ...
    Cause and prerequisites
    The MRP indicator for a certain storage location of a material is only taken into account in operative planning (requirements planning, MRP).
    The long-term planning occurs exclusively at plant level.
    Solution
    This is no error. The system works as intended.
    The individual storage locations should not be distinguished in the long-term planning, in order to perform a comprehensive long-term planning.
    This is important, for example, within the kanban processing where the storage locations with kanban MRP are excluded from the MRP, but in spite of that should be included in the long-term planning.
    ==========================================================================
    Regards,
    Siva

  • Need to exclude storage location from MRP.

    Hi Gurus,
    Is there an option to exclude a specified storage location from MRP at configuration level. But not at material level as in MRP4 view.
    We have excluded the stoarge location in config OMIR, however the system considers that stock if the same is not excluded in MRP4 of that material.
    Now, the problem is every time i need to go to the material master of every material  i have to excude from MRP, which is very time consuming..!
    Please advise me is there any option in point of view of Storage Location,  just simply  define the storage location to be excluded from MRP run.
    Thanks in advance.
    Naveen.

    Dear,
    Yes you can do it though OMIR or MMSC 1-Storage location stock excluded from MRP.
    Also check this link for more details,
    Exclude purchase order on storage location from MRP
    Regards,
    R.Brahmankar
    Edited by: R Brahmankar on May 25, 2009 12:22 PM

  • Deactivation of storage locations from MRP run

    Hi gurus,
    How can i deactivate a particular storage location from MRP in a particular plant.
    Regards
    Kaisar

    Hello,
    There are 2 ways of doing that.
    1. With the Transaction OMIR and selecting th indicator 1 Storage location stock excluded from MRP
    This storage location will be excluded from MRP.
    2. For a Specific Material(s), if you want the Storage location to be excluded from MRP:
    You need to select the storage locatio MRP indicator as 1 in MRP4View of the Material.
    Some concerns:
    Your Materials are extended to the St.location say xxxx.
    Now if you want this storage location to be excluded from the MRP.
    By simply seeting the Customization settings will not work.
    You need to manually select the MRP4 view and change the St.Loc MRP Indicator to 1.
    The Materials created after this customization setting will adopt this settings automatically.
    Hope this helps..
    Regards,
    Siva

  • How to exempt a storage location from MRP run

    Hi all,
    How do I exempt a storage location and all its materials from MRP run.
    I am creating a new storage location and this should not be considered for MRP and  no idoc should be generated if a purchase order or a delivery is created from this storage location( should we stop entering this storage location in BD64 filters or anything more to prevent triggering of the idoc).
    Can somebody please through some light on these issues. 
    Kind Regards
    Chakradhar
    <REMOVED>

    Hi
    You need to set up master data for that material.In Mrp-4 View  set  storage location indicator as 1(one) .In this case your storage location stock will be exclude from MRP .
    Hope this will help
    Dilip

  • Exclude purchase order on storage location from MRP

    Hi Everyone,
    We have excluded storage location 1200 from MRP.
    The result shows only stock on 1200 excluded from MRP, PO on storage location 1200 (storage location 1200 in PO) still considered in MRP.
    Is there any way to exclude PO on 1200 i MRP also?
    Best Regards,
    Bin

    Dear,
    Go to MRP 4 view of the material master .
    In the field SLoc MRP indicator field "1".
    If it is for a material than in the material master level it can be done. If you are looking for all materials in that storage location, than it is better to define this in SPRO->Production->MRP-->Planning-->Define Storage Location per MRP plant. Here for that storage location in that plant you need to define "2" - Storage location stock planned seperately or "1" - Exclude Storage location from MRP.
    Also u can use t.code MMSC.
    Select Material & Plant and Assign MRP =1 for the Sloc to be excluded
    Regards,
    R.Brahmankar
    Edited by: R Brahmankar on Nov 14, 2008 9:32 AM

  • MRP run by excluding storage location

    Dear PP experts,
    I have excluded storage location e.g. storage location 0001 from MRP in OMIR and also maintained the same in MRP 4 view in material master. As far as MRP run is considered system is ignoring the stock and giving the results.
    But now we are facing the problem in quantity confirmation in sale order in transaction code CO06. The stock is existing in storage location 0001and is not confirmed for any other sale order.
    We need to exclude the storage location in MRP but it should allow stock determination in sale order.
    Pl. let me know how this can be achieved.
    Thanks in advance,
    Regards,
    Prashant

    Dear Prasobh,
    Thanks for the reply. There is no storage location mentioned in the sale order. I tried confirming the sale order by activating the No storage location check box, still it does not confirm the quantity. If we keep the check box "Check without RLT" blank then the sale order quantity gets confirmed. But the problem here is that it confirms quantity greater than what is available in stock i.e. if we enter any quantity it is confirmed.
    I would like to ask one more question. The sale order confirms quantity available as per the ATP logic. When we have excluded the storage location from MRP the quantity is seen at storage location level and not at Plant level and hence it is not proposed in cummulative ATP quantity. Should the quantity be available in cummulative ATP quantity. If yes, how can be get that quantity in cummulative ATP quantity?
    Is there any impact of MRP area? as we have MRP area activated. Within this Plant we have one MRP area at storage location level and the other MRP area as Plant excluding this storage location.
    Regards,
    Prashant

  • I want to exclude a storage location from MRP

    I want to exclude repair storage location from MRP so that the stock with repairs storage location should not be considered for other demands.
    Also repair storage location stock should not be calculated against 'stocks'  term in MD04.
    How to do this ? Pls share.

    Hi,
    In transaction OMIR, choose your plant & then for the storage location you want to exclude from MRP enter 1 (exclude from MRP).
    After this setting is maintained, whenever a material is created in this plant & storage location, it will have MRP indicator as "1" in the mrp 4 view .
    For materials already in this storage location if the MRP indicator "1" is not maintained in mrp 4 view, please go for a mass change maintenance in the material master & maintain this indicator.
    Stock in the excluded storage location will not add up to the stock which is displayed in the top in the md04 screen. This stock will be displayed separately in the bottom of the screen.
    Please let me know if you have any questions.
    Regards,
    Senthilkumar

  • Exclude Storae location from MRP

    Dear All,
    How to exclude a storage location from MRP planning?
    What are the steps to be followed?
    Please advice
    Regards
    Edited by: Csaba Szommer on Jun 10, 2011 4:30 PM

    In MMSC,  for the Matl-Plant-Sloc combination,   in the MRP field select option-1 (exclude from MRP)

  • MRP Run in an excluded Storage Location

    Hello all. I have this situation.
    I have material X with two storage locations: SL01 and SL02. Storage location SL01 has 15 pieces and SL02 has 5 pieces. In MD04, I can see a total of 20 pieces under the "Stock" MRP Element.
    Material X also has five Order Reservations (OrdRes), for 5 pieces each. These Order Reservations are assigned to Storage Location SL02, because stock is procured from there.
    What I want is to have the "Stock" line only show me the stock of SL01 (Stock = 15 pieces). I want SAP to "ignore" whatever it has in SL02 and only consider the stock in SL01, so MRP Run would give a proposal of 5 pieces.
    I tried deactivating SL02 in Material Master MRP4 for material X, but then the MRP Run doesn't generate any proposals because my reservations are in SL02, and it's deactivated. Even if my Availability Check is set not to look at "storage location", if I the requirement is in SL02, it won't propose anything.
    Is there any other solution to my problem? How can I have the system ignore the stock in SL02, but still propose those 5 pieces I'm missing in SL01?

    I have material X with two storage locations: SL01 and SL02. Storage location SL01 has 15 pieces and SL02 has 5 pieces. In MD04, I can see a total of 20 pieces under the "Stock" MRP Element.
    Material X also has five Order Reservations (OrdRes), for 5 pieces each. These Order Reservations are assigned to Storage Location SL02, because stock is procured from there.
    What I want is to have the "Stock" line only show me the stock of SL01 (Stock = 15 pieces). I want SAP to "ignore" whatever it has in SL02 and only consider the stock in SL01, so MRP Run would give a proposal of 5 pieces.
    Sorry, but your logic is not clear to me...
    your stock:
    5 pcs (SL02) + 15 (SL01) = 20 pcs
    your requirements
    5 x 5 pcs (SL02) = 25 pcs
    Procurment proposal (w/o excluding SLoc):
    20 pcs (stock) - 25 pcs (requirements) = -5 pcs > procurement proposal 5 pcs
    You are saying:
    What I want is to have the "Stock" line only show me the stock of SL01 (Stock = 15 pieces). I want SAP to "ignore" whatever it has in SL02 and only consider the stock in SL01, so MRP Run would give a proposal of 5 pieces.
    So, you can see MRP will give a procurement proposal of 5 pcs without any SLoc exclusion...
    Please clarify your requirement / business process. Why don't you want to consider the stock in Sloc2? What is your process?
    You can see that you cannot exclude a SLoc with Sloc MRP and still consider the requirements relevant to that SLoc (unless you use reorder point planning in that SLoc).
    Thanks,
    Csaba

  • Exclude storage locations from the MRP run

    Hi all,
    Is it possible to exclude stock of specific storage location from the MRP run?
    Thanks for your help
    Thomas

    Hi,
    2 things,
    1. In OMIR for the storage location set that this location is excluded from MRP run (if am right the value to be maintained is 1)
    2. In MM02 go to MRP-4 view of the material master, specify plant & the storage location which you want to exclude & in the field SLoc MRP indicator specify that this is excluded for MRP run (if am right the indicator is 1).
    The step 1 ensures that all materials which are extended to this storage location will by default have the value 1. And step 2 ensures the materials already having this storage location view are excluded from MRP run.
    Regards,
    Vivek

  • To exclude SCARP storage location from MRP

    Hi Gurus,
    We have a issue regarding the scrap Quantities. we need to exclude these materials from the available stock for MRP. We have a setting in the MRP available stock with Blocked stock not checked and restricted stock checked.
    My question is if we un check the restricted stock, is the MRP will not consider the stock in scrap storage location.
    Please help to find the solution.
    Thank you.
    naveen.

    Hi,
    Your scrap str location is not either blocked or restricted str location. This is a regular str location but the name is scrap location.
    System will consider this str location as a regular str location. So do setting to exclude this str location from MRP as previous member explained.
    Regards,
    Dharma

  • MRP4 view exclude storage location & material provided by vendor/customer..

    Hi
    Could anyone please tell me in MRP4 view for a material,where is the option so that i can exclude or include the storage location stock from MRP?
    and also in which T code i should indicate the material is provided by vendor/material provided by customer?In CS01wher's this option?
    Please help me
    Thanks & regards
    Raj

    Hi Karthik,
    MRP area is nothing to do with storage locations settings in MRP4 view. If you want to activate MRP area and use the MRP run at MRP area level then you have to customized MRP area either at storage location level or sub-contractor level (in MRP master data settings )... then you need to assign this MRP1 view of the material and with valid MRP type.  Now when you run the MRP then planning will be carried out at this MRP area for this part.
    With storage location indicators in MRP4 view (must enter with putting the stoarge location values from MM02/MM03) you can exclude the stock of this storage location (indicator 1) in the palnning run or you can plan seperately with indicator2 with using re-order level. Here no need of MRP area.
    If helps rewards points.
    Regards
    TAJUDDIN

  • Replenishment between Storage Location with MRP Planning

    Dear PP Gurus,
    I need you expertise on the below question.
    I have a plant with multiple Storage Locations. One Storage Location is Main Warehouse and another ilocation s External Warehouse (3PL) where excess stock are kept due to storage capacity in the Main Warehouse.
    Now the requirement is replenish the stock to Main Warehouse from the External Warehouse with Stock Transfer using MRP trigger the Stock Transfer.
    I know the setting in MRP 4 View in the material master, the Indicator to set to 2, maintain a reoder point in the Sloc: 1200 and Replenishment Qty: 1500 and Special Procurement Type: (what should be the setting)
    My question is where to set the target Sloc and source Sloc, then only system will trigger the replenishment Stock Transfer?
    The storage location which is plan separately, will have a different segment. Therefore, in terms of the availability check for the Sales Order it will consider as normal based on the scope of check.
    Appreciate the reply
    Thanks & Regards
    Pooja

    Dear ,
    1.You need  to set up the MRP for Plant with group of storage location  and run MRP-MD01 .You can try SCOPE of planning -OM0E.
    As an information : In standard MRP I, f you have several storage location for your plant, you cannot plan for them separately unless you assign them to a separate MRP area.If a storage location (alone) is assigned to an MRP area, it means you wan to plan for it separately. If several storage locations are assigned to an MRP area (or let's say to a plant), it means you want to plan using all of them - and you cannot choose only one and plan for it (you can exclude a SLoc from planning w/o assigning it to MRP area).
    2.Find steps for config for activating Sloc to Sloc transfer within plant using STO : -
    follow path: SPRO--> Materials Management -->Purchasing -->Purchase Order -->Set up Stock Transport Order -->Set Up Stock Transfer Between Storage Locations
    1. Activate Stock Transfer Between Storage Locations
    2. Assign Delivery Type and Checking Rule According to Storage Location
    purchase document category 'F' , here use PO type UB, supplying plant, issue sloc and delivery type , (prefer to create new delivery type by copying delivery type 'NL' replenish delivery
    3. Define Shipping Data for Stock Transfers Between Storage Locations
    for plant defind sales org and distribution chenal and devision
    select the pline and go to sloc
    assign there customer (created for sloc)
    4. Define Rule for Determination of Shipping Point
    for newly created delivery type set L storage location specific shiping poing determination
    5. Assign Shipping Points According to Storage Location, assign her sloc based shiping poing determination
    at last when you will create PO put issue storage location, system will determine shiping data based on config done.
    after this process will be same as STO plant to plant using shiping.
    You will need to mention the issuing storage location during posting the delivery,
    ie, ME21N - Create STO
    VL10B - Create Delivery
    VL02N - Post Goods issue - here you will need to mention the issuing storage location
    Refer : STO process -Std in SAP
    Hope it is clear to you .
    Regards
    JH
    Edited by: Jiaul Haque on Jul 7, 2010 10:23 AM

  • Storage location on MRP-list

    Hi! I am trying to add Storage Location to the Purch.Requisition during a MRP-run. What prerequisites are necessary in order to achieve this? The business scenario is StockTransportOrders from Plant to Plant, where we want the storage location of the issuing plant to appear on the requisition (and hence be displayed on MD04): Any hints would be appreciated.

    Hi and thank you for your answer. I have tried to maintain storage location, and planned the st.loc. separately, but that is not enough - it seems. The SAP note 355493 desribes the essense of what I am seeking, but the note did not solve this issue regarding Purch.Req's
    brgs dag sigurd

Maybe you are looking for

  • How do I "reset" calendars and contacts on iPod Touch 2G

    I need to know how to erase and/or reset all contacts and calendars on my ipod Touch. Initially I synced with my mobileme account. When one of my contacts did not sync properly, however, I set iTunes to sync with calendars and contacts. Now I have du

  • Apple TV, PS3, Time Capsule compatibility

    I have heard that to access your movies on iTunes with Apple TV iTunes must be open. But can an Apple TV access the movies on the time capsule hard drive to play them. Also can the PS3 access the movies on the time capsule?

  • Remove duplicate Address Book emails

    I'm trying to write a script that walks through the currently selected Address Book entries, checks for duplicate email addresses, and removes any duplicates that it finds. Here's what I came up with: <pre>tell application "Address Book" set the_sele

  • SQL Server 2008 R2 Licensing Query

    Hi, If i have SQL Server 2008 R2 Enterprise License key for a single instance and I am installing all the shared features from the setup. Then is my license counted as being used or no? Or is it only used when i install Database Engine? Please mark t

  • Duplex printing of abap list

    Hi, we are trying to printing some abap lists on both sides. ich have found some information about duplex printing of sapscript / smart forms, but nothing about printing of abap lists. Ich habe changed attribute printmode ( transaction SPAD ) of prin