Experts,
how does SAP determine the replenishment lead time for a part under the following circumstances,
- purchase part (ProcType F)
- two PIR for two vendors with diffrent delivery times per vendor.
- Source list has no fixed vendor
- quote arragement in place.
in MD04 I see the correct split acc. to quote arrangement, but currently I have the effect that the replenishment lead time for this part changes form delivery time of vendor A to delivery time of vendor B from time to time. Unfortunatly I can not see a pattern in behind.
Who can explain this behaviour ?
Thanks in advance
Jörg

Hi,
- purchase part (ProcType F)
Depending on the setup done in OPPQ (push button - external procurement), the lead times will be read from Info record first if not existing then from material master or directly from material master.
- two PIR for two vendors with diffrent delivery times per vendor.
If the vendor is fixed, then the lead time from the fixed vendor is selected. If quota based, then from the vendor to whom the quota is allocated to.
- Source list has no fixed vendor
lead time from mtl master.
- quote arragement in place.
Lead time as per info rec of vendor selected based on the quota arrangement.
Now all the above is theory... so take some examples in your sandbox & do some testing to see it n revert if you face any issues.
Regards,
Vivek

Similar Messages

  • Total replenish lead time

    Hi gurus,
    anyone can explain why this field (total replenish lead time) is designed to enter manually instead of system automatically calculate from BOM for a manufactured part? and how does it work according to the following scenario:
    product X is produced in plant=1000 from material A and B (both A and B are procured externally for plant 1000, to simplify the case)
    in plant 1000, PO processing time=1day
    A: planned del.time=3 days, GR. processing time=1 day.
    B: planned del.time=5 days, GR. processing time=1 day.
    to make X need 2 operation: 1st operation need 1 day to assemble A and B together, after assembling, 2nd operation need 1 day to paint, 1 day to dry
    what's the total replenish lead time we should enter for X?
    thanks,
    cookie

    Dear Cookie
    3.if it's only for availability check, does that mean the MRP would not be affected by this field, then what would be the lead time feed into MRP? what's the relationship between MRP and availability check? why they use 2 different sets of data?
    1) MRP will not take this field into Account for Calculating Dates
    2) MRP for in-house materials - in-house production time & GR Procesing time ( Lead time )
    3 ) For external Procured materials - PR processing time , Planned delevery time & GR Processing time
    4) MRP Net Req. Calculation Concept is different from Availbility check Concept
    Regards
    Madhu

  • Need a table to check Planned delivery time & Total replenishment lead time

    Hi Experts,
    I want a report of Planned delivery time & Total replenishment lead time (MM02) for the material.
    Thanks in Advance.

    Hi,
    Planned delv time = MARC-PLIFZ
    Total Repl. lead time = MARC-WZEIT
    Vishal

  • Availablity Check in Sales Order with Total Replenishment Lead Time

    Dear PP Consultants,
    This is regarding the TRLT field functionality during availablity check of Sales Order.
    I understand the TRLT field is defined manually in Material Master MRP-3 view as the sum of the longest lead time of raw material, in-house-production time and floats.
    If during the availablity check of Sales Order, the raw material which is having the longest lead time is already available in stock, can the system calculate the TRLT dynamically and propose the delivery date in sales order only based on in-house production time??
    Is there any setting that can be made so that during availability check of Sales Order, the system considers the stock of raw materials and then propose the confirmed dates?
    Your early respose is much appreciated. Thanks a lot in advance for your valauble suggestions.
    Thanks,
    Kishore

    Hi,
    The RLT is not dynamic, and is not related to the stock situation of the components.
    It's only purpose is to give an estimated availability date for the finished material (sold) when no better information is present (like a procurement element).
    The only way I know to get an availability date taking into account the availability of components, is the assemble-to-order scenario. In this scenario (MTO!), a production order is created automatically during the creation of the sales order. The system can then use the production order features like scheduling and availability check of components to propose the availability date for the finished product.
    Besides that, you can get much more complex solutions for ATP using APO's ATP engine.
    Regards,
    Mario

  • Total Relenishment Lead Time vs. Routings Lead Time  ( very urgent)

    Hello PP Champs
    Need urgent help
    I am facing a scenario in current project -
    My Customer service quotes for delivery to an customer with in 3 days for a stock item by seeing the availability check with Total Replenishment Lead time in MAterial Master , but when production order is created SAP schedules the same on routing Lead time basis with a date after 7 days. this seems technically correct as per Std.SAP settings
    1=but How to avoid this business conflict in SAP PP module?
    2=another thing we are nt using the capacity planning with this client ,but incase we get 2-3 orders with same start date and same requirement date for a single work center " how to priortise the selection of production orders" w/o capacity planning
    pl consider first query as most urgent and help me
    Could somebody put a thought on this and help me out.. I'll reward full points any helping hand for the same
    Thx in advance
    BR
    Sumit

    Hi,
    you can define via define  the checking scope opjj whether to include the RLT
    in availability check or not.
    Note:
    Items for which the delivery date falls within the replenishment lead time, but for which there is no inventory, are confirmed for delivery after the replenishment lead time. In the case of items for which the delivery date falls after the end of the replenishment lead time, the system assumes that everything can be confirmed.
    In the standard version, leave this field blank if you want the system to check the replenishment lead time.
    Dependencies
    If you want the system to check the replenishment lead time, you should make sure that you have entered a value in at least one of the following three fields in the material master:
    GR (goods receipt) processing time (Purchasing view)
    Planned delivery time (MRP I view)
    GR processing time (MRP II view)
    Otherwise, the system confirms every requirement
    Regards,
    nandha

  • Replenishment lead time & Scheduling Agreements - Please help

    Hi,
    I have a few questions & issues in regards to Replenishment lead time & Scheduling Agreements.
    1.     Where are stock requirements & Replenishment lead times configured?
    2.     What is a stock/requirements list?
    3.     What is Replenishment lead time in MD02/MD04?
    4.     Why do negative supply values appear under replenishment lead time in MD02/MD04?
    5.     What are the differences between MD02 & MD04?
    6.     How do you get to the following screen, since I canu2019t get here from MD02 or MD04 (missing buttons and Replenishment lead time information):
    http://i34.tinypic.com/9hl9hz.jpg
    Please help. This is very important.
    Thanks,
    Laura

    Hi Laura,
    The RLT can be set in the Masters Materials.MMR and Also in the Documnet Type Configuration.
    But as per SAP standard Procedure the Prority will be the document type.
    That means the RLT given in the Order document will overseed the RLT given in the MMR.
    Go to material master and select MRP3 view. There see what is maintained for "Strategy group". Now go to OVZG, select this Requirement Class and tick the field "Rq" against this.
    Now go to OVZH, select your Requirement Type and ensure that the above Requirement Class is assigned to your Requirement Type.
    Now create a sale order and check in MD04.
    Hope ethis helps u..
    Cheerzz..
    subbzz..

  • Reg: lot size and replenishment lead time

    1. please explain about lot size and replenishment lead time.
    2. please also explain about consumption based planing and in steps explain how to perform manual and automatic reorder point(transc code please)

    You use the lot-sizing procedure to determine how the system is to calculate the reorder quantity in the planning run.                                                                               
    A lot size defining the lot-sizing procedure is assigned to every material master record applicable to materials planning.                                                                               
    The lot size is defined in Customizing by the combination of the lot-sizing procedure and the lot-sizing indicator.                                                                               
    Three procedures for lot sizing are available:                                           
    o  static lot-sizing procedures                                                          
    o  period lot-sizing procedures                                                          
    o  optimizing lot-sizing procedures                                                                               
    You use the lot-size indicator to define the procedure.                                                                               
    The following parameters are also available for controlling the lot-sizing procedure:                                                                    
    o  Short-term and long-term lot size                                                     
       You can split the lot-sizing procedure into a short-term and a long-term period. This means that you can select one lot-sizing procedure in the near future and a different one in the distant future.                                                                               
    You define the periods in the section of the screen entitled "End of the short-term period/start of the long-term period".                                 
       The valid from date of the long-term lot size area is defined via:                    
       -  a periodicity                                                                      
       -  a number of periods                                                                
       The beginning of the long-term period is calculated by taking today's date and adding the number of periods in the future; the long-term planning period then starts on the next complete period.                              
       Note                                                                               
    For materials that are planned using the short and long-term lot size,                
       it is recommended that you define a maximum MRP period. Defining the                  
       MRP period has the effect that materials after a certain period are                   
       included in planning even if no changes relevant to the planning run                  
       have occurred. This avoids a situation where order proposals created                  
       with the long-term lot size move into the short-term period because no                
       changes relevant to MRP have occurred for the material.                               
       You define the maximum MRP period in the step, "Define maximum MRP                    
       period". A material that is planned on a regular basis should also be                 
       provided with an MRP type that contains the indicator for regular MRP.                
    o  Scheduling indicator                                                                  
       For period lot sizes, you can use the indicator for scheduling to                     
       determine whether the availability date;                                              
    o  is to be set to the first requirements date in the period                             
    o  or is to be set to the beginning of the period                                        
    o  is to be set to the end of the period                                                 
    o  or whether the period start represents the beginning of the planned                   
       order and the period end represents the availability date (repetitive                                                                               
    manufacturing)                                                        
      Interpretation of the delivery times                                  
      For the lot-sizing procedure, you can also define whether the period  
      start is to be interpreted as the delivery date or as the availability
      date using the indicator, "interpretation of the calendar times".     
      NOTE                                                                  
      The indicators, Scheduling and Interpr.deliv.times are mutually       
      exclusive.                                                            
      Indicator for the splitting quota                                     
      For the quota arrangements, you can determine whether the requirements
      quantities are to be distributed to several items, that is, whether   
      they are to be split. With the splitting quota arrangement,           
      requirement quantities are not simply allocated to the smallest quota 
      rating. Instead, they are distributed among various sources using the 
      following formula:                                                    
      Quantity for source of supply X = Quota of source X * reqmts quantity                                                                               
    Sum of all quotas          
      Overlapping indicator                                                 
      The overlapping indicator along with the cycle time in the material   
      master record are used to split the planned orders into several       
      partial quantities whereby the in-house production time overlaps by   
      the cycle time.                                                       
      Lot-sizing procedure for make-to-order production                     
      In make-to-order production, you can use the indicator, Lot size for  
      make-to-order production to determine whether,                        
      the order quantity is to be calculated using the exact lot size       
      the order quantity is to be calculated using the exact lot size and   
      the system is also to take the rounding quantity or the minimum and   
      maximum lot size into account                                         
      the order quantity is to be calculated using the lot-sizing procedure 
      defined for the short-term area                                       
      Maximum stock level variant                                           
      The system only displays the Maximum stock level variant field in the 
      lot-sizing procedure, Replenishing to maximum stock level. The        
      indicator only has an effect in connection with reorder point planning
      taking external requirements into account and in connection with      
      material requirements planning and controls how the system calculates 
      lot sizes.

  • Replenishment Lead Time Change Log

    Hello Experts
    While making change to Replenishment Lead time field in the Product Master, the changes are not visible in the change log in transaction /SAPAPO/PROD_CD_READ. Can you please advise?
    Thanks in advance.
    Best Regards,
    Parth Soneji

    Hi Parth
    Please go to SE11 --> Data type /SAPAPO/RELDT.
    Go to further Characteristics and click on change document tab.
    This flag is used to create change documents for business objects. Please let me know if this helps.
    Thanks
    Amol

  • Batch and replenishment lead time

    Hi,
    I read the following statement in SAP help portal and am confused.
    Please help explain with an example.
    The replenishment lead time should not be considered in the dynamic availability check for batches, since batches are not reproducible
    Question: Why not? basically not understand above statement.
    thanks
    tuff

    Since a batch is created on a given date at a given time, and it has specific charactreristics and values, you cannot make anymore of that particular batch.  The only available qty of a specific batch is what you have available in actual inventory.  Therefor no replenishment lead time is to be considered because you can't replenish a batch.
    You can use replenishment lead time in say ATP because that will tell you how long it takes to make a batch of material that meets the general spec of the material.
    When a material is not batch managed you can use replenishment lead time in the availability check if you want since you can make more material to meet the customers requirement, (i.e. the general material spec).
    FF

  • Replenishment Lead Time

    I am going through TSCM60 and am facing a problem understanding the concept of Replenishment Lead time. I will explain what problem I am facing grasping the concept.
    As can be seen, Replenishment lead time according to the manual:
    Only the inward and outward movements that take place within the replenishment lead time are included in this check.
    Now this seems in contradiction to checking the box: Include Sales requirements because this considers the requirement from the already made sales orders. On the other hand the RLT only the time till the product (from inhouse production or external procurement) becomes available.
    For example,
    For an already confirmed Sales Order requires a Material Availability Date of 7 October for a delivery on 10 October. Now, an order comes along later that requires a delivery on 8th October and hence a MAD of 5th October. The problem is that if using the RLT, the required MAD is to be provided to the system for the latter Sales Order (5th Oct. MAD), the full amount of the material is not available on 7th October for the former Sales Order.
    So what is the system going to do if both RLT and Include Sales requirements are being employed?
    The graph in the manual makes it look as if the system is going to commit the full amount for the 5th October MAD and snub the customer requiring the delivery on 10th by sending him/her the remaining material i.e. a partial delivery on requested date of delivery.
    Edited by: shabie on Sep 26, 2011 7:52 AM

    Hello,
    Thank you for the appreciaton.
    Yes. Your understanding is correct - that it is generally advisable to not activate it but it can be activated for in-house production and materials that are easily available.
    For your question regarding points:
    For it's use in real life - You just appreciated me & that is the genuine example of use of points in real life. It is more about feeling of satisfaction - to give back something to the forum from which I have got so much. I remember of so many instances in past when client was bombbarding me with issues & I did not had ready solutions. SDN Forums & it's memers have always helped me during those times.
    I don't know whether I am selfless or not... but one thing I can say for sure, contributing to SDN forums has help me a lot in learning SAP SD. Also there are many other senior contributors in the forum who are really selfless since last couple of years...
    Thanks again,
    Jignesh Mehta

  • Replenish Lead time effecting Materials

    We have issue in Sales orders, For some materials confirmed qty is getting 0. Availability check codes and material determination are maintained correctly .
    It happens once a week, then user have to edit order manually. Its happening for different materials at a point of time(Ex: Item 1002876 unable to get confirmed qty, after some time we test creating order with same material and there is no same issue)
    Can any one faced this kind of situation before, please share thoughts on same. Does RLT enhancements effect orders?

    Hi Guys
    Thanks for looking into it.
    Yes the material i have listed above is a BOM that has 6 products under it with item category: L (stock item). The BOM products have item category as NORM and 4 products are material type: HAWA (trading goods) the rest two are FERT: finished

  • Check without RLT (Replenishment Lead Time) not working as expected

    Dear All.
    We're seeing a sales order ATP situation for externally procured materials, in wihch RLT is not checked.  Or at least we've flagged the checkbox in atp config to not include RLT. 
    However, RLT is still picking up the planned delivery time and GR time.
    And if I blank out the GR time and planned delivery timie, then it just confirms it.
    It acts like RLT is still being used in the check even though RLT is turned off in the availability control (OVZ9)?
    Ideas?  Anyone see something like this?  Does it only work on internally procured materials?
    Many Thanks!!!

    RLT is turned off in the availability control (OVZ9]
    Make sure, the box is checked in OVZ9 to avoid RLT in the availability check. You can do more analysis, by highlighting the sales order line item, then clicking the display availability button. In the next screen click on scope of check button, which shows the OVZ9 details.
    Did you check other parameters like Route, pick/pack time?
    Regards,

  • Mass change - Lead Time

    Hello,
    Do we have a standard transaction for mass change of lead time for material-plant level for all materials in a plant. This should also consider lead time for DC.
    Regards
    Prashant Kedare

    >
    Prashant Kedare wrote:
    > Hello,
    >
    > Thank you for the replies so quickly. But the planned delivery time is to be maintained only for materials from external vendors. How about receiving goods from a Warehouse which takes 1-2 days for receipt of material. Where do we set this parameter and how do we mass change it?
    >
    > Regards
    > Prashant Kedare
    In MASS,  use Total RL time = MARC-WZEIT for updating total replenishment lead time and just update materials which are for external vendors.
    Use GR Proc. Time = MARC-WEBAZ for updating Gr proc. time field records and you can give range of materials for which records needs to be updated or created.

  • Splitting Replenishment Generated PO by Delivery Lead Time

    Dear Folks,
    When I run replenishment, I would like the auto generated PO to be created based on the replenishment lead time/planned delivery date.
    Is that possible?
    For example, I have 2 SKU, one with planned delivery time of 2 days and 1 with planned delivery time of 1 day by the same vendor for same plant.
    When I do a replenishment run, I would like to have 2 PO created.
    Best Regards
    JW

    Dear folks,
    It could be that my original question was not very clear.
    In each PO line items, there is this field 'Delivery Date', this date is usually derived from the Planned Delivery Time from the material/article master. I am using SAP retail.
    Basically, what I would like to achieve when I run auto-replenishment is:
    - different PO created with each PO containing on the items with the same 'delivery date'.
    - if an item has a different delivery date from the rest, a separate PO will be created.
    Assume that the requirements/demands are already triggered - reorder point etc.
    Any advice would be appreciated. Thank you.
    Best Regards
    JW

  • Purchase order with transportaion time+replenishtment lead time in PP/DS

    The process: Location 0011 buys by supplier 1080 with normal purchase order. 
    Delivery lead time 30 days of this 20 days transportation time and 10 days replenishment lead time of the supplier. Delivery free on board.
    What to do that the date for free on board is in the purchase order.for example.: Beginning November.
    And the inbound delivery date end of November in the md04 R3 and product view PP/DS.

    Yes 30 days is the total lead time . I am not so good in modelling of FOB in PP/DS.
    In R3 we have a not so good solution for FOB. There we have add the transporting time inte the GR Processing Time. This is not so good.
    The solution beeing
    in the  purchase order the date for finish the supplier on board
    and in the md04 R3 and product view PP/DS the to arrive in the firm location
    kind regards Feth

Maybe you are looking for

  • My iPod 5thG it's stuck

    Hi, I have a problem, as in the title. My iPod nano 5thG doesn't turn on. It has less then 2 years. When it is not in charge, it seems die, but when I connect it to the usb of my mac, or the socket, the apple appear, for few seconds and than..black s

  • Profit Centerwise Receivable & Payable

    Dear all, Can you help me in getting the open line items as of a given date profitcenterwise (back end table would be faglflexa instead of BSEG) which is similar to our standard T-Code of FBL5N/FBL1N. FBL5N/FBL1N does not give the output on the basis

  • [svn:osmf:] 14453: DVR: unit tests, continued.

    Revision: 14453 Revision: 14453 Author:   [email protected] Date:     2010-02-26 07:30:14 -0800 (Fri, 26 Feb 2010) Log Message: DVR: unit tests, continued. Modified Paths:     osmf/trunk/framework/OSMFTest/org/osmf/OSMFTests.as     osmf/trunk/framewo

  • SOA and B2B Domains

    Anuj, You told me before in an other thread that i'm able to logically saparate B2B from SOA creating two domains in same installation. 1 - Hosting B2B 2 - Hosting OSB + SOA Suite So in this scenario I must have 2 Admin Servers one for each domain, i

  • Can I switch back to my Iphone 3g until I get a case??

    I activated my beautiful amazing Iphone 4 yesterday. I just couldn't wait. I am just very nervous about taking it around with me without a case. I'm gonna get a case in a week or so. In the meantime, can I somehow switch back to my Iphone 3g so I don