Hi Everybody,
             I have come across a problem. In transaction cor3 when I give the process order then in goto>costs>analysis  in the given  report I wouldnt be able to find the relevent tables for the field 'Total Target Cost' if someone could help me from where I will be able to reterive this field data  int he definition they gave me the fomula
Total Target cost = Target Cost debit + target Cost credit.
If someone have any information regarding target Cost Debit and Target Cost Credit  please help me out. I will be very thankful to him or her.
Regards,

Hi Everybody,
             I have come across a problem. In transaction cor3 when I give the process order then in goto>costs>analysis  in the given  report I wouldnt be able to find the relevent tables for the field 'Total Target Cost' if someone could help me from where I will be able to reterive this field data  int he definition they gave me the fomula
Total Target cost = Target Cost debit + target Cost credit.
If someone have any information regarding target Cost Debit and Target Cost Credit  please help me out. I will be very thankful to him or her.
Regards,

Similar Messages

  • Pocess order - target quantity in cost analysis report

    hi experts ,
    i am not getting the target quantity in cost analysis report of header material , though i have made the GR of the process order .
    target quantity is showing zero.
    i am getting target quantity of components , sfg used.
    kindly give your inputs.
    reagrds,
    satish

    Dear
    First Check the Validity of the standard cost for the header material, It can be seen in ck13n, Dates tab.
    Target costs are populated when you do the goods receipt. System will search for the released standard cost estimate and then apply that for each material component. If these 2 conditions are passed, then you will get target cost in order.
    Plan cost = Plan qty * std cost estimate
    Target Cost = Actual qty * std cost estimate
    Actual cost = Actual qty * actual costs
    Eg:
    A production order is planned for producing 10 units of a material
    Then plan cost on the order = 10 units * std cost
    Target costs are calculated once production is confirmed.
    Suppose only 9 units were produced out of 10 planned
    Then target cost = 9 units * std. costs
    Regards
    Ganesh M

  • How to read the Variance Analysis report S_ALR_87013139,  Pdt cost by Order

    Hi,
    Could someone tell me how to read the variance analysis report, S_ALR_87013139 - Cumulative for product cost by order. The report has the following fields, Target (Debits),     Actual (Debits),     Scrap,     Var. Without Scrap,     Work in Process(WIP),     Control Costs.
    I am looking to find how the numbers add up.
    Thanks for your help.
    Ram
    Message was edited by:
            Ram R

    Thanks Sridhar,
    When I analyse the report S_ALR_87013139 - Cumulative , for a product for a period (with no scrap), I get the following
    Target (Deb) -   46,855.55
    Act (Deb) - 58,315.87
    Scrap - 0.00
    Var W/O- Scrap -  11,269
    WIP- 0
    Control Cost - 0
    Here Actual - Target is not equal to Variance. What could be the issue?
    Could you please tell me how SAP would update this report  with target & actual costs with respect to open production orders, carried over from previous periods.
    Thanks,
    Ram

  • Total Target Costs not updated in Process Order

    Hi All,
    I  have a scenario in a Process Order,
    The Process order is Released, Goods Issued and GR done. But the when i go and check the Cost Analysis i did not see anything in the Total Target Costs  and Total Target Qty coloumns agianst all the cost elements. It show as zero for all.
    It looks very strange. There is variance in the component issues and GR  as well. I simulated for the same material with a new Process order and found the vales get populated automatically on GI and GR's with variation against requirement quantity.
    Could any one explain me why it is so ..? or is my understanding is wrong.....?
    Thanks for your time and patience.
    Regards,
    Srinath V

    Srinath Venkatr,
    I think you are missing PP CO integration configuration during master data creation. There might be information massage to you during process order creation saying , 'Logs during Cost calculation", you are skipping the same and creating process order withought resolving the same.
    Check whether you followed all the steps for product costing.
    Material master,
    BOM,
    OPKP:-Controlling area-activate components and Controll indicators
             :- Assignment of co codes
    KS01: Cost center
    KA01/KA06:- Primary/ Secondary Cost elements
    KL01:-Activity Types
    KP26:- Activity Price Planning
    Then Work center/Resource- assign these cost center and activities with costing formulas.
    Then Routing/Recepi-
    After master data, demand management,MRP- process order. while creating process order check cost calculation errors.
    Hopes that will clear your dought
    Tara

  • Total of  actula product cost to  total of target cost

    Hi
    all
    Total of  actula product cost to  total of target cost .... How can we get data for this report  plz provide me , is there any standard report available for considering this data
    Many Thanks
    MvNr

    guess..........due to lack of full information in your thread, it is not answered.
    Total of actual product cost to total of target cost...........??
    which object ?? production order?? sales order?? wbs element??.......can u clarify?

  • Total target cost

    Hi...,
    I want to know the formula or table-field for"Total target cost" for activity type for production order.
    For exm. - Tcode CO02 - goto - cost -analysis ,.. here system gives activity wise production cost.That target cost I want to give in zreport.
    Thanks in advance.
    hemant

    Target cost is calculated field during runtime as i am aware of.
    but how to calculate that which i can share with you
    Total target costs = Target cost debit + Target cost credit
    Target costs are the planned costs adjusted to the actual operating    
        rate.                                                                               
    The target debit on a manufacturing order is the sum of the            
        activity-independent planned debit of the order and the                
        activity-dependent planned debit of the order multiplied by the actual 
        quantity of the order.                                                                               
    The target credit of a manufacturing order results from the goods      
        receipt postings to stock. The delivered actual quantity is valuated   
        with the planned price according to the price control.                                                                               
    The total value of the target costs is the sum of the target debit and  
        the target credit.                                                                               
    The target costs are calculated during variance calculation and updated 
        to the database.                                                                               
    The target costs cannot be shown until you have performed variance      
        calculation for this target cost version. The target credit for the     
        calculation of the total variances and production variances cannot be   
        calculated until an actual quantity for an order exists after a goods   
        receipt posting.                                                                               
    For the calculation of variances, the target costs are compared with the
        control costs.
    The system uses the operating rate to adjust the plan costs of a period to the actual activity
    Operating rate = (Actual activity  Plan activity) X 100
    Total target costs = Fixed plan costs + Variable plan costs X Operating rate
    example -
    The system uses the operating rate to adjust the plan
    costs of a period to the actual activity. The operating rate is based on the following formula:
    Operating rate = (Actual activity / Plan activity) X 100
    Targeet qty is ac alculated qty = BOM ratio * actual production qty
    i.e. A product X is the componet 
    A production plan 10
    Actual prodution = 12
    Component qty plan = 1
    component actual qty = 2
    cost of compnent = 1$
    target qty = 12*1/10= 1.2
    I hope it will help you

  • Sales Analysis report does not match Cost of Sales Account

    My client is running SAP B1 8.81 PL 6.  He has set all items to standard costing method.  He has discovered that the difference between the Sales Amount and the Gross Profit amount on the Sales Analysis report, which should equal the Cost of Sales for the Items, does not match the Cost of Sales G/L account on the P&L report.  If you look at a sample of rows, the above difference divided by the quantity equals the standard cost of the item.  There are no manual journal entries that affect the COS account for the posting period that is being analyzed.  I cannot see any mathmatical difference or problem with the above analysis, nor can I find the problem.  There is about an $85K difference between the reports.  The Sales Amount on the Sales Analysis report matches the revenue account on the P&L to the penny.  Has anyone ever compared these 2 reports?  Thank you for your help.
    Bill Turek

    If you right click on an Invoice and choose "Gross Profit" it will give you a setting on how you want to calculate the Gross Profit for that invoice.
    In the accounting point of view the "Base Price" should be "Item Cost" so that the Gross Profit will be (Net Selling Price - Item Cost = Gross Profit). This will give you the same Gross Profit amount between P and L and Sales Analysis Report.
    However, SAP B1 gives the user the ability to select a different base price other than the Item Cost.
    This gives the user the flexibility for the Sales Report. Example (Net Sales Price - Vendor Sales Price = Gross Profit). People do this sometimes because  the item's cost fluctuates if you use FIFO or average cost and they want a uniform cost to calculate their Gross Profit.
    In summary if the Base Price is not set to "Item Cost" then there will be difference in the Gross Profit between the P and L and Sales Analysis Report.
    See screenshot:
    -Eric Alo-
    B1 Financial Consultant

  • Cost Analysis Report - For a range of process orders

    Dear all,
    Is there a standard report available to get the cost analysis for a range of process order? COR3 --> Go to --> Cost --> Analysis. Here I can see the cost analysis for one report. But I wanted to get the cost analysis report for a range of process orders. Please help.
    Thanks
    Nagarajan

    Dear
    You can use cost analysis report like
    1.S_ALR_87099932 - Variances Between Costing Runs
    2.S_ALR_87099931 - Price vs Cost Estimate
    3.S_ALR_87099932 - Variances Between Costing Runs
    5.KOC4
    Regards
    JH

  • Analysis report for standard cost in CK33N

    Hi,
    Analysis report for standard cost
    Using variant Z003 in CK11N.
    Planned cost 3 is the output used for planning and this is adjusted by making changes to the BOM throughout the process
    In CK33 you compare the 2011 cost for the product with the proposed cost for the next year.  For some parts it works and for others it splits the lines,  though the calculation is still correct.
    Regards,
    T.Harish Kumar

    Hi Revital,
    I believe the last option is correct.
    Thanks,
    Gordon

  • Report showing total costs pr. cost center and internal order..

    Hi FI Gurus,
    Do any of you know a standard report, which can display G/L, Company code, Period, total cost in local currency, cost center and internal order. The report should be at summarizational levet (not line items) and we should be able to sum costs at cost center and internal order.
    Finally we should also be able to transfer the report to BI via an extractor etc.
    Thanks for you help
    Pernille

    Hi,
    Cost Centre vise Report you can take from KSB1
    Internal Order Vise Report you can take fro KOB1
    Regards,
    Sridhar Sha

  • How to get Cost element for a component in co03 cost analysis report

    Hi,
    I'm using table COSP to find the quantity for a production order component.  However, I need to identify the cost element first to get the unique data.  In CO03 cost analysis report, there is cost element for the component.  Does anyone know how to get it ?
    Thanks.

    CSKA stores the basic info about the cost element
    There is no data in CSKB.
    I'm trying to use different tables to get the cost element.
    AUFK, AFKO, AFPO, RESB, ...but no luck...

  • Activity type origin text doesn't have been showed on Cost analysis report

    I have defined three acitivities TMAQ, TMO, CIF. But  the origin text column of these acitivities is not showing in cost Analysis report(althoug the origin is showed), i.e. when we go to an order & navigate to "Cost Analysis".  TCODE:CO02 (Production order)
    Anyone knows how to show the origin text ?
    Thanks a lot for your comments.
    Vero

    Hi Veronica
    I think maybe it´s missing the description in language you are running the report.
    Check transaction KL03 to see if the activity type has the description in the language you are logged.
    If not go to KL02 and update the description and try to run it again.
    Regards
    Fred

  • Total Target Costs - Factory Output showing "0"

    Hi,
    We have repetitive manufacturing at our location here. After the backflush has been posted I am unable to see any factory output updates under target costs in my "costs" under cost collectors. We dont have std cost estimate for our materials and our material prices are periodically updated through material ledger through the monthly costing runs. All FG's have preliminary cost estimate and our target cost versions point towards this estimate. Could you please let me know what could be the reason behind not seeing any costs under the "factory ouput" under "Total target costs"?
    thx,
    CN

    Hi
    Please Transfer the source Cost Components to the Target  Cost component structure ( Ex. Cost Component Structure 01, updating all the source CCS ) in T.Code : OKTZ
    Please check and get back to me.

  • Report  for bom wise target and actual cost as well as qty at line item

    Dear Experts,
    Is there any standard tcode for bom wise target and actual cost as well as qty at line item level for the month.
    there is one tcode s_alr_87013127 but user has to double click in order to get line item details.
    I want to see line item wise breakup/bom wise target and cost cost as well as qty.
    Thanks in advance.
    regards
    RK

    Dear experts,
    I am still looking for a revert.
    regards
    RK

  • Standard Cost Analysis Report  (MCI3)

    Hi,
    On SAP standard Cost Analsys report, i have been unable to dig out the reason of not populating values in following few columns.
    - Int. wage costs
    - Int. Mat. Costs
    - Ext. Wage Costs
    - Extenal Mat Costs
    - Services Costs
    Can anybody guide me in populating these values.
    Regards
    Shah

    hi
    if you have posted any material against the order ,then the cost will be reflected in int.material cost ,which is also same for other parameters
    also check whether you info structure is switched on OMOS
    regards
    thyagarajan

Maybe you are looking for

  • Where (in the filesystem) are network settings stored?

    Hello, i did a clean install of mavericks, and want to import the network settings from an older backup i did (have both: 10.8 full backup and 10.9 library folder backup) into the new system; unfortunately i don't know where they are stored, and can'

  • TS4079 Since the latest IOS update Siri is not working correctly on my IPhone 4S.  What happened?

    Any help in understanding why Siri is not working properly would be most appreciated.  Siri has not been working properly since I received the update to iOS 6.0. Siri acts as though it is looking for an answer or making an appointment for several min

  • HT1937 i dont have facetime on my iphone 5

    i dont speak english that much any way i bought this iphone 5 n there is no app facetime on my phone even i try to find it out on the general n system i couldnt found it

  • Distribution Profile

    Regarding building the app with "Device - 3.1 | Distribution" option in XCode - is this profile/option used *only* to build the app for putting it in the App Store (using iTunes Connect) - or can I use it to install the built app on the device also?

  • ARD 3 crash on Macbook Pro

    My crashes are that all inventoried systems go offline and the status will not refresh. I checked the console.log and besides a ton of stuff I don't understand yet, I noticed an AgentListener error 22 and an Apple Warning that says: *WARNING: Method