Track Changes the qnantity change of PR after MRP run

Hi Experts
Please suggest as i am unable to find any solution of following problem.
My CLient wants to keep track the changes made to PR's after MRP run. When running MRP, already existing requirements (PRs) are automatically changed. These changes are not taken into account by BW extractors since no change document is generated.
for e.g ,if we check stock requirememt list (MD04), PR of qty 20 exists. Now if i create a manual reservation of qty 20 and then run MRP, the the PR qty will change to 40. But i am unable to track this in CDPOS or CDHDR tables.
Please suggest.
Pradeep Bansal

There are 2 ways to track the PR changes
1.Goto PR display ME53N  --> Environment ---> item changes
2.Goto CDHDR Table ,input doc object - BANF ,object value as PR no and get the docuemtn no .Pass this doc no to CDPOS and get the change details
Hope it helps

Similar Messages

  • PR created after MRP run, instead of schedule line

    Dear all,
    I want to create schedule lines automatically from the planning run, for raw material. I have maintained info record, scheduling agreement, quota arrangements and also the source list.
    For the raw material, safety stock of 1000 nos. has been maintained. The current stock of the material is 0.
    After MRP run, based on the upper level PIRs, schedule lines are generated properly. But, against the safety stock of 1000, a PR is generated.
    I donot want a PR to be generated.
    Please suggest a solution.
    Thanks in advance,
    Shrenik
    Edited by: Shrenik on Mar 8, 2008 4:17 PM

    Dear all,
    I checked an found that the schedule agreement date does not have any effect. Even if the requirement date falls outside the date range, i am able to create schedule lines.
    I also found that if i maintained GR processing time, then always a PR is created. If GR processing time is 0, then only schedule line is created. Moreover, planned delivery time does not have any effect on the calculations, even if it is 10 days, 20 days or 900 days.
    Can someone please clarify all these? How are these times taken into account?
    Thanks in advance,
    Shrenik
    Edited by: Shrenik on Mar 9, 2008 3:04 PM

  • Purchase req type after MRP Run

    Ca we control the type of Purchase req after MRP Run.
    Now for every material it is creating "NB" type purchase req.
    Can we control it material type or by mat number.
    We have 2-3 purchase req types in system for Material.
    Amit Shah

    Dear ,
    Goto -OPPR-Enter Plant Code and Maintain MRP Group -0000( as SAP Standrad for External Procurement ) -Select Scheduling /Doc Type tab -Here you can assing the PR type as per your requirement so the while MRP run , it will selct the PR documents types based on OPPR .At the same time , assing this MRP group in MRP1 view of the material .
    Try and come back
    Regards
    JH

  • Got Unwanted PR after MRP run

    Hi,
    Can sombody give me some tips?
    The following is my perplexed thing:
    Material Strategy group is 10.
    Today is 2010-05-19, the stock is zero.
    The material's planned delivery time is 30 work days .There is a LSF requirment 500 pc on 2010-05-19.
    And also There is a 500 pc PO whose Delivery Date is 2010-07-20.
    When MRP run,we find we get a PR whose purposed quantity is also 500 pc and Delivery Date is  2010-06-18.
    However since there is a PO whose Delivery Date is 2010-07-20,we only need an Exception message number for the PO,not a PR after MRP run. In another client we can get what outcome we antcipate. But in this client we can not find where the problem is.Can somebody tell me where the problem is ?
    Regards
    chunhui

    Hi,
    Is there no exception message for the existing purchase order??
    As i u/s there would be exception message for the purchase order exception message might be 20(cancel process).
    If it is so then check the settings for reschdeuling (OMDW)  with the existing client & in the client where you are getting the result correctly.
    Check n revert.
    Regards
    Mithun

  • Report to track changes to infotypes prior to running the  payroll interfac

    wants a report to track changes to infotypes prior to running the  payroll interface.  The attached report looks like it should work but it returns nothing.  Is there config that turns on "Track Changes": for select infotypes?  If so, can they be activated for key infotypes so this report will run?
    Name, Address, position, etc.
    Not attendance and absence ITs.

    Hi,
    IMG – Personnel Management – Personnel Admin – Tools – Revision – Set up change document:
    This node has three items:
    Infotypes to be logged
    Field Group Definitions
    Field Group Characteristics
    Using these three options you define which infotypes you wish to log, then which fields, then you define which groups of fields are to be saved. Click each link, or see the sections below:
    Infotypes to be logged
    Here you define which PA infotype numbers you require logging. Select New Entries and enter a transaction class (A for Pers Admin, B for recruitment), then enter the infotype number and save.
    Field Group Definition
    When changes are made to a logged infotype, the field contents before and after are recorded. This is the very reason for logging the infotype, but there is an overhead in performance and disk space used so it needs to be given consideration. Typically you will want to record fields that are pay relevant.
    Using the field group definition, you specify which fields you wish to record changes in. When any of the fields in the group are changed, all the fields in the group are saved. You can use an asterisk to log all the fields of the infotype but this is not recommended for space and performance, also there are many fields on an infotype that you will not be using, that will be saved also. Ideally you will pick individual fields of the infotype and enter them like so:
    The field group number is a freely defined number you allocate to the group, it will be used in the next step. For normal use, simply pick any number not already used in that infotype. All fields with the same field group number are recorded in the log, even if they have not changed.
    Click New Entries and enter the infotype number, field group number and field names that you wish to record.
    Field Group Characteristics
    When you have set up the field group numbers, use the field group characteristics to activate the logging of those fields. You can also specify a supplementary field group; this means that the contents of another field group can also be saved at the same time, even though the contents have not changed. In practise it is not used much. Simply select new entries, enter the transaction class, infotype, and in the DocFieldGr enter the number you assigned to the field names that you want to store, then enter L for Long Term Documents (short are not supported)
    The Audit Report
    To access the report showing the logged infotype changes, use the HR report tree available from various menu paths, including:
    Main Menu – Human Resources – Pers Management – Administration – Info System – Reports - Documents – Infotype change – logged changes in infotype data. (RPUAUD00).
    When you run the report, select the infotypes you require, and select and execute.
    Cheers
    Prasanth

  • How system calculate the required qty. after MRP RUN

    Hi,
    I want to know if we are using MRP Type as PD and also we are calculating automatic saftey stock and re order point qty. after MRP RUN according to which rule formula system calculate the safty stock, reorder point qty. and the required qty. as a PR.
    and if we are not using calculate safety stock automatically and if we set safety stock qty. manually in this case how system will calculate the required qty.
    regards,
    zafar

    please check the below links.
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/6f/b441a9a1b011d3a82d0000e82a3c24/content.htm\
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/f4/7d256344af11d182b40000e829fbfe/content.htm
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/ff/515c4749d811d182b80000e829fbfe/content.htm
    please check the above links may get some idea.
    Regards,

  • After I covered 250 miles I got the automated congratualtions, but now after every run I get the recorded message again saying I just covered another 250 miles. Can I reset or stop it without completly resetting everything?

    I run with the Nano and shoe sensor. After I covered 250 miles I got the automated congratualtions, but now after every run I get the recorded message again saying I just covered another 250 miles. Can I reset or stop it without completly resetting everything?

    Same issue here.  This is really disappointing.  I used to look forward to the milestone messages after each run, especially when I was surprised by a celebrity voice.  Now, it's the same thing every single time, "Congratulations on another 250 miles.  Way to go!" or something along those lines.  I was proud of the 250 mile mark, but please...I don't want to hear it every time! 
    I hope there's some movement on this issue.
    ~ Heather

  • Availability/GR Date after MRP Run

    Hi All,
    After MRP Run for perticular period, system plan the material at the start date of the period. Is there any ways where we can set it to last date of the period.
    Like if I will put the PIR for Month of March and April, system will create the PIR on 01/03/07 and 01/04/07. so is there any ways where it can be change to 31/03/07 and 30/04/07 for march and April.
    Regards
    Pavan

    Hi Pravan,
    you can configure lot size key in SPRO accordingly
    lot size procedure-p
    lo size ind-M
    Scheduling-2
    no of period 1
    assign it o material in MRP 1 view.
    Regards
    Hemant Gadhari

  • After mrp run-planning file

    dear gurus,
               after mrp run.planning file entry should be deleteted.if not deleted what will be the reasons for that?
                 what is replanning of materials?
    please through some light on this issues
                             -gide

    Hi,
    Planning mode controls how the system is to deal with proc proposalexisting
    from last planning run which are not yet firmed in the next run.
    When we are changing reqmts qty and dates for proc proposals the system
    automatically take this into account.Where as if there is any change to
    bom/material master whether these changes will have an effect on planning run
    will be controlled by planning mode.
    Planning mode is set automatically set in the planning file and also
    we can override in md02.
    Mode 1: Inthis mode system reactivates the existing planning data
    ie the system adapts existing planning data.
    ex changes to qty/dates
    Mode 2 : In this mode the system reexplode tho bom for all existing proc
    proposal which are not firmed if there is any changes to bom
    ex changes to bom /sales order bom
    changes to production version / bom explosion no
    Mode 3 : Inthis mode the existing proc proposal are deleted and again recreated
    ex changes to inhouse prodn time / planned delivery time/sch margin
    key
    Hope this will help
    Regards,
    nandha

  • Schedule lines are not coming for HALB after MRP run

    Dear All,
    I am not getting schedule line after mrp run, inspite of all required setting only purchase requisitions are coming.
    Material type is HALB and involve a subcontracting process (30). For raw material I am getting the schedule line but in the case of HALB, it is not coming.
    Pls let me know if I am missing something and guide me further on this.
    Thanks & Regards
    Kundan Kumar

    Hi,
    In transaction OMDT you have to enable the indicator create schedule lines
    In MD02 MRP control Prameter here select the Delivery schedules -3- Schedule line. Processing Key as NETCH and Planning Mode - 3 delted and recreated.
    Maintain source list ME01, in that put MRP indicator as '2' i.e. schedule lines via MRP.Put your agreement no in that.
    If u run MRP properly u will get schedule lines automatically in ME38.
    Make the schedule agreement, make it source relevent in the source list make is FIX and MRP indicator as 3.

  • Schedule lines are not coming after MRP run for HALB material

    Dear All,
    I am not getting schedule line after mrp run, inspite of all required setting only purchase requisitions are coming.
    Material type is HALB and involve a subcontracting process (30). For raw material I am getting the schedule line but in the case of HALB, it is not coming.
    Pls let me know if I am missing something and guide me further on this.
    Thanks & Regards
    Kundan Kumar

    Dear All,
    I am closing this thread. As the vendor mentioned in scheduling agreement is not a subcontracting vendor. Its a individual vendor.
    Thanks for all the reply.
    Thanks & Regards'
    Kundan Kumar

  • How system will generate schedule line for PO after  MRP run.

    Dear Experts,
                                 i have updated  MPS in MD61, the period indicator was  M (monthly),  after  MRP run, system  generating schedule  lines  on daily basis for Scheduling Agreement(ME38), i want  schedule lines   on mpnthly basis, how to achive this,
    thanks in advance.
    regards
    rajakarthik

    Hi
    1. Are you maintaining any Planning time fence period for MPS- No 
    2. What is the PIR qty you maintained in MD61:
                                                                                    i.) FG01 is having BOM  child part RM01.
                              To  produce 1 nos of  FG01 , I need 1 nos of  RM01                                                                               
    ii.) i maintained  FG01 in MD61  with PIR  Qty 5000. in MD61,Planning period is M  and planning hirizon1- jan10To 31-Jan10
           ii.)  i maintained lot size:Monthly lot size for RM01.
           iii.)  there is  no stock  available for  both RM01 and FG01.                                                                               
    3. After MRP how much qty is get planned on what date-     
         i)   planned order created for FG01 in co41 with qty-5000 nos.
         ii)  in ME38, schedule  line created for RM01,  on 01-01-2010, with 5000 nos,  currently Category of Delivery Date
    field is D and delivery date is   01-01-2010, but i want Category of Delivery Date should  be M and delivery date should be 01.2010.
    thanks
    raja

  • Automatic creation of Schedule line after MRP RUN

    Hi,
    Till now we are  using only PO for placing orders to vendor, now we want to use the functionality of scheduling agrement,  so that after MRP run,  we can get automatic schedule line creation,  for this ,  what are settings required, how system create the automatic schedule lines based on which criteria, second thing while creating on eschedule agrement i found that the conditon which i can add for a vednor in ME21N  that all condition are not coming while creating schedule agrement  even my vendor is same for PO and Schedule agrement,  so what are  the setting required for this.
      regards,
       zafar

    Hi
    1.In material master purchasing view data auto PO is to be flagged.If scheduling agreemet with release documentation.
    Then flag JIT indicator 1.
    2.maintain MRP views in material master
    3.In source list for fix vendor,source list usage 2 is to be maintained.
    4.Vendor master purchasing data auto PO indicator is to be flagged.
    5.Then when you run MRP automatically schedule lines are generated.
    For JIT and forecasting maintain creaton profile in OMUP transction.
    Assign the creation profile in scheduling agreement.

  • Automatic creation of PR after MRP run

    Hi,
    can anyone please tell me what all fields are picked up in a Purchase Requisition(PR) in the scenario of automatic creation of PR after MRP run.
    If we are using more than 1 PR type in the system how is it determined during the MRP run that the PR will be created for which type.I understand that source list will have to be created and maintained but how is the PR type determined
    Thanks in advance

    In PR the system checks for the material and vendor. See the steps below.
    Step1:Auto PO tick in material master Purchasing view (mandatory)
    Step2:Auto PO tick in vendor master Purchasing view
    Step3:Maintain Source list for vendor and material (If u r not using source list for auto PO creation, the assign the Source of supply to a PR in ME56)
    Step4:Maintain Pur. Inforecord
    Step5:ME59n : execute for PR and Vendor In ME59n, you can also select the PR document type. If you want to select different document types, go for multiple entries and enter the doc types.
    When u execute, the system will give the appropriate PRs. Select the required and convert to PO.
    But through MRP you cannot create PO directly only Planned orders can be created.
    Reward if helpful..
    Thanks,
    Srib

  • Creation of Purchase Order automatically via PR after mrp run.

    Hi Experts,
    I want  to know that , after MRP run  i got the no of PR'S. As i know , through MD04  i can create purchase order from particular pr but is their any option from which purchase order  get generated automatically from pr's which are generated afrer MRP run.
    Thanks n Regards
    Anupam

    Hi,
    You can maintain source list Tcode ME-01 and make it MRP relevant by selecting Sorce list MRP relevant. In sorce list you can maintain vendor and material data valid for particular period and make it MRP relevant.
    With this you can automatically generate purchase order from Purchase requisitions after MRP Run.
    Regards,
    Tushar Patankar

Maybe you are looking for

  • Is my i7 MBP GPU malfunctioning?  Strange pattern on screen?

    Happens in the morning after the computer has been sleeping all night. Diamond shape artifacting I guess? Computer runs for about 3 minutes, then screen gets a strange pattern across it, then locks up. Looks like this after the hard boot. Pics http:/

  • Missing songs on iPod that are in iTunes.... ????

    There are about 40 songs in my iTune Library that I can't get to sync with my 5g iPod. I've done the automatic and manual updates and nothing. I've tried creating them in playlist and nothing. I know what folders those songs are in. They play in iTun

  • Adding Parameters to a generated URL

    Hi All, We have a client requirement to send email to a set of users with a link to a specific page. When the user clicks on the link, it should ask for the login, and once the user enters the credentials, it should take the user to the specific page

  • 827H router web setup not working

    We were having problems with our 827H router, so I decided to reset it to the factory defaults and re-run the quick setup. I've done that before with no problems. This time, after it loads the configuration in the web setup, it keeps checking the mod

  • Changing log file sizes

    is it possible to change je.properties : je.log.fileMax size and restart the db without having to dump and load it? i.e. is it okay to have different size log files in one environment?