Hello ,
Can anybody explain the concept of stock transfer plant (manfacturing) to plant (selling) in indian scenario and also
its implications in FI, CO and excise.
The current situation here is manf plants transfers materials toanother plant. the receiving plant material stocks should be
valuated at cost of the material from manf plant plus the freight cost. The manf plant also transfers material with markup
price say 7% to the receiving plant. This markup should be captured as unrealized profit in CO for MIS purpose. The markup + freight cost should be loaded unto the material in receiving plant .
I am unable to capture the cost. Right now the transfer is taking place at price in the material master in the supplying plant.
Regards
Nandini

Hello Nandini,
I saw that your question was apparently answered already, but I have the same issue: when receiving the material on the STO, the stock-valuation is done against the value of the supplying plant. I would like to have this differently (=against standard cost as defined in receiving plant).
Did you figure out the solution to your problem? If yes, would you be able to share it with me?
Many thanks in advance,
Martijn

Similar Messages

  • Stock transfer order between 2 plants in same company code

    Dear All,
    We have the requirement, where in the stock tranfer order (between 2 plants in same company code) instead of Material valuation price, MAP/Standard (depends on Price Control) gets picked up from supplying plant ,user should be able to enter its own price while creating stock transfer order.
    For fullfilling this requirement, I have created new condition type(where i have changed condition category from internal price "G" to "H" - Basic Price)
    Instead of using condition type- P101 in the stock transfer pricing,I have used above created new condition type, in pricing procedure then also while doing the post good issue against the outbound delivery( move type-"641", moving average is getting picked up.
    Can you please tell,where is the setting where we can make the system to consider manual given price while creating the stock transfer order instead of picking moving average price.
    Its very Important requirement ,please Provide valuable Inputs else provide some alternative.
    Thanks & Regards
    Nitin Chhabra

    Stock Transfer Order between Plants in the same Company Cpde are not relevant for pricing, as there is no billing. Billing only takes place between company codes. As same company code it would be like selling something to yourself - it doesn't make sense.  The stock value in the receiving Plant depends on the price contol there. If standard price, then you must enter the price when creating the material or use material revaluation to change it. When you transfer the material from the issuing plant, the value there will be transferred. In case of standard price any difference is posted to stock transfer differences. If using MAP then the value will be transferred from the issuing Plant in full.
    If you use costing with standard price in main plant, then it is possible that you can transfer the cost from the main plant to the second plant, by using special procurement key for costing.
    Rgds
    Richard

  • STO from Plant to Plant in same Company Code

    Dear All ,
    Please give me brief idea about STO(with screen ) from Plant to Plant in same Company Code
    ganga

    Dear Ganga Mukerjee
    Welcome to SDN
    There are plenty of threads available on this topic in both SD general,Sales and MM forums
    Please make a search
    As this is your first qn i am giving here with some simple steps for STO from Plant to Plant in same Company Code via SD route
    INTRA COMPANY STO.
    1. There should be two plants in the given company code for intra STO to
    happen.
    2. Assign Purchasing org of the ordering to the supplying plant.
    3. Create a customer in the supplying sales area.
    4. Assign the customer to the ordering sales area.
    5. IMG > MM > Purchasing > PO > Setup STO > Define shipping data for plants
    here go to supplying plant and mention its own sales area.
    6. In the ordering plant assign the customer created in the supplying sales area
    and also the supplying sales area.
    7. Maintain checking rule as 01.
    8. Assign the delivery type NL supplying plant checking rule and PO Doc type
    UB.
    9. Assign document type UB supplying plant and ordering plant then decide up
    on either 1 step or 2 steps.
    10. Create PO with doc type UB.
    11. Go to VL10B give the PO No. and enter, select the line item and click back
    ground. (Where Del. Will be created in the back ground)
    12. Go to VL02N for picking and PGI.
    13. If 1 step no need of doing MIGO else for 2 steps do MIGO.
    Hence forth make search
    Regards
    Raja

  • Stock Transfer Between two plants within same company code

    Hello,
    We are using scenario-'Stock transfer between two plants within same company code. Scenaro is like Plant A is receving plant and Plant B is delivering Plant.
    Plant A release PO for 100 nos to Plant B
    Plant B issues 100 nos (via delivery) to Plant A
    But Plant A receives only 50 nos physically so they do Goods receipt for 50 nos , but document got generated for 100 nos (when plant B issues material).
    Now Plant A do not want to receive remaining 50 nos physically, but wants to reduce material document which got created when goods issue posted by plant B
    Now stock in transis (mb5t) is 50 nos.
    How to reduce this material document. or any another alternative solution for this?
    Thanks,
    Shailesh

    Hi There
    Reversal of partial is not possible ,
    But you can use the Mov Type 557 and 558 to do the adjustments in Stock in transit qty
    Few more details on STO adjustments
    Hi There
    it can be settle in many ways,,,
    1. Receive the goods as 100 and Scrap the 50 nos from the received plant,,- If the receiving plant is responsible
    2.Revert the PGI/Transfer movement(Vl09) and send the 50 nos again from the supplying plant- of the Supplying plant is responsible,
    3.Also we have the movement type 557 and 558 without doing the above two steps you can correct the qty from stock in transit itself,,
    4. also you can check the below similar thread
    STO - material lost during tranfer from plant A to plant B
    5. If above are not ok, then receive the goods as 100, And raise the STO as your plant as supplying plant and receiving plant is (Supplied 50 nos less) plant,, Do the process without sending the material.. in this way that 50 nos can be adjusted,,
    6.Here is some more details
    557 Issue from stock in transit (adjustment posting)
    Only use this movement type (also the reversal movement type) under the following circumstances:
    Using movement type 557, you can correct purchase-order-independent stock in transit if
    - a good receipt cannot be posted to a purchase order without stock in transit, even though there is still stock in transit according to the purchase order history
    - stock in transit still exists, even though there are no open stock transfer orders for the particular material
    This movement type may ONLY be used in the cases mentioned above after careful analysis, to correct stock in transit that has rounding errors.
    This movement type may not be copied.
    Note!
    Before using this movement type, note the following:
    - 392205 Analysis stock in transit / Correction if split valuation
    Possible special stock indicators:
    E, Q
    7. As previous post says if you have the note for this issue you can use that also
    You can use any one of the way to solve the issue, Hope it helps
    Cheers
    Senthil P

  • Can Equipment No same for 2 Equip in different Plants of same company code?

    Hi Gurus,
                Please tell me if there is any possibility of having same Equipment No for 2 Equipments in Different Plants.
                The 2 plants are in the Same Company code.
                e.g.  Equip           Plant                Company Code
                   1)  Equip_DIE    Plant1              A
                   2)  Equip_DIE    Plant2              A
               If it is possible how the Equipment histroy and Breakdown history is updated in the PMIS.         
               Also tell me the advantages and Disadvantages of keeping same Equipment no for 2 diiferernt Equipments or otherwise keeping different equipment no.
    With best regards,
    Narendra Dere

    Hi Pete ,
              Thanks for your valuable reply.
              Actually I am doing implementation for 5 plants within same Company Code.
              They are geographically distant (say 50km from each Other.)
              The Finish Product is same but the method is different.
              They have already assigned some Equipment Numbers in the Plant for Regular Maintenance Activities.
              Since Planning and Maintenance can be done at the different Plant and team of the MAintenance is different, they dont hv anyproblem if equipment number is same. Otherway they wll have the added advantage that they can continue with there own Equipment no which can be same in differnt Plant.
           e.g 800TONPRESS - Plant1
                800TONPRESS - Plant 2.
       With best regards,
       Narendra Dere

  • Restrict PO creation for multiple plants for same company code

    Hi Gurus,
    We want to restrict PO creation for multiple plants in the same company code. Based on Standard SAP settings for Purchasing organization assignment with multiple Plant and multiple Plant assignment with single company code, this is happening. Is there a way that we can restrict by doing some customization change.
    Any thoughts or ideas will be highly appreciating.
    Thanks and Best regards,
    Karun Kumar

    Hi,
    Said functionality is not available in SAP standard.
    To avoid the same ,i can suggest implement release strategy for PO,and then higher authority / commercial team can check created PO,if multiple plants available in single po then they have the option of rejection for the same.
    Or else check BADI-ME_PROCESS_PO_CUST,take the help from abapor and apply the restriction to select multiple plant in PO.
    Hope this will resolve your query,
    Thanks & Regards,
    Sandesh Sawant

  • Can we give same Excise Group to two diff.  Plant within same company code

    Hi,
    Can anyone please tell that whether we can assign same Excise Group to two different plants within the same company code in SAP.
    Regards,

    Yes you can use but, you shouldn't use same excise group for two different plants in one company code, if their physical location is different.
    As many excise report are fetched on the basis of excise group, there it will show combined values for both plants, whcih may not be acceptable to exices authorities.
    Regards,
    Sachendra Singh

  • STO not working for plants of same company code assigned to a Purchase Org

    We have two company code ( A & B ) assigned to a single Purchase Org .
    when we are trying to do STO of company code A , we are getting an error message like that
    The plant you have entered does not belong to the company code that was
    determined via the purchasing organization.
    Any suggestion please. we assigned all the plants to the Purchase Org .
    Thanks
    JJ

    Hi,
    While creating STO you are entering the plant.
    Please check whether that Plant is assigned to the Company code A Error message clearly tells you have assigned the Plant to the company code A
    G.Ganesh Kumar

  • STO from one plant to another plant of same company code

    Hi Friends,
    I have one specific scenario to map in SAP.
    I am transfering gaseous material from PLANT 1 to PLANT 2 thru' STO delivery. PGI has done for Qty 18 MT from PLANT 1. GR against STO at PLANT 2, here GR qty 17.5 (actual) remaining 0.50 MT is not getting discharged as it is in vapour form. This short receipt quantity will go back to PLANT 1 and there it will be treated as truck recovery. When the next delivery will take place they will create the billing document for 18 MT again but in actual the truck will be loaded with 17.5 MT.
    How to adjust In Transit stock of 0.50 MT? What will be the excise treatment for the same?
    Looking forward to your valuable and early response please.
    Regards,
    Ravi

    Hi,
    The goods which are loss in transit , you can follow it by scraping or do a physical count .
    Receive Qty 18 MT  with 101, then scrap 0.50 MT with 551. 
    OR
    Receive Qty 18 MT   with 101, then do a physical count and post the difference.
    OR
    Donu2019t receive Qty 18 MT   ; let the issuing plant cancel the goods issue. And redo with the correct quantity Qty 17.5 MT   . Then receive this correct quantity.
    Regards,
    Biju K
    Edited by: Bijay Kumar Barik on Aug 3, 2009 9:31 AM

  • Settings for the new plant under same company code

    Dear all,
    As I am into the roll out project. I need to know the necessary configuration settings from FICO (FI and Contolling Settings) point of view.
    I need this very urgently. If u have any documentation with regard to the same, u can forward to my mail id  [email protected]
    Input will be of great help and rewarded too.
    Thanks
    Niha

    Hi Neha,
    please follow the follwing steps relating to new plant in all madual.
    Steps needs to be configured
    1.New Plant to be created (Copy the new plant from the existing Plant)– Configuration
    2.Create Plant as Location - Configuration
    3.Define Shipping Point- Configuration
    4.Transport Planning Point Description to be changed – Configuration.
    5.Create a new Profit Center – Master Data
    6.Create a new Cost Center – Master Data
    7.Cost Center allocation to Shipment Cost – OKB9 – Configuration
    8.Assign Business Area to New Plant – Configuration
    9.Assign New Plant to Sales Organization & Division - Configuration
    10.Update all the GLs related to the new Plant. Default assignment to a Profit Center - 3KEI – Configuration
    11.Update Table J_1IT030K_V for Indian Tax Account Determination. - Configuration
    12.Account Assignment Category – VKOA – Assign GL Accounts to Sales Org/AcctAssgGr/AcctAsgnmt/Plant/Acct Key – Configuration
    13.Maintain Excise Registration for New Plant- Configuration
    14.Maintain Plant settings for New Plant- Configuration
    15.Maintain Excise Group for New Plant- Configuration
    16.Define GL Accounts for taxes – Configuration
    17.Specify GL account for Excise Transaction- Configuration
    18.Create all Inbound and Outbound Routes for new Plant –Configuration
    19. Assign new plant to company code.
    Please note that the above steps are for new plant by copying the existing plant and modification. If you define a new plant without copying the existing plant lot of steps are involved.
    as per FI/CO part point nos 5 to 8, 10 to 17.
    Hope this will help u, please assign the points if its helpful.
    please cheek your mail i have sent the material.
    regards
    sai krishna

  • Stock transfer between two plants in same company code at price

    Hello,
    Hello,
    I have a scenarios. One plant is selling a part to other plant at a margin. Both plants belongs to the same legal entity.
    How can I map this scenario in SAP?
    What will be the cost of my part in these two plants?
    What mechanism I would use to transfer the stock from supplying plant to the buying plant?
    Your urgent reply is appreciated.
    Thanks,

    Prem,
    Yes, for this scenario, you will have to implement EC-PCA. This is different from CO-PA.
    Detailed information can be found in http://help.sap.com/saphelp_erp2005vp/helpdata/en/eb/13759643c411d1896f0000e8322d00/frameset.htm
    The Stock valuation is different from MM and PCA point of view. Stock Transfer within Co Code does not have any effect on the Stock value from MM point of view. The Stock value changes only from the PCA point of view. The solution works the same way with Standard Cost also. Your Standard Cost can remain the same in both the Plants.
    The PCA entries are triggered by the Profit Centre data in Material Master. The Profit Centres should be different for both the Plants.
    Hope this clarifies.
    Thanks

  • Stock transfer between two plants within same company code at price

    Hello,
    Hello
    I have a scenarios. One plant is selling a part to other plant at a margin. Both plants belongs to the same legal entity.
    How can I map this scenario in SAP?
    What will be the cost of my part in these two plants?
    What mechanism I would use to transfer the stock from supplying plant to the buying plant?
    Your urgent reply is appreciated.
    Thanks,

    Hi Pream
    You can do it through Intra Company STO, but in this scnerio the libility never gets generated to the receiving plant because it is transfer from one pocket to other. but you can always transfer the goods on the assessable valu. you have to maintain the ***. value in J1ID, then while bill system picks the same ***. value in UTXJ condition.
    But if you want to salel at a margin then use SO-PO i.e. create PO from receiving plant and against sale order, do the delivery of the material to the respective plant.
    I think this will help you.
    In case of any qurty feel free to contact
    Girish

  • Stock Transfer from Plant to plant ..Same company code, No FI impact

    Dear All,
    I wanted to transfer materail from one plant to other, without any financial impact. Please suggest me a method.
    I am assuming to use T code MB1B, and movement type 301.
    please let me know, is this right ?
    Thanks in advance
    regards
    venkat

    Thanks Sarita,
    Does movement type 301 have financial impact.
    Please let me know.
    Thanks ..
    Regards
    venkat

  • Stock transport scheduling agreement between plants under same company code

    We created outbound delivery and post goods issue in the supplying plant.When I do GR for outbound delivery  for receiving plant" The message displayed is PL stock in transit is excceded by the quantity to be posted ". So I could not post GR using MIGO.
    The Master data created are
    1) Created customer master for receiving plant with account control vendor number for supplying plant ( Account control customer no for receiving plant)
    2) Created vendor master for supplying plant with additional purchasing data for supplying plant
    3) maintained sales views of the material for both the plants.
    4) in IMG shipping data shipping data for plants: receiving plant - customer no for the receiving plant ; sales org for supplying plant and distribution channel and division.
    After posted goods issue in outbound delivery I check plant stock for supplying plant I could see the stock in transfer of the amount issued.
    Can anyone could explain How I could resolve this issue.
    Thanks in advance,
    Nathan

    We created outbound delivery and post goods issue in the supplying plant.When I do GR for outbound delivery  for receiving plant" The message displayed is PL stock in transit is excceded by the quantity to be posted ". So I could not post GR using MIGO.
    The Master data created are
    1) Created customer master for receiving plant with account control vendor number for supplying plant ( Account control customer no for receiving plant)
    2) Created vendor master for supplying plant with additional purchasing data for supplying plant
    3) maintained sales views of the material for both the plants.
    4) in IMG shipping data shipping data for plants: receiving plant - customer no for the receiving plant ; sales org for supplying plant and distribution channel and division.
    After posted goods issue in outbound delivery I check plant stock for supplying plant I could see the stock in transfer of the amount issued.
    Can anyone could explain How I could resolve this issue.
    Thanks in advance,
    Nathan

  • Plant to plant stock transfer in same company code

    Hi everyone,
    I want to know the process for stock transfer between plant to plant in same company code.
    Regards
    Prabudh

    http://help.sap.com/bp_bblibrary/500/html/J51_IntProcSTwD_EN_IN.htm
    In a company, goods movements do not only occur in the form of goods receipts and goods issues. Depending on the organization of the company (for example, decentralized storage) and its sales policy, internal stock transfers might also be necessary.
    The stock transfer with delivery is a plant to plant scenario. You are posting a goods issue in plant BP02 and a goods receipt in plant BP01.
    This type of stock transfer can only be carried out from unrestricted-use stock of the issuing plant to unrestricted-use stock of the receiving plant.
    You post the placement into storage at the receiving plant in a second step. Only then is the event completed and the transferred quantity part of unrestricted-use stock.
    Function List
    The following functions are provided to support the J51 building block:
    Creating a Planned Independent Requirement
    Creating a stock transport order in plant BP01
    Generating a delivery in plant BP02
    Picking of the material and posting the goods issue in the delivering plant
    Posting the goods receipt in the receiving plant
    Key Points
    The quantity posted from stock is first of all managed as stock in transit of the receiving plant. Only once the goods receipt has been posted is the quantity posted to the unrestricted-use stock of the receiving plant. This enables the quantity "on the road" to be monitored.
    The transfer posting is valuated at the valuation price of the material in the issuing plant.
    Delivery costs can be entered in the stock transport order.
    Regards,
    Rajesh Banka
    Reward suitable points.

Maybe you are looking for

  • Windows exe file

    I bought windows through Microsoft online and I have received an exe file.  I can't seem to open it on my iMac, I have downloaded the windows support files from boot camp but I still can't get anywhere.  What do I need to do? Thanks,

  • VIDEO CONFERRENCE OPTIMATION !!! help..

    Hi all, I'm still developing my video conferrence project ( over LAN ). I've modified AVTranmit2 and AVReceive2 to be one application. And I want to manage little client-server application, so that each user can make a conferrence with other user (mo

  • Names of other networks

    how do i get rid of the names of other networks in my area in the drop down menu of airport?

  • What version of iMovie can I download for mac os x 10.8.5? (and where?)

    Hi, Can someone please tell me what versions my Mac will support and were I can download it from? Thank you Chris

  • How do I and should I upgrade from Mac OSx 10.5 to 10.6?

    I currently have OSX 10.5 on a 2008 macbook pro. Does it make sense for me to upgrade to OSX 10.6 and do I have to first upgrade to SnowLeopard to do that?