Transfer SOP plan to Demand Mgmt

Dear friends,
   I  have created SOp through MC88. And i wants to transfer SOP plan to demand management through t.code MC74.
While filling the data in the fields, i do not know what to enter in the field "Version" either "00" or "GP".
Please guide me what data to be entered in the "version" field?
Thanks
Shri

If i understand clear on your querry you want to transfer the SOP plan to the demand management.
1.In such case you can use any version.
2.But the version needs to be active .
version in Demand Management:
1. these are used to just manage the diff types of demand in the demand table just for recognising them
2. If they are active then they will be included int he MRP ELSE no.
let me know if you need more answers
reg
DSK

Similar Messages

  • SOP - Flexible Planning u2013 Demand Management.

    Hello Gurus
    Can any one guide me  SOP - Long term plannng  / Flexible Planning  - Transfer to demand managment Process
    Thanks
    JJ
    Edited by: JJ_SAP_S on Jul 28, 2008 12:24 AM

    Hi,
    Transferring SOP  to Demand Management :
    Use:
    You can pass on data planned in Flexible Planning or Standard SOP to Demand Management.
    Demand Management determines the requirement dates and requirement quantities for important assemblies and specifies the strategies for planning and producing/procuring finished products. The result of Demand Management is the demand program. The demand program differentiates planned independent requirements and customer independent requirements. It gives the information needed in MPS and MRP for planning at SKU level. The placing of sales orders eventually consumes planned requirements and triggers updating to the Sales Information System. This actual data can then be used as input for future sales planning. For more information, see PP Demand Management.
    Prerequisites:
    The system distributes the data to the appropriate plants in Demand Management on the basis of the quotas you set in Customizing (in Define proportional distribution across plants). You can also make these settings in the Flexible Planning or Standard SOP menu by choosing Settings ® Plant distribution. Plant distribution works as follows:
    If a plant or plants can be found for the material in the planning hierarchy, data is transferred to Demand Management for these plants.
    If no plant can be found in the planning hierarchy, the system checks to see which plants have been maintained for the material in the material master record. It then checks to see whether distribution quotas have been maintained for the material. If quotas have been maintained, the transfer to Demand Management is based on these quotas.
    If no distribution quotas are found for the material, the system checks to see whether you have set generic distribution quotas; that is, distribution quotas that apply to all materials. If so, the transfer to Demand Management is based on these quotas. If generic quotas exist for some but not all plants maintained in the material master record, the system assumes that the distribution quotas of plants without generic quotas are 0.
    If no distribution quotas are found at allu2014neither material-specific nor generic onesu2014, the system splits the data equally among all the plants in the material master record.
    See also:
    Plant Distribution Quotas
    Features
    Independent requirements are created in Demand Management for all materials whose data has been transferred. These independent requirements are created in the base unit of measure of the material. The base unit of measure of the material is not necessarily the same as the base unit of measure of the information structure or the unit in which you planned the material. See also Switching Units in the Planning Table.
    You can transfer SOP data to Demand Management in the following ways:
    Transferring Online, Synchronously and Automatically:
    You set the following information structure parameters in Customizing for Sales & Operations Planning (in Set parameters of info structures and key figures).
    Field name of the key figure whose values are to be transferred
    Planning version from which the data is to be transferred
    Demand version to which the data is to be transferred
    The system creates or overwrites independent requirements in Demand Management every time you save this planning version of the information structure in Flexible Planning.
    Transferring Online, Asynchronously and Manually
    You choose between the following options:
    Transfer of the planning data of all members of a single-level product group from standard SOP (a single-level product group is a product group whose members are materials)
    Transfer of the planning data created for one material from standard SOP
    Transfer of key figure values from an information structure
    You make the following general settings:
    The material or product group whose data you want to be transferred
    The plant of this material or product group
    The planning version of the information structure in which the data is stored
    The dates for which you want the data to be transferred
    Whether you want to check what the data looks like as independent requirements before you transfer it
    The requirements type
    If you do not make an entry, the system sets the requirements type via the MRP group which is maintained in the material master record.
    The version of the demand program to which you want the data to be transferred
    Whether this version of the demand program is active and therefore relevant to MRP
    Depending on the option you chose in step 1, you set one of the following strategies.
    Transferring Planning Data from a Single-Level Product Group:
    You transfer the sales plans of the materials direct.
    You transfer the sales plans of the materials as proportions of their owner product group (using the proportional factors defined in the product group master record).
    You transfer the production plans of the materials direct.
    You transfer the production plans of the materials as proportions of their owner product group (using the proportional factors defined in the product group master record).
    Transferring Planning Data of One Material from Standard SOP:
    You transfer the sales plan of the material direct
    You transfer the sales plan of the material as a proportion of the product group of which it is a member (using the proportional factor defined in the product group master record)
    You transfer the production plan of the material direct
    You transfer the production plan of the material as a proportion of the product group of which it is a member (using the proportional factor defined in the product group master record)
    Transferring Key Figure Data of One Material from Flexible Planning
    The information structure from which you want the key figure data to be transferred
    The key figure whose values you want to be transferred
    This key figure must be a quantity key figure.
    For more details go to the following link :
    http://help.sap.com/erp2005_ehp_03/helpdata/EN/a5/63238b43a211d189410000e829fbbd/frameset.htm
    Hope this helps.
    Reward if useful.
    Regards,
    Tejas
    Hope this helps.

  • Sales Planning  vs Demand management

    Can any body explain how to process the sales planning vs Demand management !

    Hi,
    Demand Management  : The function of Demand Management is to determine requirement quantities and delivery dates for finished products assemblies. Customer requirements are created in sales order management. To create a demand program, Demand Management uses planned independent requirements and customer requirements.
    To create the demand program, you must define the planning strategy for a product. Planning strategies represent the methods of production for planning and manufacturing or procuring a product.
    Using these strategies, you can decide if production is triggered by sales orders (make-to-order production), or if it is not triggered by sales orders (make-to-stock production).You can have sales orders and stock orders in the demand program. If the production time is long in relation to the standard market delivery time, you can produce the product or certain assemblies before there are sales orders. In this case, sales quantities are planned, for example, with the aid of a sales forecast.
    Sales & Operations Planning (SOP) is a flexible forecasting and planning tool with which sales, production, and other supply chain targets can be set on the basis of historical, existing, and estimated future data. Rough-cut planning can also be carried out to determine the amounts of the capacities and other resources required to meet these targets.
    Use SOP to streamline and consolidate your company’s sales and production operations.
    SOP is particularly suitable for long- and medium-term planning
    SOP constitutes the planning functionality of the LIS information systems.
    You pass on SOP plans to Demand Management (PP-MP-DEM) in the form of independent requirements. In turn, this data is fed to Master Production Scheduling (PP-MP-MPS) and Material Requirements Planning (PP-MRP).
    An interface with Profitability Analysis (CO-PA) allows you to use CO-PA data as the basis for sales planning in SOP.
    You can also pass on the results of SOP to Profitability Analysis (CO-PA), Cost Center Accounting (CO-OM-CCA), and Activity-Based Costing (CO-OM-CCA).
    Application Link Enabling (CA-BFA-ALE) supports the distribution of data to different operating units in your enterprise
    I hope this information will help you.
    kiran.

  • Transfer sales plan to md61

    Dear Experts,
    In my Scenario  Sales Deptt. Update sales Scheduling Agreement in SAP By VA31 and then MRP is running & creating Planned orders .
    Now We wants to change our Process ,
    NOW Before MRP Run we wants to transfer Sales schedule to Demand management MD61 , Where we can manually change Production plan which is not equal to Sales delivery schedule .
    To copy sales schedule , I am doing   Edit > Copy Requirement > Sales Plan > Total sales
    Here system do not copy plan and shows below given error
    u201C No production plan exists for product group  XYZ u201C
    Please let me know  that how to copy sales schedules in Demand management (MD61) .
    Regards,
    ashutosh

    Ashutosh,
    ???? VA01 and VA31 are not plans, they are sales documents (execution).  If your question is 'does SAP support a direct copy from sales documents (such as sales scheduling agreements) to planned independent requirements, the answer is no.  It would make no sense.  Sales documents usually consume planned independent requirements, depending upon your planning strategy.
    If you want your production plan to be increased, for the reason of planned scrap/yield loss, you normally enter that yield loss quantity in one of the scrap or yield fields in either the Material Master, or in the Bill of Materials (depending upon your planning methods).  In this way, every time MRP suggests a supply order (planned order), it will suggest quantities large enough to cover planned yield loss.  It is normally considered a waste of time to have a planner manipulate these types of numbers manually for each iteration of the production plan.
    http://help.sap.com/erp2005_ehp_06/helpdata/EN/f4/7d28d544af11d182b40000e829fbfe/frameset.htm
    http://help.sap.com/erp2005_ehp_06/helpdata/EN/be/43bdd865f411d3b4e60004ac160649/frameset.htm
    If your yield is totally unpredictable (according to your statements, this is not the case), then you would also consider using one of the standard planning tools (like Safety stock)  to create some buffer stock. 
    Demand plans are usually not created for the sole purpose of accommodating yield issues. The most common reason to create a demand plan is to provide an orderly way to plan the entire supply chain in the most efficient manner.  This is especially important when your customers demand a lead time that is longer than the total time to procure all raw materials and build all subassemblies for your finished goods.
    Best regards,
    DB49

  • Way to find CTM taking more time to plan a demand

    Hi,
    Normally a demand in CTM gets planned in less than 1 second. But sometimes there are abnormailities may be because of Data or system and CTM takes more time to plan a demand. Is there a way or method to find why a demand has been planned in more time?
    Need your help
    Thanks
    Deepak

    Hi Deepak,
    1) Once the CTM run is started, it will record & execute all the events of the program mentioned in the function module and each event will be stored in the OPTIMISER TRACE FILE. 
    The trace files will be recorded in back end and you can check with basis team to help you in extracting & convert into your requirement form with suitable fields and you can develop a custom report on this so that you can execute on daily/weekly basis and analyse.  The trace file will be available only in optimiser server.
    2) The other areas that you can look at is /SAPAPO/OPT12 - Process Overview wherein u will get process related informations but not at very detailed level
    3) Check with basis team whether any database alerts can be developed if at all your CTM run gets strucks or extends for want of data or performance.
    4) Check the application logs/inbound/outbound queues/sysfails which will figure out any specific item containing errors.
    Regards
    R. Senthil Mareeswaran.

  • Data transfer from planning to ASO.

    Hi,
    Like that:
    Data load in Planning, and data retrieve in ASO. And we want a real time data transfer from Planning to ASO.
    Transparent partition from BSO to ASO is a choice, but the performance is an issue.
    If we user replicated partition, data cannot be transferred to ASO instantly, since there is a step to replicate data to ASO.
    And for Map Reporting Application in Planning, we got the mapping issue, since there are some dimension members totally different between Planning and ASO.
    So, can anyone help to show other ways to do that?
    Thank you.

    iTunes does transfer files like pictures, music, video, and I believe under the apps section it should transfer specific app files too.
    otherwise I don't know. I tried to get my ipad to link to my computer with bluetooth (it saiys it is linked now) but when I try to transfer a file or browse the device it won't work.... I dunno!

  • Knowledge Transfer / transition plan template

    Hi all I need to transition off a project and need to come up with a knowledge transfer / transition plan.  Does anyone have any that you have used on SAP projects in the past.  When I google, I get very generic type of plans that are not IT/SAP specific. 
    If you do have one would appreicate it you could provide a copy.
    Email is [email protected]

    Hello everyone,
    thanks for your feedback in the last couple of days. It has been helpful in the decision making process.
    We are now planning to offer this training at the following date and location:
    Timeframe: Monday, April 20 until Wednesday, April 22
    Location: SAP India, Bangalore
    Please reserve these dates.
    We will provide registration details and the agenda for this training offering after next week.
    Looking forward to seeing you there!
    Best regards,
    Tina

  • HT4582 How do I transfer cellular plan from ipad2 to iPad air?

    How do I transfer cellular plan from ipad2 to iPad air when the SIM cards are different sizes? At the apple store I was told to just swap them..

    Hey there, Tom.
    I Know it's be a while since these messages were posted.  Just need to rant.
    why does it have to be so friggin' hard to transfer my data plan from one iPad to another?!!
    what you suggested doesn't work because the account info never shows up!
    SO, I called the local att office.  "Hmmm... We've never dealt with an iPad air 2, but bring it in and we'll see what we can do. 
    Okay, great.  The AT&T office is only 15 miles away, no problem,  but really???
    (Why is there no caps lock?)
    WHy does it have to be so HARD?

  • I am planning on buying an iphone 4 from some one. The phone still has the Apple Care Protection plan on it. Would there need to be a transfer of plan onto my name? If so, how is this done?

    Hi, I am planning on buying an iphone 4 from some one. The phone still has the Apple Care Protection plan on it. Would there need to be a transfer of plan onto my name? If so, how is this done?

    As the others have said, transferring AppleCare to your name is not absolutely essential. It can make things easier in some cases, though, should questions arise, so it's worth having done. The person from whom you're buying the iPhone will have to call AppleCare Plan Administration (s/he can call the normal Apple support line and ask to be transferred) and arrange to have the plan transferred to you.
    Regards.

  • SOP PLAnning version -# Digit

    Hi Experts,
    Can anybody  tell  me if we can set SOP Planning version to 4 digit.
    Because my client using planning version -909 -2009 for september month
    in 2010 Jan we have to create planning version 1001 . IS possible to crate four digit planning version.
    Prashant

    Hi Prashanth,
    As per my knowledge Std SAP allows only upto 999 versions
    Regards
    kumar

  • Transfer cost planning to operative

    hi
    We r using CJ40 and unit costing where v r planning materials.
    i want to transfer these planned material to be transferred to projects ( networks). How?
    Regards
    KP

    It is not possible to transfer material codes you have used for unit cost planning.  Actual material will have to be attached to network activities manually.  As of now i.e. in ECC 6.0 there is no facility to transfer the material codes used in unit cost planning to be used for procurement directly.  However, there is a facility called easy cost planning.  Material code used there can be converted as procurement item using easy execution services.

  • Transfer plan to demand management

    Dear All
    i have maintained an active sales plan in mc93 for 30 materials.Now i can transfer plan of one material
    to demend management by mc 90. But i want to transfer whole version to demend management i mean plan of all materials instead of one by one. so is it possible to transfer whole version in which so many materials are planned to demend management

    Hi ahmad
    with ref to your query i want to add few points which will clarify your issue upto certain extent
    if youwant to transfer all 30 materials to demand management you may work with product group scenario  instead of material(one)
    you maycreate rough cut plan for product group save it against version make it active
    you may trnasfer to demand management by using t code  mc74 with respect ot active versionas well as defined version
    which creatingrough mc35 you have to select w r to sales or production plan
    once the sales plan or production plan trnasfer to demand management you can view the results in md62 for results
    i hope it will clarify your issue for a certain extent
    thanks
    shaik

  • SOP plan transfer to COPA

    Hi all,
    I want to tranfers the planning i have created in trans. MC9C to COPA. I think that the customizing is o.k. but i dont which is the transaction to transfer plan.
    Thanks in advance.
    mmuribar

    hi
    check this
    http://forums.sdn.sap.com/thread.jspa?threadID=1112281
    krishna

  • MC74 : how transfer SOP to PIR for a specific mrp area

    Dear guru ,
    i want to transfer Planning Data of a SOP Version for a single material to Demand Management.
    The copy to Demand is run directly into the plant of the SOP Version.
    I manage MRP Area.
    How can I transfer directly SOP to PIR for a specific mrp area ?
    Thanks in advance

    Hi..
    In  MC87 you have to first create  planning data.. SOP.
    Then if you go to MC74 your planning data will be transferred..
    Ii.e you will get the PIRs automatically from Demand management..
    Hope the above clarifies..
    karthick

  • Transfer forecast values to demand management

    Hi Gurus,
    Can anyone let me know how i can transfer the forecast values to the demand management on mass as a background job.
    Thanks,
    Ravi

    Hi Brahmankar,
    Thanks for the reply.I would try with MD70 and let you know.Can you please answer my other threads on the forecasting.I am really waiting for answers but unfortunately could'nt get any.
    Please look into the below thread and answer.
    Rough cut planning profile
    Thanks,
    Ravi
    Edited by: kumar s on Sep 1, 2009 2:18 PM

Maybe you are looking for

  • At the time of Presentation Audio is not Coming in sx 20

    Hi All, We have two modes of presentation here – 1-Air Media wireless presentation 2- Presentation via Direct HDMI cable. We have made use of an Extron HDMI switcher to switch between the 2. Either mode of presentation successfully gives Audio output

  • Unable To download apps due to --Please Close FlashLightSIMBLAgent--

    So I have tried downloading Illustrator and Photoshop (Latest versions from Creative Cloud) and each time it asks me to Please Close FlashLightSIMBLAgent. I have tried force quitting it via activity monitor but that has not worked. What should I do.

  • URGENT TO FIND JDEVELOPER DIRECTORY ON REDHAT LINUX

    Sir I have office website on redhat linux,jdeveloper10g using websphere and struts and ejb.We are not getting directory structure and location website files(public_html)f i find it i can maintain and update it. can the website files be transferred on

  • Powerbook wont boot anymore

    I have a problem with my powerbook. I wanted to install Leopard beta from the external firewire hard drive, so I set the target startup mode on (I thought it will boot the laptop from the external hard drive) After that I could not boot my mac at all

  • TCODE- MIR4- Details of Multiple Account Assignment

    Dear SDNers, In the TCode MIR4, We input the invoice doc number and the year and hit on enter. We come to the screen that displays the Invoice Document. In this screen,we are able to see a sub screen headed PO reference. In this PO reference sub scre