Transfer to demand management - Flexible Planning

Hi everyone,
I was wondering whether someone has carried out the next process in the following scenario. I am working with flexible planning in SOP (level-by-level planning and dual level planning type, since I am working with product groups).
Now I would like to transfer to demand management some data stored in a ratio associated to one field (disaggregated value) in my planning table.
I tried to do it using the online mode but I just could transfer aggregated level values. I also tried to do it with batch processing (by creating a trannfer profile, then an activity, then a job and finally scheduling and executing the job) but there was an error message that looks like "No dual planning requirements allowed".
I would be very grateful if someone could give some useful information about how to solve my problem. I guess that someone in this forum has faced this challenge formerly.
Thanks in advance and best regards.
Ben.

Hi,
Yes, dual level was specified in the MC8A.
Thanks.

Similar Messages

  • Transfer of data from flexible planning to PIR table when saving the trans.

    Dear all.
    I have a query regarding Flexible LIS Planning (MC93 or MC94). My question is about on transaction MC94. When I save the data on this transaction, it automatically transfers to PIR (Planned Independent Requirement) table. I donu2019t know how this been done by the consultant; is this a configuration, abaping or any enhancement? Any one has any idea regarding this please advice.
    I am very thankful for your help.

    Hello,
    This is 100% SAP standard functionality.
    Go to transaction MC7F.
    There, pick your Info structure SXXX and go in the details of it (CtrlShiftf2 or loop icon)
    In the bottom right of your screen there is a block called "synchronization of planned independent requirements".
    Delete the data that is there or simply untick the requirement "active" check box.
    Alternatively, in that same screen above in the right there is a block called system paramaters - the least setting is transfer to demand management with user exit - uncheck that.
    Hope it helps.

  • Error during transfer to demand management in tcode MC88

    Hi Expert,
    I am getting an error 'No data maintained for material F1475078 plant 2000 in transfer period' during processing transfer to demand management in tcode MC88. Anybody know what is the root caused behind?
    I try to search in internet and no solutions have been found so far, I plan to inform basis to restart the SAP server and try whether can solve the problem or not, which is my last option.
    Hope to get a solutions from you guys soon.
    Thanks.

    Hi,
    Refer to the below threads, it should resolve your query, else revert.
    Error "No data maintained for material XXX plant YY in transfer period"
    No data maintained for material MAT1_AJ plant 0001 in transfer period
    Re: SOP transfer to Demand Management
    Regards,
    Vivek

  • SOP and transfer to Demand management for MTO material

    Hi all,
    I have the following situation:
    I have a material, a finished goods product with planning strategy 20 Make to order defined in the material master. I enter a sales forecast for the material in SOP in SAPECC (transaction MC87), works fine.
    But when I try to release the forecast to Demand Management (MC74), I get the following error message: "No requirements type exists for material 110100 1 in plant 2". I can see that planning strategy 20 MTO does not have any requirement type defined.
    But what is the best practice then to forecast on MTO materials (with strategy 20 MTO)?
    What I want to do is to bring down the requirements of the MTO material to Long term planning to get a BOM explosion for the components. I realize that I should not start a production plan for the MTO material, but I want to plan the requirements for components several months ahead.
    What is the best practice? Should I use a different production strategy? Am I missing config or any fundamental thinking here?
    I need to have the material as a MTO strategy, but I want to plan the components.
    Please, give me input on this if you have any solution.
    Regards,
    Lars

    Hi Lars,
    Here's what you need to do:
    1. Instead of pure 20, customize a strategy group that has in it 20 and 10, and attach this strategy group to your material.
    2. In MC74 specify requirements type LSF, demand management version, and make sure to uncheck the "active" box (otherwise you will get requirements in the operative system, and not only in LTP).
    3. Do the transfer, and include the version in a LTP scenario.
    Regards,
    Mario

  • Re: Sales forecast transfer to Demand Management

    Hi All,
    I am facing an issue regarding the Sales forecast transfer.
    Actually what is happening is When I Enter some Sales forecast in the combination of a Customer/Payer/SLoc/product /Qty. using T-Code :KEPM  & Then Further I transfer this Sales forecast by t-code KE1K.
    I am able to see the quantities in the MC95 for that particular combination of as chosen while KEPM.
    Now this happening in the right manner in the Quality client.
    But when the user is trying to do the same in PRD client what is happening is the Plan is getting distributed to three location with same quantities which makes the total Sales forecast three times the actual.
    Now I had recommended the user to input the specific data like customer/company code/Profit center & SLOC while KE1K.
    Still he is facing this issue.
    Please advice how to go for this.
    Regards,
    Vivek

    .

  • SOP:transfer to demand management.

    How to transfer the bom collectively in SOP & how tondelete the product group.
    Regards
    bhuvan

    Bhuvan,
    What do you mean by "transfer the bom collectively in SOP"? There is no concept of BOM, but there can be product groups, which can have Product Groups / Materials as members, the lowest level of the product group should contain material as members.
    Product group is nothing but Material master, with material type PROD, so you need to follow the reorganisation process same as the one for material master to delete product group. If you are looking at deleting the members of a product group, then that is possible in the change mode of the Product group transaction.
    Regards,
    Prasobh

  • SOP - Flexible Planning u2013 Demand Management.

    Hello Gurus
    Can any one guide me  SOP - Long term plannng  / Flexible Planning  - Transfer to demand managment Process
    Thanks
    JJ
    Edited by: JJ_SAP_S on Jul 28, 2008 12:24 AM

    Hi,
    Transferring SOP  to Demand Management :
    Use:
    You can pass on data planned in Flexible Planning or Standard SOP to Demand Management.
    Demand Management determines the requirement dates and requirement quantities for important assemblies and specifies the strategies for planning and producing/procuring finished products. The result of Demand Management is the demand program. The demand program differentiates planned independent requirements and customer independent requirements. It gives the information needed in MPS and MRP for planning at SKU level. The placing of sales orders eventually consumes planned requirements and triggers updating to the Sales Information System. This actual data can then be used as input for future sales planning. For more information, see PP Demand Management.
    Prerequisites:
    The system distributes the data to the appropriate plants in Demand Management on the basis of the quotas you set in Customizing (in Define proportional distribution across plants). You can also make these settings in the Flexible Planning or Standard SOP menu by choosing Settings ® Plant distribution. Plant distribution works as follows:
    If a plant or plants can be found for the material in the planning hierarchy, data is transferred to Demand Management for these plants.
    If no plant can be found in the planning hierarchy, the system checks to see which plants have been maintained for the material in the material master record. It then checks to see whether distribution quotas have been maintained for the material. If quotas have been maintained, the transfer to Demand Management is based on these quotas.
    If no distribution quotas are found for the material, the system checks to see whether you have set generic distribution quotas; that is, distribution quotas that apply to all materials. If so, the transfer to Demand Management is based on these quotas. If generic quotas exist for some but not all plants maintained in the material master record, the system assumes that the distribution quotas of plants without generic quotas are 0.
    If no distribution quotas are found at allu2014neither material-specific nor generic onesu2014, the system splits the data equally among all the plants in the material master record.
    See also:
    Plant Distribution Quotas
    Features
    Independent requirements are created in Demand Management for all materials whose data has been transferred. These independent requirements are created in the base unit of measure of the material. The base unit of measure of the material is not necessarily the same as the base unit of measure of the information structure or the unit in which you planned the material. See also Switching Units in the Planning Table.
    You can transfer SOP data to Demand Management in the following ways:
    Transferring Online, Synchronously and Automatically:
    You set the following information structure parameters in Customizing for Sales & Operations Planning (in Set parameters of info structures and key figures).
    Field name of the key figure whose values are to be transferred
    Planning version from which the data is to be transferred
    Demand version to which the data is to be transferred
    The system creates or overwrites independent requirements in Demand Management every time you save this planning version of the information structure in Flexible Planning.
    Transferring Online, Asynchronously and Manually
    You choose between the following options:
    Transfer of the planning data of all members of a single-level product group from standard SOP (a single-level product group is a product group whose members are materials)
    Transfer of the planning data created for one material from standard SOP
    Transfer of key figure values from an information structure
    You make the following general settings:
    The material or product group whose data you want to be transferred
    The plant of this material or product group
    The planning version of the information structure in which the data is stored
    The dates for which you want the data to be transferred
    Whether you want to check what the data looks like as independent requirements before you transfer it
    The requirements type
    If you do not make an entry, the system sets the requirements type via the MRP group which is maintained in the material master record.
    The version of the demand program to which you want the data to be transferred
    Whether this version of the demand program is active and therefore relevant to MRP
    Depending on the option you chose in step 1, you set one of the following strategies.
    Transferring Planning Data from a Single-Level Product Group:
    You transfer the sales plans of the materials direct.
    You transfer the sales plans of the materials as proportions of their owner product group (using the proportional factors defined in the product group master record).
    You transfer the production plans of the materials direct.
    You transfer the production plans of the materials as proportions of their owner product group (using the proportional factors defined in the product group master record).
    Transferring Planning Data of One Material from Standard SOP:
    You transfer the sales plan of the material direct
    You transfer the sales plan of the material as a proportion of the product group of which it is a member (using the proportional factor defined in the product group master record)
    You transfer the production plan of the material direct
    You transfer the production plan of the material as a proportion of the product group of which it is a member (using the proportional factor defined in the product group master record)
    Transferring Key Figure Data of One Material from Flexible Planning
    The information structure from which you want the key figure data to be transferred
    The key figure whose values you want to be transferred
    This key figure must be a quantity key figure.
    For more details go to the following link :
    http://help.sap.com/erp2005_ehp_03/helpdata/EN/a5/63238b43a211d189410000e829fbbd/frameset.htm
    Hope this helps.
    Reward if useful.
    Regards,
    Tejas
    Hope this helps.

  • SOP flexible planning  transfer to  demand managemnt

    hi guys,
    very good morning...
    any one plz light on SOP flexible planning  transfer to demand management  from inactive version to active version with flow,
    thanks in advance,
    mohan m

    Hi,
    In flexible planning the nomal flow is as follows
    1. MC21
    2. MC7F
    3. MC8A
    4. MC61
    5. MC93
    6. MC8V/MC8Q
    7. MC90
    In MC90 u transfer the requirements from SOP to demand management.Here u give the requirements type and the planning version from which it is to be transferred.
    Manisha

  • Sales Planning  vs Demand management

    Can any body explain how to process the sales planning vs Demand management !

    Hi,
    Demand Management  : The function of Demand Management is to determine requirement quantities and delivery dates for finished products assemblies. Customer requirements are created in sales order management. To create a demand program, Demand Management uses planned independent requirements and customer requirements.
    To create the demand program, you must define the planning strategy for a product. Planning strategies represent the methods of production for planning and manufacturing or procuring a product.
    Using these strategies, you can decide if production is triggered by sales orders (make-to-order production), or if it is not triggered by sales orders (make-to-stock production).You can have sales orders and stock orders in the demand program. If the production time is long in relation to the standard market delivery time, you can produce the product or certain assemblies before there are sales orders. In this case, sales quantities are planned, for example, with the aid of a sales forecast.
    Sales & Operations Planning (SOP) is a flexible forecasting and planning tool with which sales, production, and other supply chain targets can be set on the basis of historical, existing, and estimated future data. Rough-cut planning can also be carried out to determine the amounts of the capacities and other resources required to meet these targets.
    Use SOP to streamline and consolidate your company’s sales and production operations.
    SOP is particularly suitable for long- and medium-term planning
    SOP constitutes the planning functionality of the LIS information systems.
    You pass on SOP plans to Demand Management (PP-MP-DEM) in the form of independent requirements. In turn, this data is fed to Master Production Scheduling (PP-MP-MPS) and Material Requirements Planning (PP-MRP).
    An interface with Profitability Analysis (CO-PA) allows you to use CO-PA data as the basis for sales planning in SOP.
    You can also pass on the results of SOP to Profitability Analysis (CO-PA), Cost Center Accounting (CO-OM-CCA), and Activity-Based Costing (CO-OM-CCA).
    Application Link Enabling (CA-BFA-ALE) supports the distribution of data to different operating units in your enterprise
    I hope this information will help you.
    kiran.

  • Difference between standard SOP and Flexible planning

    Hi, Pls explain the difference between Standard SOP (sales and Operation planning) and flexible planning?

    Hi,
    Following links will help you to understand.
    https://forums.sdn.sap.com/click.jspa?searchID=20534538&messageID=6314185
    The contents are as below :
    Steps
    1) Create Planning for material MC87
    2) Copy to Active Version MC78
    3) Transfer to Demand Mangement MC74
    B) STD sop for Product Group
    Here also the Characteristics are same material->product group
    You have to maintain master data Product group
    steps:
    1) Create Product Group MC84
    2) Create Plan for Product Group MC81
    3) Disaggregate Product Group Plan MC76
    4) Copy to active version MC78
    5) Transfer to Demand Management mc75 for Pg or mc74 for material
    FLEIXIBLE PLANNING
    Here you can able to Define your own characteristics and Key figures
    Char like Sales org,Dis chann, Div,......
    Key figures like stock,invoice qty,....
    steps
    1) Create Info structute MC21
    2) Maintain Planning Parametes MC7F
    3) Create Planning Type MC8A
    4) Create Flexible Planning MC93
    5) Copy to active version MC8V
    6) Transfer to Demand managemet
    5) Create Std SOP Planning -MC
    6) Transfer to DM from change mode of Flex Plann with active version MC94
    if you want use the flexible planning info like SIS in std sop
    after the 4th step of above it will be like
    5) MC87 std sop there Sales data from SIS it will ask for info str and version then you can get it automatically then the std steps like
    6) Copy to Active Version MC78
    7) Transfer to Demand Mangement MC74
    Please refer this link also,
    SOP Process

  • Transfer to demand

    Hai friends
    Created new info structure for flexible planning .
    1) MC21- Info structure
    2)MC8A-Planning Type
    3)MC7F-Planning parameters
    4)MC61-Planning hirechay
    5)MC93-Planning
    6)MC8V-Copy to active version
    7)MC8G-Schedule
        Then palnning data transfer to demand management .I have no of materials in one plant .
    How to transfer all materials to demand management ?
    Edited by: kandan kandan on Jun 30, 2008 1:41 PM

    Hi,
    Yes, dual level was specified in the MC8A.
    Thanks.

  • Demand management table

    Sir,
    We are following the process of SOP in REM as follows:-
    1) Creation of Product group.
    2) Upload the Sales plan for product group
    3) Desagregation of products
    4) Copy to active version from inactive version
    5) Transfer to demand management
    we reqire the table for Sales and operation plan and also after transherring to demand management which table is updated. This is required as we are preparing a report for Sales Plan v/s Production plan.
    Thanks & Regards,
    Nilesh

    Dear Nilesh,
    Check these tables,
    P445V                            Sales and Operations Planning: Versions
    PGMI                             Product Group/Member Allocation
    PGPL                             Sales & Operations Planning (SOP)
    PGPLE                            SOP Characteristic Values
    PGZU                             Product Group/Member Quantity Conversions
    Regards
    Mangalraj.S

  • Demand Management Through SOP

    Hello Everyone,
    I have a scenario where I receive an 8 week rolling forecast from marketing. This is transferred to production. 2 weeks before actual production the plan is firmed.
    I was hoping to implement this using SOP transfer to demand management. I was also planning to use an MRP type with a planning time fence. But am not exactly sure of the best practice to transfer Rough cut plann data to demand management. Do I directly transfer the Rough cut plan to a "requirements plan" version?
    If not what would be the best possible solution to run SOP?
    Also Please suggest as to any specific configuration settings to be maintained for SOP.
    Any help in this regard would be greatly appreciated.
    Sincerely,
    Aji Kurian Mani

    Hi
    It depends on at which aggregation level you are receiving the Forecast.
    if you are receiving at Plant -Material level. I would advice you to directly upload in to MD61.
    SOP is required, if you need to do any forecasting in SAP.
    or if you need to publish , analsyse the Historical and Forecasting Values at diffrent Org Levels(Plant, cutomer, Material,Sales org....etc)
    using the planning tables you can maintain the Figures at one Level, which gets aggregated automatically.
    Regards
    Ratan

  • Demand managment tranfer problem

    Dear PP guru's,
            When ever i am trying to transfer data from demand managment systeam shows msg that no data is maintain for material,plant in tranfer period ,how to solve this query
    Regards
    Amit Naik

    Hi,
    In MC74 you have to select the option of radio button for Production plan for material or PG member, You have to select requirement type and version with date and then save the it will be copied to Deman Management which you can see in MD62.
    Or you can try to transfer from MC87 create the plan then go to Extra--Transfer to demand management.Deselect invisable tranfer maintain period with active versio.
    Please try and come back.
    Regards,
    R.Brahmankar

  • SOP and Demand Management!

    Hello SAP Gurus, I need a litle help,
    I have created a SOP in transaction MC87 for a material/plant with quantity 100 for month 10. Then I make a copy to Demand Management and in MD04 I have the requirements. So far so good.
    The problem is: when I change the quantity in MC88 for the material/plant to 0, the system doesn't copy to demand management the 0 quantity.
    Is there any way to put this to work this way or do I have to go in MD61 and delete the requirements for the material/plant?
    Thanks in advance,
    Adelmo Silva

    Hello again SAP friends,
    Maybe I can explain myself beter:
    SAP v4.6C
    1. MC88 - I change de Rough-Cut Plan for my material/plant with production values equal to 0 (zero).
    2. I transfer to demand management and everything works fine!
    SAP ECC 6.0
    I do the same as SAP V4.6C and I get the error: "No data maintained for material ARS_PA_01 plant 1000 in transfer period Message no. MA640"
    Can someone help me with this?
    Thanks in advance,
    Adelmo Silva

Maybe you are looking for