Hi,
We are in the process of implementing DP for one of our clients,
We are facing the following problem, while releasing the Demand ( as PIR) to SAP R/3.
Transfer to R/3 using mixed periodicities is not allowed
We have maintained below mentioned steps;
1.Periodicities of Planning area maintained only weekly buckets.
2. Maintain Transfer Profile (SAPAP/MC8U)
3. Define activities for Mass Processing (SAPAPO/MC8T)
4. Create Demand Planning for Background job
     (SAPAPO/MC8D)
5. Schedule demand planning in Background (SAPAPO/MC8G)
6. Through SM37 I checked the Spool List.*Error: Transfer to
     R/3 using mixed periodicities is not allowed*
Kindly request if anyone knows provide solution.
Regards
Sadasivam R K

I think you can have only month, quarter and year in your storage bucket profile when you release forecast to ECC.
Anything lesser than that will give you an error when you release forecast to ECC.
If you want to send forecasts in weekly buckets, then you need to maintain the period split profile (Transaction /SAPAPO/SDP_SPLIT - Maintain Period Split Profile ) and assign this profile to the transfer profile.

Similar Messages

  • IPad Air iOS8.0.2. I used the photos app to edit my photos and created a new album for them. When I transfer my photos to my PC via cable (not allowed to use cloud services by my boss) i can only transfer the unedited versions. Any tips? Thanks!

    iPad Air iOS8.0.2. I used the photos app to edit my photos and created a new album for them. When I transfer my photos to my PC via cable (not allowed to use cloud services by my boss) I cannot choose this edited album, only transfer the unedited versions. Any tips? Thanks!

    Hi Anjohi,
    Thanks for visiting Apple Support Communities.
    If you've edited photos on your iPad and only see the original version when you import them to your computer, the tips in this article may help:
    iOS: Edited photos show original photo after import or in other apps
    All the best,
    Jeremy

  • An entry using this combination is not allowed

    Hi, everyone.
    I created 1asset, posted value and run depreciation. After that, I use t-code F-92 to retirement. When I choose asset to retire, the system has error: An entry using this combination is not allowed, .
    Can u help me configure this error?
    Thanks so much.

    I have same problem with Asset having its threshold value 5% .
    system has stopped to calculate depreciation value last year for this asset
    now we are selling this asset to customer. but during entry in F-92 , system shows error message
    An entry using this combination is not allowed (see long text)
    Message no. AA338
    Diagnosis
    You have made contradictory entries regarding the determination of values.
    The possible entries are as follows:
    - You want to post a complete retirement
      => Set the indicator for complete retirement, do not make any
         other entries
    - You want to post a partial retirement
      => Enter either the amount or the appropriate percentage
         rate.  If quantity updating is used for the asset, you can
         also enter a quantity.
      => Enter only the quantity being retired (this is only possible if you
         are not dealing with a generic retirement, and quantity
         updating is used for the asset).
    Procedure
    Check your entries.
    i have  try all fields  one by one and also to gather, but system shows same error message for every selection.
    complete retirement
    amount
    qty
    percentage.
    if i am not selecting any one of these fields  then system force me to select any one field by error message
    please help to resolve it
    Regards,
    Riten Patel

  • HT2486 i created a group in address book and when wanted to use it it does not allow me to use it in email how do use a group name i created?

    I created a group in address book and wanted to use it, it does not allow me to use it in email how do I use a group name i created?

    How many in the group? Some ISP's have a restriction on that. Check with your ISP.

  • Select statment using FOR ALL ENTRIES  not allow to do sum,

    Hi All,
    SELECT DELIV_NUMB
           SUM( GRS_WGT_DL )
           UNIT_OF_WT
      FROM /BIC/AGSSD000600
      INTO TABLE I_GROSS
      FOR ALL ENTRIES IN I_LAYTWO
      WHERE DELIV_NUMB = I_LAYTWO-DELIV_NUMB
      GROUP BY DELIV_NUMB UNIT_OF_WT.
    While compiling it shows the error
    The addition "FOR ALL ENTRIES" excludes all aggregate functions with
    the exception of "COUNT( * )", as the single element of the SELECT
    clause.
    Please give some solution to do sum
    with regards,
    Thambe .

    You could just select all entries into an internal table and then loop through and use COLLECT or similar to get your sum values.
    Gareth.

  • It does not allow me go in a webpage that i could previously use, it just does not allow me to log into the webpage

    i previously using firefox could access this webpage, but it logged me out and from then onwards i could no longer logg into the webpage as it keeps denying my information to log in, it is not the webpage as i can log in using internet explorer so i assume that the problem lies with firefox and the webpage.

    Numbers documents from iOS need Numbers 3.2 on a Mac to open. And Numbers 3.2 requires Mavericks. If you are using Mavericks you can get Numbers 3.2 from the Mac App Store. It will be free IF you have Numbers 2 (iWork '09) installed. Otherwise you must buy it.
    Your other option is to send the Numbers file as an Excel file via e-mail to yourself to open with an earlier version of Numbers.

  • Address still in use; change to validity not allowed

    Hello all,
    I use the program BBP_VENDOR_SYNC to synchronize supplier data between SRM and R/3.
    I noticed that if the supplier in SRM have a relation with a contact person (table but052) the address data can't be change.I can't change the "E" error type to "W" because it is written on the code. I also try OBMSG transaction.
    Any idea?
    Best Regards,
    Nacho

    Hi
    I think you can change contact person data via manage business parner (WEB).
    since he has a separate BP in SRM.
    where did you setup w e for which messagge?
    regards
    muthu

  • Mixed Storage not allowed

    Hi,
    Below is the scenario....
    I created a Standard Purchase Order and an Inbound delivery...
    When I trying to create Transfer orders for that Inbound delivery through LT03, and save it....I am getting error message saying "Mixed Storage is not allowed in storage Type xxx"...
    If I change the destination storage type from XXX to YYY and save it, I am getting error message saying " Quant XXXXXXX not consistent with other Transfer Order data".
    Can you please help me resolving this?.....

    Your storage type is not mixed storage type.
    SPRO>Logistics Execution>Warehouse Management>Master Data>Define Storage Type.
    For your warehouse storage type check your settings.If wabnt allow both you have to activate mixed storage type in configuration.

  • Mixed periodicities in a forecast are not allowed In Demand Planning

    Hi All,
    I am running forecast in background by defining activity and job in transaction /sapapo/mc8t and /sapapo/mc8d .
    I am scheduling the job in transaction in /sapapo/mc8g.
    Before scheduling the job i checked the job in transaction /sapapo/mc8i and this check is fine.
    When I am running the job in background i am getting the following error message:
    "Mixed periodicities in a forecast are not allowed".
    This error I am getting in the spool of job in SM37 transaction.
    I ran a copy key figure macro in the same planning book with the same view and it is having no problem.
    In my planning book i am having only one dataview    and with that dataview    only i am scheduling the job.
    The strange thing is that the forecast is running smoothly in  interactive mode in same planning book,same data view with same forecast profile.
    Did anybody face the same problem in the past?
    I am using SAP SCM 7.0 version.
    Thanks In Advance,
    Mukesh Pandey

    Hi,
    I contacted SAP on the same and they suggested me exactly what was the problem.
    I will try to explain the problem with an example here as that would be easy.
    Say, My storage bucket profile is a custom week.
    suppose i am doing forecast at custom week level.
    my time bucket profile in the planning book is "2 years in months".
    So here in the background job we are expecting from the system to first divide years in months and than months to custom weeks. Here we are referring to mixed pereodicities.
    So the rule is your time bucket profile and the bucket of forecasting should be directly in proportion of storage bucket profile.
    it should not be
    Year-->month--
    >week
    it should be
    Year-->week or year>month or month--
    >week.
    I hope i am clear.
    Regards,
    Mukesh Pandey

  • Mixed periodicities in a forecast are not allowed ???

    Hi All,
    When I try to run the forecast in DP in BACKGROUND then I see following message "mixed periodicities in a forecast are not allowed", but when I execute the forecast in foreground it works completely fine with that forecast profile and everything same.
    Can anyone suggest the way to handle this???
    Best Regards,
    Chandan Dubey

    Hi Chandan,
    This is the standard design in the background.
    If you run your forecast in batch you can only use one periodicity and
    not mixed periodicities. Per design it is not allowed to             
    use different periodicities for forecast in mass processing.         
    In interactive demand planning, the forecast key figure and other key   
    figures, such as the adjusted past within the past and forecast horizon 
    are saved independently of the planning horizon of the planning book or 
    planning view. This means in particular that the forecast also saves    
    results outside of the planning horizon for the planning book or        
    planning view.For performance reasons, however, the horizon of the      
    planning book must be greater than the horizons in the forecast profile 
    in the background processing.It is sufficient therefore if the horizon  
    of the planning book in greater than or equal to the forecast horizon.In
    this case, the forecast results are saved but the adjusted past or the  
    expost forecast cannot be saved.Therefore, a warning message indicating 
    that the horizon of the planning book does not contain the past period  
    for the forecast is issued here.In addition, note that for performance  
    reasons the period units of the planning book and forecast profile must 
    be identical in the background processing.This is directly due to the   
    fact that you are not allowed to you use planning books with mixed      
    period units in the background processing.These restrictions do not     
    exist in the interactive planning.      
    I hope this helps.
    Regards,
    Tibor                                                                               
    Furthermore, note that data is not saved in lines or areas that are not 
    ready for input in the background processing.Therefore if, for example, 
    you want to save the adjusted past, then the past horizon for the       
    planning book must be ready for input.

  • How does one transfer CS5 actions for use with CS6?

    CS6 installation, which was uneventful, has transferred none of my actions from my copy of CS5. The CS5 actions are located in the actions folder of the APPLICATION/PHOTOSHOP CS5/PRESETS/ACTIONS.  The "actions" folder in application support/adobe in my library is empty, and has always been so.
    Only the CS6 default actions are located in the same folder for CS6.
    I use imac i7, lion.
    Note that i also have CS3 and CS4 on my machine. This due to recent upgrade to CS5 and recent upgrade to LION, and my general paranoia.
    Must i load each action into CS6, one at a time?
    thanks to any and all.
    vince

    Re: how does one transfer CS5 actions for use with CS6?
    On a Mac - There are multiple ways to do this.  I have done them both ways. In order to do this you need to know where you have your actions stored, and you can move them all at once if you have them stored in the same location.
    1. You can load an action ONE AT TIME into your actions palette by:
         A. Open up the action palette and click on the little arrow with 4 little horizontal lines next to it on the upper right corner of the actions palette.
         B. Select "Load Actions" and a Finder window will open up and you can search your computer through this window for your actions.
         C. Click on the action from the Finder window then click 'Open' at the bottom right of the finder window.
         D. To save these so that they appear every time you open up your actions palette, go back to the little arrow at the top right of the actions palette and when the drop down window opens- click on 'Save Actions'. It will select the location where the          actions are currently stored as the place to save them. If you want to change that path, you can do it at this time in the little path window.  I just leave it, since I keep all my actions stored in the same file.
    2. TO MOVE MULTIPLE ACTION SETS AT ONCE
         A. Open up CS6 (or CS5) and move the Photoshop workspace it to the right side of your computer screen so you can see your desktop on the left side.
         B. Open up your Finder search window from your dock (the square blue head icon thingy for those who are new to photoshop). Move this to the left side of your screen so you can see the Photoshop work space on the right and the Finder window          on the left. In the Finder window, navigate to the file where all your actions are stored, select all the actions in the file (command+A will select everything in the file if you are actively inside the open file) or you can select multiple files           individually by continuously holding down the command key and clicking on the different actions you want to move.
         C. With the Photoshop workspace visible on the right, and the actions palette open so you can see that the actions actually transferred - In the Finder window, click the selected actions you want to load and drag them over to the Photoshop           workspace.  I did this without an image open, I just dragged them onto the empty workspace.  The actions should all appear immediately in the actions palette that is open.
         D. To save these so that they appear every time you open up your actions palette, go back to the little arrow at the top right of the actions palette and when the drop down window opens click on 'Save Actions'. It will select the location where the           actions are stored as the place to save them. If you want to change that path, you can do it at this time in the little path window.  I just leave it, since I keep all my actions stored in the same file.
    I hope this helps. 
    and I hope there are no typos. 

  • Order Import failing with error "The specified subinventory is invalid to use, the profile option INV: Allow Expense to Asset Transfer is set to No. Change the profile option to Yes or choose a valid subinventory."

    Hi All,
    I am getting this error while importing an internal sales order.
    “The specified subinventory is invalid to use, the profile option INV: Allow Expense to Asset Transfer is set to No. Change the profile option to Yes or choose a valid subinventory.”
    I have tried to set mentioned profile as ‘Yes’. But still getting same error.
    Also, provided subinventory is present and active in given inventory organization.
    Please share if anybody encountered this before and have a solution.

    Hi 2878342
    Please refer the following metalink note, it should resolve your problem.
    Order Import Interface.Error Message Specified Subinventory Is Invalid To Use (Doc ID 406411.1)

  • SDOC transfer  using CS_ITM_CDOC-CVL is not working

    Help! we have used /SAPSLL/IF_EX_IFEX_SD0C_R3~IF_EXTEND_CUS_CDOC to transfer pricing conditions from ECC to GTS.
    On the GTS side, we have ensured that there is mapping of conditions from Feeder system set up. We have verified this.
    The code in BADI is ...
    We have a table in ECC, with ECC price condition and corresponding GTS price condition (table below shown as GT_PRIC_COND_MAPPING)
    GV_POSNN = LS_ITEM_GEN-ITEM_NUMBER.
        LOOP AT IT_KOMV ASSIGNING <LS_KOMV>
                WHERE KPOSN = GV_POSNN.
          READ TABLE GT_PRIC_COND_MAPPING ASSIGNING <GS_PRIC_COND_MAPPING>
                     WITH KEY ZKEY3 = <LS_KOMV>-KSCHL.
          IF SY-SUBRC EQ 0.
            CLEAR LS_CVL.
            LS_CVL-ITEM_NUMBER  = LS_ITEM_GEN-ITEM_NUMBER.
            LS_CVL-QUAL_VAL     = <GS_PRIC_COND_MAPPING>-ZVAL.
            LS_CVL-VALUE        = <LS_KOMV>-KWERT.
            LS_CVL-VALUE_FLOAT  = <LS_KOMV>-KWERT.
            LS_CVL-VAL_CURR     = IS_VBRK-WAERK.
            LS_CVL-VAL_CURR_ISO = IS_VBRK-WAERK.
            LS_CVL-CVRTQ        = IS_VBRK-KURRF.
            APPEND LS_CVL TO CS_ITM_CDOC-CVL.
          ENDIF.
        ENDLOOP.
    The structer for CS_ITM_CDOC-CVL in the BADI seems to look right. has all the value we want to transfer to GTS.
    However, this data does not go to GTS. Do we need a commit statement?
    Any pointer will be very much appreciated.
    Thanks,
    Padma

    Hi Padma,
    The standard code finds and populates the first Duty Type with VALTY = '003'.  That doesn't have to be Duty Type 'W001' - you could easily configure another to receive the Statistical Value that you transfer.
    BUT...
    My previous answer was wrong, and I'm sorry about that.  After checking the code, I now realise that you CAN transfer individual conditions using the _CVL item-level table, so your technique should work.  Be sure that your mapping from Condition Type to GTS Duty Type is in either table /SAPSLL/TLCAVS or /SAPSLL/TLCAGS (Logical System or Group of Logical Systems).
    Looking at your code, I think you should take a little more care with the ISO value of  the currency.  And if you have problems, it might be best not to transfer the Exchange Rate at first, in case that is giving problems.
    Hope that helps.
    Regards,
    Dave

  • Transfer data through bdc using as01 tr. code

    hi gurus,
    please tell me transfer data through bdc using as01 tr. code.please guide me through coading how to i will proceed.i am using call tr. through recording.
    thanks
    subhasis

    Subhasis,
    Best way to Convert data to AS01 is to Use BAPI BAPI_FIXEDASSET_CREATE.
    Trouble free and easy conversion.
    Hope this helps.
    Vinodh Balakrishnan

  • Our company has users on both Acrobat X and XI.  We have custom stamps in X that the XI users need to use. How do we transfer the stamps to use in the newer version?

    Our company has users on both Acrobat X and XI.  We have custom stamps in X that the XI users need to use. How do we transfer the stamps to use in the newer version?

    You just copy the stamp files from one machine and place them in the correct directory on the other. You can find the location of both the user and app stamp directories by running the following code in the interactive JavaScript console:
    app.getPath("user", "stamps");
    app.getPath("app", "stamps");
    Select both lines and press Ctrl+Enter (Windows) or cmd+enter (Mac). Here's what I get with this using Acrobat 11 on a Mac:
    user folder: /Macintosh HD/Users/georgejohnson/Library/Application Support/Adobe/Acrobat/11.0/Stamps/
    app folder: /Macintosh HD/Applications/Adobe Acrobat XI Pro/Adobe Acrobat Pro.app/Contents/Built-in/Comments.acroplugin/Stamps/
    The stamp files (PDFs) might have cryptic looking names, but you can safely open each to see what stamps they contain.

Maybe you are looking for

  • ICal 2.0.2 doesn't display week view

    so i've been running ical fine for a while, but lately whenever i click on the week view it minimizes ical the day and month views both work fine does anyone know how to solve this problem? it's getting frustrating since i use the week view almost al

  • PDF links not working in Safari?

    I'm noticing that links in PDFs (made with Acrobat 9) are not accessible when viewing the PDF in Safari (although they do work in iBooks). Does anyone have any suggestions? Thanks.

  • Diablo II Cinematics

    Hey. I've played Diablo II for a while on my iBook G4, I got an Intel iMac and installed it on there. I put my save file on the iMac but no cinematics came with it. I put the movies folder from the iBook on the iMac and still nothing. Is there a way

  • Deletion of condition table

    Hi Guys, I created condition table, access sequence by using condition table ,created condtion type and used condition type in pricing procedure.  later becasue of some reason I need to remove the condition table. Hence, from the end I removed condit

  • Shutdown Manged server without Admin

    Hi All, I have a requirement to Restart Managed servers via NodeManager but without AdminServer. Using WLST I could start Managedserver using NM. (nmConnect, nmStart). But for Stopping a Managedserver without Admin. I see the option nmKill. But I don