Hye GURUS,
I am unable to close the text box for the open trips. In other words i approved the request, Aproved the TRIP and I have even settled the trip but even then I am unable to remove or finsih the the trip information from the main page of trip manager.
Secodnly i would like to know that how cani use Travel planning without integration with service providers. I want to enter the planning manually about the date adn tickets and expense related stuff
your advices would be highly appreciated.
Regards
Waqas Anwar
Edited by: waqas anwar on Jan 2, 2008 1:14 PM

Just Check
In SPRO
Travel Management-> ESS -> interface configuration….. ->schema and single field ……->Trip Prov. Variant = 40 (India Scenario)
Regards,
Umesh

Similar Messages

  • Question about POWL in Travel Management

    Greetings!
    currently, we are in the process of implementing SAP Travel Management on our DEV System (Request and Expenses) and therefore of designing business processes. One major crucial point is the process of Approving the Travel Request.
    We are on ECC 6.0 EHP 4 and therefore use the WD4A Travel Scenarios. We use a portal ess/mss with respective Stacks/SPs and BPs.
    Business Process Draft A:
    The Traveler is filling out his Travel Request (FITE_REQUEST) and is assigning the relevant cost centers himself (they are initially defaulted to IT0001, but IT0001, as per our definition, isn't nessecarily correct always; thus, manually cost center assignment possible).
    When the Travel request is sent for approval, the Manager who is responsible for the cost center chosen in the request has to be chosen as the approver. If there is more than one cost center, there will still be only one approver. There hasn't be decided yet, who, in that case will be it, but this is of none concern for my particular question at the moment.
    For the first step to do I would naively say "I make a POWL query with an own POWL feeder class saying 'Assign all Users to me, which travel for a certain cost center' ". Would this be possible?
    Now, let me explain what I am unsure about, concerning the following use-case:
    1. Traveler creates a request on 28th of February 2012 for the Date range of 1st of March 2011 till 3rd of March, choosing Cost Center A so the Request should be visible to Manager A for Cost Center A. Traveler is assigned to Manager A's POWL. Manager A can see the traveler from 28th of February onwards.
    2. Traveler creates yet another request on the 28th of February 2012 for the Date range of 7th of March till 10th of March,
    choosing Cost Center B so the Request should be visible to Manager B for Cost Center B. Traveler is supposedly assigned to Manager B's POWL. Manager B can see the traveler from 28th of February onwards.
    Question: What happens to the POWL? Who can see what
    Manager A must only see travel request from cost center A.
    Manager B must only see travel request from cost center B.
    What I assume will happen is:
    - Both Managers can see both travel requests because both managers have User Traveler assigned, which is forbidden due to business restrictions...
    Any Ideas, solutions, discussions are welcomed.
    Best regards,
    Lukas

    nzworld, thanks for your idea. However this is not possible because the relation of user to cost centers to approvers can be
    1 - n - n.
    After the feedback here, talking back to my colleagues and debating this with our consultants, we will not be using POWL for our approval process, because it's simply not flexible enough for our cause. Closing thread.

  • ESS-portal integration with Time and Travel management(HR) in R/3

    Hi,
         Im doing with ESS-portal configuration with Time and Travel Management in R/3,So please kindly send me Documents for integration part.I'll b so thankful if u people send me docu as soon as possible.
    send me documents to [email protected]
    thanks
    pavi

    Hi
    Please go through this functional module HRMS_BIW_EXTRACT_PY1 in r/3 side to know the exact table where u r getting the data.
    There are lot of tables involved in HR-payroll info types.
    As far as your problem is concerned you take one employee and go to PA20 and analyse the payroll for each week or twice a month (depends up on ur client)
    run the report on the payroll cube and find out exactly what u want.
    Thanks
    Roopa
    Assign points if help full

  • Report to see all trip details in Travel Management !

    Hi All,
    I need a report in travel management to see complete Trip Details like Trip No, Trip Start and end date, Receipts, Mileage, Trip type enterprise-specific, licence plate, vehicle type, vehicle class, start & end location and comments,
    Please assist !
    Best Regards,
    Devendra Reddy D.

    Hello
    You wont find many reports in standard. SAP doesnt deliver a lot of them because every customer have their own concerns and needs.
    However I think that the one which is the closest of your needs is program RPR_TRIP_HEADER_DATA / transaction S_AHR_61016401 (contains link to trip details such as receipts, mileage..).
    Regards
    Mathieu

  • Travel Management-Receipt Maximum rates and Default values

    Hi
    I need some help on one of the issue we are facing in Travel Management. We are expected to Go-live very soon.
    We are unable to apply a very basic check of receipt maximum amount at
    the receipt entry in the portal for travel expenses. This functionality
    is very much provided by SAP in the backend configuration but it is not working in the backend also in our Development system.
    This is concerning the maximum and default amounts in
    View V_T706B2 are related to the IMG
    "Define Influence of Control Parameters: Receipt Maximum Rate"
    I have analysed the table entries but could not
    get the desired solution.
    In the meanwhile based on SAP note: 808437-Warning message when max
    rate is exceeded negative value, we looked into the code and found that
    the code for checking the maximumum amounts is "commented" in the
    lastest SP32 SAP HR version in the DEVELOPMENT system we are working
    on.
    I also looked into (SAP Note: 1114398---Country and Region when
    reading maximum amounts and defaults) and have found that the
    correction suggested in this note may already be applied as our D35
    System EA_HR patch level is already SAPK-60211INEAHR and Note
    correction in SAPK-60203INEAHR is of old level, hence we have not applied this correction.
    Furthermore I have checked and found that in our IDES system these checks
    for Maximum amounts and defaults are working fine. The IDES system is
    at level 0002 and highest support package is SAPKE60002.
    Many thanks in advance !
    Ritesh

    Hi Ritesh:
    We had a situation in which our expense types require both a warning message and request for additional information when the maximum is exceeded. We were told that ECC6.0 can handle only one action per expense type/amount. In our old system, R4.6C, it could handle multiple actions per amount for a receipt type.
    I am not sure if this is your issue - having multiple actions for a expense type/amount combination.
    We got around this by leaving one action at the expected amount and setting the other to 0.01 lower.
    Lisa

  • Implementing travel management.

    Hi friends;
    We are implementing travel management in ess where the employee will create a request for reimbursement and then the concerned finance department person will approv or reject the request and then the respective infotypes will be updated.
    We are using portal 6.0 and r/3 4.7c .
    1. Now is there any standard functionality available for this . Like are there any standard iviews for the same  in portal and do
        we   need to install any business packages for this on portal and is any patch required to be applied on r/3.?
    Please suggest.?
    2. Also let me know what would be the advantage for travel management  if we upgrade to ecc 6.0?
    Please help.
    Thanks in advance.

    << Do not post the same question across a number of forums >>

  • Error message in SAP Travel Management

    Hi alll,
    I am trying to change an address in PRMD tx code
    Error message:  Enter a house number
    Also it is not possible to change existing addresses as the same error comes up.
    I also tried in other company codes and there it seem to work fine so the issue might only be for company code 0376
    Could you please let me know if there is any restrictions from the field u201Cstreet and house numberu201D so that it can be entered and changed as free form text?
    Thanks for your help!
    It is SAP 6.0

    Are you sure you mean PRMD?  This is the T-code to update HR master data and is not related to travel management!
    Did you mean PRAA perhaps if you were trying to update master data from HR to vendor as there are some known issues around the structure of the PRAA report and house number and address (see the notes 570023 and 663350)
    cheers
    Sally

  • FM Travel Management Integration Deactivating

    Hi All,
    How to deactive the integration of Travel Managment with Funds Management module, since we are controlling the expenses from HR module.
    After activating funds management in the system, while creating a travel request we got the following error. Anyone can help on this, for idenifying the problem.
    In the travel request portal we are getting this error :
    " com.sap.tc.webdynpro.modelimpl.dynamicrfc.WDDynamicRFCExecuteException: No expense type for estimated costs has been defined. Cannot save , error key: RFC_ERROR_SYSTEM_FAILURE and No expense type for estimated costs has been defined. Cannot save , error key: RFC_ERROR_SYSTEM_FAILURE "
    Thanks
    RK

    Hi,
    Check your patch level n upgarde it.
    Please implement the note correction of the note 1286257. This should solve the issue you describe.
    Thanks
    Neha

  • No number range found for 01 RP_REINR SP11--Travel Manager

    Hi
    While creating Travel request in in Travel manager i got this error messages"No number range found fo 01 RP_REINR SP!!-Travel Manager..Plse advice me how to resolve this..
    Thanks&best regds
    Shaila

    In adition to task from Shailaja .. Consider this:
    Please note that while defining your number ranges, the number must be two Digits  i.e ( 01,02,03)  , it must NOT be single digit  i.e (1,2,3)..
    I'd had the same issue, but with the two digits number it has been solved.
    Regards,
    Rodolfo

  • Gain or loss due to foreign currency exchange rate in Travel Management

    Hi Experts,
    I am facing some issues in foreign currency surrender in Travel Management.
    Example:-
    An employee goes on a foreign trip in which he takes advance in USD. After returning from the trip, if any USD balance is there then he returns it to company. If the exchange rate falls or increased, then company books it as gain or loss to comany. How the same can be handled in Travel Expense Report. Below is an example of the same.
    USD
    Exchange Rate
    INR
    Advance taken
    550
    65
    35750
    Expenses claimed
    500
    65
    32500
    Difference
    50
    65
    3250
    But Returned to company in less exchange rate
    50
    60
    3000
    Loss on Exchange
    250
    Regards,
    Daniel

    HI Sigi,
    The problem is, during a International trip. While taking the advance, the exchange rate of USD is something & while returning or excess expenditure the exchange rate is different. Because the posting to be done in INR & the expenses are adjusted against the advance.
    But when there is a change in the exchange rate then the whole advance is not adjusted. SO to adjust the same the balance amount to be adjusted as gain or loss to the company a/c.
    Regards,
    Daniel

  • Employee as a Vendor in Travel Management

    Hi Experts,
    Please guide me about Employee as Vendor in Travel Management?
    Do we need to make employee as vendor for Reimbursement Payments.

    Thanks Cheyu..
    I am putting up my Understanding please correct me if i am wrong.This process is followed for Payment of Reimbusrsement amount to FI.
    Employee has taken advance & his actual expenses are beyond advance amount taken.
    First employee as a Vendor to be created BY HR Administrator.
    HR Administrator will create a Posting Run PRFI to create posting run( Do i need to create wagetypes for this)
    Transaction PRRW to create posting in FI- Activiity is done by HR Admin
    FI documents are created, there is a debt on supplier account so it must be paid. Payment is done by transaction F110 by FI guys.- This carried out by FI Admin.
    I believe this is the Process for Payment by FI to Employees
    Please guide.

  • Problem with Per diem calculation in Travel Management module

    Dear ALL,
    We have configured Travel Management module in SAP and we have an issue with per diem calculation, viz.,  whenever we add an additional destination in the trip (T.code TRIP). 
    Ex: Employee's travel plan from 10/8/2011 (06.00 hrs) to 13/8/2011 (06:00 hrs)... in 24 hrs format.  When the employee goes directly to one destination and coming back, the per diem calc is coming right.  i.e., per diem amount for 3 days. 
    But when we add additional destination between the trip period-  viz.,  either 10th eve (18.00 hrs) or on 11th Aug-  the per diem calc is being done by system for 4 days instead of 3 days only.
    In otherwords, for every additional destination in the itinerary, one extra per diem is being calculated (when we simulate in T.Code: PR05)
    Would appreciate guidance ASAP.
    Regards,
    Santosh

    hello,
    I am having similar kind of problem can you please share your solution
    Regards
    Sarthak Arora

  • TRAVEL MANAGEMENT and ESS help required

    Hi
    Can anyone help me how to configure TRAVEL MANAGEMENT and ESS in IMG
    Please help.
    Regards
    Sonu

    Hi duxten,
    That is fine but how you will suggest me to go ahead, as i am configuring fo the 1st time so what are the steps i need to follow.
    Please can you suggest me.
    Thanks
    Sonu

  • Close a trip in Travel Management

    Hi, team,
    I have a question about travel management. In PR05 there is some trips that the user'd like to close without FI posting. But no deleting or cancelling the trip, only close it. Is it possible? Thanks a lot and regards, L

    Unfortunately this is a limitation of the backend functionality because the REGION field was a new functionality starting ERP2005 in Web Dynpro, and this field is only available in FITVFELD_WEB. The field was integrated with the "Country" field in Web Portal. The customising point for Travel Request was also added in Portal which as you see is not available in FITVFELD.
    And when you create expenses for the request, the REGION field can be input manually, the value is maintained in Table T702O.
    So as a standard solution so it is not possible without making a modification
    I mentioned modifying the table PTRV_T706Z_FLDS but actually just reading it again I dont think this will work for TRIP in this manner.
    Edited by: Sally Redmond on Dec 13, 2011 12:10 PM
    Edited by: Sally Redmond on Dec 13, 2011 12:11 PM

  • Blank Tax Code in Travel Management

    Hi all,
    Is it possible to define a blank tax code (no tax input) in Travel Management? It is a required field in the config and I can't seem to leave it blank. My FI consultant is telling me that it is a SAP standard where if it is blank it means there is no tax input.
    Please help.
    Regards,
    Eric

    Hi,
    I can't select "no input tax" from V_706D_B as I also have some expense type that have input tax. According to my FI consultant, a blank in the tax code means it is not applicable to tax. But in Travel Management, I cant put in a blank in the tax code. Is there a way to put blank for the tax code or I have to define a "No Input Tax" tax code?
    Regards,