Hi,
I have this error with the tx. MC89
"Date 01.11.2005 comes before start of factory calendar with ID A1"
Can someone help me solving these error please?
Regards,
Yolvi
Edited by: yolvisoft on Nov 19, 2010 10:53 PM

Dear Yolvisoft,
Welcome to SDN !
Check this link
[12/01/2009 date lies before start of factory calendar. (Please correct).;
Regards
Madhu

Similar Messages

  • Factory calendar in project differs from plant factory calendar

    Hi Experts,
    When i enter the plant name in project definition and save it at once, am getting the following error message,
    "Factory calendar in project differs from plant factory calendar
    Message no. CJ707"
    Its not allowing me to save the project at all. I am able to only cancel and come out of the project.
    Please advise.
    Thanks & Regards,
    Kabir

    Hi Nitin,
    Thanks for your reply.
    The Issue is solved. The PP guy had defined a customised calendar for the plant. Then i had matched it with the same in Project Profile.
    Regards,
    Kabir

  • Factory Calendar issue in creation of Sales Order/ Delivery Order

    Hi all,
    There is one issue. Our user is not able to create Sales Order/ delivery order as he is getting the below error message u201CDate 2010-12-27 lies after the end of Factory calendar F1u201D. But when I checked the plant in customization, the Factory calendar assigned is u201CKRu201D and not u201CF1u201D. So I donu2019t understand why this error message is appearing. But when I checked Factory calendar u201CF1u201D, it was valid only up to 2010 and there are special rules also set. Only few days in the year are working days. Factory Calendar u201CF1u201D description says u201CKOR customers billed on the 25th of every monthu201D
    Please advice.
    Regards,
    Brijesh

    Dear
    If F1 is the correct calander , then goto OP03-Calander Maintenece -select the Holoiday Caleneder  and extende the Valaidity till 2020 and also Select the Factory Calander  do the same till 2020 .Now Goback to main screen of OP03-Plant asisngement -re-assing the same F1 calaneder .
    Secondly check the factory calender of the plant in OX10.Then in SPRO > enterprise structure >Definition > logistic execution>define shipping point .Select you shipping point and assgin the proper factory calender
    .Goto OVX5 , choose your sales organization, click on details, Detailed information tab - Sales Org Calendar (maintain your factory calendar here not Sale Org Calander )
    .Check in VOV8, use the "Propose delivery date" and "Lead time in Days" options to default today's date as the requested delivery date.
    Refer : Public holiday dates issue
    Regards
    JH

  • 61 062 & date comes after end of valid factory calendar. (Please correct)

    Hi Experts,
    I am Getting the Error in Creating Purchase Order:
    Error Message No. 61 062 & date comes after end of valid factory calendar. (Please correct)
    Please suggest.
    Regards,
    Ashok

    I got a Solution For this. Actually User has Maintained Wrong Planned Delivery time in PIR for the Same it was Behaving like that.
    Thanks

  • Maintenance Order & Factory calendar

    Hi,
       How to Link Maintenance Order & Factory calendar so that when i execute the 'Cost Evaluation' table
    S115, i will get cost for the maintenance order Activities for specified month based on factory calendar.
    Pleaes Let me know.

    PeteA,
         When i execute the maintenance Order in table S115 with input data fiscal year variant (Calendar Year 4/4/5) , Order type & Month (say 02.2009) system throws message "No table entries found for specified Key" .....
    But when i execute the same table with all input data except fiscal year variant (Calendar year 4/4/5), system gives the output of my order type.
      So i think Fiscal year variant should be maintained in Order. That procedure i want to know
    (Note: In Work center "Capacity' Tab, we can only assign the factory calendar; Not fiscal year variant(4/4/5 year)
      Pls let me know

  • Deliv. date outside period covered by factory calendar IN

    Hi Experts,
    I am trying to create Purchase Order with 2011 year delivery date system is showing bellow issue in production server.
    Deliv. date outside period covered by factory calendar IN
    Message no. ME078
    Please advice me how can i overwrite this problem immediately.
    Thanks in advance,
    Chandhu

    Dear Experts
    I tried the method which mentioned above, but when I tried to change the Valid Fr. Year 1996 to Year 2011, it probe me the message "Please enter validity area between years 1995 - 2010." and I wasn't allow to save.
    Pls advise how to solve the above problem.
    Thanks.

  • Date is outside the factory calendar range

    I am trying to run a BW query. When I click on the calnedar icon field. It gives this error.
    Error: Date is outside the factory calendar range
    Msg No. FK884
    What could be the problem in the query? Has anybody had the similar problem before? I tried to search in SAP notes and could not find anything close to this.
    I will  Appreciate your help. Thanks a lot.
    Abhi

    Hi Abhijit,
    We got the same error message in 2010.
    1) Check in transaction SCAL that the Factory Calendar ID 01 (i.e. German) is valid to 2009. This explains the error message.
    2) Found SAP Note 1136142 about the configuration of default factory calendar ID of F4 Help and hierarchy for Time-characteristics in BI 7.0.
    SAP Note Solution:
    The key figure attribute obtains its value from the default work calendar as it is maintained in transaction RSRHIERARCHYVIRT (General Settings -> Default Factory Cal. ID).
    This setting is valid across the entire system and does not permit any variable selection of the factory calendar for each query.
    Furthermore, a value for 0NUMWDAY is calculated only for the period in which the default factory calendar is valid.
    3) Check in transaction SCAL that the Factory Calendar ID of our location is valid to 2050.
    The problem is solved after changed the Default Factory Cal. ID from 01 to the ID of our location in transaction RSRHIERARCHYVIRT.
    Regards,
    Ricky

  • BEx variables: Date is outside Factory Calendar Image

    Good day
    A user received the following message when selecting the inpiut help for a date variable for a CRM query:
    " Date is outside Factory Calendar Image"
    I have checked tcode SCAL and noticed that the factory calendar for South Africa = 1996 to 2010. I checked the CRM source and their factory calendar is the same. In the mean time I have transferred the global settings for SAP DNI (parts) into BW and the factory calendar setting for South Africa now shows 1996 to 2015.
    Problem is that the CRM query still shows the same error message.
    Question:
    1) Should factory calendar settings for all SAP sources (Modules i.e. CRM...) be imported into BW, or is there another setting that I must check?
    Thanks in advance.
    Cj

    This is what I have done:
    Whe have the following R/3 modules (source systems in BW)
    SAP DNI
    SAP dFM
    SAP CRM
    SAP SRM
    etc.
    (Tcode = SCAL, selected 'factory calendar', selected 'rebuild tables')
    Firstly I have transferred the global settings for SAP CRM (as the BEX query is from CRM). Their factory date was 2012. This did not solve the problem.
    secondly, I did SAP DNI, their factory date = 2015, this also did not solve the problem.
    I then transferred the global settings for SAP dFM, our main reporting module, their factory date = 2020. The problem was solved.
    Seems as if only ONE of the modules depicts the factory calendar date for BEX.
    I have rested this again and only SAP dFM global settings rectified the BEx display problem.
    Hope this helps?

  • Company factory calendar validity error

    While maintaing Delivery schedule , when i entered year 2010. Then got the massege
    Delivery date outside period covered by factory calendar .
    Error Message no. ME078
    How to solve this ?

    Hi,
    Can u please Check what is the validity Period maintained in factory Calender? and your Inputs in Schedule lines?
    SPRO=> SAP Netweaver => General Settings => Maintain Calender....
    if its 2010 Please extend it to Max till Date your company purchased the License of SAP.
    Regards,
    Ninad Kshirsagar

  • Factory calendar doesnt exist

    Hi,All........
    We are creating production order manually with matrl, Prod. Plant and order type as input...When we  enter required quantity for Production and finish date as we are using Backward Scheduling.
    The system throwing a messgae that factory calendar Z3 does not exist.
    Message no:co034......
    Pls guide me to resolve the issue.
    what needs to be checked in the system.
    Rgds,
    Yogesh.....

    Hi Yogesh,
    It seems that you have assigned the factory calendar Z3 to plant or to the workcenter used in the routing for the material.
    This customizing you may have carried forward but probably you have not carried the factory calendar Z3 customising to the client where you are trying to create the order.
    Hence create the factory calendar in customising (SCAL-Tcode) in the client you are working.
    I hope this will help resolve your problem once the factory calendar has being defined in the client you are working.
    Thanks & Regards.
    Santosh Joshi

  • Factory calendar error (returncode = 3)

    Hi,
    I am trying to create planning for product group, but getting error Factory calendar error (returncode = 3)
    Message no. MA408
    I have checked the validity for factory calendor but it is found ok with valid upto 2013. and allocation of factory calendor with plant 1000. the same factory calendor with validity is observed.
    Pl help me out of this issue.
    Regards,
    Anil

    Dear,
    Please check  have you maintained different factory calendars in the customizing for SOP (Transaction MC7F for S076) and for the plant OX10.
    Please use same calendar in MC7F. and check again.
    Regards,
    R.Brahmankar

  • Warning of " Date of  outside  the factory calendar Range"

    Hi Experts,
            I have created a variable  of ocalday,It is taking  # values and it showing warning " Date of  outside  the factory calendar Range".How avoid this warning.Actually intially in the one of infocubes carries the # value for 0calday, now we have deleted it, even then  it taking # values and showing same warning.I have check at variable it doesnt carring any default value.Now to delete the # values from variable so that it should not show any warnings.
    Can any body suggest me any thing.
    Thanks
    Vinod

    Hi Srinivas ,
       Thank you very much for your reply.There is # value in the master and transaction data.Even im not able to suppress this message.As it indicating a msg no 884 which is not there message list in RSRT.
    Can you suggest me any other thing.
    Thanks
    Vinod

  • In VL10A tcode after execution in section scr "Incorrect factory calendar"

    Hi,
    After execution of the tcode VL10A gives the information messge in the selection screen as
    "Incorrect factory calendar; date calculation not possible".
    How to remove this informaition message.
    Thanks,
    Sanjay

    Do check with your FICO people and they will be able to help you to check on the factory calendar problem.

  • How to extend factory calendar

    Hi,
    We need to do extend our factory calendar before we
    update the time stream. Our factory calendar
    only up to year 2010.
    Kindly please advise how to extend the factory calendar?
    Thank you.

    Hi Harish,
    I try to change the "To Year" from 2010 to 2020, but there is an error message coming out and does not allowed me to change: "Please enter validity area between years 1998 - 2010".
    Kindly please advise. Thank you.

  • Factory calendar error in service order

    Dear Guru's
    could any body help me in solving the below issue.i created the service notification in iw51 after that i clicked the service order tab then system gives the pop up mesage in that i mentioned order type,planning plant,business area,main work center after that i got the below error.
    Date 09.09.2011 is after the valid factory calendar period
    Message no. IW432
    Diagnosis
    You entered a date for which the factory calendar was not maintained in your factory.
    System Response
    Processing will not be continued.
    Procedure
    Enter a valid date.
    If you want to use the date rejected by the system as a valid date, you must maintain the factory calendar in your system with the help of the Customizing function:
    Proceed
    If you are not allowed to perform the function, contact your system administrator.
    from which master data system is picking the Factory calendar.
    how to solve the problem.
    Thank you in advance.
    suribabu.

    Thanks to every body.i solved the problem.