Typical Planning Scenario

Hello
My client have the following scenario
1) They wait to produce the orders till the orders are accumulated and full capacity of workcenter is reached, then they execute the orders in a single or multiple joborder.
for Ex.    xxxx10 material   50000 qty,      yyyy10  material   50000  qty,
              xxxx11 material   35000 qty,      yyyy11  material     5000  qty,
              xxxx12 material   25000 qty      yyyy12  material     5000  qty,
              xxxx13 material     2500 qty,      yyyy13  material     5000  qty,
             xxxx14 material     3500  qty,      yyyy14  material     3500  qty,
             xxxx15 material     5000  qty      yyyy15  material     5000  qty,
Then they plan such a way that the production is continued with a product mix of different material so a min joborder quantity is maintained in each joborder.
can anyone please suggest a better scenario to map the requirement as client is very particular and want to run this scenario as this suits their requirement.
regds
Venkat

Hi,
You can Use capacity planning for this, Capacity evaluation should help you.
You can check the capacity available against work center and capacity occupied.
You can then also see precisely the no,. of orders and Which orders are getting planned against this work Center.
Regards
Raghu

Similar Messages

  • Reduction of PIRs in Production lot planning scenario is not happening.

    Hello Experts,
    I am facing the following problem:
    I have a Production lot planning scenario. I have done all customizing and master data maintenace as described in SAP Help for realizing the scenario with transfer posting to plant stock (req class 092).
    However my PIRs wich are assigned to the specific production lot are not getting reduced after the transfer posting to plant stock. I need your help to resolve this problem.
    Thank you in advance for your input.
    Best regards,
    Nikolay

    Hello Satyajit Kumar,
    Thanks for your reply.
    The movement type that I use is 411 "Q" and the WBS is the correct one, but PIR still remains unreduced. Please advise.
    Best regards,
    Nikolay

  • Allow alphabetical to be inputted in key planning scenario (RM61L-PLSCN)

    Dear Expert,
    As i know, now i can only input numeric /number for key code planning scenario in MS31. the challenge is how if I have used all the variant numbers as the system allows 3 characters only for planning scenario code.  The only way I can think is by using alphabetical  ( a -z). can we change the system setting to allow the alphabetical to be inputted in planning scenario code/ key?
    Thanks
    Pauline

    Hi Mario,
    Thanks for your reply,
    How about if I add to 4 characters, means i can have up to 9999 scenarios with numeric. we have our own reasons to use all the 999 scenarios, example here:
    106 - for january 2006
    206 - for february 2006
    and so on...
    Thanks
    Pauline

  • Typical modeling scenario

    Experts,
    I am facing very typical modeling scenario which is mentioned below, in which result for the same data needs to be change based on user input.
    Cube data is:
    1st Row:
    Subscriber   =   S1
    Order No.   =   1001
    Valid from   =   01-Sep-2009
    Valid to    =   31-Dec-2009
    Renewal Flag   =   u2018 u2018
    Renewal Order   = u2018 u2018
    Count = 1
    2nd Row:
    Subscriber   =   S1
    Order No.   =   1002
    Valid from   =   01-Jan-2010
    Valid to    =   31-May-2010
    Renewal Flag   =   u2018Xu2018
    Renewal Order   = u20181001u2018
    Count = 1
    Second row is the renewal order after 1st subscription expiry date.
    Now in the report user wants to know lost subscriber based on period he enters for e.g.
    User can enter date range/Months/Years, so if he executes report for Year 2009,
    Number of lost subscriber = 1. (based on 1st row.)
    But if user executes report for year 2009 and 2010 out put should be,
    Year                       2009  2010
    Lost subscriber         0        1
    Because he got renewed immediately hence not considered as lost.
    Consider the data in million and user can execute report for about 4 Yrs together. And I can not store the number of Lost in cube at all because same row has two different answeres for two inputs.
    Currently I have fixed it using Virtual cube, but I am afraid of performance.
    Any suggestions?
    Thanks in advance!

    closing

  • Typical business scenarios for SAP ME demos

    Hi,
    Can somebody comment on some typical business scenarios / applications for building demos in a SAP ME sandbox environment?
    Regards,
    Chanti.

    Chanti,
    A while ago there was some document on SMP next to ME Installation and other guides. It is called "SAP ME 5.2 Business Scenario Description". However, for some reason I can't find it there anymore. You migth ask Consulting service about it.
    Regards,
    Sergiy

  • Career planning scenario in the PD module

    Hi Experts,
    I am doing the Career planning scenario in the PD module.
    While we create a career plan, growth of the employee in org unit, can the no. of years of experience in the organization be included?
    If ,for ex., the career plan path is built with the various positions hierarchy in the org unit starting with the lowest level, then is there any way to depict that the employee should have an exp of 3 years or so to aquire a higher position in the path ?
    Please guide me.
    Thanks & Regards,
    Vijetha

    Try this out
    after career development is made
    go in change mode
    and in path if u double click the job / position u created it will pop-up the  Maintian duration
    u can give years / months as u wish
    with regards
    partha
    keep learning and sharing

  • Different planning strategy in defferent planning scenario

    Hi ,
    Is anybody can explain me how can use different planning strategy in different planning scenario ?
    Thanks !

    Hello Denny
    Planning strategies represent the business procedures for the planning of production quantities and dates. A wide range of production planning strategies are available in the SAP R/3 System, offering a large number of different options ranging from pure make-to-order production to make-to-stock production. Depending on the strategy you choose, you can:
    Use sales orders and/or sales forecast values to create the demand program
    Move the stocking level down to the assembly level so that final assembly is triggered by the incoming sales order
    Carry out Demand Management specifically for the assembly
    <b>Choose a make-to-stock strategy, if:</b>
    The materials are not segregated. In other words, they are not assigned to specific sales orders.
    Costs need to be tracked at material level, and not at sales order level.
    You should always use make-to-stock production if you produce stock independently of orders because you want to provide your customers immediately with goods from that stock later on. You might even want to produce goods without having sales orders, if you expect that there might be customer demand in the future. This means that make-to-stock strategies can support a very close customer-vendor relationship because your objective here is to provide your customers with goods from your stock as quickly as possible. Returns that have passed quality inspection and other unexpected goods receipts can be used for other sales orders.
    This does not mean that you have unreasonably high stock levels. You can avoid them by doing one of the following:
    Create a production plan in advance (in Demand Management) to plan your stock.
    If you make use of this option, you may also want to decide whether sales orders exceeding your plan are to affect production or not.
    Receive sales orders relatively early on (using scheduling agreements, for example).
    <b>Choose a make-to-order strategy, if:</b>
    The materials are segregated. In other words, they are uniquely assigned to specific sales orders.
    Costs must be tracked at sales order level and not on material level.
    reward if it is useful
    thanks
    kedar

  • Problems with planning scenarios

    Dear all
    I've a huge problem with the scheduling of a project. I hope I can explain it properly.
    I've created a project with some networks in it. The planning scenario is free scheduling and strict bottom up. I'm using the backward scheduling.
    Some of the networks, which are connected with the "Main" Network now are not scheduled properly. For example I have an acitivity in the "Main" network which is connected with a FS relationship to an activity (this activity has set up a constraint earliest possible) of another network. When I'm carrying out the scheduling this activity is planned much later than the activity in the Main network. In some other similar networks the scheduling is carried out regurarly.
    Now, when I'm changing the planning scenario to bottom up, canceling the start date in the network of concern and making a new scheduling of the whole project, the activity is placed in the right period. When I'm changing back the planning scenario and rescheduling the project once more, the activity is again postponed, even further in the future than before.
    is somebody out there who is able to help me?
    many thanks

    Hello
    is nobody out there who could help?
    Best

  • LONG TERM PLANNING-pLANNING SCENARIO

    Hello friends,
                       I am using long term planning and creating a long term planning scenario.
    Where the version created of PIR is allocated to the planning scenario?how? give me the steps..
    regards,
    Ajay

    In MS32
    folow the menu path
    Edit --> Pl ind requirement
    in the pop up  screen, enter the varsion you have created for LTP, leave blank vsrion to be replaced... and click on confirm..
    it will asign the PIR version to LTP.

  • General Cost Center planning scenario

    Good day house, I am wondering if the general cost center planning Best Practice scenario can be used for planning for fixed asset cost considering that only primary cost elements are included in the download for update.  Can this scenario serve this purpose? If yes, how considering that the cost elements for fixed assets are statistical?

    Hi,
    You can plan on statistical cost elements exactly as you do on real one. Please, specify your question...
    Regards,
    Eli

  • Clarify on this Cost Center Planning Scenario

    Folks,
    Would appreciate inputs for the following scenario that I am attempting in overhead planning
    In the planning layout I need to enter proposed budget for the various cost elements
    The cost element is master data; the requirement is against the cost element I would require another column which is the cost element description; description is maintained in the text table; description is not identified as an attribute in the cost element characteristic
    How can I add description along with the cost element code
    1. Do clarify whether this is feasible only if the description is identified as an attribute
    Thanks for your time
    Regards
    Ramesh

    Hi Ramesh,
    For getting the cost element description alongwith the code, go to Change Layout
    1. In the layout you would be having Cost Element as the Lead column on the first screen, select the type of text you would like to be displayed for the Cost element here i.e. Short, Medium, long
    2. Continue and go to the second screen of the layout.
    3. Go to the Lead columns tab here.
    4. Select the Display option here for "cost element" here as Key/Name and you will be able to see the description alongwith the cost element code
    Hope it helps.
    Cheers
    Anurag

  • Typical business scenario

    we have a typical scenario if any one has encountered with the same problem please post ur views
    Std Ord. 2640856 / 170     
    . std delivery - FC 52986652 / 10      
    .. Shipment 252438 / 1                 
    .. WMS transfer order 2000251805 / 1   
    .. GD goods issue:delvy 4907877393 / 1 
    .. Std Invoice  3905256477 / 170  
    ... Accounting document 800250867      
    .. Cancel. Inv. ZIV1 3905256486 / 170  
    ... Accounting document 800250875      
    .. RE goods deliv. rev. 4907891378 / 1 
    .. GD goods issue:delvy 4907900924 / 1 
    .. RE goods deliv. rev. 4907901398 / 1 
    we have raised a sales order for 17 line items where the cnd record  was maintained in the combination of customer hierarchy.but of all the 17 items only 1 item price has come properly The user has some how delivered one line item where the price was properly picked and shipped.
    the problem is our shipping process is through online.where we cannot revert back the shippment
    after some time they realised that defective price in sales document and reversed the whole scenario.
    now the customer hierarchy should pop up in the sales order so that price picks up automatically.
    we have even tried to enter the customer hierarchy manually, but it is not taking.
    please throw  u r view as how to over come this issue

    closing

  • MSS: Compensation Planning Scenarios (deselect users u00BF?)

    Hello
    we are using EP NW2004s with Manager Self Service Business Package for ERP 2005.
    We have a problem in Compensation Plannig scenarios.
    When we clic on the iview, we see ALL employees selected (check box on the left hand side are selected)
    What we want is when accesing Compensation planning iview, display employees with check box unselected.
    Do you know how to do it¿?
    any parameter on ivew¿?
    thanks and Regards
    Noemi

    Hi John,
    Did you check with OSS? We have ECM up & running and completed two annual merit cycles in MSS. Never had this issue..
    Regards,
    Suresh Datti

  • Personnel Cost Planning Scenario documentation..

    Hi all,
    If anyone of you have done Personnel Cost planning..then I will really appreciate any kind of documentation on it It will help me greatly as a reference as we are starting a new project on the same.
    willinuk "at-the-rate" gmail.com
    Help much appreciated,
    Rgds,
    Wills

    Hi,
    Try this.
    Personnel administration
    http://help.sap.com/saphelp_nw04/helpdata/en/63/351e3c6a2fc036e10000000a114084/frameset.htm
    HR pre configured scenarios here.
    http://help.sap.com/bp_biv170/
    https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/505351fe-ec8c-2910-c5b5-a43bbf53f6fc
    Thanks,
    JituK

  • Typical sales scenario

    Hai All,
    My client belongs to manufacturing industry.
    their order process is as follows:
    customer place for RFQ (req for quotation , we ll consider it as Inquiry ), Client wont maintain any Inventory in Plants. Based on customer order, material will be transferred for production.
    but in some cases, ( at the time of dispatch customer have an option to choose specific qtty to receive,where as production is already done.
    eg: customer order- 2000 EA, prod-2000 EA, at the time of dispatch customer revise his order to 1500 EA,the same will be deliver to the customer. the remaining qtty will be stored in Inventory i.e.500 EA.
    now when the other customer places order for the same material say, 1000 EA.
    System has to deduct the inventory stock and for the rest has to go for production.
    Can someone give me MTO document Flow, starting from sales order
    my doubt is:
    1) This can be done through MTO- will use the item cat group in Material master , by the item cat det'n system .
    but how would the system consider the inventory stock also.
    2) customer places req on last week of current month (for which he req's next month, its monthly req ) & at the same time he will place 2 more req's for next 2 months ( which is called "tentative schedules") ,but the production dept has to produce next month req completely & 80% of the tentative schedules.
    How this will be addressed?
    plz clarrify,

    Manufacturing does not work that way. Even in the case of MTO, orders which are  requirements are cumulated every day, week, fortnight or month. Based on this a production plan is drawn up. Please remember there is a sourcing lead time for the raw materials for the finished product and it ca vary from a day to three months if the material is imported.
    So how does one have a plan. Sales order plan is the basis on which estimates are made and production plans are made. Again it also depends on the working capital cycle in real time as well as to how far you can plan given the specific nature of the product.
    But lets consider that the company has fairly large orders which is the reason why he is going in for SAP. How can one determine whether a customer is going to pick up 505 of the goods or 60% or 100% Unless you have some historical data,
    Either way Availability check and TOR in SAP takes into account all these eventualities and it cumulates the requirements with the stock available and generates exactly for the difference. This is standard SAP behaviour.
    regds
    Jude

Maybe you are looking for

  • I'm can't get iMessage to work with all my Apple devices.

    So i cant seem to get iMessage to work across all my Apple devices. My wife and I use the same Apple ID but have different phone numbers. Is there a way to get all our messages on our shared devices and our personal messages on our phones? (iPad, iMa

  • Two Accounts - Want to delete my acc

    Hi, I have two skype account. The one I have problem with is the fact that I link it with my Microsoft account, and now unlink it...so I can't log in and wants to delete my account..please help

  • E63 - Mail sound notification

    Hi, is there a way with the E63 so that after a mail comes in, it doesnt sound every few minutes. Its very annoying specially if a mail comes during sleep hours. Thanks in advance!!

  • LAST Aggregation and AGO Function in OBI Administration Tool

    I'm struggling a bit with the AGO function and LAST aggregation. The problem is when I try to compare balance from the last day from last month compared with last day of this month. To get the balance of the last day of this month, I'm using based on

  • FW8 - turn background color into gradient?

    Is there any way to turn the background color into a gradient. Right now I'm making a box the size of the canvas and coloring it with a gradient and then sending it to the back. I thought in the older version of fw there was a "more options" selectio