UD at operation level

Hi,
Is there any possibility in standard SAP for UD to be given in in-process inspection at each operation level of production?
Please answer.

You can use the functionality Operatoin Complete.  This is available in 6.0, maybe a version earlier.  Can't remember when it came in.  You'll find the config set up under,
QM-->Quality Inspection >Resutls Recording>Make Settings for Operatoin Complete.
It will allow you to assign the selected set of UD codes to the inspection type/plant combination.
This functionality has not integrated functions in SAP at this time and is primarily information only.  But you could use user exits at various points and custom programming to check that operations are complete before performing other actions in the system.
FF

Similar Messages

  • Standard Report for missing parts at production order operation level?

    Hi PP Gurus,
                We have standard report for missing parts at production orders level.
    For our client, they need a report for missing parts analysis at production order operation level. Do we have any such standard report in the SAP?
    Please help.
    Thanks,
    Reddy.

    Hi Arvind,
          Thanks for for your response.
    1. List: Components,  Layout: Standard layout          set the Missing part
           It shows the component requirement/withdrawn  quantity for each operation of production order. It is not showing the commit quantity.
    2. List: Components,  Layout: Pick list          set the Missing part
           It shows the component requirement/withdrawn  quantity for each production order.
    3. List: Components,  Layout: Missing Parts List-Material View          set the Missing part
           It shows the component requirement/commit quantity for each production order. It is not showing the commit quantity at opertion level.
    4. List: Components,  Layout: Missing Parts List-Order View          set the Missing part
           It shows the component requirement/commit quantity for each production order. It is not showing the commit quantity at opertion level.
          We are unable to get the solution from all these 1 to 4 reports from COOIS.
    Do we have any option to change the existing layout (ex: 3 ) to get the commit quantity for operation with missing parts indicator?
    If avilable, what is the procedure to be followed?
    Thanks,
    Reddy.

  • PM: change all Orders from sub-operation to operation level

    Hi Folks,
    I've a requirement to change all PM-Orders from Operation-SubOperation to only Operation Level.
    Example:
    Op SubOp --> New Op   (no subOp)
    10__10__-->____10
    10__11__-->____11
    10__12__-->____12
    10__13__-->____13
    10__14__-->____14
    20__10__-->____20
    20__11__-->____21
    Does someone here know, how I can make do this in an easy and save way?
    The only way I see is to make an own report with calling BAPI BAPI_ALM_ORDER_MAINTAIN.
    Have someone another solution
    - SAP-Standard-Report?
    - LSMW?
    Regards

    Hi Raghu,
    Many Thanks for your quick reply.
    Okay ... no LSMW.
    And also no Standard-Reports?
    Do you think, making my own program is the best way?
    Regards,
    Daniel

  • User status at operation level

    Hi,
    I have created one user status profile and attached in order type. In this profile I have included Operation and Order header as an "Allowed object type"
    My problem is when I am changing  user status at order level , it is not getting changed automatically at operation level.
    Pls suggest me the solution.
    Thanks

    Hi,
    I dont think it is possible .
    A suggestion not sure if it works .
    Assign user status profile operation wise and then have some development to check the operation status and
    then update production order status with same user status you mentioned in operation.
    FM: STATUS_CHANGE_EXTERN will help you to change the user status of order.
    Regards,
    Vishal

  • BAPI to change data at operation level

    Hi,
    I have this requirement:
    I need to change data at operation level, more particularly Person No (PERNR) by using a BAPI.
    Is there any BAPI - in which I can pass the basic data (say Order data and Operation data) and change the PERNR for it.
    The name of the BAPI and its usage will help.
    Ankur

    Hello,
    Assuming you are talking about maintenance or service orders, you can use BAPI_ALM_ORDER_MAINTAIN. See function module documentation from SE37. The structure BAPI_ALM_ORDER_OPERATION contains PERS_NO field.
    -Paul
    Please use Enterprise Asset Management (EAM) forum for PM/CS specific topics
    Enterprise Asset Management (SAP EAM)

  • Error in operation level result recording

    Hi,
    I need held; result recording of inspection type =03 (operation level Quality inspection)
    A product manufacture via three operations (10, 20, 30)
    All operation quality inspection active let operation no-10, all products reject and confirm as rework.
    Next operation level quality record is done but confirmation not allow Reason is operation -10, rework quantity, (Actual quantity is more than planned quantity)
    How to add the quantity after reworks for next operation quality inspection?
    Pl helps me finding the solution.

    Hi,
    As per your more clearence , As per Example  production order Quanity =1, passes 3 operation10,20,30
    Operation=10 require rework as per quality ,
    Operation =20 system raise the error message = Operation =10 rework .
    If want to operation =10 ok Quantity =1 then system raise error messges =Actual quanity more than planned Quanitity
    ( 1 Rework + 1 Ok ) .
    Supose rework order create and confirm then next 20 & 30 operation how complete .
    Real scenerio :- Rework on operation =10 then again Quality check then goes to 20 operation Quality check pass / Rework if rework then again quality pass then goes to next operation level
    I hope under stand my problem
    Need help- please

  • Cannot attach documents at order operation level in PM order.

    Hi,
    We have recently upgraded to EHP6 and I have activated the EAM business functions including LOG_EAM_CI_6. In my PM work order, on the Additional Data tab, I can see the "Document Assignment" section at the bottom. Here I attach an existing document and choose Assign to Order. Then I attach another existing document and choose Assign to Operation (0010). After saving the order if I go back into it (IW32/IW33). the document assigned to order header is still there but the document attached to the operation disappears.
    I have defined the document type that I am assigning at header level and operation level in Customizing for Cross-Application Components under Document Management --> Control Data --> Define Document Types. I have also specified in Customizing that the assignment to objects PMAUFK (order) and/or PMAFVC (operation) is allowed for the document type of those documents.
    Can someone please advise what's wrong here ? I have to attach/assign docs to operations.
    Thanks,
    Sandy

    Hi Sandy
    Can you please make sure two things:
    1) IMG --> DMS --> Control Data --> Define Document Types --> Select Doc Type ---> Define Object Links. It must be something similar to this one. Without entering CREATE DOCUMENT settings, you may not be allowed to attach a document. That might be causing the issue. If you do not want from within IW31, someone is creating documents then make sure this setting has value =2.
    One more possible reason for this is 1:n field in this same setting. If 1:n is not selected, please read the help for that field and make sure the uniqueness of your document attachment to objects.
    2) IMG --> DMS --> Control Data --> Maintain Screen for Object Link
    For this one make sure that you have a screen entry for PMAUFK and PMAFVC.
    Now if attachment does not work, try creating a document and let us know what is the error message.
    And do you know that there is another way of attaching documents to the operation which is attaching them as PRT. Just select the operation, click on PRT button and select document and attach it.
    I hope this will help.
    Regards
    Savas
    Message was edited by: Savas Yazici

  • In process inspection - Rejection Booking at operations level

    Hi All,
    Need some help regarding inporcess inspection.
    As we aware about '03' insp type is not stock relevant
    The requirement is , i having operations are like 0010 ,0020 ,0030 ,0040,0050 in Production order in Routing
    Now while operation wise confirmation i want to book the rejection and that needs to get effect on further operation confirmation.
    For example : Suppose I have confirmed 50 TON against operation 0020 , hence at the time of confirmation 0020 i want to book the rejection 2 TON
    Hence while confirming 0030 system should not allow to cofirm 50 TON , system should allow to confirm only 48 TON through CO11N and Some where that rejection has to be display in report.
    Is there any provision in standard to enter rejection at operations level.
    Stock posting not required , Only qty tracking required like operation wise confirmation.
    Please advise to make this scenario success.
    Thanks,
    Abhishek

    Hi Abhishake,
    As in inspection type 03 lot you dont have stock posting option, you can scrap the rejected material operation wise in CO11N at the time of confirmation (Mov Type 551).
    As scraped material will no more in system, you can also look forward for bi-product assignment in bom if you don't want to go with first option.
    Also you can check for early lot creation if can solve the purpose, as in this case you will get inspection lot of inspection type 04 at the time of release of production order and stock will be adde to quality inspection as you do confirmations operation wise.
    Regards/Rohit

  • Printing the Pick List at operation level

    Hi all,
    Is  it possible to Print the Pick List at operation level.
    Components are assigned  to each operations and release of  production order takes place at operational level. Once operation is released then only relavent component assigned to that particular operation should come in pick list.
    Thanks in advance for your time and efforts.
    Regards,
    Siva
    Edited by: Siva Kumar M on May 19, 2008 3:40 PM

    Hi ,
    System will not select the Opertaion which has status CRTD by default.
    For further selection please try with below settings. ,
    Profile = std profile
    Production Order Number,
    Selection at Operation level
    System status = CRTD  and Actiavte Excl .check box.
    Now system will display the pick list for  released operation and it`s component only 
    Please check, Reward if it is useful.
    Pradeep
    Edited by: Pradeep Kumar on May 19, 2008 3:45 PM

  • Release of Production Order at operation level

    Dear Experts,
    Production order to be released at operation level automatically one by one, after confirmation of operation.
    Let us suppose
    Op 10 ...... 10 Confirmed
    Op 20 ...... 10 Confirmed
    then in the Op 30 ..... 4 Qunatity to be released automatically once Operation 20 is confirmaed.
    Please give your valuble inputs
    regards
    Ram Kumar

    Dear Experts,
    Production order to be released at operation level automatically one by one, after confirmation of operation.
    Let us suppose
    Op 10 ...... 10 Confirmed
    Op 20 ...... 10 Confirmed
    then in the Op 30 ..... 4 Quantity to be released automatically once Operation 20 is confirmed.
    How to create trigger point for this?
    Can anybody give clear idea, what all the fields I need to maintain ?
    regards
    Ram Kumar

  • FM/BAPI to update Production Order at Operation Level

    Hi Friends,
    Can any one help me in this issue.
    My rek is, needs to update Production Order Sequence Number(AFVC-CY_SEQNRV) at operation level.
    There are some Production Orders under one Project.User is updating theSequence Numberfor the first order in that group (TCode CO02),at the time of save remaining Orders in that group needs to be updated with the same Sequence Number.
    Please provide me with FM/BAPI(operation level not at header level)
    Points Rewarded,
    Thanks in advance,
    PRBode.

    Prathap,
    Have you tried using the Bapi :  BAPI_PP_TIMETICKET
    This would confirm at operation level..
    Hope it is useful.
    Regards
    Ram

  • BAPI/FM for Confirmation of Production order at operation level

    Hi ABAPers,
    I am using the 'BAPI_PRODORDCONF_CREATE_ACT'for Confirmation of Production order at operation level.
    I am able to pass the Production order number and Active Operation get the confirmation done.
    But the Confirmed Qty is not being updating in AFKO table.
    The 'BAPI_PRODORDCONF_CREATE_HDR' cannot be used for Confirmation of Production order at operation level as there is no Operation/Activity(Vornr) field in the input table. Hence using this bapi confirmation of Prod order can be only at Order level.
    Can someone know any FM/BAPI which can be used for the Confirmation of Production order at operation level(not order level).
    Thanks in Advance
    Ramesh Babu Cikka

    Hi Ramesh,
    Please use FUNCTION 'BAPI_PRODORDCONF_CREATE_TT'.
    This will work as like as T/Code "CO11".
    I hope this will help you.
    Example :
      CALL FUNCTION 'BAPI_PRODORDCONF_CREATE_TT'
        EXPORTING
          POST_WRONG_ENTRIES = '0'
          TESTRUN            = ' '
        IMPORTING
          RETURN             = ZRETURN
        TABLES
          TIMETICKETS        = ZBAPI_PP_TIMETICKET
          DETAIL_RETURN      = ZBAPI_CORU_RETURN.
      CALL FUNCTION 'BAPI_TRANSACTION_COMMIT'
        EXPORTING
          WAIT = 'W'.
    Lanka

  • Operation level not getting auto approved

    Hi ,
    Can anyone help me to make operation level request auto completed in oim 11g R2

    use Identity System Administration console and create new approval policy:
    - select request type
    - set Auto Approval check box
    - select scope
    - set rule (meet your requirement)
    a.

  • Help - Web Service Operation-level (rather than end-point level) policies

    Hi Guys,
    According to the documentation:
    http://download.oracle.com/docs/cd/E15523_01/apirefs.1111/e13952/taskhelp/webservices/ConfigureWSPolicyFile.html
    you can associate a policy at the end-point level, or the operation level.
    I'm wondering if the service implements policy at the operation level, what is required from a client perspective to set SecurityPolicyFeature just for a specific operation?
    Or, does one have to continually keep requesting a new port with the appropriate feature for each operation?
    e.g.
    // operation without policy
    StockMarketPortType port = service.getStockMarketPortTypePort();
    Integer stockprice = port.getStockPrice("ORCL");
    // if ORCL stock price looks good ... :)
    // operation with SAML policy
    SecurityPolicyFeature securityFeatures[] =
    new SecurityPolicyFeature("oracle/wss11_saml_token_with_message_protection_client_policy")
    port = service.getStockMarketPortTypePort(securityFeatures);
    boolean result = port.sellStock("ORCL", 500);
    thanks
    Matt.

    Matt,
    As Bethune mentioned, the WSS implementation that is part of WebLogic does support operation and message-level policy attachments, but Oracle Web Services Manager (OWSM) does not. The SecurityPolicyFeature you reference in your sample is from OWSM. Do you mind sharing any more details about your use case (and specifically why you would have different policy for different operations) that I could share with OWSM?
    In the meantime, your workaround is a good one (different port instances).
    Thanks,
    Ryan

  • Setting field (system condition) required at work order operation level

    Hi everyone,
    I wanted to make 'required' system condition field at operation level, however neither it's available in OIOPL nor in OIOPD..
    I'd appreciate if anyone could suggest something
    Thanks in advance

    Hi Sergey,
    The System Condition field enables you to reserve capacity in Production Planning Work Center so that during any maintenance, Production Planning work center should not be undergoing any production.
    But the system condition that is taken into account for the above scenario is the System Condition field at the header level which indicates whether the maintenance requires the equipment to be shut down or in operation so apart from the header System Condition field, the operation system condition fields do not create any capacity requirement at PP Work Center.
    The Operation Sys Condition field is just for reporting purposes and does not hold any significance in PP-PM integration so for that fact there is no provision for setting this field mandatory at Operation level rather it can be set mandatory at Order header level.
    Best Regards,
    Muhammad Usman Kahoot

  • Why Template, request and operation level approval from 11g?

    Hi All,
    I''m very new to OIM 11g and could not understand the logic behind having three categories of approval workflow, sucn as Template, operational and request level approvals? In 10 g, on the contrary, we can achieve multiple level approval using one approval process against a resource object. Having said that, i think we can also achieve a multi level approval in one BPEL process using the serial or parallel type of approval. So, a single approval process, say request level approval process can be configured to catered to multiple level of approvals. If this is the case, i could not figure out the reason behind the availability of 2 further categories template and request level approval. Can anyone please shed light on the actual usage with a context and also render reference to a 10 g functionality for these approval categories.
    Thanks,
    Srini

    Request Level & Operation Level :
    Re: Difference requestlevel and operational level
    Template Level : It is also same as Request Level where you can reject the complete request in one shot. In latest version of OIM i.e. OIM 11g R2, you won't find this Approval Level.

Maybe you are looking for

  • Looking for FULL SCREEN flash web gallery template

    Hi, I'm looking for a plugin for PS to make full screen flash gallery, something similar to this: http://www.paulvanroekel.nl/picasa/CoolFullScreendemo/index.html anyone know of any? free would also be good Cheers, TBK

  • Http - file - problem with sender namespace

    Hi, We are receiving data via http. When I'm testing the flow throught a http-testapplication everything runs correct and when I look in "monitor for processes xml messges" the namespce is the right one. But when the customer sends testdata via a web

  • OS X not keeping correct file dates

    I have an issue with OS x and the date modified/date created - someone sends me a dvd with a file on it - I drag that file into a folder on my local HD and once it's done copying the file shows the "date modified" as the date that the file was create

  • Steps required in calling Function Module in VC Model

    Hi, How to Call a 'Z' or Standard function Module of BI/BW in VC Application.Could anybody tell step by step or details? Thanks and Regards, A.D.

  • Website payment and shopping cart buttons not working on Windows Phone browser

    A customer shopping on our site notified me that the "add to cart" and "view cart" buttons were taking him to the PayPal main site and not the shopping cart. I tried a Windows Phone at the Verizon store and found the same issue. I have tested the sit