UMB and GBB-BSA after run material ledger

Hi guys,
Last month the user changes in some materials standard-price by MR21. So the user had a debit balance in the 501002002 account (because MR21 uses UMB key of OBYC).
After that the user run CKMLCP process and so he checked the balance in the 501002002. Aftel material ledger process the  account balance was changed for zero.
Its occured because the GBB-BSA key used the same account determination of UMB key and GBB-BSA did a credit with the same amount in 501002002.
My question is: Is it correct UMB and GBB-BSA key uses the same account?
Many thanks,
Ricardo Sanerip

Absolutely agree with Ajay .. we use different GL account for BSA  and lock the GL account for further postings after implementation is completed ..
Please change the GL account as suggested by Ajay also
Regards
Sarada

Similar Messages

  • The relationship between production order and purchase requistion After running MPS

    Dear Experts:
         I met a issue . My users want to know the relationship between production order and purchase requistion . In my company we create production order and  purchase req. by  running MRP. our operations are:
    1. T-CODE: MD41  create planned order .
    2. T-CODE: CO41 convert planned order to production order .
    3. T-CODE: MD15 convert planned order to purchase Requisition.
      but I can't  find the  relation of them. would you like to give me some advices? thank you very much.

    Hello
    On the standard MTS process there is no link between the requirement (STO) and the replenishment element (production order).
    See the below extraction from note 12955:
    There is no index that the system could use to determine which issue element (sales order, planning, reservation, dependent requirement, ...) is covered by a certain receipt element (purchase order, production order, purchase requisition, planned order, stock level ...).
    A production order, for example, can be created to cover several different requirements, even when you are using lot sizing procedure EX.
    You can use transaction MD09 or MD04to determine the pegged requirements, but they are calculated dynamically and there is not fixed link between requirement and receipt.
    BR
    Caetano

  • "Flickering" on iMovie and IDVD porojects AFTER running updates

    We had an iDVD completed and ready to burn. Actually we burned one copy last Friday and it was great, but needed to go back to iMovie and make some voice corrections. When I turned on the iMac yesterday a long list of updates were available so I went aheat and ran those. We made our voice corrections, etc., shared it back to iDVD, got everything set, burned the DVD and there is "flickering " now all throughout. It seems to have to do with the Ken Burns effect and the updates. Has anyone else experienced this since updating various updates? We are on a 20" iMac running 10.4.9 and is the intel core 2 duo.... The only thing I can attribute this sudden "flickering" to is the ken burns effect and the updates. Somehow they did not mesh. Any suggestions, we have a huge Board of Ed presentation tomorrow night!! Thanks so much, Connie

    Welcome ConnieS
    Try burning the project to a disc image. Like this:
    Click Here
    Then use apple's DVD Player to play the image.
    Click Here
    If it plays as expected then use apple's disc utilities (or Toast) to burn to Verbatim/Maxell DVD-R media at 4x or slower.
    If the Disk Image fails too then please post back for additional troubleshooting recommendations.

  • Material Ledger : Cost component split different in CO PC and ML

    Hello SAP People,
    In ML cost component split I don't have the same split that in CK13N COPC.
    History
    We changed the cost component structure in OKTZ, because we wanted to split on two different cost component the cost of Copper :
    -     Copper
    -     Primes :Premium cost (transformation cost for producer) on copper.
    In CK11N the split is OK and we can read the new cost element corresponding to premium cost.
    To split the costing tool goes on the purchase info records to read condition type that are different for copper and premium.
    The problem we have is that when we run Material ledger we are not able to see after a good receipt a similar split in the cost component view.
    We already run MLCCS_RESET and MLCCS_Startup programs this month and created new Raw material after. But it seems the ML do not take care of this and all the actual cost (I stop to single level) are on the copper cost component and there is nothing on Premium cost component.
    We just run single level on ML for current month.
    Could you please help me to explain why we are not able to obtain the correct split between Copper and u201CPrimesu201D

    Hi Marco,
    yes, these both are independent from each other. You will have no issue when these are different.
    It is very typical that you want to report different kind of information for activities as for materials.
    A typical setup might be
    Activity                                   Material
    Asset depreciation                   Raw Material Cost
    Room cost                               Energy
    Labour                                     Production Cost
    labour overhead                      Production Overhead
    Electricity                                 Packaging
    When you use the activity for the production of a material (confirmation CO15) the assignment goes normally to a single cost component in the material, above for example into production cost. This is controlled by the cost element. Only when the primary cost component split is activated and a transfer structure betweeen both is maintained you could achieve
    Asset depeciation, Room Cost, Labour overhead  -> Production overhead
    Labour -> Production Cost
    Electricity -> Energy
    Best regards,  Udo

  • GR/IR account problem with material ledger

    Hi,
    I just found an issue as effect of material ledger implementation.
    after the material ledger is active, when we post a transaction in foreign currency (invoice receipt), the LC 2 amount of GR/IR account is somehow different from the document amount, and the difference is transferred into Material price difference account that we maintain in OBYC - PRD transaction.
    because of this, the LC2 amount of  GR/IR account can't be cleared.
    any suggestion, please?
    thanks,
    Nasikhin

    hi,
    It will affect your valuation for the document, which are still open..
    You shd run this only after closing all documents and completing whole MM cycle..
    Once this is run, you can't go back and make settlements...
    So, beware...
    Regards
    Priyanka.P

  • Material Ledger Data Conversion

    Hi,
    We are going live on Material ledger on 1st.July 2009
    Below are the steps for the cut over task:
    i) Do not open the next period 07 using MMPV in 1st.July 2009
    ii) Make the backposting on 1st.July 2009 for June 2009
    iii)Open period 7 using MMPV
    iv) Transport the ML cosfiguration
    v) Do CK40N & MR21
    So if we follow above steps then point (v) can be executed successfully
    for the opening price in July 2009.
    Hope to hear from anyone soon.
    Thanks.
    Regards,
    Stagazer

    Hi Stagazer,
    I guess you have it on your list, but you didn't note it down:
    after iv) and before v) you have to run material ledger productive startup and CKMM. Note that these might runtime-intensive jobs, depending on your data volumes, particularly in the purchase order history.
    Following notes are interesting for that:
    [ Note 384145 - Advice note on material ledger production startup|https://service.sap.com/sap/support/notes/384145]
    [ Note 398949 - INFO: CO-PC-ACT (Customizing/preparation production start)|https://service.sap.com/sap/support/notes/398949]
    [Note 596558 - Material ledger production startup|https://service.sap.com/sap/support/notes/596558]
    best regards,
                            Udo

  • Material ledger production start up

    Dear expert,
    we are working on a project that has two main objectives:
    1) now the customer is using the mtv 103/105 and we want to move to the 101
    2) now the customer is using a custom 'medium price calculation' and we have to activate the material ledger.
    I red the note 596558 and I have some question; first at all I would like to find some documentation about this activity and the effects of  a Material ledger production startup, could someone tell me we can I find info ?
    The question are
    At point f) is wrote
    u201CYou should always transfer purchase orders and purchase order histories before activating the material ledger. This ensures that the system translates the purchase order history in all additional currencies.u201D
    What does it means? Why it is necessary translate? How?
    If a company has only the local currency is it necessary the translation?
    At point j) is wrote
    u201CWe recommend that you close open orders before activating the material ledger and recreate them after the activation if required.u201D
    WHY?
    The posting logic for postings that reference a purchase order is changed in the parallel currencies due to the activation of the material ledger. As a result, there may be unexpected price postings and exchange rate difference postings for purchase orders that are not closed in business transactions (goods movements and invoices) that are posted later.
    Which unexpected postings? Refers to new u2018Transactionu2019 (e.g. BSX, WRX, PRD, KDM, u2026) used after the material ledger start up? 
    Now the customer is using a custom u2018medium price calculationu2019; we think to reverse all movements in the year (103, 105, invoices) for order item not closed and recreate the goods movement with  the new model (101, invoices) after the ML activation.
    Thanks in advance.

    In our case CKMSTART was definately done before Inventory load. This Tcode was part of config prior to Master data creation and migrated data loads....

  • Activation Material Ledger with material working in price control "V"

    Hi experts!
    I have activated Material Ledger and I have a question about this..
    1) Before the activation, I have for example a material with the next values in the "Accounting 1" tab:
    Total stock = 7 UNI
    Price Control = V
    Moving price = 166 USD
    Standard price = 166 USD
    Total value = 1.162 USD  (7 UNI*166 USD)
    2) And after the Material Ledger activation, In the same material appears the next values in the "Accounting 1" tab.
    Total stock = 7 UNI
    Price Control = V
    Standar price = 166 USD
    Per.Unit price = 23,71 USD
    Inventory value = 166 USD
    I don´t understand if my total value before activation was 1.162 USD, when I have activated ML, the new value is 166 USD.
    I dont´t understand why the value for the "Per.Unit price" is 23,71USD and not is 166 USD because this is the original value before ML activation..
    I think that my inventory value must be the same before Material Ledger activation, (1.162 USD)???
    Best Regards
    Manuel

    Hi Shaubhikg:
    At first, thanks for your response.
    I have founded another material wich has the next information before the material ledger activation:
    In the Accounting 1 tab:
    Price control: V
    Moving price: 1.265,80 USD
    Total stock: 5 UNI
    Standard price: 553,00 USD
    Total value: 6.329,00 USD
    After the material Ledger production start up, the same material has the next information in USD:
    Standard price: 553,00 USD
    Per.unit price: 1.265,80 USD
    Price control: V
    Inventory value: 6.329,00 USD
    In this case the total value of the stock is the same after and before to do the activation of ML. I think that this is good..
    And can,t understand the example wich I saw you before.. In that case the Total value of the stock after activation Material Ledger is not the same that before activation..
    The material doesn´t have any modification in his unit of measure..
    Could you tell me someting about this issue??
    Best regards!!
    Manuel

  • Questions on material ledger

    Dear All,
    i want to activate material ledger in a company code, but i have some concerns that maybe some of you could give me the best suggestion.
    1. is it possible to activate Material Ledger in the middle of SAP operation (i mean in the previous years, we didn't activate the Mat Ledger, just by now we have the idea to activate it)
    2. what are the impacts by activating Material ledger, and some concerns that maybe exist in activating it?
    3. is there any recommended link that gives the steps for activating it? i got some resources, but apparently the steps don't apply to my system, especially the step when I want to set the valuation area as productive (FYI, my SAP version is 4.7)
    Many many thanks!
    Nasikhin

    you may check below notes, hope it can helps:
    Note 596558 - Material ledger production startup
    After activate material ledger, you need to start up the ML using tcode : CKMSTART , then check using CKM9 for detail.

  • Material ledger accounts range

    Dear Experts
    can you please explain ,
    1]What is " Material ledger accounts Range " were it is created ,
    2] what is its use
    3]How to run material ledger
    regards
    bhaskar

    Hi,
    Material Ledger is created to follow the transaction posted through various movement types and check for any price changes.
    The configuration for Material Ledger is done in Controlling > Product Cost Controlling > Actual Costing/material ledger.
    The number ranges for material documents are based on the nature of transactions and transaction groups.
    You have to create the Material ledger documents under document type ML and for passing on the entries to accounting
    use document type 47.  Material price valuation is a periodic activity done through CKMF and CKMH.  You have the
    analysis of the material prices through CKM3.
    Regards,
    Sadashivan

  • Material Ledger with Split Valuation Type 'X' with FIFO

    Hi,
       The requirement from the customer is to have Raw Material, Intermediary and Finished Products valued at Actuals and on a FIFO basis. According to me, this is possible only if we activate Material Ledger, have batch split valuation u2018Xu2019 as the valuation type and have a batch search strategy which does a FIFO. Are there any technical issues with this solution? Or is there a better solution? Is any organisation ever using this solution for a similar requirement? As an extension of this requirement, how does commodity trading companies running in SAP handle their inventory and COGS valuation?
    Thanks and Regards
    Shivram.

    Hi,
    Using Material Ledger with batch management and split valuation of each batch ("X") leads to most aaccurate FIFO valuation result, however, depending on how many material and batch the customer has, huge number of materials will be processed and it will affect the performance issues. You should check the number and expected period-end time frame scheduling at least.
    Financial responsible tell you to need this kind of solution (detailed FIFO calculation)?
    They usualy needs to get simple FIFO valuation, meaning they don't care each individual logistic material movement as FIFO, but only care of periodic FIFO. I know, it depends on Finacial responsibes or their auditors, so it's also not general.
    Please double-check the new FIFO valuation function for Material Ledger with using Periodic Closing and AVR. Some information is in SAP Note 1431829 and 1247053. Related transactions are there, CKLMBB_xxxx under Actual Costing/Material Ledger -> Balance Sheet Valuation Procedures. I couldn't find any official documents for Material Ledger + FIFO valuation (like Release Notes).
    Hope this will be an additional option to yours.
    Best regards, Takashi

  • HELP - ABAP Program Cancelled After Running for 2.5 Hours in Background

    I have an ABAP report program that was being tested in our QA system and it died after running for 2.5 hours with the status of "Cancelled" (which, I assume, means it was terminated by SAP for exceeding some type of governor).
    I ran Code Analyzer and no performance issues were recognized.
    I am running several SELECT statements during program execution.  These are a list of all the SELECT statements used in my program.  Also, I'm using PNPCE to get a list of pernrs for which to pull data at the beginning of the program.
    SELECT *
          INTO CORRESPONDING FIELDS OF TABLE gt_p0167
          FROM pa0167
          WHERE pernr EQ gt_selected_pernrs
            AND bplan IN s_bplan
            AND begda LE pn-endda
            AND endda GE pn-begda.
              SELECT SINGLE fgbdt fasex
                INTO (lv_dob, lv_gender)
                FROM pa0021
                WHERE pernr EQ gt_selected_pernrs
                  AND subty EQ <fs_dtyxx>
                  AND objps EQ <fs_didxx>
                  AND begda LE pn-endda
                  AND endda GE pn-begda.
      SELECT SINGLE agency ansvh
        INTO (p_agency_out, lv_ansvh)
        FROM pa0001
        WHERE pernr EQ p_pernr_in
          AND begda LE pn-endda
          AND endda GE pn-begda.
      SELECT SINGLE vorna nachn gbdat perid gesch
        INTO (gt_control_table-fname, gt_control_table-lname, gt_control_table-dob, gt_control_table-mskssn, gt_control_table-gender)
        FROM pa0002
        WHERE pernr EQ p_pernr_in
          AND begda LE pn-endda
          AND endda GE pn-begda.
      SELECT SINGLE perid
        INTO (lv_ssn)
        FROM pa0106
        WHERE pernr EQ p_pernr_in
          AND subty EQ p_subty_in
          AND objps EQ p_objps_in
          AND begda LE pn-endda
          AND endda GE pn-begda.
      SELECT SINGLE smoke
        INTO (p_smoker_out)
        FROM pa0376
        WHERE pernr = p_pernr_in
          AND begda LE pn-endda
          AND endda GE pn-begda.
      SELECT SINGLE state pstlz zcounty
        INTO (p_state_out, lv_zip, p_county_out)
        FROM pa0006
        WHERE pernr EQ p_pernr_in
          AND begda LE pn-endda
          AND endda GE pn-begda.
      SELECT SINGLE werks btrtl
        INTO (lv_werks, lv_btrtl)
        FROM pa0001
        WHERE pernr EQ p_pernr_in
          AND begda LE pn-endda
          AND endda GE pn-begda.
        SELECT SINGLE region
          INTO (p_region_out)
          FROM zpat_county_code
          WHERE county EQ p_county_in.
          SELECT SINGLE pernr
            INTO lv_pernr
            FROM pa0002
            WHERE perid EQ gt_cobra_table-l_essn.
      SELECT SINGLE eecst ercst
        INTO (lv_eecst, lv_ercst)
        FROM t5ubi
        WHERE barea EQ '01'
          AND bplan EQ lv_bplan
          AND bcost EQ p_bcost_in
          AND cstv1 EQ '0001'
          AND smoke EQ p_smoker_in
          AND begda LE pn-endda
          AND endda GE pn-begda.
        SELECT SINGLE kwert
          INTO lv_kwert
          FROM t511k
          WHERE molga EQ '10'
            AND konst EQ 'ZCOB1'
            AND begda LE pn-endda
            AND endda GE pn-begda.

    The screen shot the tester sent me only says that it was canceled.  However, the log shows the following:
    09/17/2008 16:54:32 Job Started
    09/17/2008 16:54:32 Step 001 started (program ZBNI001...
    09/17/2008 19:22:09 ABAP/4 processor: DATASET_NOT_OPEN
    09/17/2008 19:22:09 Job cancelled
    I'm not sure it was an error, per se, but maybe SAP canceled it because it had been running too long?  The "DATASET_NOT_OPEN" is curious although I've no idea what it means.
    Thanks for your help.

  • Material ledger activation in material master

    A material has been extended in plant xxxx and due to some reason material ledger could not get activated in accouting 1 view of a material master. As of now there is no transaction has been made in plant xxxx for tis material. Pls guide how we can actaivte the material ledger in material master.
    Note : Material ledger is activated at plant level because for other material it is activated.

    Maintain the same through Transaction variant SHD0.
    Best Regards,
    Ankur

  • Difference between normal Costing run and Costing run in Material Ledger

    Hi everybody,
    I have a question i wanted to know why we implement Material Ledger .
    If material ledger is for settling variances on material then that is also possible without material ledger
    Please clear the doubt what is different in ML as compared to normal costing run
    thanks in advance
    Regards
    Deepa

    Costing run is to calculate the std cost estimate of materials and Material Ledger costing run is to calculate Actual cost of production of materials.

  • Run CKMLCP (material ledger cockpit) for closed period in MMPV

    Hi,
    I would like to run CKMLCP for period 12.2008, however MMPV was run in 02.2009, and only january and fabruary 2009 are allowed for material postings.
    How can I settle material ledger in 12.2008? I know about note 361236 (CKMLCP: No period-end closing operations after period shift), but don't know if this will do all the proper postings or only close 12.2008 technically.
    Regards,
    Karol

    Hi Carol ,
    Please remeber costing Run i.e CKLMCP is a closing activity so it should be done only at the time of closing a particular period .A syou said two periods are open for MM but costing also post some Accounting enteries if FI period is closed the its not possible.
    And its not recommended to run costing any time in middle of the period.
    Thanks
    Deepa

Maybe you are looking for

  • IPhoto library from 7.1.5 to 5.0.4?

    I want to duplicate my iPhoto library onto a G5 mac running Tiger with iPhoto 5.0.4 it currently resides on an Intel Leopard machine with iPhoto 7.1.5 (which came with that Mac so i don't have the upgrade option right now) is this possible? when i ex

  • Can not open FXML files in DataApp example

    Hi, I download javafx_samples-2_2_0-windows.zip and unzip, and open DataApp project. I build and run, it's ok. but I cannot open many fxml files, for example, it gives me following error messages: Error loading file 'C:/work/tianqing/Java/JavaFX/Test

  • When I plug in my iPod, iTunes dies

    Well the title say it all, when I plug in my iPod, Itunes "stops working". WHY??? PLEASE HELP!!!

  • Strange thing happening

    hi friends, I'm not able to understand what's happening with the already Executed JAR file is not loading Archived class files even when the path is defined in the CLASSPATH variable but the same works fine when the program is executed with the main

  • Write in file problem

    My problem is: I wanna write in a file. But what happen if another application is writing in that file in the same time? Is it possiple to check if anyone is writing in this file or what can i do not to get in a write conflict? I use the class FileOu