Unable to create Schedule line(Maintain sch.agreement)
Hi experts,
After running MRP i got Planned order for a certain material and for that material procurement type maintained as "Both internal and external" in material master. After completing the process planned order to purchase requisition, i separately created schedule agreement . Now here i am facing one problem that if i create schedule line with reference to purchase requsition i am getting the error Requisition doc. type NB not allowed with doc.type LP.
pls anybody suggest is there any prob made in the above process
Regs,
SR
Edited by: SP Ramesh on Jan 1, 2010 8:22 AM
go to tcode OLME> schedule agreement> select the line of document type LP and then slecte the folled item category and then selce each item category one by one and then click on the second folders link document type and there give source document type NB
cause of the issue is : the source document type NB is not set with LP document type of schedule agreement
Similar Messages
-
Firming the Schedule Lines in Sch.Agreement
Hi , I have done the following to firm the schedule lines in Scheduling agreement.
1. Firm Zone as 30 days
2.Tradeoff zone days as 60 days
3.Binding MRP indicator as NULL(Lines not changeable within Zones)
4.In OMIN , Firm Schedule lines enabled for the MRP group
When i run the MRP, schedule lines are getting created with Firm Indicator (*) for the requirements lying within these zones. After transmitting the schedule lines to vendor , if i change the requirement again, the schedule lines within Firm Zone are getting adjusted as per the new requirment. I dont know whats the purpose behind maintaining these Firm Zone and Trade off Zone.
Pointers are much appreciated.
Thanks and regards,
Milton IsaacHi,
Rolling delivery schedules issued under scheduling agreements are divided into different time zones indicating the degree to which lines of the schedule are binding.
Firm zone (zone 1) (go-ahead for production).
The schedule lines within this zone count as firm and thus as fully binding. If you cancel a schedule line that falls within the firm zone, the vendor is entitled to charge you with both production costs and the costs of procuring input materials incurred by him as a result of the cancellation.
Trade-off zone (zone 2) (go-ahead for procurement of input materials)
This is the "semi-firm" zone, giving the vendor the go-ahead to procure necessary input materials for the manufacture of the item ordered. If you cancel a schedule line within this semi-firm zone, the vendor is only entitled to charge you the material costs. Schedule lines falling within this time zone are thus less binding that those falling within the firm zone. -
Output type is used for sending / printing "schedule lines" against sch agr
hi
which output type is used for sending / printing "schedule lines" against sch agreement
LPET or LPH1?
saraHi Sara,
It is LPET.
Thanks & Regards,
Kiran -
Any function module available for creating new schedule line specifying schedule line type along with other schedule line related entries
HI,
you can user FM : ME_CREATE_SCHEDULE_DOC to create schedule line agreements.
Thansks,
Nelson -
Error in creating schedule line aggrement through BAPI
Hi All ,
I want to create schedule line aggrement (VA31) by using BAPI / FM .
I am using " SD_SALESDOCUMENT_CREATE" FM .
Here i am getting error in output when i enter shchedle line data in input .
Error is given below .
E V1 434 No schedule line category could be determined during quantity adjustment
Error only come when i want to create new schedule line ....in Changing any schedule line aggrement there is no error .
I am able to create schedule line aggrement manually .
please help .Use BAPI_SAG_CREATE
-
Creating Schedule lines in Scheduling agreement using LSMW
Hi,
I want to upload multiple schedule lines in scheduling agreement using LSMW. I have done the recording and maintained multiple lines in input file. However during execution LSMW creates only one line and keeps on ovewritting the same line. Please let me know how can I create multiple schedule lines.
RegardsFirst you should search for existing standard LSMW migration objects that possibly cover your scenario. These normally take care of complex header / multiple items / multiple subitems relations.
With a recording you can only load flat structures. Sometimes a "create new lines" / "enter first line" / "save transaction" logic can be constructed to load multiple items to a header (or even subitems to an item?) with a recording, but this can be pretty awkward.
Thomas -
Help me to guide create schedule lines in MRP
hi
This is my MRP initial screen
Processing key NETCH Net change for total horizon
Create purchase req. 1 Purchase requisitions
Delivery schedules 3 Schedule lines
Create MRP list 1 MRP list
Planning mode 3 Delete and recreate planning data
Scheduling 1 Basic
I already Maintain the Source list in ME01 with Vendor & Plant then input the Scheduling agreement number and the MRP as 2.
but i counld,t get schedule lines why
thanks
jai
Edited by: Jai on Sep 30, 2008 12:55 PM
Edited by: Jai on Sep 30, 2008 12:55 PMhi friends,
once i run the MRP MD03 it creates only PR
there is no schedule lines
thats also my problem
please expalin and solve my problem
thanks
jai -
Provide -- the steps involve (in detail) to create schedule lines from MRP
Dear All
Please provide me with the steps (in details) involved to create the schedule lines automatically from MRP.
Early help would be appreciated.
Regards
Rahul BhardwajHi,
1. In Material Master --> Purchasing View --> maintain the Tick for Scource list.
2. Create th Scheduling Agreement. (valid)
3. Maintain the Source list with the Scheduling Agreement and MRP indicator as 2.
4. MRP Control Parameters - Delivery Schedules - 3 (Schedule Lines).
After MRP Run, system will create the Sched. Lines for you..
For your earlier questions also please check these points..
Regards,
Siva -
Automatically create scheduling lines based on quantity and number of containers
Dear Gurus
Our business requires that when creating a sales order automatic scheduling lines should be created based on the quantity and number of containers.
i searched and found of using VOV6 but i am a bit confused on how to set up this calculation logic.
Thanks and RegardsDear Arun kumar
Our business requires that when creating a sales order automatic scheduling lines should be created based on the quantity and number of containers.
Generally shedulines are confirmed Based On qty only ...Or Number of containers
Check OVLZ Maintain Days
MMR--Maintain RLT MRP 3 VIEW Or goods pressing time MRP2 VIEW
VOV8--Lead time in days
VOV6--Activate availability check, Req check box
OVZ9--Remove RLT Check box
SCAL--Factory Calendar also impact please check
If customer Is maintain complete delivery ..Make it Complete check box in XD01 But while creating Sales order if he agrees Partial delivery also according to company activate check box Fixed qnty/date in Schedul lines
And make it availability check in sales order level not in delivery level
Let me know your requirement is some thing different -
Can't Delete/Change Schedule Line in Sceduling Agreement
Hi
I can't delete schedule line in scheduling agreement.
Actually The PO History has diff data & Scheline screen have diff data.
In Po History the Delivered Qty is 1520 GI Qty is 1520 GR Qty is 1520 but when I checked in Delivery Schedule screen in ME33L the data is diff.
The Scheduled Qty 1520 Delivered Qty is 1520 GI Qty 360 & GR Qty 360.Even when I am trying to reduce the Scheduled Qty to GR Qty that is 360I am getting message Quantity 360 less than delivered qty 1520.
Kindly help me to resolve this problem.Hi..
The Scheduling agreement is one which is created runing MRP not VA31.
I know that is two transaction data in SAP.
One is Sales Data other one is Purchasing Data.
This is second one.
Thank you your response. -
BADI / user-exit for MD02 while creating Schedule Lines
Hi experts,
I have a problem with implementation that I'm designing.
Current situation:
While MRP run (MD02 or background) new Schedule Lines are being created in reference to MM Scheduling Agreement.
Example:
04.08.2014
SchLne
5500000415/00010
200
04.08.2014
IndReq
VSFB
200-
05.08.2014
SchLne
5500000415/00010
300
05.08.2014
IndReq
VSFB
300-
2 Schedule Lines where created - for wuantity 200 and 300.
Target:
There is a need to create more than one Schedule Line per day during MRP run. According to example there should be for example 2 Schedule Lines in 04/08 and 3 Schedule Lines in 05/08 all for quantity = 100. There is possibility to change Schedule Lines in ME38, but there is a need to make a change during creatin while MRP run.
04.08.2014
IndReq
VSFB
200-
04.08.2014
SchLne
5500000415/00010 *
100
04.08.2014
SchLne
5500000415/00010 *
100
05.08.2014
IndReq
VSFB
300-
06.08.2014
SchLne
5500000415/00010 *
100
06.08.2014
SchLne
5500000415/00010 *
100
06.08.2014
SchLne
5500000415/00010 *
100
So instead of creating only 2 Schedule Lines, MRP should create 5.
I'm looking for a BADI/user-exit to edit Schedule Lines which are to be created by MRP and change it tn reference to the needs.
I found only one BADI:
BADI: MD_CHANGE_MRP_DATA
method: CHANGE_MDPSX_MDBS
The priblem is that this method is only being executed when there are Schedule Lines which already exist.
Maybe some of you have done some extension similar to mine? Please give me advice where I should put extension.
Thanks in advance!Dear Saravaran,
Thanks for the reply.
This will not suits to us. The provided BADI will works upto Posting the material document in transaction MIGO and it will not considered for the FI level entries.
Hope you could have understand mine requirement.
The requirement of mine is:
While doing the GR with ref to PO the material documnet will be posted and subsequently FI documnet will be generated in Background. While generating the FI document i need to manipulate the values for the G/L. So that the manipulated values will be flow into BKPF and BSEG tables.
Thanks.
Regards
Swamy -
Schedule line in STO agreement
Hi,
Business is doing Good receipt against standard purchase order and stock is updatedin the particular storage location(example :XXXX),They are transferring the material from one location(xxxx) to another(YYYY) via STO process.
(Two locations are belongs to one plant only )
Now business wants that whenever the Goods receipt happens in XXXX location,schedule line automatically to be created in the STO agreement..
How to meet this requirement ,Kinldy share your ideas on this
Regards,
Renuga.AHi ,
First part of your question is not clear to me also
Second part can be addressed by planning calendar and lot sizing procedure.Please refer to the thread
Re: Planning Calendar
Regards
Ankur -
MRP - Problem in scheduling of MRP created schedule lines
Hi,
I am working with single level BOM of FG and trying to generate Schedule lines for RM as per requirement coming from FG - BOM explosion during MRP run -
Material master setting of RM is as below -
MRP type - PD,
Lot Size - Ex,
Procurement type - F,
Planned dlv time - 14 days
i am getting dependent requirement as below -
06.07.2009 - 2000 EA
13.07.2009 - 1500 EA
01.08.2008 - 1000 EA
And schedule lines are generated as below -
06.07.2009 - 2000 EA
13.07.2009 - 1500 EA
01.08.2008 - 1000 EA
The date of schedule line should be after taking calculation of planned del time of the RM, which is not happening. I can't understand why?
The planned dlv time is same in all 1) Material Master 2) Scheduling agreement and 3) Pur info record
Please help.
Regards,
AmolDear Amol,
the date shown is the ultimate reciet date and not start date.
Since you have already converted PR into schedule lines you will not be able to see the actual start date.
If it was still a PR you can see the release date as planed delivery time days early.
If the requirements date was say 31/05/2009 and you were taking planning run today then the recieved date would come as 05/06/2009.that is 14 days from today.
if requirement well beyond planned delivery time then the planned delivery time will not reflect in recipt date. -
MRP in third party scenario. System not creating schedule lines
HI
I am using third party subcontracting scenario. As i am purchasing material but i am not taking material in under my company. I am paying to my vendor but the delivery is going to my subcontractor.
Here i am able to create planned order or purchase requisition. But MRP is not generating schedule lines for that vendor.
Regards,
Anand.Hello,
Check the following settings.
1. Source list active in Material master.
2. Valididy of the source list.
3. Any quota arrangement
4. Purchase infor record.
Note: all are OK, but still PR's only created, then check for the requirement date, if the requirement date lies before the validity of the source list then also system will create only purchase requisitions.
for this calculation you have to check the lead time for procurement cycle you have to check. Based on this no. of days only system will try to create the procurement proposals.
If the lead time is very high and this is going beyond the sourcelist validity, then also PR's only created.
So there are so many possibilities. check for the above said things and revert back.
regards,
<Manick> -
Converting contract to sales order does not auto create schedule lines
Hi
When I convert quotation to sales order, then schedule lines get auto created.
But when I convert contract to sales order, then schedule lines don't be auto created. Instead, a confirmation screen for proposal delivery date pops up for every line item in the sales order.
Is there any suggestion how can I solve my problem ?
Thanks..Hi,
In standard SD module, system checks availability for each line item, gives you popup screen of confirmation.
If you don't want availability or popuscreen of confirmation,then
Go to VOV6 >>> Select schedule line which you are using in sales order for line item >>> Remove tick mark of availability check.
Else
Remove availability check rule from material master >>> Under tab Sales : ganral/plant
kapil
Maybe you are looking for
-
Specs: MB - K7N2 Delta L FSB 400 CPU - AMD Athalon XP 2800+ Video - GeForce 2 MX400 (PCI) Hard Drive - (When attached) Maxtor 160GB 7200RPM 8MB Cache RAM - Kingston 256 MB DDR400 CL2.5 (KVR400X644C25/256 PSU - AXIO 480W 3.3V - 28A +5V - 37A 12V -
-
Error when trying to use ImageIcon
Hi, I am trying to use an ImageIcon to store an icon for plugins so that they can customize their menu and toolbar entries. I use a generic class, PaletteClass, to design all the plugins, and then extend PaletteClass to create individual plugins. Pal
-
Fuzzy / Blurry Font on Unibody macbook (late 2008)
I have have recently started using my wife's macbook as my macbook air died. On the air the text was always clear and crisp. On the unibody macbook the text is blurry on screen. I have compared it to my colleagues previous generation Air. The funny t
-
To break out of a non-global zone and become root user in the global zone
Hi folks "to break out of a non-global zone and become root user in the global zone through a kernel bug exploit" Is this possible and has SUN allready a fix/workaround/patch for that? Cheers
-
Randomise midi events in garageband?
Hi. Anyone know of a plugin or method to randomise midi events in garageband? E.g. I'd like to be able to randomise (to a controlled degree) note velocities (preferably within a specified range perhaps ± one or two points) and note beginnings (± a fe