Unable to open the Projects from Project center with the Alias name PWA 2010
Hi,
I am unable to open the Projects from Project center with the Alias name with the server name i am able to open the projects, version is project server 2010,
My system is ABC.DC.IN alias name i have given is DEF.AD.COM
With the system name i can able access PWA and all are working fine.
As i have observed with alias name i can able to login to pwa and all the server setting approval center all are working fine but only in the project center i am not able to open the projects (http://DEF.AD.COM/pwa/ProjectDrillDown.aspx .xxxx) its
is coming in the below of the ie.
But with Alias name these are the issues i am facing,
1.when longing with alias name its asking two times for user name and password
2.when i click on a project from project center its taking some time and asking for user name and password after i enter user name and password "PAGE cannot displayed" error i am getting.
3. I have observed one more thing if click on Project details then only this issue is coming project schedule and project information is also opening with Alias name.
can any one Help me.
Vijay kommireddi
Hi
Hope the below link will help you.
And also please check the browser which you are using as mostly IE 8.0 won't support, Please try it in IE 9.0 and Chrome.
http://social.technet.microsoft.com/Forums/sharepoint/en-US/c03300d2-2a27-4d5d-b3f6-a3660805e125/alternative-access-mapping-when-accessing-the-site-it-is-asking-for-username-and-password
Thanks
Geeth If you feel that the answer which i gave you is Helpful please select it as Answer/helpful.
Similar Messages
-
How does iCloud manage app data( like whatsapp) ? Does it overwrite the data everytime I backup to I cloud with the data on the phone when i backup or it merges the data from previous backups with the new data?
You need to subscribe to iTunes Match to store your music on iCloud:
http://www.apple.com/itunes/itunes-match/
To transfer iTunes Store purchases made on your phone to your computer, connect your phone then choose "Transfer purchases..." from the File menu in iTunes.
Photostream transfers photos taken on your iOS devices to other devices and your computer. For troubleshooting Photostream see: http://support.apple.com/kb/TS3989 -
I am currently running two email accounts on my iPhone 4s.
Both accounts have email/contacts/calendar synced to the phone so I can have all contacts on the phone.
I now have to close one of these accounts due to work but I would like to keep all the contacts on the account I am closing, on the iPhone.
Does anyone know how to save these contacts to my phone so I dont lose any?
Much appreciated.Sorry you get only one notification sound for all email accounts. you can send a suggestion to apple here http://www.apple.com/feedback/
-
Unable to Open Public folders from Windows XP after the upgrade of CU4 to Cu7
We still have few machines running windows Xp, who cannot access Public folders after the upgrade to the latest CU7. Is there any fix for it other than moving them to Windows 7?
Hi DNair,
Hope you are already upto date. But still just putting it through to cross check.
Outlook Versions Supported by Exchange 2013
The following Outlook client versions are fully supported by Exchange server 2013. Please bear in mind there’s a difference between what is supported and what might be compatible with Exchange 2013.All
of the Outlook versions listed below have been thoroughly tested by the Exchange Product group:
Outlook 2013
Outlook 2010 SP1 with November 2012 Cumulative Update ( available from
http://support.microsoft.com/kb/2687623 )
Outlook 2007 SP3 with November 2012 Cumulative Update ( available from
http://support.microsoft.com/kb/2687404 )
Entourage 2008 for Mac, Web Services Edition
Outlook for Mac 2011
Outlook clients earlier than Outlook 2007 are not supported.
Find and Manage
Outlook Updates here.
Regards,
Satyajit
Please “Vote As Helpful”
if you find my contribution useful or “Mark As Answer” if it does answer your question. That will encourage me - and others - to take time out to help you. -
How to setup my Palm 700wx to connect to the Internet from your computer with the USB
http://i35.tinypic.com/znx2yw.gif
Can I surf using my pda web browser on my 700wx without using my cellular phone for ISP connection? If so, does anyone on here might know how to set this up on a 700wx palm? Thanks again.
Message Edited by deeptester on 10-18-2009 10:02 PMDo anybody on this board might know if there is a wx700 USB modem software available?
-
Project Pro hangs while opening a schedule from Project 2010 server.
Hi,
We have an issue with opening a schedule from Project server 2010. Project client is not responding. when we try to open schedule in PWA. I am getting unable to open file do you want to open in default view. No matter which view I choose keep getting the
same error. The only view i can see resource view however it will not let me edit. I did notice Project Manager had entered resource names first, last name format which do not exist in our resource pool. We can open other schedule except this particular
one.
Thank youObviously, my first thoughts are that this plan is corrupted in some fashion. Entering Resource names differentluy should not cause this issue, they will just not be recognized as Enterprise Resources by the system.
Are you experiencing the issue if you try to open the schedule from PWA? If you are able to open from PWA, try publishing it from PWA and see if it throws any errors.
Also, how about trying it from a different machine?
And finally, it might be worthwhile to check if you have the latest Client Update for Project installed (or atleast matching with the server).
If none fof these work,
a) you could try restoring it from Archive Database (assuming you have a daily schedule backup running)
b) If you are able to open it from another machine, you could use the "Save for sharing" feature to try and resolve any corruption with the schedule itself.
Prasanna Adavi,PMP,MCTS,MCITP,MCT http://thinkepm.blogspot.com -
Unable to open any of my projects in CS6
I'm suddenly unable to open any of my projects in CS6. Each time I try to open one (either from its folder, or from "Open" when I'm already in CS6) a new box comes up like this:
Then it seems unable to find the project, no matter what. If I try clicking "skip" or "offline", this comes up:
Thanks in advance for any help!That dialog screen is asking for the location of the first "missing" file, as Craig mentions. For more detail, see this article: http://forums.adobe.com/message/4598705#4598705
Good luck,
Hunt -
UNABLE TO OPEN FCP 6.02 PROJECT FILES AFTER INSTALLING LEOPARD!
**Unable to open FCP 6.02 project files after installing Leopard**. Tested and found that the files can be opened on another computer with OS 10.4.10, but not OS 10.5. Spoke to apple support many times, and have tried reinstalling FCP, but it didn't work.
Apple is now saying to erase my HD and reinstall from scratch. This presents a problem since i have software installed but no disc due to a move, (they are deep in offsite storage).
Anyone have this problem? Anyone know a fix?Lynne,
There is a section in the manual on the migration tool... I don't have my machine fired up right now so can't direct you to the exact page. I think a search for migration or migrate should do it.
Two other things to try:
1. There have been numerous reports that Quicktime 7.3 is what is killing older projects. According to one of the third party program makers Apple re-wrote Quicktime changing the null value to Zero from minus-one. I'm not a code junkie so can't vouch for this but the upshot would be, go back to Quicktime 7.1 or 7.2 not 7.3
2. There is a Quicktime plugin called "Perian". For lots of people it has caused numerous problems.
Look for Perian on your machine and if you find it, drag the app to the trash... re boot and try again.
Of course the ultimate solution would be to reinstall Tiger, Final Cut Studio 2 and Quicktime 7.2. So far the most stable combined setup for me and lots of others on G5 machines.
36 degrees and thunderstorms with sleet here this afternoon. The door on my storage unit is staying closed.
Message was edited by: John Criswell -
Anyone know which render format I should use, my film will be used on a video wall (12 screens) and I need super quality. My footage format is 1080p HD resolution 1920x1080. I will be running the project from a mac with a direct line to video wall. Thanks in advance.
I do some VJ-type work, involving playback of QuickTime files from the computer to projections, and I get good results using ProRes 422. That's convenient, because ProRes 422 is such a great editing codec, too.
Traditionally, VJs use PhotoJPEG codec, which also works well, but it's a bad editing codec. So you would have to export an edited master, then convert.
If you want it to look as good as possible, definitely schedule some time to test the footage on the wall. You may want to change the color correction of your footage to match the projectors. And if you feed the video wall some flat gray, you can see if any of the projectors need to be adjusted.
I'm not sure what application you're using for playback, but QuickTime Player 7 works well. It has an option to play fullscreen on an external monitor (View > Present Movie…). -
Dear Sirs,
I need your support over the following MS EPM 2013 issue:
Publication of the big-sized Enterprise projects from Project Professional 2013 to Project Server 2013 takes about 30+ minutes. We
need to reduce this total publication time down to acceptable working values 10+- minutes.
Environment information:
Single App Server (Virtual): 16 Gb RAM, x64 4xCPU, HDD > 50 GB free disk space, OS Windows Server 2012 Standard Edition x64 Service
Pack 1, MS SharePoint Server 2013 and MS Project Server 2013 with CU December 2013 (KB 2850024) applied.
Single RDBMS MS SQL Server (Virtual): 8 Gb RAM, x64 4xCPU, HDD > 200 GB free space, OS Windows Server 2012 Standard Edition x64 Service
Pack 1, MS SQL Server 2012 x64 SP 1 Enterprise Edition.
We have 1Gbit LAN between APP, DB server and 1Gbit LAN between APP and Proj Prof Client.
Yes, we are on the way of migrating to the Prod environment
with 3-tiered architecture (with SP1 slipstream and CU December 2014 applied), but this issue also
presents there.
Project’s file information:
Tasks in the file: [~4900], resources in the file [~396] enterprise task’s custom fields used in the file [~23].
Project save procedure for this new project would last about 7 minutes. Project publication would last about 47 minutes. We noticed that
tasks synchronization process took about 1 second for each ~2,5 tasks, to add them to the sharepoint tasks list. So for all 5148 tasks it took about 5148/3/60 = 34 minutes. Other 13 min was used for reporting database publication and other tasks relevant
for new sharepoint site creation.
Case 1: Issue description:
During the Enterprise project’s file save and publication we have the following sharepoint 2013 log messages:
07.31.2014 12:43:17.22 Microsoft.Office.Project.Server (0x0358) 0x3D5C SharePoint Foundation Monitoring b4ly High Leaving Monitored Scope
(Persisting list changes). performing time =376.068676326181 22dca99c-4696-70f1-e9e2-06851d0bcffd
07.31.2014 12:43:17.69 Microsoft.Office.Project.Server (0x0358) 0x3D5C SharePoint Foundation Monitoring b4ly High Leaving Monitored Scope
(Persisting list changes). performing time =361.652807828928 22dca99c-4696-70f1-e9e2-06851d0bcffd
It shows that sharepoint spend at least ~350 milliseconds (or 0,35 sec*4900 tasks = 1715 sec, or 28,5 min) for each task update during
project publication. And we also have another log file that shows that about 0,7 sec (or 0,7 sec*4900 tasks = 3430 sec, or 57 min) sharepoint spend for save each task in project file to project server. So total save and publication time more then 60+ minutes
for that project file. The same result we have even if user didn’t do any changes at the project file.
We use only enterprise projects (dbo.MSP_EpmProject_UserView.projectvisibilitymode = «False»), and do not use sharepoint tasks lists,
but the synchronization between MSP Plan and SharePoint tasks list works at any case.
Case 2: Issue description:
- For the second test we created a new project with new sharepoint project’s site on basis of our «issue» project, with total amount
of tasks in it of 5148 (yes, we increased the tasks list default limit at the sharepoint site up to 6000 items in it – standard limits for sharepoint view list – 5000 items).
- Project save procedure for this new project would last about 7 minutes. Project publication would last about 47 minutes. We noticed
that tasks synchronization process took about 1 second for each ~2,5 tasks, to add them to the sharepoint tasks list. So for all 5148 tasks it took about 5148/3/60 = 34 minutes. Other 13 min was used for reporting database publication and other tasks
relevant for new sharepoint site creation.
-Then we deleted the
tasks list for that new test project from the sharepoint site and republish the project plan one more time. This time project save procedure took about 7 minutes, project publication about 2 minutes and 3 minutes for other relevant queue jobs. So total time
is 12 minutes.
As a conclusion: yes, we have determined
the exact problem - during synchronization process (from Project Server to SharePoint) it perform copying all tasks and related data from Project to SharePoint in spite of fact that you changed only ONE task or ALL of them. At any case, synchronization will
copy ALL of them from Project Server to SharePOint task’s list.
Our workaround is to disable the task’s synchronization for such big-sized project plans:
– to delete the SharePoint «tasks» list at the SharePoint site tied with project plan.
- or deattach the SharePoint site from the project plan.
Thank you for reading this topic, please if you also forced with such issue provide us any known workaround or maybe any official response
\ feedback from MS about it.
Thank you in advance,
Best Regards, AndreyRegarding my topic, I also said that every time when sync works it updates All items from project’s plan at Project Server to corresponded task’s list at SharePOint server. Inspire of the fact that you changed only One task or group /
all of them at your project’s plan.
And it seems to me and my colleagues that it’s probably (maybe) a “bug” at the product. Here is what we have if looked a little bit closer to the code:
Share Point determines what task to sync from Project’s plan to sharepoint list. To do that sharepoint needs to know was that task changed or not, based on the following fileds (check SQL stored procedure “[MSP_READ_TASKS_FOR_SYNCRONIZATION]”):
TASK_UID TASK_NAME TASK_START_DATE TASK_FINISH_DATE TASK_PCT_COMP TASK_PARENT_UID TASK_OUTLINE_NUM
WSS_LISTITEM_UID TASK_ID TASK_IS_ACTIVE
We noticed that at any case synchronization performs for all tasks, EXCEPT the ROOT one. Then we looked at the comparison of TASK_PARENT_UID field. So sharepoint compares TASK_PARENT_UID with ParentID (this is internal name for lookup
field “Tasks” at the Sharepoint, and it stores their values at the format "ID;#Title").
And comparison performs like following:
SharePoint looks for Task at the Tasks’s list corresponded to Project’s plan with ID represented at the TASK_PARENT_UID field. Then it takes SharePoint ListItem ID (“int” type) and store it to the “num” parameter;
num = this.GetCachedListItemByUniqueId(listItem.ParentList, nullable.Value).ID;
2.Then it compares “num” with task’s “ParentID” at SharePOint as follow with operator “!=”:
((SPItem) listItem)["ParentID"] != (System.ValueType) num
3. If comparison was success (true) – then it tell us that values (at the Project’s plan for tasks) was changed, then it need to be synchronized. Corresponded Method setup “true” flag, and then returns it.
The “bug” is that this expression at the Step 2 will always return “true”, because in fact it compares “string” (see above – that this is lookup field at SharePoint side)
with “number”. For example if the parant task ID is “55”, then we get:
"55;#Task 1" != 55
And by the rules of .Net the “string” will never equal “number”
Furthermore this is approved by the SharePoint logs:
In that case we always get the note “Setting ParentID to” at the logs (we see it if turns on Verbose for “Project Server” -> “Sharepoint Integration” category).
So at any case of publishing project’s plan we always get that note at the logs for tasks that have Parent task, and we have Parent for all of them EXCEPT the ROOT one, exact logs represented further:
10/15/2014 02:37:32.26 Microsoft.Office.Project.Server (0x07D8) 0x06E8 Project Server Sharepoint Integration ado0d
Verbose Setting ParentID to 1 bf2fc29c-7727-b00d-fa4a-34f22ea9ec1d 10/15/2014 02:37:32.62 Microsoft.Office.Project.Server (0x07D8) 0x06E8
Project Server Sharepoint Integration ado0d Verbose
Setting ParentID to 1 bf2fc29c-7727-b00d-fa4a-34f22ea9ec1d 10/15/2014 02:37:32.63 Microsoft.Office.Project.Server (0x07D8) 0x06E8 Project Server
Sharepoint Integration ado0d Verbose
Setting ParentID to 1 bf2fc29c-7727-b00d-fa4a-34f22ea9ec1d 10/15/2014 02:37:32.67 Microsoft.Office.Project.Server (0x07D8) 0x06E8 Project Server
Sharepoint Integration ado0d Verbose
Setting ParentID to 1 bf2fc29c-7727-b00d-fa4a-34f22ea9ec1d 10/15/2014 02:37:32.69 Microsoft.Office.Project.Server (0x07D8) 0x06E8 Project Server
Sharepoint Integration ado0d Verbose
Setting ParentID to 5 bf2fc29c-7727-b00d-fa4a-34f22ea9ec1d
The following is the complete Method’s code from the corresponded reflector:
private bool UpdateParentID(DataSet taskDS, DataRow row, SPListItem listItem, Dictionary<Guid, SPListItem> redoEntries)
bool flag = false;
int index = taskDS.Tables[0].DefaultView.Find((object) DataRowExtensions.Field<Guid>(row, "TASK_PARENT_UID"));
if (index >= 0)
Guid? nullable = DataRowExtensions.Field<Guid?>(taskDS.Tables[0].DefaultView[index].Row, "WSS_LISTITEM_UID");
int num = -1;
if (listItem.Fields.ContainsField("ParentID"))
if (nullable.HasValue)
try
// STEP 1
num = this.GetCachedListItemByUniqueId(listItem.ParentList, nullable.Value).ID;
catch (ArgumentException ex)
if (redoEntries != null)
if (!redoEntries.ContainsKey(DataRowExtensions.Field<Guid>(row, "TASK_UID")))
redoEntries.Add(DataRowExtensions.Field<Guid>(row, "TASK_UID"), listItem);
//STEP 2
if (num != -1 && ((SPItem) listItem)["ParentID"] != (System.ValueType) num)
((SPItem) listItem)["ParentID"] = (object) num;
ULS.SendTraceTag(845443U, (ULSCatBase) ULSCat.msoulscat_PS_ProjectSharepointIntegration, ULSTraceLevel.Verbose, "Setting ParentID to {0}", new object[1]
((SPItem) listItem)["ParentID"]
//STEP 3
flag = true;
else if (((SPItem) listItem)["ParentID"] != null)
((SPItem) listItem)["ParentID"] = (object) null;
ULS.SendTraceTag(2495056U, (ULSCatBase) ULSCat.msoulscat_PS_ProjectSharepointIntegration, ULSTraceLevel.Verbose, "Resetting ParentID to null");
flag = true;
return flag;
Any thoughts about it would be much appreciated! -
Required reference document to issue the material from project stock
Hi All,
we have procure the project stock material with Acct. assignment Grp as "Q", now the material is laying in project stock.
the things is we can issue the warehouse material with reference to Project Reservation similarly my client wanted to use some SAP document for records purpose to issue the material from project stock.
i have checked this functionality in SAP which is not available except straight way issuing the material from project stock using MB1A( 221 Q).
please help me out to resolve this requirent.
manoj singh
we canHi,
Did you implement PS module in your system? How were your project stocks reserved?
Cheers,
HT -
Revision: 12883
Revision: 12883
Author: [email protected]
Date: 2009-12-12 15:53:50 -0800 (Sat, 12 Dec 2009)
Log Message:
Remove the skin classes from the halo theme project to avoid redundancy with the airframework/framework swcs.
QE notes: No
Doc notes: No
Bugs: SDK-24293
Reviewer: Glenn
Tests run: Checkintests, smattering of Halo and AIR mustella tests
Is noteworthy for integration: Yes
Ticket Links:
http://bugs.adobe.com/jira/browse/SDK-24293
Modified Paths:
flex/sdk/trunk/frameworks/projects/framework/src/FrameworkClasses.as
flex/sdk/trunk/frameworks/projects/halo/build.xml
Added Paths:
flex/sdk/trunk/frameworks/projects/framework/src/mx/skins/halo/WindowBackground.as
Removed Paths:
flex/sdk/trunk/frameworks/projects/halo/assets/
flex/sdk/trunk/frameworks/projects/halo/src/HaloClasses.as
flex/sdk/trunk/frameworks/projects/halo/src/mx/skins/ -
I am unable to open my iMovie HD project in Final Cut Express
I am unable to open my iMovie HD project in Final Cut Express. All I get are error messages, no matter what I try.
Tried everything, please help!
Thank youSee if this helps explain your difficulties.
https://discussions.apple.com/message/10831726#10831726 -
Unable to open PDF files from my banking statements.
I think almost every dev is on arch-general, so that is the place to contact the group in general. Specific points can probably be emailed to the dev involved, if one is identifiable and if the bug tracker is not a better place (bug reports to my email get ignored).
I think the whole problem here is that there is really no dev in charge of that package. So your emails were probably seen then skipped over by all devs thinking not my problem... (I know that is true for me). Then Andrea noticed an "orphan" package that needed updated and went ahead with it without connecting it to your previous emails, which is unfortunate.
Now our maintainer backend is fixed, hopefully we can get all the orphan packages adopted out, or at least know if we need to bring on new people to maintain them. That way, there should always be someone who information about specific packages should be sent to. -
Problem with the% deviation from Project Server 2010 field
hello
I have a problem with the% deviation from Project Server 2010 field.
Within a file or project, this project contains tasks.
Each task has completed the field% deviation.
Within the row "Summary" in the field of% deviation does not perform the sum of all fields of tasks.
Only occurs on certain projects, these projects have the view of PR Progress Report
Anyone know happens?
thank you very muchHi
Sorry, I'll be more specific now.
Within the field% deviation. Your settings in PWA is:
The formula for field% Deviation:
Str (IIf ([Job baseline] = 0; IIf ([Working] = 0, 0, 100); IIf ([Working] = 0; -100; Int (100 * ([Job] - [Work Online base]) / [Working baseline])))) + "%"
Under the heading rows Calculation Summary:
> Use formula.
Within the field Allocation Calculation of rows:
> It is labeled the "Apply unless you manually specify".
The field [Job] and field [Job baseline] are fields Pack project server.
The error is in project, in the list of tasks.
In the top row, this row summary makes the sum of the ranks of the tasks of the file.
But in my case only in the summary field the same value appears in the tasks.
In all the cells in column% deviation appears the same value.
I hope it helps.
thank you very much
Maybe you are looking for
-
Twice, shortly after turning on my MBA from a restful night's sleep, my keyboard and trackpad have stopped working. Works fine after a hard reset, but considering this baby is brand new, it shouldn't be happening. I am in law school and don't have t
-
FRM-10221 solution required?
i have 10gds and i want to deploy my 6i's forms n reports. The Problem is that All the forms are running without attaching the menu But while i attach my menu to any of the form it give the error FRM-10221: Cannot read the file Sys_menu Although i ha
-
when trying to get to a certain web site, it says can not support netscape. how do i fix this
-
Tuning multiple interrelated PID controllers
Hi, I am attempting to control forces with pneumatic pistons and regulators. Feedback comes from a 6 degree of freedom load cell. I already have a program designed with PID controllers which works ok. The trouble is tuning the parameters. So far, I h
-
Found a BUG on Create a Procedure Form Cancel Branch.
FYI... From the Page level add a new region / Form / Procedure Arguments / Procedure Owner / Next / Cancel Instead of branching back to the page level it branches to Create Page Define with no options.