Hello,
My query is we have a SCM 5.0 system which has a java stack in it. But now we are going to upgrade it to SCM 7.0. - Is SCM 7.0 has a java stack ?
If it doesn't have , can we upgrade SCM 5.0 to SCM 7.0 without Java Stack ? Is it posssible to upgrade without Java Stack or not ?
Is it possible that we can convert Java Stuff into ABAP web dyn pro ? If yes , how shall we can achieve it ? If not, how shall we proceed in an alternate way ?
Thanks for your help in advance.
Madhu

Hi Manoj,
Yes the system is running okay and I can login without problem. The question I have is that the upgrade program started with default system number 00 loaded, where I don't know how to change it to match our system setting. Our system is currently having system number 01.
Thanks,
Eric

Similar Messages

  • Is it okay to upgrade from os x 10.6.8 to yosemity without first getting the other operating systems?

    is it okay to upgrade from os x 10.6.8 to yosemity without first getting the other operating systems?

    Hey there jpenilla,
    Welcome to Apple Support Communities.
    Yes. The webpage below provides the answer to your question, about upgrading to Yosemite from OS X Snow Leopard (v10.6.8), and it provides additional information that you may find helpful.
    Apple - OS X Yosemite - How to Upgrade
    You can upgrade to OS X Yosemite from the following:
    OS X Snow Leopard (v10.6.8)
    OS X Lion (v10.7)
    OS X Mountain Lion (v10.8)
    OS X Mavericks (v10.9)
    So long,
    -Jason

  • How can I upgrade from Photoshop CS4 to Cs 5 or 6 without buying the creative cloud?

    How can I upgrade from Photoshop CS4 to Cs 5 or 6 without buying the creative cloud?

    Well CS5's ship has sailed.
    CS6 can still be purchased on Perpetual License but it's not going to have all the bells & whistles that the current versions have.  Just as long as you understand what you're getting.
    Creative Suite 6
    Nancy O.

  • After upgrading from 4.01 to 5.0 the Flashplayer and Java environment don't work.

    Made an update yesterday morning 21/6 from 4.01 to 5.0. It worked except that LastPass gives an error message at login, but it still works. Later 21/6 I downloaded an update from Mozilla. After that no Flashplayer plugins like in YouTube work. Neither does Java like in http://hem.ektv.nu/~ekt000851/mane.html, that I use as a test site.
    However my most precious plug in Nexus Personal works in both versions. I cant figure out what is the difference.
    I run Firefox on Linux Mint LMDE 64 bit in the /home/directory/

    Made an update yesterday morning 21/6 from 4.01 to 5.0. It worked except that LastPass gives an error message at login, but it still works. Later 21/6 I downloaded an update from Mozilla. After that no Flashplayer plugins like in YouTube work. Neither does Java like in http://hem.ektv.nu/~ekt000851/mane.html, that I use as a test site.
    However my most precious plug in Nexus Personal works in both versions. I cant figure out what is the difference.
    I run Firefox on Linux Mint LMDE 64 bit in the /home/directory/

  • Upgrade from CRM 6.0 to CRM 7.0 without upgrading MSA

    Hi all,
    we are currently running CRM 6.0 with the Mobile Client for a field sales group of 2000 users and we have some plans to move to the latest release being CRM 7.0. As upgrading MSA for 2000 users is extensive task we would like to know if it is possible to upgrade the backend to 7.0, but without upgrading the MSA to 7.0. Is there a way with some cheats and tricks to manipulate some tables in order to make it work with a CRM 7.0 backend system ?
    Thanks,
    Christophe

    Hi Christophe,
    We do not support the landscape which you are planning to move into. This sceanrio is not validated either.
    Refer to SAP Notes
    1226055 - SAP CRM 7.0 Mobile Client Component: Collective Note
    1095553 - SAP CRM 2007 Mobile Client Component: Collective Note
    These Notes give you information on Client-Server mapping which is officially supported by SAP.
    Regards,
    Ganga

  • Upgrading from R12.1.1 to R12.1.2

    Hi,
    I have the following configuration:
    Oracle Enterprise Linux:5.3
    EBS Version:R12.1.1
    Database version:11.1.0.7
    OracleAS 10g Forms and Reports:10.1.2.3.0
    OracleAS 10g: 10.1.3.4.0
    Please explain is it recommended to upgrade all Tech stack Components before upgrading from R12.1.1 to R12.1.2
    I am upgrading from R12.1.1 to R12.1.2 without upgrading any tech stack components, as it requires minimum versions and R12.1.1 tech stack components are supporting those versions
    Can i go ahead on production after applying it on test
    will it create any problem, if i could upgrade tech stack components later, will it be a problem for me
    Please explain...
    Thanks,
    Alig
    Edited by: user12257829 on Aug 17, 2010 12:30 AM

    Hi
    Hussein
    While Upgrading from R12.1.1 to R12.1.2 faced many errors(Applied 8502056 patch) and then applied 7303033
    first adrelink failed.
    1. An error occurred while relinking application programs.
    Continue as if it were successful [No] : Yes
    but i entered Yes to continue as my OS is OEL 5.3 binutil version is binutils-2.17.50.0.6-9.el5
    as my system binutil is updated one but in the note at MOS 758831.1, binutils-2.17.50.0.6-6.0.1.el5.x86_64.rpm, this doesnt apply to my system as my binutil is updated one.
    2. The following Oracle Forms objects did not generate successfully:
    au resource OKLCSASD.pll
    An error occurred while generating Oracle Forms library files.
    Continue as if it were successful [No] : Yes
    as i entered yes to continue with the patch and tried to compile OKLCSASD.pll thru adadmin and manully aslo but didnt succeed.
    The patch is completed atlast, and a huge number of invalid objects where created ..
    I tried to recompile thru admin,utlrp,adcompsc.sql & utl_recomp.recomp_parallel but unable to compile a single objects
    How could i make sure that patch is applied successfully & recompileinvalid object
    find below invalid objects
    BIS_MEASURE_SECURITY_PVT
    BIS_INDICATOR_REGION_PVT
    BIS_TARGET_LEVEL_PVT
    BIS_ACTUAL_PUB
    ENG_ECO_PUB
    BIS_PMF_REG_SERVICE_PVT
    ENGECOBO
    AS_SALES_LEAD_OPP_PVT
    BISVIEWER_PMF
    BIS_PMF_DEFINER_WRAPPER_PVT
    IES_TELESALES_BP_PKG
    OKL_REVERSE_CONTRACT_PVT
    OKL_CONTRACT_PVT
    OKL_AM_PARTIES_PVT_W
    OKL_AM_CREATE_QUOTE_PVT_W
    OKL_AM_REPURCHASE_ASSET_PVT_W
    OKL_AM_RESTRUCTURE_QUOTE_PVT_W
    OKL_AM_SEND_FULFILLMENT_PVT_W
    OKL_SPLIT_ASSET_PVT_W
    OKL_TRX_QUOTES_PUB
    OKL_CONTRACT_REBOOK_PUB
    OKL_AM_TERMNT_QUOTE_PUB
    OKL_TXL_QUOTE_LINES_PUB
    OKL_TRANSACTION_PUB
    OKL_ACTIVATE_ASSET_PVT
    OKL_GENERATE_ACCRUALS_PVT
    OKL_ASSET_DETAILS_PVT
    OKL_AM_ASSET_DISPOSE_PVT
    OKL_ACTIVATE_IB_PVT
    OKL_AM_PROCESS_ASSET_TRX_PVT
    OKL_AM_QA_DATA_INTEGRITY_PVT
    OKL_AM_PARTIES_PVT
    OKL_AM_ASSET_RELOCATION_PVT
    OKL_AM_UTIL_PVT
    OKL_AM_ASSET_RETURN_PVT
    OKL_BLK_AST_UPD_PVT
    OKL_CONTRACT_BOOK_PVT
    OKL_KBK_APPROVALS_WF
    OKL_COPY_ASSET_PVT
    OKL_AM_CONSOLIDATED_QTE_PVT
    OKL_AM_CREATE_QUOTE_PVT
    OKL_AM_CALCULATE_QUOTE_PVT
    OKL_CS_CREATE_QUOTE_PVT
    OKL_CS_WF
    OKL_CURE_CALC_PVT
    OKL_EQUIPMENT_EXCHANGE_PVT
    OKL_FUNDING_WF
    OKL_INTEREST_CALC_PVT
    OKL_LA_JE_PVT
    OKL_CREATE_KLE_PVT
    OKL_LCKBX_CSH_APP_PVT
    OKL_LIKE_KIND_EXCHANGE_PVT
    OKL_AM_BTCH_EXP_LEASE_LOAN_PVT
    OKL_AM_LEASE_LOAN_TRMNT_PVT
    OKL_AM_LOAN_TRMNT_PVT
    OKL_LOSS_PROV_PVT
    OKL_AM_LEASE_TRMNT_PVT
    OKL_MASS_REBOOK_PVT
    OKL_MISC_TRANS_PVT
    OKL_QA_DATA_INTEGRITY
    OKL_AM_QUOTES_WF
    OKL_CONTRACT_REBOOK_PVT
    OKL_CURE_RECON_PVT
    OKL_RELEASE_PVT
    OKL_REV_LOSS_PROV_PVT
    OKL_AM_REPURCHASE_ASSET_PVT
    OKL_AM_RESTRUCTURE_RENTS_PVT
    OKL_AM_RESTRUCTURE_QUOTE_PVT
    OKL_AM_RECYCLE_TRMNT_PVT
    OKL_AM_PROCESS_RV_TRX_PVT
    OKL_AM_RV_WRITEDOWN_PVT
    OKL_AM_SEND_FULFILLMENT_PVT
    OKL_LA_STREAM_PVT
    OKL_SPLIT_CONTRACT_PVT
    OKL_SPLIT_ASSET_PVT
    OKL_AM_SV_WRITEDOWN_PVT
    OKL_AM_AMORTIZE_PVT
    OKL_TRANS_CONTRACTS_PVT
    OKL_AM_TERMNT_QUOTE_PVT
    OKL_CS_TRANSFER_ASSUMPTION_PVT
    OKL_TRANSACTION_PVT
    OKL_VARIABLE_INTEREST_PVT
    OKL_GENERATE_ACCRUALS_PUB_W
    OKL_VP_K_ARTICLE_PUB_W
    OKL_AM_CONSOLIDATED_QTE_PUB_W
    OKL_AM_CREATE_QUOTE_PUB_W
    OKL_TRX_QUOTES_PUB_W
    OKL_CONTRACT_REBOOK_PUB_W
    OKL_AM_REPURCHASE_ASSET_PUB_W
    OKL_AM_RESTRUCTURE_QUOTE_PUB_W
    OKL_AM_SEND_FULFILLMENT_PUB_W
    OKL_SPLIT_ASSET_PUB_W
    OKL_TRX_ASSETS_PUB_W
    OKL_TRX_CONTRACTS_PUB_W
    OKL_TRANS_CONTRACTS_PUB_W
    OKL_TXL_QUOTE_LINES_PUB_W
    OKL_TRANSACTION_PUB_W
    AST_UWQ_WRAPPER_PKG
    OKL_AM_CNTRCT_LN_TRMNT_PVT
    OKL_CS_PRINCIPAL_PAYDOWN_PVT
    OKL_SERVICE_INTEGRATION_PVT
    OKL_AM_TERMINATE_INV_AGMT_PVT
    OKL_AM_TERMNT_INTERFACE_PVT
    CSC_ACTION_ASSEMBLER_PVT_W
    OKL_AM_SYSTEM_PARAMS_PUB
    OKL_VENDOR_AGREEMENT_PUB
    OKL_AM_INTEGRATION_PVT
    OKL_PERIOD_SWEEP_PVT
    OKL_SEC_AGREEMENT_PVT
    OKL_VSS_WF
    OKL_SSC_WF
    OKL_AM_SYSTEM_PARAMS_PUB_W
    WSH_IB_TXN_MATCH_PKG
    WSH_RCV_CORR_RTV_TXN_PKG
    WSH_IB_UI_RECON_GRP
    OKL_AM_BAL_WRITEOFF_PVT
    OKL_VP_SYNC_CR_PVT
    OKL_CREDIT_LINE_WF
    OKL_PROP_TAX_ADJ_PVT
    OKL_PROCESS_PPD_PVT
    OKL_LA_SALES_TAX_PVT
    OKL_AM_TERMNT_VENDOR_PRG_PVT
    OKL_AM_VENDOR_RES_SHARE_PVT
    OKL_MULTIGAAP_ENGINE_PVT
    one thing important while generating .pll/.fmb thru adadmin it asks for FND_INSTALL_PROCESSES & AD_DEFERRED_JOBS to be dropped, if we select to drop it will drop this tables and patch process will not continue if these tables were dropped and created for .pll/.fmb generation
    How to avoid this  & to apply patch cleanly
    Thanks,
    Alig
    Edited by: user12257829 on Aug 19, 2010 3:56 AM
    Edited by: user12257829 on Aug 19, 2010 3:59 AM

  • HT1338 Can I upgrade from Tiger (10.4) to Lion (10.7)

    Can I upgrade from Tiger (10.4) to Lion (10.7) without purchasing and installing Leopard (10.5) and Snow Leopard (10.6)?
    The spects on this MacBook5,1 is MacBook (13-inch, Aluminum, Late 2008)

    You can't.
    In order to get Lion you must be running Snow Leopard 10.6.8
    To get there you must purchase the Snow Leopard install DVD from Apple
    Then update to 10.6.8 which will give you the App Store to purchase Lion
    Since Lion is no longer available on the App Store, you will have to call Apple and purchase a code to download it from the App Store
    Allan

  • How to upgrade from 1.0.3 to 1.1.1? (can it be done w/o adding 1.1 first?)

    Sorry for the seemingly silly question, but can you upgrade from 1.0.3 to 1.1.1 without first having to upgrade to 1.1?
    I had downgraded from the 1.1 to the 1.0.3 because of that stupid hiss. Now, each time I connect my iPod, it asks if I want to upgrade to 1.1 (which, of course I DON'T).
    Any ideas? Thanks for helping out a newbie.
    All the Best,
    -T.

    Sorry for the seemingly silly question, but can you upgrade from 1.0.3 to 1.1.1 without first having to upgrade to 1.1?
    Whenever you update the iPod's software, it will always update to the latest version. There is no need (indeed no facility) to update via interim versions.

  • Upgrade from SCM 5.1 to SCM 7.0 SR1 (with NW 7.0 EHP1 SR1)

    Hi folks,
    we are trying to upgrade our SCM5.1 to SCM 7.0 SR1. There seems to be a problem in the phase, where SAPup is trying to detect the needed CDs / DVDs. SAPup recognizes that "FRP" is used within the system. There appears a dialog to enter the mount points for the DVDs required for the upgrade.
    It says <<Enter at least the mount point for the DVD titled "FRP Software DVD">>. All other needed media is accepted, but not the DVD with the FRP-Software.
    SAP Note "1300960"  explains, that as of SAP Business Suite 2008 onward, no media without a MID.XML file will be accepted for upgrades (e.g. media containing Add-Ons).
    I have opended a message to SAP Support, but there is no solution / workaround until now. I cannot skip the phase and therefore it is not possible to launch / continue the entire upgrade.
    SAPup Version is "7.10/7, build 31.010 for UNICODE"
    Has anyone faced the same problem with no-MID.XML based media?
    Thank you for any advice!
    Kind regards,
    Marcel Jentsch

    Hi,
    We just upgraded from SCM 5.0 to 7.0 sp9.
    You need not deactivate the DP planning areas before upgrade.
    We did not face any issues because of this.
    Regards,
    Ashok

  • Upgrade from SCM 5.0 to 7.0

    Dear all,
    I am in the situation to present the deltas between SCM 5.0 and 7.0. As we are running on 5.0 right now and would like to upgrade to 7.0 I need some input about the benefits for the upgrade. Clear is that 5.0 is running into extended support end of this month, but the question is which Deltas we have. May be someone could me help out here. We are currentls working with SAM-DP and SNP.
    Thanks to help me a little bit out here.
    BR
    Ingo

    Hi,
    We just upgraded from SCM 5.0 to 7.0 sp9.
    You need not deactivate the DP planning areas before upgrade.
    We did not face any issues because of this.
    Regards,
    Ashok

  • Upgrading from SCM 4.1 to SCM 2007/5.1 (HP-UX/MaxDB)

    Here's my  challenge - I need to upgrade an SCM 4.1 system (HP-UX IA64 11.23/MaxDB 7.5) to SCM2007/5.1.  From what I can see in the Product Availability Matrix, SCM2007/5.1 requires MaxDB 7.7.  What I need to know is how and when should the MaxDB database and liveCache be upgraded from 7.5 to 7.7 (or 7.5 > 7.6 > 7.7).  I've tried to run PREPARE on the first system we wanted to test the upgrade on, but it fails with the following hard error: "ERROR: MaxDB Version is not supported by this upgrade.  ERROR: Error in database software path determination (ERR -10)".  This leads me to believe I need to upgrade the database before upgrade upgrading the application, yet I can't seem to find this requirement documented in any of the SCM upgrade guides.
    Any assistance will be appreciated.
    John

    Hi Kaushik
    just a little input about funtional DP (not sure of system architectural improvements) :
    I dont think performance would drastically improve per se
    the areas that might be of some impact/ use in terms of performance are -
    - parallel processing profiles
    - macro improvements
    - changes in Admin Workbench (BW 7 functionality might make things easier)
    - changes in Planning area (no negatives for eg can help remove macros that used to do that function making it easier)
    The important improvements are in more functionality
    Its recommended to do some better process and layout deisgns to get performance improvements
    pl note, there would be an initial long run time the first time you perform any transaction because of indexes being created

  • SCM Upgrade from 5.0 to 5.1 or 7.0

    Hi, We are contemplating to upgrading from SCM 5.0 to 5.1 or 7.0. Any advice that we need to consider to eliminate serious problem. Also, any issue with interfacing with ECC5 and BI 7? Thanks for your reply.

    Hello Nida,
    For restrictions on both SCM releases (5.1 and 7.0) please check the content of notes 1021662 and
    1284461.
    I hope it helps.
    Regards,
    Michel Bohn

  • Moving Planning areas and Planning books from SCM 4.0 to SCM 5.1

    Hello Experts,
    Can anyone have idea of how to transport planning areas and Planning book from SCM 4.0 to SCM 5.1.
    Do we need any prerequisite to Transport Planning area and Planning book from Lower version (SCM 4.0) to higher version SCM 5.1.
    Any suggestion could be very helpful for me.
    Thanks!
    Best Regards,

    I have never done this, but I suspect it might be tad easier to just recreate them in 5.1 There are scores of tables that Planning Book configuration lies in. I would not rely on a transport mechanism working across versions to migrate every bit of the configuration accurately.

  • Failed to upgrade from ERP 6.0 EHP4 to EHP5

    Dear SAP Gurus,
    we are running ERP 6.00 with EHP4 (HCM-component) based on Windows 2003
    SP2 X64 and SQL Server 2005 SP4 (64-bit).
    We are using SAP Kernel Unicode 7.01 PL 133 (64-bit).
    We intend to upgrade from EHP4 to EHP5.
    Upon running SAPehpi, we encountered issue which stopped us from
    proceeding with the upgrade.
    Case 1: Direct upgrade to 605
    The upgrade failed on PREP_INPUT/VERSCHK_INI with error message: The
    following combination is not supported (SAP_APPL 600, SAP_BASIS 701,
    SAP_ABA 701).
    Case 2: Upgrade SAP_APPL component from 600 to 604 (due to the above
    error message)
    The upgrade failed on PREP_INPUT/VERSCHK_INI with error message:
    Release '701' of component SAP_BASIS is too new.
    Case 3: upgrade via SAINT is not supported by SAP. When uploading the
    Stack XML file, we got error saying that the stack is not supported.
    Attached is the complete list of the current SP Level of Installed
    components.
    Please advise on how we can perform the upgrade to EHP5.
    Many thanks in advance.
    regards,
    Denny

    The thing is Solution Manager was able to produce the XML file during the previous upgrade to 604 (the one without SAP_APPL 604).
    So how can it not be supported by SAP?
    If it is not supported by SAP, how can I proceed from here?
    Component Software C SP-Level Support Package Short description of the component
    SAP_ABA 701 0007 SAPKA70107 Cross-Application Component
    SAP_BASIS 701 0007 SAPKB70107 SAP Basis Component
    PI_BASIS 701 0007 SAPK-70107INPIBASIS Basis Plug-In
    ST-PI 2008_1_700 0003 SAPKITLRD3 SAP Solution Tools Plug-In
    SAP_BS_FND 701 0008 SAPK-70108INSAPBSFND SAP Business Suite Foundation
    SAP_BW 701 0007 SAPKW70107 SAP Business Warehouse
    SAP_AP 700 0021 SAPKNA7021 SAP Application Platform
    WEBCUIF 700 0008 SAPK-70008INWEBCUIF SAP WEBCUIF 700
    SAP_APPL 600 0018 SAPKH60018 Logistics and Accounting
    SAP_HR 604 0035 SAPKE60435 Human Resources
    EA-IPPE 400 0018 SAPKGPID18 SAP iPPE
    EA-APPL 600 0018 SAPKGPAD18 SAP Enterprise Extension PLM, SCM, Financials
    EA-DFPS 600 0018 SAPKGPDD18 SAP Enterprise Extension Defense Forces & Public Security
    EA-FINSERV 600 0018 SAPKGPFD18 SAP Enterprise Extension Financial Services
    EA-GLTRADE 600 0018 SAPKGPGD18 SAP Enterprise Extension Global Trade
    EA-HR 604 0035 SAPK-60435INEAHR SAP Enterprise Extension HR
    EA-PS 600 0018 SAPKGPPD18 SAP Enterprise Extension Public Services
    EA-RETAIL 600 0018 SAPKGPRD18 SAP Enterprise Extension Retail
    FINBASIS 600 0018 SAPK-60018INFINBASIS Fin. Basis
    ECC-DIMP 600 0018 SAPK-60018INECCDIMP DIMP
    ERECRUIT 600 0018 SAPK-60018INERECRUIT E-Recruiting
    FI-CA 600 0018 SAPK-60018INFICA FI-CA
    FI-CAX 600 0018 SAPK-60018INFICAX FI-CA Extended
    INSURANCE 600 0018 SAPK-60018ININSURANC SAP Insurance
    IS-CWM 600 0018 SAPK-60018INISCWM Industry Solution Catch Weight Management
    IS-H 600 0023 SAPK-60023INISH SAP Healthcare
    IS-M 600 0018 SAPK-60018INISM SAP MEDIA
    IS-OIL 600 0018 SAPK-60018INISOIL IS-OIL
    IS-PS-CA 600 0018 SAPK-60018INISPSCA IS-PUBLIC SECTOR CONTRACT ACCOUNTING
    IS-UT 600 0018 SAPK-60018INISUT SAP Utilities/Telecommunication
    LSOFE 600 0018 SAPK-60018INLSOFE SAP Learning Solution Front-End
    SEM-BW 600 0018 SAPKGS6018 SEM-BW: Strategic Enterprise Management
    ST-A/PI 01M_ECC600 0001 SAPKITAR7F Application Servicetools for ECC 600-605
    VIRSAHR 530_700 0012 SAPK-53312INVIRSAHR SAP GRC Access Controls 5.3 for 700 HR S
    VIRSANH 530_700 0014 SAPK-53314INVIRSANH SAP GRC Access Controls 5.3 for 700 HR a

  • Upgrading from SQL Server 2005 Compact Edition [ENU] to SQL Server 2008 Express Edition OR HIGHER for Microsoft Security Compliance Manager

    I have downloaded the MS Security Compliance Manager, which is in two parts:  MS SQL Server 2008 Express Edition & the SCM. The install instructions state the the server needs to be install before the SCM.  So as the install continues I get
    an error message, which cancels the installation.  So, I am trying to install SQL 2008 EE separate from SCM.  My question is: 
    Can I upgrade from my current SQL Server 2005 Compact Edition [ENU]
    directly to SQL Server 2008 Express Edition (or higher)?

    So as the install continues I get an error message, which cancels the installation. 
    And which error message did you got?
    SQL Server Compact Edition is something different then SQL Server Express (or Standard) Edition, you can't upgrade it as you asked for,.
    Olaf Helper
    [ Blog] [ Xing] [ MVP]

Maybe you are looking for

  • My power adapter is not working at all

    Hello Recently, my power adapter has stopped working. I'm down to 33% battery power and no way to recharge! If I unplug the adapter and plug it directly into a wall outlet (grounded), it still does not work. No light on the adapter plug at all. What'

  • How do I install two instances on the same Server and avoid a conflict?

    Hi, I have one Server and I want to install two instances of SQL Server on it. 1. Will be a default instance. 2. Will be a named instance. The Server has an IP address of 192.168.0.10 and the default instance will be using port 1433. I want them to s

  • Problem in accessing query

    Hi Experts, I am facing a strange problem when working with BI 7.0, can you please help me out. One user is facing some authorization problem while executing queries, he is using query through BEX. In order to analyse when i copy his user id and when

  • Cannot export to Quicktime anymore. Please help.

    Hi all, I did some maintenance on my computer recently and now I can no longer export to Quicktime format.  The maintenance involved deleting old footage plus a bunch of "Media Cache Files," which were taking up nearly 90 gigs of space.  90 gigs!  I

  • How do I get "Vanishing Point" to work properly on iMac Retina 5k