Upgrading from SAP R/3 4.7 x200 to SAP ECC 6

Our company is planning to upgrade R/3 4.7 EXT 200 to ECC 6.0. We are planning to do the Unicode upgrade on the R/3 4.7 system then do the ECC 6.0 upgrade. Would this be an appropriate way to go about the upgrade? Has anyone done the Upgrade in this fashion, and have you experienced any big problems?

Hi,
as per my knowledge no need to do the uccheck in 4.7,in upgrade we r doing the uccheck in ecc6.0.
Upgrade means we r installing the new software.
The major stages of a technical upgrade can be
1.System preparation and stack level patch upgrade u2013 Basis Team
2.SPDD Phase u2013 ABAP and Functionals
3.Up gradation of the system u2013 Basis Team
4.SPAU Phase u2013 ABAP and Functionals
5.DBACOCKPIT for indexing u2013 ABAP TEAM
6.Issue resolution and error tracking u2013 ABAP and Functionals
7.Z programs corrections u2013 obsolete function modules and objects
Regards,
Madhu

Similar Messages

  • Upgrading from Iseries 810 (v5r2) to Iseries 520(v5r4) sap 4.6c

    We're upgrading our ISeries 810(v5r2) to Iseries 520(v5r4).
    WE did a save 21.
    Ran restore 23 (omitted libraries qgpl and qusrsys on rstlib)
    ALl userprf - configuration - libraries - dlo - authority all were restored.
    New kernel library (2291).
    When we go to start SAP on iseries (v5r4) it starts and quickly ends.
    WE have no logs - nothing gets created.
    Please Help
    Where's the problem
    Thanks
    Joe

    Hi Joseph,
    unfortunately based on this information, it is not really possible to solve your issue. In my eyes, it will be necessary to logon and check on the issue.
    Regards
    Volker Gueldenpfennig, consolut international ag
    http://www.consolut.de - http://www.4soi.de - http://www.easymarketplace.de

  • Upgrade from XI 3.0 (SP17) to PI 7.0 (SP12): Best Practices

    Hi mates,
    I've a few questions regarding the upgrade to PI 7.0.
    If the upgrade process is done in phased manner i.e. DEV, QA, PRD in that order over a period of 3 weeks,
    How do we handle the transports from DEV->QA->PRD when DEV is 7.0 and QA & PRD on 3.0 using CMS?
    Will there be inconsistencies when transports are moved, because a few features could be different or internal representation of IR/ID content could be different in 3.0 & 7.0?
    What are the upgrade best practices, phased manner or all at a time?
    Please throw more light on this. I appreciate the inputs from people who've helped clients upgrade from 3.0 to 7.0. Any SAP documentation related to this?
    I looked at the thread Transports from XI 3.0 to PI 7.0 but the answert is very generic, w/o any supporting documentation and real time experience.
    thx in adv
    praveen

    <i>> Hi mates,
    >
    > I've a few questions regarding the upgrade to PI
    > 7.0.
    >
    > If the upgrade process is done in phased manner i.e.
    > DEV, QA, PRD in that order over a period of 3 weeks,
    > How do we handle the transports from DEV->QA->PRD
    > when DEV is 7.0 and QA & PRD on 3.0 using CMS?</i>
    Im my experience you should implement a change freeze for this period, with the exception of emergency transports - and these have to be justified.
    <i>> Will there be inconsistencies when transports are
    > moved, because a few features could be different or
    > internal representation of IR/ID content could be
    > different in 3.0 & 7.0?</i>
    Full regression testing will be needed on each interface.  If you implement a change freeze this process becomes easier
    <i>>
    > What are the upgrade best practices, phased manner or
    > all at a time?</i>
    Allow plenty of resources to fully test every interface, as you would with any upgrade.
    You could also take the time to implement the new <a href="https://www.sdn.sap.comhttp://www.sdn.sap.comhttp://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/80bbbd55-5004-2a10-f181-8bb096923cb6">CTS+</a> for this new version to avoid any further transport issues (PI7.0 SP12 +).  A new method for a new system!
    Also, how is your SLD set up for XI?  This can have an impact.

  • Issues to be aware of when upgrading from SP1 to SP7

    Dear All,
    We are planning to upgrade from SP1 to SP7 of Microsoft version of SAP BPC.
    Are there any major pitfalls that we should be aware of with this upgrade?
    Is SP7 a stable release?
    Thanks in advance,
    Mark

    RE:  SP5 - I have been running SP5 since November.  Overall it has worked well with two exceptions:  It is not compatible with Japanese Windows (Fixed in SP6 onward, by enabling use of a new XceedZip version 6.5).  I have a manual workaround for this which works for infrequent dimension refreshes and a low number of Japanese users to support.  Also the SendGovernor fails to restart after just about every reboot (Resolved with an SSIS package that checks the status of the SendGovernor, and restarts it if it is turned off).
    I am looking to SP7 so would like to hear others comments as well.
    Greg

  • Upgrade from SAP Webas 6.40 to SAP Netweaver 2004s

    Do we have to change the virtual host name used for high availability clustering environment to local host name before we conduct the upgrade from SAP WebAS 6.40 to SAP NetWeaver 2004's ?

    Do we have to change the virtual host name used for high availability clustering environment to local host name before we conduct the upgrade from SAP WebAS 6.40 to SAP NetWeaver 2004's ?

  • Follow up activities after SAP (CU&UC) upgrade from SAP 4.6c to ECC6 EHP4

    Dear Friends
    We have completed SAP (CU&UC) upgrade from SAP 4.6c to ECC6 EHP4.
    We refereed the upgrade guide for follow activities and we required confirmation before performing the activities.
    Could you please help us what needs to be done immediately after upgrade.
    Regards,
    Bharathi

    Dear Nils,
    Thanks for the support.
    Yes, we are following the same document 'CUUC46C_to_NW701SP07' for unicode conversion after the upgrade from the note 928729.
    Please suggest us in that document which are the steps should be carried out after ECC6.0 EHP4 upgrade,
    1. Preparation
    2. Unicode Preconversion Phase in SAP Basis 4.6C
    3. Upgrade Process
    4. Unicode Conversion Phase
    5.  Unicode Conversion Completion Phase
    6. SAP Notes
    Regards,
    Bharathi

  • Issue with SAP GUI 7.30 launching with users upgrading from 7.10

    We started rolling out SAP 7.30 GUI Final 7300.3.7.117 out to people, and we've ran into this error with people who had upgraded from SAP GUI 7.10.
    Our environmental variable uses saplogon.ini (SAPLOGON_INI_FILE) and points to c:\windows\saplogon.ini
    I don't know why the program is trying to search for saplogontree.xml.
    I've tried uninstalling, rebooting, reinstalling. Deleting some of the %appdata% SAP folders.
    I need some guidance as people who upgraded from GUI 7.20 do not run into this issue.

    This popup would make sense Jason,as the path C:\Windows\SapLogonTree.xml would not be a valid path to this file.
    Really, 7.10 should not have been used at all as an upgrade path as this had finished support in 2009
    If you have a small number of users with 7.10, it's recommend to remove it via add/remove programs in the OS, then install a clean 7.30 gui.
    The environment variable should not point to C:\Windows\ at all since this is a restricted folder in
    Windows Vista and higher, and will only cause further trouble later on in the updates
    See note http://service.sap.com/sap/support/notes/1409494
    Jude

  • Urgent SAP upgrade from 4.0B to 4.7 Oracle 9.2.0.6

    Dear support,
    I have upgraded my oracle database to 8.1.7.4 with 4.0B extended kernel along with upgradation from NT 4.0 to Win 2000 is finished , and we are planning to upgrade SAP to 4.7 version.Please let me know whether i need to upgrade my database to oracle 9.2.0.6 before upgrade prepare phase ,
    If yes then , do 4.0B ext kernel on Win 2000 will support oracle 9.2.0.6
    I am not able to find any info on service.sap.com\PAM , because info about 4.0B
    version not available.
    Best Regards,
    AjitR.

    -> regarding 40B_EXT see sapnote 1.009.695
    -> see sapnote 85.838 (section Operating System: WINDOWS FOR X86):
    <b>SAP KERNEL 4.0B_COM 32-BIT:</b>
    <b>ORACLE 8.1.7      WINDOWS SERVER 2000/IA32 32BIT    4,5
    ORACLE 9.2            WINDOWS SERVER 2000/IA32 32BIT     6,7,8</b>
    ORACLE 9.2            WINDOWS SERVER 2003/IA32 32BIT     9
    SAP KERNEL 4.0B_EXT 32-BIT:
    <b>ORACLE 9.2            WINDOWS SERVER 2000/IA32 32BIT     6,7,8</b>
    ORACLE 9.2            WINDOWS SERVER 2003/IA32 32BIT     9
    GreetZ, AH

  • Is it possible for XI 2.0 to connect to ECC 6.0 upgraded from SAP R/3 4.6?

    Hi,
    I just wanted to know whether it is possible for XI 2.0 to be used with ECC 6.0 which is upgraded from SAP R/3 4.6.
    If yes, could you forward some links so as to know how.
    Thanks,
    Fariha

    hi,
    >>>>Is that Possible..?
    yes
    >>>Wont there be any additional configuration needed ?
    if you use IDOCs then you don't need anything special
    Regards,
    michal

  • Regrding upgradation from sap r/3 4.6 to ECC 6.0

    Hi Friends,
    We want to upgrade from 4.6C to ECC6.0 .
    Pls can any one suggest me which tool i have to use .
    Possible pls send me some docs on this one.
    Thanks & Regards,
    Ramnaresh.P

    hello,
    u need to post in forums SAP Solutions » SAP ERP 6.0 Upgrade .this is not the forum to post,
    For the info:
    For the functional and technical changes, check out the release notes for SAP ERP 6.0 and SAP NetWeaver (AS ABAP usage type) on the help portal respectively. http://help.sap.com
    You can also check out the SAP ERP solution browser on the SAP ERP upgrade page. http://service.sap.com/erp-upgrade.
    http://solutionbrowser.erp.sap.fmpmedia.com/
    Please refer to the following links -
    https://wiki.sdn.sap.com/wiki/display/HOME/ERP2005+Upgrade
    https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/webcontent/uuid/7308da46-0d01-0010-30aa-b61527ba008c?rid=/library/uuid/9cfdd546-0d01-0010-6688-ba8ddc48edc9
    http://www.id.unizh.ch/dl/sw/sap/upgrade/Master_Guide_Enh_Package_2005_1.pdf
    http://www.sap.com/solutions/business-suite/erp/pdf/ERP_Upgrade_Guide.pdf
    Reg,
    Dhanya

  • Upgrade from SAP R/3 4.6 C to ECC6.0 - To find obselete and new tcodes

    Hi,
    We are planning upgrade from 4.6C to ECC6.0 .Is there a table in SAP which contains old and new transaction codes? or is there any easy way to find obselete transaction codes and new Tcodes.
    I also want to know the new tables added and replaced tables .Any
    help is appreciated.
    thanks
    Venkateswara Rao Yeleswaram

    Hi
    Try this link, which will give functionality enchancements between different versions of SAP.
    http://solutionbrowser.erp.sap.fmpmedia.com/
    Regards
    Ramakrishna

  • Upgrade from Training and Events managment to SAP LSO

    Hi,
    We've upgraded from Training and Events management to SAP LSO 604 and during that process we have run the execute booking relationship harmonization node in IMG.
    We still have references to Business event groups and Business event type in themaster data catalog instead of Course groups and Course types. Are we missing something?
    Thanks,
    Swathi.

    Hi Swathi,
    You have not missed anything, they  resemble the same both in TEM & LSO so dont worry.
    Go Ahead >>>>>>>>>>>>>>
    Regards
    Rafi

  • How  to Upgrade from SAP NetWeaver 7.01 to NW 7.02?

    Hi Experts,
      I am working on GRC upgrade project,we need upgrade to GRC10.0 from GRC3.0.
    GRC 10.0 only work on NW7.02,we now have NW7.01. 
      How  to Upgrade from SAP NetWeaver 7.01 to NW 7.02?
    Use EHPI tools or just spam/saint  or any other way ?
    current version:
    SAP_ABA 701 0006 SAPKA70106
    SAP_BASIS  701 0006 SAPKB70106
    PI_BASIS 701 0006 SAPK-70106INPIBASIS
    SAP_01 0006 BW SAPKW70106
    Thanks!

    HI,
    Net wevaer 7.2 CE is totally different from Net weaver 7.01.
    No relation i feel.kindly check the links.
    http://help.sap.com/saphelp_nwce72/helpdata/en/44/d958673ef05f4de10000000a11466f/frameset.htm
    http://help.sap.com/content/documentation/netweaver/index.htm
                      OR
    You do not need Netweaver 7.2 CE for using NWBC 3.0. You just need netweaver 7.02.
    You simply need to apply enhancement package 2 on your existing 7.01 system to make it 7.02.
    Please refer to installation guides on service marketplace, there you can see the EHP2 installation guides.
    Also, see SAP Note 900000 - Netweaver Business Client - FAQ. This will give you all the details required.
    *Regards,
    Ajitabh

  • SAP AFS Upgrade from version 5.0 to 6.4

    Hi Experts,
    I wanted to know if someone here was familiar with the SAP AFS upgrade from 5.0 to 6.4. I wanted to know how exactly they improved the  areas listed below. (obtained from SAP Course). Your help would be greatly appreciated
    http://www.sap.com/services/education/catalog/globaltabbedcourse.epx?context=%5b%5b|wdedaf||1||de|%5d%5d|
    1) Improvements in the areas of planned independent requirements, seasonal concept, value add services, Combined order, productionu2013 warehouse interface
    2) Production Planning Basic Data - Enhancements of AFS Bill of Material (AFS BOM), SKU Group Based Routing
    3) Manufacturing Execution u2013 Collective Planned Order Conversion, Combined Order Confirmations
    4) Batch Determination/Classification for SAP Apparel and Footwear
    5) Handling Unit Management for AFS
    Thanks,

    Hi Ronny,
    Thanks for the reply!
    These patches you speak of, is it for the types of issues I mentioned in my first post or do they cover the entire AFS functionality? I assume it still requires complex configurations but are there a lot of complications with going from AFS 5.0 to 6.4, compared to a new AFS 6.4 implementation? Specifically with the grids, categories and BOMs?
    /Cheers

  • MB_DOCUMENT_BADI - SAP R/3 release upgrade from 4.7.1 to ECC 6

    Once finished upgrading from SAP R/3 4.7.1 to SAP ECC 6, from SPAU I see that there was no problem on the implementations of this BAdI. But when I tried the transaction, where this BAdi was implemented in, I realized that my implementations were not working. In addition, from SE19, I see that these implementations are active, so why they aren't working?
    I think that there are some problem in BAdI implementations when upgrading SAP release, but I don't know how to solve my problem and turn on my implementations.
    Thanks,
    Luca

    Hi Sunny,
    i continued with the option - without ADD ON.
    So, this mount point and ADD ON dvd issues are over.
    In the next screen, i have to specify the xml file and place the packages under EPS/in. I have done that accordingly and now i get a new error - No matching SAINT package for 'SAP_APPL' found.
    Any ideas where i have done wrong?
    Thanks,
    Mohan.