Uploading the past cost on project
Hi,
We have implemented PS module in our company recently. We have many ongoing projects, whose past cost and revenue need to be uploaded on a WBS so that actual cost and actual revenue for that project comes true in all PS reports. How can i do this without affecting any GLs ad i dont want to disturb GL balance.
Regards
Kalpesh
Hi Kalpesh,
You can upload Planned Cost and Revenues using BDC or BAPI Function Module. Show the way how you are going to do cost planning to your ABAPer and He will guide you the suitable method to be choosen for uploading the Data at WBSE Level and can generate a program for uploading data from external flat file in to SAP.
Br
Hari
Similar Messages
-
Hello All,
I have successfully installed Primavera Unifier R9.12 on my system. I had searched a lot but I didnt find any document which tells you how to upload capital planning/cost control/project delivery management module in Primavera Unifier R9.12. Can anyone pls share the steps or document.
Thanks
AKHILHI Akhil,
I'd love to help you in this area but i only know the product from a tech/install side of things.
My functional colleagues had the exact same gripe that you have regarding sample data - unfortunately with the way Unifier is designed in regards to it being both customizable and difficult to delete/change some objects it doesn't quite lend itself to having sample data the way P6 does.
Good luck playing/learning the tool
Regards
Alex -
How to reconstruct the statistical cost of project stock?
Hi, Experts,
We added the statistical cost element of 90 category for project stock BS account.
Now we find that some of the project stock don't have statistical cost,
some of the project stock have statistical cost(Value type: WRTTP=11).
How can we reconstruct the statistical cost of project stock to make it right?
Thanks a lot in advance.
Best Regards,
NansenTry running CJEN for your project. Make sure you remove the test run tick.
Regards -
How to upload the RM and PM budjeted cost in sap.
Dear sap guru's,
Could you please suggest me , how to upload the 2008 budjeted cost(RM/PM) in sap, One way i can upload the budjet Through materi master( costing2 tab) ie planed price1 or 2 , Please suggest me is there any other way to upload the Budjeted cost of (RM/PM), or if i upload in planed price 2 is there any effect in future. Kindly suggest me to this example ,
BUDJETED OCST ACTUAL COST VARIANCE
FG COST IS -: 5 Rs FG COST IS : 4 RS FG COST IS :1 RS
Two materials under FG Two materials under FG
Budjeted Price MAP
1) RM cost ;- 2 Rs RM cost ;- 1 Rs RM cost ;- 1 Rs
2) PM cost :- 3 Rs. PM cost :- 2 Rs PM cost :- 1 Rs
Please suggest me is there any report to view Total budjeted ocst , actual cost and variance report for Each FG wise and RM AND PM wise.
Kindly consider this issue as an high priority one, pls guide me, my client is very much urgent.
Thanks & Regards,
Kumar.. TCode : LSMW.
2. Enter Project name, sub project name and object name.
Execute.
3. Maintain object attributes.
Execute
select Batch Input recording
goto->Recording overview
create
recording name.
enter transaction code.
start recording
do recording as per ur choice.
save + back.
enter recording name in lsmw screen.
save + back
Now there will be 14 steps.
2. MAINTAIN SOURCE STRUCTURES.
Here you have to enter the name of internal table.
display change
create
save + back
3. MAINTAIN SOURCE FIELDS.
display change
select structure
source_fields->copy fields.
a dialogue window will come .
select -> from data file
apply source fields
enter No. of fields
length of fields
attach file
save + back
4. MAINTAIN STRUCTURE RELATIONS
display change
save + back
5. MAINTAN FIELD MAPPING & CONVERSION RULE
display change
click on source field, select exact field from structue and enter
repeat these steps for all fields.
save+back
6. MAINTAIN FIXED VALUES, TRANSACTION, USER DEFINED
execute
save + back
7. SPECIFY FILES.
display change
click on legacy data
attah flat file
give description
select tabulatore
enter
save + back
8. ASSIGN FILE
execute
display change
save + back
9. IMPORT DATA.
execute
display change
save + back
10. DISPLAY IMPORTED DATA
enter ok, it willl show records only.
back
11. CONVERT DATA
execute
display change
save + back
12. DISPLAY CONVERTED DATA
execute
display change
save + back
13. CREATE BATCH INPUT SESSION
tick keep batch input folder
F8
back
14. RUN BATCH INPUT SESSION.
sm35 will come
Object name will be shown here
select object & process
inputs given by KAPIL -
How to use LSMW using the IDOC to upload and maintain cost center group
Hi Everyone,
Is there anyone who knows how to use LSMW using the IDOC functions instead of the recording. I wanted to upload the alternative cost center group I created in the system.
reply would be greatly appreciated
Warm RegardsHi Praveen,
There is a risk trying to migrate data directly into standard tables because this can generate database inconsistences or wrong inserted data according to what is customized in the target system. I do not recommend migrate like this.
With LSMW you use objects like direct input programs, idocs, bapis and recorded batch input. Try to create a project and use an standard object for your data. Also, check in SXDA transaction (Goto-->DX programs) if there is a standard program for your data.
Anyway, if you want to upload data directly to tables, read below thread:
["UPLOAD CSV FILE";
[how to upload .csv file into a custom table;
Regards,
Roger -
Uploading the Cost to Network - Activities in Cut over
Hi All,
As a part of Cut over activities, Is that possible to upload actual cost to Network - activities in Producion environment?
As a best practice, till now in my projects, I have uploaded the Intial cost to WBS only.
Regards
Prabu KHi Abdul,
While using KAFD, we can post legacy or historical actual cost.
The most important this is that, define one WBS element in your project structure and name it as Historical WBS element which will receive all your legacy costs. By doing so, we are posting all our legacy costs to One WBS element only.
Here what you have to do is difine the Historical cost elements which are used only for these migrated projects and not for regular opeative structures.
Input the current period - current period always be in which period project is being migrated.
then input the Year - in our case we have not defined multiple years but as a lumpsum amount in current year (the year project is migrated) that will stay as historical cost. You will not see any break up of historical costs in SAP but you can see break up of actual coss in legacy system.
Hope this clarifies and let me know if you need any further inputs.
Regards,
PSR
Edited by: PSR on Oct 10, 2011 4:09 PM
Edited by: PSR on Oct 10, 2011 4:29 PM -
When the labor cost of timesheet go to the Actual Cost Line Items report ?
Hi ,
when the user book the time in timesheet on Network / Activity, when this record reflect the actual cost of project ?
After Timesheet Approve via CATS_APPR_LITE
Or after Confirmation
Or after transfer via CATA
Who can tell me the relationship among these three steps ?
Thanks and Regards
ShubinHi,
The flow is like this ( if u r using timesheets for confirmation):
CAT2 : Timesheet: Enter Times : User enters the time.
CATS_APPR_LITE : Approval of timesheet
CAT5 : Transfer to Projects.
This will post cost to Projects.
Another way of getting the Actual cost is Confirmation using CN25 or CN29.
Regards, -
Retirement Cost in Project Costing
Hi,
Can anyone help me out the steps to capture the retirement costs in Project costing for Capital Projects.
Regards,
MurthyWell, in a capital project, you collect the CIP and expense costs for each asset you are building. The same applies to retirement costs. You use a capital project to accumulate/capture costs associated with the retirement of a group asset. Oracle manuals do specifcally use the term "retirement of group assets" when capturing retirement work in process (RWIP). You would then interface the RWIP costs to Oracle Assets (the same Mass Additions process as setting up a new asset). Why they say group asset, that I do not understand? Why should it matter if it is a group asset or not, when it comes to retirement? I personally have never done this though. If we have any retirement costs, we just record directly to the general ledger - don't record any Oracle project cost. But then we don't have a lot of assets and don't retire many assets as a result. Will be interesting to see if any Oracle customer out there is actually doing this. You may have to end up going to Oracle Support to get this information. The user guide is not very information about exactly how this RWIP thing works. Make any sense?
John Dickey -
I have uploaded photos from the past and they are automatically arranged by date. As a result, there are many events grouped into one library/event/folder/album (not sure of the proper terminology) I'd like to separate them into folders/albums/smart albums so that I can easily identify the contents. How do I do that and do I delete the originals?
It would be good to take the tutorials and learn iPhoto - these are for the previous version but the concepts are the same and much of the command is the same - and it would be a worthwhile investment of time to take the iphoto tutorials - http://www.apple.com/findouthow/photos/ - they are very helpful and will save you a lot of time and frustration. - also the tutorials in iPhoto Help will be helpful - while iPhoto is easy and intuitive it does have a learning curve and it will save you time and pain if you spend a few minutes learning the basics
as to organization - events are generally time based and are the basic automatic organization - you can merge and split them to make them work better for you but they are not a good way to do detailed organization - best to leave them time based
albums are logical things that contain photos and are just pointers to the photo in the event so they take no extra space and all changes to a photo anywhere are reflected everywhere
Smart albums are the same except they are automatically filled based on the criteria you set when you create them
Folders are containers that you create and a folder can contain albums, smart albums or other folders so they are a big help in organization - like a vacation folder that holds folders for France, USA, China with each of thos folders holding albums of photos from the country
LN -
Is there a way to copy & paste a clip from the timeline in one project in to another project?
Hello Popular Premiere Pontificaters,
I am using Premiere 6 on a Windows 7 machine.
Is there a way to copy and paste a clip from the timeline in one project in to another project?... I can copy my clip, but when I open the other project, it will not allow me to paste it in there... but I am able to copy and paste a clip within a single project. I tried everything... pasting in to a new video track and pasting in to an existing video track in the second project, but the paste option simply isn't there when I open the second project.
And if Premiere itself will not allow me to do this in any way, will a copy-paste clipboard type of accessory app allow me to do this?... if so, which is the best, trustworthy copy-paste app that is malware free?
Thanks,
digiHi Bill Hunt,
I just read the page that you provided about "Handles"... thanks allot for that ARTICLE. In your article and the subsequent article HANDLES, "Transitions Overview: applying transitions" linked from your article, it indicates (in PrE and PrPro anyway - I'm in Premiere 6) that transitions can be applied to non-Video 1 tracks... the paragraph below is a quote from that "Transitions Overview: applying transitions" article...
"Whatever is below the transition in a Timeline panel appears in the transparent portion of the transition (the portion of the effect that would display frames from the adjacent clip in a two-sided transition). If the clip is on Video 1 or has no clips beneath it, the transparent portions display black. If the clip is on a track above another clip, the lower clip is shown through the transition, making it look like a double-sided transition."
So this indicates that transitions can be applied to non-Video 1 tracks since it is referring to content in tracks beneath a transparent fade that would show through... and only non-Video 1 tracks can be transparent and have other clips "beneath" them in the timeline, right?
In the screenshot sample in your article at this LINK, I see the handles (referred to as B and E) and I can see in my monitor window how those handles would be represented by the two little bracket symbols { } ... you can see how they appear in my monitor window in Premiere 6 in this screenshot, and below, from a different thread that isn't related to this topic.
But I'm still trying to figure out how the handles can be applied in the non-Video 1 tracks in the timeline to insert a transition (cross-dissolve) between two clips.
Can you advise me on this?... I posted a separate thread HERE on this topic, but I haven't got any further with finding an answer.
Thanks so much for your article,
digi -
I've unable to Export iMovie project in everyway I have attempted for the past 2 weeks.I have a late 2012 iMac with 8gb of RAM and 700 gb of free space on the hard drive. The video I am trying to export is 48 mins long with most of the source footage from a NIkon D3100 and several other cammcorders. I've been exporting with Apple Intermediate codec because that was the only one that has work so far but it only worked once and since then I have had to make changes to the project and now I'm unable to get it to work. For all Quicktime exports in H.264 or AIC (my prefered format for this export since I figured it'd offer the highest quality when I import it into Encore for making a dvd out of it) Which just stops exporting in the last few minutes without explination as to why or it crashes and quits. It either leaves a partial file or nothing at all. When I do "export movie" I get a "not enough memory Heap zone error"
I don't know what to do any help would be greatly appreciated!
By the way I happen to have Adobe CS6 Production Premium but didn't know how to use it as well when starting the project and now really regret not using it because it appears to be 10x more stable and capable of handling all the tasks I want it to do.Hi
Error -108 memFullErr Ran out of memory [not enough room in heap zone]
Turn off - TimeMachine usually works - re-try.
(the Application down in the Dock - not the Device)
But this can mean many thing's - My first thought is
Free Space on Start-Up hard disk. How much ? (other disks do not count)
AppleMan1958
Are your event clips in h.264? If so, you can solve this by Right clicking on your Event Name and choose "Optimize Media". You can choose Full for 1080P or Large for 960P according to your preference.
After you have optimized your Event, you should be able to Share with no problem.
Lennart Thelander
-108 mean you are running out of (free) RAM.
Try restarting the computer just prior to sharing. That frees up RAM.
from mynameisearl
Final Entry
Ok - after much cutting, trial and error and days of work I have never really established a root cause for the -108 error. Nothing I did resolved the issue to the orginal project.
The only work around I have found is to split the Original Project into two.
What I found was that anything around the 60 mins mark and above just failed to render in HD and showed the -108 error.
What worked for me was creating two project files - one around 57mins long - the other a part 2 - around 17 mins long. All using exactly the same source clips, photo's, music and transitions as the orginal.
This now works. I guess having it split in two makes it a little easier to work with as I wont have to keep rendering the first part which does not change but really wish Apple would throw some light on this.
Anyway - I hope all of the above at least proves useful for others.
Good Luck -
Cost of batch number in the past
hello
is there a way to see what the cost of a batch number was at a specific date(in the past) as well as the quantity on hand in the past?
The client wants the following information :
Batch Number
WHS
Item Code
Description
Quantity
Weight
Tonnage
Cost
CJ77974
A01
CC 0.70X1300 04
CC 0.70X1300 EN10268 HC 260
23 260.00
1
23260
CJ78006
A01
CC 0.70X1300 04
CC 0.70X1300 EN10268 HC 260
20 530.00
1
20530
CJ77925
A01
CC 0.70X1300 04
CC 0.70X1300 EN10268 HC 260
6 790.00
1
6790
CZ80386
A01
CC 1.00x1400 F65
CC 1.00X1400 G3135 SPFC 440
23 170.00
1
23170
They this want to see the cost and quantity on hand for e.g. 30/05/2014(a date in the past).
Any advise will really help.
thanks
JaniceWorked for me too. options->options->privacy->remember download history
-
I cannot upload any pictures to Flickr for the past three days, I just get the upload screen which when I click on upload does nothing I'm using PSE12, I have had no problems in the past , I still have had no response to this post and it has been several weeks since initially posted, is there anyone awake at Adobe, can someone give me advice or is there total lack of interest once the product has been purchased I have been a customer of PSE for many year since PSE6 now on 12 but lack of response may cause me to rethink
Turn off your iPad and put it in recovery mode. Try to restore it via iTunes.
http://support.apple.com/kb/HT1808 -
Recently erased my entire mac HD do to mavericks update going wrong. I do not have a back up for my music. But my itunes match account has all my music. If i add this computer with my itunes match will it put all the music i had back in my itunes library or just upload the little bit of music i purchased on itunes in the past that im only seeing now in my itunes? I do not want itunes match to sync or upload the little bit of purchased music i have on my itunes now..Please Help Thanks..
Hello gogreenj14,
If you had iTunes Match updated with all of your non iTunes purchased content already, then yes, when you enable iTunes Match with the following article it will have all the content that has been uploaded to iTunes Match will be available for download.
iTunes: How to add a computer or iOS device to iTunes Match
http://support.apple.com/kb/ht4913
Open the latest version of iTunes on the computer you intend to add. You can download the latest version of iTunes here.
Sign in with the Apple ID you use with iTunes Match.
Choose Store > Turn On iTunes Match.
Click the Add This Computer button.
When prompted, enter your Apple ID password.
iTunes will automatically begin scanning your computer's library for matches.
A status indicator will allow you to track progress. You may also manually pause and resume the process at any time by clicking the Stop or Start button.
Once iTunes has completed matching and uploading your iTunes library, your music in iCloud will be integrated into your local music library. A download button will appear to the right of any content that you have in iCloud that doesn't already exist on your computer.
Thank you for using Apple Support Communities.
Cheers,
Sterling -
When making a photo book, my iPhoto freezes during uploading the book to the storey. I have attempted this 4 times now and I don't know what to do! I know the file size is massive due quantity of large image files, but I don't want to reduce the image file size and compromise quality in the book. How can I get past this?
My macbook air is os x 10.9, using iPhoto 11 9.5 (902.7).Try Old Toad's solution here: See Re: iphoto : upload impossible to print a book
Try to boot into Safe Mode and order this way, or sign into a different user account and try to order as a different user.
Léonie
Maybe you are looking for
-
ITunes stopped syncing movies on my iPod Touch
This one is driving me crazy today. iPod Touch - latest generation. iOS 8.1. iMac 27 - Yosemite 10.10. All updates current. iTunes 12.0.1.26 For a few years now, I've had home videos of my granddaughter on my iPod Touch. About a dozen of them. Today
-
Set Delivery date blank - URGENT
Hi All I am working on SRM 5.0. I have received a requirement to blank out/clear DELIVERY DATE/ REQUIRED ON field. For example: Click Describe Requirement ,and there will be fields to be filled up and the REQUIRED ON field is defaulting to system dat
-
I have a dynex 32" lcd tv and a pavilion dv6 and cant view the laptop on the tv using hdmi cables
trying to view netfilx my computer has windows 7 when i plug in the hdmi cable in the computer screen goes black and there is no signal on tv
-
Web Gallery: Two things needed
I desperately need (or want) two things: 1) a simple number scheme on top of the thumnails, 1,2,3 etc, so I can say to the client, "check out, 1,2,3, &... etc without having to open the image to it's larger preview. 2) A way to color label the thumbn
-
I'm trying to create a JavaBean to use with Forms 6i. I have the Java code right, however I'm stuck on how to implement the bean in Forms. Does anyone know the process/steps to go through to get the forms to recognize your bean?