Urgent!! Process Chain Failure!!

Hi Guru's:
One of our PC's failed today with the below error message:
@5C@     Process Local Process Chain, variant SF 45  Account Recievable Tran. Data. has status Canceled (instance 2L9PVZWCAX8DTIDK5TFKL1T     @35@
Help needed!
Rgds,
BH

It looks like the process was aborted externally. Check the data targets, if the contain any failed requests, delete these and restart the process chain.

Similar Messages

  • Process chain failures...

    Hi Gurus,
    Can someone please send me a link which has got some common process chain failure issues with the resolutions....
    Thanks & Regards.
    Pawan.

    Hi,
    Common Errors can be like
    1. SID Failure while loading data.
    2. Activation Failure.
    3. Idoc failure
    4. Failure in Source System.
    5. Table space issue while loading.
    6.No SID found for a characteristics
    7.No Data found in the soucre system
    8.DATASET Errors: Short dump with Various DATASET errors
    9.Hierarchy load fails with error ‘Incorrect Hierarchy Structure with Consistency Check’ / NodeID XXXXX not included in the Hierarchy.
    10.Invalid character error
    11.File not found (System Command for file check failed).
    12.Error occurred due to Short Dump.
    13.Attribute Change Run failed  -  ALEREMOTEBW was locked.
    Thanks,
    Nagesh.
    Edited by: Nagesh Mule on Jan 30, 2008 7:19 AM

  • Process chain failure due to weekly maintanence

    Hi experts,
    we have BI sytem shutdown every week ok sundays due weekly system maintanence.In that process we have few process chain failure as well as batch job failures and each time we have to fix it by manual loading of data.
    Any one help me fixing it once for ever.
    Thanks for your help.
    Thanks
    Smitha.

    Hi,
    Is ur PC running when the system is shut down?? if yes then u have to fix manually...The best practice is to finish off the loads before the system is shut down. Make sure that all the deltas are pulled before the system is down..
    try this for restarting PC
    /people/siegfried.szameitat/blog/2006/02/26/restarting-processchains
    after cleaning up all the datatargets u can restart it as mentioned in the above link...
    Regards,
    B

  • "Syntax error in the MDX statement " in Process chain failure??Urgent pls

    Hi Experts,
    could any one suggest me the procedure to rectify the below problems in process chain?
    1."Syntax error in the MDX statement "
    2."Error when getting data (Error when getting data (AXI))"
    Rgds,
    BH

    In which case it'll be that Access has a different date format to MySQL, and you're trying to push the string "'25-Apr-12 10:55 PM" into Access, which it's not understanding. To get around this, you need to treat your variable as a true date/time object, rather than a formatted string.
    CFQueryParams should be used on absolutely every database platform, they'll stop your website being vulnerable to SQL Injection attacks for one, which at the moment you're wide open to. Replace your query with something like this:
    <cfquery name="input_comments" datasource="#DSN#" username="#DSNUSER#" password="#DSNPASS#">
          INSERT INTO comments(
                             commenter,
                             comment,
                             datetime,
                             post_id
                   VALUES(
                             <cfqueryparam cfsqltype="cf_sql_varchar" value="#form.commenter#" />,
                             <cfqueryparam cfsqltype="cf_sql_varchar" value="#form.comment#" />,
                             now(),
                             <cfqueryparam cfsqltype="cf_sql_numeric" value="#form.post_id#" /> )
    </cfquery>
    The QueryParams will handle the data types for you, and should pass values around more safely and with fewer issues. Assuming you just want to store the current date and time you don't even need to get ColdFusion involved, as databases have their own functions for this. I believe Access' version is simply NOW(), so I've put that in your query.
    Give the above a go.

  • URGENT:Process Chains And events Related

    Hi All,
                  I have created a new process chain which is a normal ODS Process Chain.For that I started with the start Process and then created event in sm62 to trigger the start of process chain.Similarly,I have at the end of the process chain ,I have added 2 ABAP Programs ,one to mark the successful completion of process chain and another to mark the Error or Unsuccessful completion.For these programs,I maintaines Processvariants and here, we have utility Programs.So used the relevant utility program and created a program variant and Events ,One for successful completion of process chain and another to mark the Error or Unsuccessful completion.
    But ,Now ,I find that when I trigger the eventin sm64,I find that the process chain is not being run.Is that any problem with the events I created.This is the first i am involved  with creation of events in SM62.Can anyone help me in  this regard.
    Can anyone,tell me thatdo we need to do anything else apart from  Creating events .Imean like assigning jobs and then Programs in the Step of that Job.
    Please Kindly help me in this regard.It is very very urgent for me.Thank you.Points will be assigned.
    Regards,
    Samir

    Hi,
    I have tried in the same way you have said .I have maintained as after event and activated and scheduled.after that  i triggered the event insm64.But still,I am not able to see the Load in RSMO.
    I have just checked out in sm37.And found that some jobs have failed.I think this might be the reason for the Process chain to not run.
    I am just pasting the error msg and solution.
    Job BI_PROCESS_ABAP, waiting for event RSPROCESS 489W6WH6I7OHV7BL3N9909F7F, has no predecessor
    Message no. RSPC003
    Diagnosis
    Although job BI_PROCESS_ABAP has been started by event RSPROCESS 489W6WH6I7OHV7BL3N9909F7F and is recognized in the process chain, the current run for this process has no job preceding it.
    This is why the system was unable to determine a log ID, and the chain is broken.
    System response
    The job has been terminated.
    Procedure
    With the exception of the start process, each process must have a process that precedes it.
    Then Another error for the another cancelled job is
    Job BI_PROCESS_OR, waiting for event RSPROCESS 489WC2QYBC4AJSYILQ10TWABF, has no predecessor
    Message no. RSPC003
    Diagnosis
    Although job BI_PROCESS_OR has been started by event RSPROCESS 489WC2QYBC4AJSYILQ10TWABF and is recognized in the process chain, the current run for this process has no job preceding it.
    This is why the system was unable to determine a log ID, and the chain is broken.
    System response
    The job has been terminated.
    Procedure
    With the exception of the start process, each process must have a process that precedes it.
    Please kindly help me if you understand the problem.
    Thanks,
    Samir

  • Process chain failure at AND condition

    Hi gurus,
    Please help me with this issue .
    the process chain is failing at  the AND process after the DTPgets succesful . its giving the error message as"THIS AND PROCESS IS NOT WAITING FOR EVENT RS PROCESS".
    PLEASE SUGGEST.

    Yes,
    there are two dtps which are connected to this AND process.process chain is successful untill this dtps and failed at this AND condition. please suggest to fix this and let me know wht will be the possible reason for this failure.
    thanks for your help

  • Importing TR related to Process chains failure in quality

    Hi I am getting following error while transporting process chains from dev to quality it is saying method execution failure and log is giving as below. please suggest me the solution.
      Execution of programs after import (XPRA)
      Transport request   : SCDK904729
      System              : SCQ
      tp path             : tp
      Version and release: 372.04.82 700
      Post-import methods for change/transport request: SCDK904729
      Post-import method RS_AFTER_IMPORT started for RSPC L, date and time: 20100526112312
      Start of the after-import method RS_RSPT_AFTER_IMPORT for object type(s) RSPT (Activation Mode)
      Start of the after-import method RS_RSPV_AFTER_IMPORT for object type(s) RSPV (Activation Mode)
      Start of the after-import method RS_RSPC_AFTER_IMPORT for object type(s) RSPC (Activation Mode)
      Version 'M' of chain Z_AP_BNL_SCEN_2_3 was saved without checking
      Results of check for process     in chain  :
      Version 'M' of chain Z_AP_CZ_SCEN_2_3 was saved without checking
      Results of check for process     in chain  :
      Version 'M' of chain Z_AP_PT_SCEN_2_3 was saved without checking
      Results of check for process     in chain  :
      Version 'M' of chain Z_AP_SK_SCEN_2_3 was saved without checking
      Results of check for process     in chain  :
      Start of the after-import method RS_RSPC_AFTER_IMPORT for object type(s) RSPC (Delete Mode)
      Start of the after-import method RS_RSPV_AFTER_IMPORT for object type(s) RSPV (Delete Mode)
      Start of the after-import method RS_RSPT_AFTER_IMPORT for object type(s) RSPT (Delete Mode)
      Errors occurred during post-handling RS_AFTER_IMPORT for RSPC L
      The errors affect the following components:
         BW-WHM (Warehouse Management)
      Post-import methods of change/transport request SCDK904729 completed
           Start of subsequent processing ... 20100526112312
       Execute reports for change/transport request:
       Reports for change/transport request have been executed
            Start of................ 20100526112312
            End of.................. 20100526112312
       Execution of programs after import (XPRA)
       End date and time : 20100526112312
       Ended with return code:  ===> 8 <===

    In rspc , check for the four process chains given in error log ( there is a check button in the menu bar , once you click that it will show the process variant which has error as red )
    Version 'M' of chain Z_AP_BNL_SCEN_2_3 was saved without checking
    Results of check for process in chain :
    Version 'M' of chain Z_AP_CZ_SCEN_2_3 was saved without checking
    Results of check for process in chain :
    Version 'M' of chain Z_AP_PT_SCEN_2_3 was saved without checking
    Results of check for process in chain :
    Version 'M' of chain Z_AP_SK_SCEN_2_3 was saved without checking

  • 'AND' process in a process chain failure - need help

    For the first time and out of no where, two separate 'AND' processes in two separate process chains failed on two separate days. It displayed error the same messages in both isntances as below. It seems that when the first load completed and the second was still in progress, this 'AND' attempted excecute and failed.
    I had to manually resume the chain by setting the 'AND' status'to 'G' in RSPCPROCESSLOG table. I also plan to recreate those 'AND'.
    But did anyone here experience this problem and know the root cause?
    Thanks for any assistance!
    Julian
    This AND process is not waiting for event RSPROCESS, parameter      
    Job cancelled after system exception ERROR_MESSAGE

    Thanks, Shambhu!
    I am planning to create new ones. But my problem is that I hate to recreate all 'AND's I have in all our chains. There are a lot of them. But if I don't, I have no idea which is the next victim ...
    Julian

  • Process chain failure

    Hi Guys,
    We have process chain defined for sales order history upload from BW to APO planning area. Its failed with logs :
    1- DataSource 8PBSD_C01 has to be replicated (time stamp, see long text).
    DataSource 8PBSD_C01 does not have the same status as the source system in the Business Information Warehouse.
    The time stamp in the source system is 19.12.2008 23:55:19.
    The time stamp in the BW system is 30.07.2008 16:36:49.
    2- Errors in source system.
    Message no. RSM340
    The process chain failed at very first step. please help to resolve it.
    Quick question:
    1. how to see the planning area wether it's on full load or delta load?
    2. how to compare the planning area data and infocube data so that i can see data difference?
    Cheers
    PK

    Thanks a lot Venkat. Here is process steps which i am going to follow.Since, i am doing it very first time ,please let me know if  any step is missing/doing anything wrong.
    Steps to solve this problem
    Replicate data source
    Step 1 u2013 Replicate source system. In RSA1 go to BW data source data mart -BW info cube (8PBSD_C01). Right click on info cube and click on REPLICATE META DATA.
    STEP 2- Activate Transformation rule for APO info cube 8PBSCM_C04 and save in transport request.
    STEP 2.1- Activate Data Transfer Process and save in same transport number.
    STEP 3- Delete initializations in info package.
    STEP 4 u2013 Select Delta initialization with data transfer.
    STEP 5 u2013 Execute info package.
    Prerequisites
    STEP 1- Delete APO info cube 8PBSCM_C04 data.(how to do it?)
    STEP 2- Delete PSA data.(how to do it?)
    STEP 3- Delete Index in APO info cube 8PBSCM_C04. (Manage  performance delete index).(how to do it?)
    STEP 4- Check planning area data in Live Cache. Delete and regenerate Live Cache.(how to do it?)

  • Urgent: Process Chain Priority Pop-Up

    Hi,
    We are trying to schedule a process chain from an abap program using the function module RSPC_CHAIN_START. But on execution a pop up is appearing to set the job priority. Is there any way to set this value through the program to avoid the pop-up or is there any other suitable function module that can be used to set this priority while scheduling the process chain.
    Thanks,
    Pratik.

    you must give the Priority before secheduling the PC only once. There will be A B & C Priorities & you can select any one of these so as to sechedule the chain.
    Regards
    Sivaram Daggubati

  • URGENT-Process Chain - transport error

    Hi
    I am facing a problem in process chains
    when I tranport to quality system my chains are not activated after importing it is raising the error as
    Error in remote call of destination ABAP Connection
    Message no. RSPC051
    Diagnosis
    The following error occurred during the remote function call for destination ABAP Connection:
    Name or password is incorrect (repeat logon)
    System Response
    A short dump has probably been written in the other system.
    Procedure
    Look at the short-dump overview in the other system.
    I am unable to get the solution!!!!! how to activate the chains in Quality.........It sreally urgent

    hi,
    chk the start variant of ur process chain whether an start immediate is choosen, if so change it to some date in future and try to transport.
    Ramesh

  • Process chain failures and errors therein

    Hi all,
    Can anyone please guide me as to why the process chain fails?
    what are the <b>various kind of errors</b> most often encountered? and how we can recifty them.....???
    Your kind suggestions are thankfully acknowledged,
    thanks and regards,
    shalini.

    Hi Shalini,
       Process Chain fails due to several reasons. if you come up with any questions our masters will guide you.
    Process Chain fails mainly due to data problem.
    Regards,
    Nagesh.

  • Notification by email about Process chains failure

    Hi,
    I scheduled a process chain to run once every hour and sometimes it fails for knowing problem.
    I would like to get an email every time it fails.
    Could someone guide me how to get a document which gives the steps to follow or provide me a step by step for this.
    Thanks,

    Hi Mohamed,
    You can create messages for a process that are trigerred either when the process failes, or succeeds, by right clicking on a process and choosing Create Message.
    Please also check the following:
    Re: Sending email from process chain not working
    Hope this helps...

  • Urgent Process chain

    Hi experts,
                  can any one tell me how to copy the process chain with step by step info
    thanx regards
    rajesh

    Hi Rajesh Y 
    Jus click on u r process chain in RSPC and then Just put "COPY" in the
    command tool bar..
    it will promt for a name..give it and say continue..
    by the way this avilable only in Bi 7.0 ..
    Hope itz helps a little..!
    Cheers
    Kishore M Reddy
    ***Assigning pointz is the only way of saying thanx in SDN ***
    **Learning the thingz is never end process if u stop it will Be a devil if u continue it will be a divine***
    > Hi experts,
    >
    > can any one tell me how to copy the
    >  process chain with step by step info
    >
    > thanx regards
    > rajesh

  • Process chain failure at save hiearchy step

    Hi Experts,
       I am facing one issue with the process chain, it has failed at Saved Hiearchy step, i have tried repeating the step twice but still it didnt work out, since i am new to BW  please suggest me pointers regarding the solution as i am  unable to solve to myself.
    Any Help/Guidance Regarding this will be Appreciated.
    Thanks.
    SB

    hi,
    kindly check whether you hiearchy is in M or A state in RSH1, generally it happens when the hiearchy when it is modifed(M) state then tit fails at save hierachy step...
    kindly activate it their and then try either repeating the step/retrigger the chain
    regards
    laksh

Maybe you are looking for

  • MSI 865PE NEO2-V booting problems [Solved]

    Hi.  I've been building a new computer and am seeing some weird stuff. System Specs: -P4 3 GHz Socket 478 -MSI 865PE NEO2-V -V22 http://www.saveateagle.com/865pe-ne...EO2-V&ovtac=CMP -128mb ATI Radeon 9800 pro -120 GB Western Digital -1GB dual channe

  • Nodes with Only One Lower-Level Node = Hide

    Hi everyone Have anyone present this situation: Iu2019ve a quey to report inventory aging. It has two hierarchies to show data. In Rows I have Major Markets and in Columns a date hierarchy to show aging Ex: from 0 to 8 months, 9+ and 13+. Of course h

  • Can I get iOs 5 on IPad 1

    Can I get iOS 5 on the iPad 1

  • Too many responses (!)

    I recently posted two questions in the forum, later I received over 100 replies (about 105 I think) in my e-mail, most of which were not related to my question. I don't know if I did something wrong, checked something I shouldn't have or what - I am

  • Track goods movements

    Hi All, Due to space constraints we had to move our stock to an outside storage facility in addition to our existing storage location and also use the outside facility for receiving external goods. How can I record goods movements in the system