Use of Planning Table (MF50) in Capacity Levelling with Production Order

Hello Experts
I wish to know that is it possible to perform Capacity Levelling in planning table (tcode MF50) with respect to a Production Order ? It is known that MF50 is used in Repetitive manufacuring to do the capacity levelling with respect to Planned orders. But in our discrete manufacturing scenario we want to use planning table to the capacity levelling with respect toa Production order.
Any clue or help pertaining to this will be highly appreciated.
Thanks in advance
Regards
Jayanta

Dear ,
MF50 is does the cacapcity leveling based on mateail -run schedule order (planned order ) where as in discrete manufacturing , when you run the MRP ,  MRP system assume Infinite Capacity  and schedule the order as per your selection in MD02(2,1,3,3,2)  and then you convert those planned order to Production order .Here you checkied the Capacity in Production Order level .
In stanadrd SAP  , it is not possible to use MF50 for discrete production order.
In discrete order or process order ,  do the caapcity leveling , there are seperate planning table available based on Over all Capacity Profile and Schedule type .This can be done  in following way :
1.CM31-Production Order Wise -Tabular
2.CM23-PO wise -Graphical
3.MC88: Ruf Cut Planning
Work Centre Wise : CM21 -Graphical , CM22-Tabular Planning Table .
Make sure the below set up before  you carry on the Capacity leveling :
.Define time profile in OPD2.
Define the strategy profile in OPDB
Define the Overall profiles in OPD0.
In OPJK  maintained check capacity with SAPSFCG013 profile for your production order type
In OPU3 , scheduleing parametre s: Generate Capacity , Scheduling Type , Automatic Log ,Start date in Past as per your req.
In OPJU , chekc the contol tab of the scheduleing as per OPU3
In OPKP- Production scheduling paranmeters assing the overall capacity profile -SAPSFCG013  with finte scheduling tick.
Master Data :
1.Materials Master define the Production scheduler and production scheduling profile
2.Work Center - Define the capcity planner group,activate checkbox Relevant for Finite sceduling,on the capacity header define the shift timings,break timings and unit of measure,no of individual capaity, enter formula for scheduling in capacity view.
3.Routing - enter the values for the standard values. Use control key with scheduling.
Hope this will help you .
Regards
JH

Similar Messages

  • Planning Table MF50

    Hello experts,
    Can some one please explain the purpose of the planning table MF50 and how to use it for capacity levelling. I am in a REM environmnt.
    Thanks
    Raman

    HI
    1)In Repetitive Manufacturing, the master plan is represented by the planning table. The planning table is a tool for operative planning and is used to plan the production quantities:
    2) In a repetitive manufacturing environment, planning and control is usually carried out in a period and quantity basis. The layout of the planning table has been designed to support this requirement and is also based on periods to provide a very clear, easy-to-interpret overview of materials and production lines.
    3)The planning table is the planneru2019s/MRP controlleru2019s most important tool for planning the production quantities. At a glance the planner can check production quantities, monitor the available capacity of the production lines and check up on the availability situation of the products produced on each line.
    4)You can directly enter and change production quantities in the planning table. You can assign u2018non-assignedu2019 production quantities to the production lines or you can reassign production quantities to alternative production lines.
    5) You create the production quantities or assign them to the production line in the planning table.
    6 )You can also use the planning table with capacity planning. Here, planning is based on lead time scheduling. The basis for lead time scheduling is the routing. You can access the capacity planning table directly from the REM planning table.
    Regards
    Anupam Sharma

  • Reg: Functions of Planning Table MF50

    Hi Friend,
    i wish you all a happy Friendship day...
    I need to know the following Function in REM,
    1. Functions of Planning table.(MF50)
    2.When we carry out Backflush , Components , activities get Posted. where can i find the reports for activities and components posted.
    3. Preliminary Costing Values.
    Thanks in advance.

    Hi dayanan,
    1. Planning table MF50 is used to create a manual planned order respective date wise inspite of creating in MD11 one by one.
    2. When you assembly backflush in MFBF your component consumption and Activities will get posted automatically GI, GR & Activities will be posted. This component consumption you can see through movement type 261 in MB51. Cost of that consumption and activities you can monitor in Product cost collector. PPC. for that go to KKF6N-select version- Header---- costs.... There you can refer the updated cost of consumption and MHR.
    3. If you to consume additional component without GR that means only GI, goto MFBF and select component backflush and enter the component which you want to consume.
    Hope this will clear all your doubts.
    Regards,
    Santhosh.

  • Resource scope when performing capacity leveling with Optimization method

    Hello,
    Can anyone tell me if, when performing the Optimization method in Capacity Leveling for transportation resources production resources are validated? I am currently testing this and I found out that if the capacity variant of the production resource is no 00, 01 or 02 the system will give an error message when trying to level a transportation resource, the message indicates that there is no available capacity for the production resource.
    When reading documentation in help.sap it appears to me that Capacity Leveling should only focus on the resource to be level not in other resources and in this case my transportation resource has available capacity that shouldn't be affected for master data errors of production resources...
    Could somebody help me clarify this issue?, I have already open a message and they suggested me to change the capacity variant of the production resource, evidently when I do this everything works but I still don't understand why capacity leveling, with Optimization method, of a transportation resources is checking on production resources.
    Thanks!
    Erika

    Hello Ian,
    I am not talking about the SNP Optimization Run that is certainly manipulated by the constraints that you update on the optimization profile; in this case "Capacity Leveling with Optimization Method" the constraints are automatically set by the system and what I need to know is if these constraints are considering not only the resource that is to be leveled (in this case the transportation resource) but also the production resource.
    Sorry but your answer does not correspond to my request, because you are talking about the Planning Optimization run and I am talking about  "Capacity Leveling with Optimization Method".
    Erika

  • Table names for Material Characteristic againgst production order

    Hi Guys,
    Actually I have a problem in finding the table name for material characteristic against production order such as Individual length, factor, color, etc. I really spend more than a day to find this. But I cudn't make it. Finally I found the flow some how, but is working only for few cases. Here is the flow.
    AFKO(RSNUM) --> RESB(OBJNR) --> INOB(CUOBJ) --> AUSP(OBJEK).
    T-code: CO02 / Fast Entry tab / Change Configuration(Item Level) / Change Characteristic values.
    Anybody knows about this. Please help me out on this. And please note that, it is not the material characteristic from MM01, it is against production order from CO02.
    Thanks
    Yasin.

    Hi Yasin,
    The best way to know Table Names in SAP is to use a Transaction Code Called : SQL Trace. Tcode : ST05. This will tell you about all the database tables that have been accessed while the Transaction was executed. And then you do a complete analysis of it, what are all the Tables that have been accessed, the fields and the data transfered. So, it's a complete trace of the SQL Query but you can use the information as needed.
    Have a look at the following Links:
    http://help.sap.com/saphelp_nw04/Helpdata/EN/17/358df9c9fee2469105731e10756921/content.htm
    http://help.sap.com/saphelp_47x200/helpdata/en/d1/801f89454211d189710000e8322d00/content.htm
    The best things is that you can use it across any SAP Transaction as it is available in SAP NetWeaver .
    Hope this helps.
    Thanks,
    Samantak.

  • Function module to calculate capacity requirements of production order

    HI
    Hav a requirement to calculate capacity requirement  for production orders like we see in cm50... does anyone know a function module to calculate capacity requirement?

    Hi All,
    Just to reopen this issue, even I am looking for a similar functionality.
    To reinstate the requirement:
    I want to find shifts and corresponding capacities for a work center. These details are obtained from CR03 and CR13 transaction.
    If possible do let me know Function module or tables for the same.
    Debs

  • Capacity for only Production orders only.

    Hi
    I am checking capacity loads in CM01.
    In this t-code its considering my Planned orers also.
    I want to capacity load for production orders only.
    we dont want during planned orders stage.
    where can i check.. what are the settings i have to do for checking capacity for only production orders.
    Regards,
    srihari.M

    Srihari,
    This is a standard requirement.
    Planned orders in a non-repetitive environment typically are not dispatched nor confirmed.  They do not, therefore, become part of the 'Basic Load'.  The capacity requirements of planned orders are there mostly so you can view the capacity requirements in sum with the production order capacity requirements (CM01 and similar).  They do not 'consume' from total available capacity.  When performing a capacity check of a production order, it will not 'see' the capacity requirements of the undispatched planned orders.
    http://help.sap.com/saphelp_erp60_sp/helpdata/en/60/13e30b133a11d3bf550000e83235ee/frameset.htm
    Best Regards,
    DB49

  • IW37n using the Planning Table with Overall Profile for Wrk Cnter Hierarchy

    Dear Experts,
      We are using IW37n to sort and filter our orders.  From there we make a selection and then GOTO the planning table to use for dispatch.  We copied the overall Profle to allow us to define the Evaluation Profile to allow for a Work Center Hierarchy and Plant to be defined.
    If I run CM25 using the overall profile the Work Center Hierarchy works fine.  If I use IW37n,  enter the same overall profile it does not execute the CM25.  Is there something else we should to get the CM25 to run?
    Regards,
    Roseanne

    Can I take this out a little further.  I verified with two orders that indeed both are being shown coming through IW37n or CM25.  I've determined that the profile is being called.  The layout shown in Chart 2 is correct.  It's chart 1 that is not showing the work center hierarchy correct from IW37n, it only shows the top node of the work center.  We have two scenario, one work center is defined with the employee linked to HRMS.  The lower node is a work center used to schedule too.  The other work center structure is the employees are defined as work centers.  We build the order to the top node and then use the hierarchy to schedule to each individual work center.  In both cases using IW37n, the lower level work centers are not shown in chart 1.
    If running CM25 independent it works fine.
    Regards,
      Roseanne

  • Clear the History Data Automatically in Production Planning Table MF50

    Dear Friends,
    I have the problem to set the Production Planning Table (Txn MF50) to
    clear the history data automatically. Currently, all the history data
    in the planning table has to be cleared manually.
    Appreciate your help.
    Rgds
    Zahari Yusof

    instead of just removing the whole history like private browsing do, i just want to remove browsing/download history and form&search. i didn't want to remove cookies and active logins, heheh. thank you

  • Table name for work centers with production or planned orders

    dear gurus,
    can you please help me on what table names have the work centers with planned or production order

    For production Order
    1.AUFNR ---> AFKO ---> AFKO-PLAF
    2.AFKO-PLAF --> AFVC -
    >  for respective VORNR get AFVC-ARBID
    3.AFVC-ARBID --> pass as  OBJID into ---> CRHD --->ARBPL (Work Center)
    For planned orders
    1.PLNUM ---> PLAF ---> PLAF-BEDID
    2.PLAF-BEDID -
    > KBKO ---> PLAF-PLNNR, PLAF-PLNAL
    3.PLAF-PLNNR, PLAF-PLNAL -
    > PLPO -
    > for corresponding VORNR (Operation number) get ARBID pass as OBJID ---> CRHD --> ARBPL (Work Center).
    Regards
    soundar
    Edited by: Soundar on May 29, 2008 9:18 AM

  • Issue met in Capacity Leveling with tabular

    Hi, guru:
    I met a fascinating issue in CM22,Remain.avail.capac. fileds in the upper area is 0, so i checked the available capacity with CM01 for the correspondent day, available capacity is 14.After i creating a production order, the capacity requirement is 1.7, but the field  display -1.7 in CM22.  so I can not dispatch it ,showing the error with overload. But i can dispatch it in CM21. I think the problem is that CM22 gets the wrong AvailCap or doesn't get it. but i don't know how to solve it . any sugession will be appreciated,thanks in advance.

    Hi Dear:
    Check you Capacity utilization into your Resource or Work Center, cause many times this parameters is the reason for you issue between these two tcodes.
    I mean, the CM22 take in count this parameter, but not the CM01
    I hope this be useful 4U
    Regards
    Omar Perea

  • TS4020 "cannot get mail" The connection to the server failed. My mail account from Icloud will work if I only disconnect my wifi in my iphone and use internet plan from carrier. Anybody else with this proble??

    My mail account from icloud will work if I only disconnect my wifi in my iphone and only use internet plan from my carrier. Anybody else with this problem??

    I've been having the same problem since iCloud appeared and complicated an otherwise trouble-free system. Doubling frustrating is that iCloud duplicates my .Mac account so I get two of everything in my Inbox. I turned off iCloud and now mail at least goes out but I can't delete the duplicate account.

  • Capacity problem in production order

    Hi Friends
    I am facing a serious problem in capacity evaluation. After MRP run with scedulling as 2. After this I am able to see the capacity in respective work centers for the planned orders. But when converted to production order I am not able to see. When I checked the order it is showing as "Order 60003310 has no requirements in the eval.period, so there is no display".
    I dont have any clue as whats happening since the capacity is there till it is a planned order. Any suggestion?
    Thanks & regds

    Hi,
    Your problem is with Evaluation period as system not displaying the capacity so first check whther is nay capacity requirement is there in this period you can check with CM01 also.
    In OPD2.
    Assuming you want to create a time profile for 2 months.
                                            Entry Type    Start Date     End Date
    Database Read Period            J                -3                   3
    The database read period specifies the period in which capacity requirements are read  from the database. All requirements are accessed which are partially or completely 
    within the database read period.
    Evaluation Period          G              -1           60
    The evaluation period specifies the period over which data is formatted and displayed. 
    The evaluation period must lie within the database read period.
    Planning Period            G              -1           60
    The planning period defines the period in which the SAP system can carry out planning. 
    The planning period is smaller than or equal to the evaluation period. You cannot move  operations outside the planning period. Equally, when automatic finite scheduling is 
    carried out for an operation the system only searches for a new date .
    Please check and come back.
    Regards,
    R.Brahmankar

  • Capacitity leveling - Dispatching production order considering PM block

    Dear friends,
    I am trying to dispatch a production order of large Qty by using transaction CM21.
    The order will take 15 days to complete.
    Two days are blocked by plant maintenance order on that work center in future. They are shown as black in CM21.
    When I try to dispatch, system is automatically dispatching the order in such a way that its end date is before PM block date or start date is after PM block date.
    e.g. Order will run from 10th August to 25th august.
    PM has blocked dates 20 & 21st August.
    Hence the expected result is start the order on 10th and will end on 27th.
    But when I dispatch the order on 10th, system automatically takes it to 22nd (First day after PM block).
    Can we not plan orders with PM block period in between?
    Best Regards,
    Avinash

    You need to enable splits in the operation (routing definition).

  • Requirement plan number is to be populated in production order

    Hi all,
    Can anyone suggest how Requirement Plan Number given in MD61 can be populated in production order.
    This is urgent.
    Thanks
    KumaraGuru

    Hi Kumra,
    When we create the Requirement Plan number in MD61 it is updated at PBIM table. And after running the MRP, Requirement plan number (PBDNR) is updated in the PLAF  ( Planned Order Header ) Table.
    I am not sure about, it can be populated in production order.
    Le tus know your requirement so that we can help u further.
    Regards,
    R.Brahmankar