User Status for project
in TCODE BS02
10 CRTD PRO CRE 10 70
20 PROG IN PROGRESS 20 70
30 KOFF KICKOFF DONE 30 70
40 SSTD SYSTEM STUDY 40 70
50 DSGN DESIGN PHASE 50 70
60 ALPH ALPHA PHASE 60 70
70 HOLD ON HOLD 10 70
this is user status of the project.
from status 10-60 I can move forward to any status directly. but I cant reverse the same.
But If I select status 70 once.
then I can move to any status even backwards also
like from 40 to 30 to 20 like this. this happens only when I make status 70 as active once.
Pls suggest.
Points will be rewarded.
Thanks
Vinayak
Hi.
There are two things:
- Transaction OK02. There the definition of the status is set. It works exactly the way it is set up there.
- Transaction OPSI. Validations are defined and may check on status changes.
Cheers!
Similar Messages
-
USer Status for Project Elements in cProjects 4.0
Hi All,
I have created Status profile in cProjects 4.0
How can I replace the system status with my created status profile?
In other words, when I select my Status profile, the system status (Created, Released, Lock) should get replaced by the custom (Ex: Available, Closed, etc)
<b>Useful answers will definitely be rewarded.</b>
Regards,
Sujay!cProjects allows User Status as an addition to System Status.
In case you need to use user status you can change it only after selecting the status profile through the status tab page. Once a status profile has been attached, System as well as user status can be selected. -
BAPI/FM for setting the user status for the Project definition and WBS elem
Hi,
I have to set the User Status for the Project Definition and the WBS elements in that project.
The User status to be set is the same for the project and wbs elements.
Please let me know if there is any BAPI/FM to set the user status..
Thanks in advance.
Regards
ShivaHi Shkithija,
There is a dump encoutered in the form "PS_FLAG_GET_GLOBAL_FLAGS" for 'chk_precommit_ok' in the "BAPI_PS_PRECOMMIT".
But it is showing SY-SUBRC = 0 when used along with BAPI_TRANSACTION_COMMIT.
May i know what are input parameters we need to pass it to "BAPI_PS_PRECOMMIT".
Do you have any idea.
Please let me know
Regards
vishnu -
Need help on to set User status for Operations in Maintenance order
Hi experts,
i am new to PM module.
i need to do BDC for IW31. i want to know some inforamtion
on user status for each opertaion.
my problem is ,, what is user status.
why it is saying order is not yet released when saving and status can not set.
in this cases how can i do BDC.User status are something set in the configuration and specific to the company which SAP hasn't given in the system status.
May be in your system user status are configured to set only after the release of the order.
For doing the userstatus you may need to release the order, you can release the order thru bdc and then do bdc for user status. Also see below link
http://www.sap-img.com/plant/user-status-set-date-in-maintenance-order.htm -
User status for component item in service order (plant maintenance order)
Dear experts,
I cannot find the customizing for assigning a user status (profile) to a component item of a service order.
IW31 - tab components - mark an entry - click on button "component status"
Can you help me?
Best Regards,
PhilippOSS message created. Answer from SAP:
11.02.2011 - 15:04:46 CET - Antwort von SAP
Hello Mr. Miller,
user status for components are not possible and not intended. I'm
sorry that I cannot provide better news.
Best regards
Reinhard Gruber
Senior Support Consultant
AGS Primary Support,
Business Suite & Technology
SAP AG
Therefore this message is closed... but not yet answered
Edited by: Philipp Miller on Feb 11, 2011 3:28 PM -
Hi All,
How can I set the user-status for a PP order, also let me know which user exit suits this requirement, as I know I have to make use of a FM or a BAPI which sets the user-status in the user-exit somewhere.
Thanks
MarkHi,
Try the following enhancements/exits for setting the status for PP order.
STATTEXT
CCOWB001
COIB0001
Regards,
Anji -
Set a User Status for Quality Notifications only if they are "Activated".
Hello experts:
I need to be able to set a User Status for Quality Notifications only if they are "Activated".
When defects are recorded for an inspection lot, a "Defect Notification" is created which can be activated to become a "Quality Notification". Initially, the only difference between the inactive "Defect Notification" and the active "Quality Notification" is that the system status DEFR is active for the "Defect Notification", but is cleared when the notification is activated.
So, I'm looking for the business process associated with the Activation to use as a trigger for my own user status.
I checked the business rules for status DEFR and found that the following processes clear this status
PMM1 - Postpone Notification
PMM2 - Put Notification In Process
PMM3 - Assign Order
PMM6 - Put Notification In Process Again
Any Ideas ?Perhaps some additional information would help you understand what I need to do.
For notification type F3, we are recording all defects found in production.
Most of these are expected defects that result in a minor reduction in yield.
For this type of defect, we do not activate the notification, and the inspection lot is closed automatically at the end of production.
However, sometimes defects are observed of an unexpected type or a higher than expected quantity.
When this happens we manually activate the notification and assign tasks to find and correct the cause.
It is only for these activated notifications that I want to automatically set a user status, which among other things, will prevent the notification from being closed until some other actions are complete and a different user status is selected.
The function of the user status currently works exactly as I want, but if it is set as the initial status for all F3 notifications, it is also preventing the un-activated defect notifications from automatically closing. I therefore want to use the Activation event as the trigger to set my user status. -
U00BFMultiple user status for WBS Element?
Hello,
I need to create multiple user status for a WBS element.
I'm using the BAPI: BAPI_BUS2054_SET_STATUS
CALL FUNCTION 'BAPI_BUS2054_SET_STATUS'
Importing
return = ls_returnbapi1
TABLES
I_WBS_SYSTEM_STATUS =
i_wbs_user_status = it_wbs_user_status"--> This table contais 2 record, with the same WBS elements and diferent status
e_result = it_result.
I put several rows (two) in the table it_wbs_user_status., I put two rows, the WBS elements for the same item with two different status, but I get error because it says that the WBS element is repeated.
¿Can you have multiple user status for the same element PEP? I try it in the transaction CJ20N too, and I don't Know.
Thanks.In transaction CJ20N you can change user status for each WBS elements.
Menu --> Edit --> Status --> User Status --> you can choise betwen "Set" or "Set & Pass On".
I want BAPI, function , etc.... that do the same thar "Set" , not "Set & Pass On".
BAPI_BUS2054_SET_STATUS = "Set & Pass On"
Thanks -
Activation of User status for Prod. order
Hi,
I have created a status profile with a status as a user status for production order. Now the thing is how to activate this user status for a specific transaction.
the requirement is after settlement the user status should get activated for production order.
Regards
Amit ParkhiHi Amit,
As told by Ajay , after assigning Status Profile in OPJH you can assign User Status to production order as below:
Pls. go through the following procedure for activating the User Status :
Activating User Statuses
Use
You can activate a user status at order header and at operation level.
Procedure
Order Header Level
Go to the order header.
Choose .
Choose Edit ® Direct entry.
The system displays a dialog box in which you can select the permitted user statuses.
Position the cursor on the required user status and choose Choose .
Operation Level
Go to the operation overview.
Select the operation in question.
Choose .
Choose Edit ® Direct entry.
The system displays a dialog box in which you can select the permitted user statuses.
Position the cursor on the required user status and choose Choose .
Pls. follow the above procedure as per rquirement and set user status accodingly.
Pls. revert if any doubt and reward if useful.
Regards,
Tejas
Edited by: Tejas Pujara on Jun 23, 2008 8:10 AM
Edited by: Tejas Pujara on Jun 23, 2008 8:11 AM -
Hi all, I want to change the user status NOCO(Notification completed) for M2 type of notification in the Quality client.I did it in Dev client for M2(Break down Notn) and imported the TR to Quality.When i try to assign this status in Quality client, the system is throwing an error as follows.
Status NOCO is not allowed (QNF 10039901). Solution please.Also provide the path in SPRO.
Thanks in advance,
Venu.Have you completed all of the tasks in the notification. Has the Notification the following system status : ATCO ,
If not, you would not be able to complete the Notification. Try Completing all the tasks and then mark the Notification as Complete.
If you have defined any user status to be NOCO, then check that whether in the User status profile, against the current user status of the Notification, the lowest and Highest columns allow the NOCO status or not. Include the status number for NOCO against the current user status. This would solve the problem.
Path for User Status Profile Creation and Assignment:
SPRO>Plant Maintenance and Customer Service>maintenance and Service Notifications>Notification Processing>User Status For Notifications-->Define Status Profile
Edited by: Usman Kahoot on Jun 1, 2010 5:19 PM -
User Status for process orders
Dear Experts,
We are using user statuses for process orders & with this we are resricting or allowing certain business transactions.
My question is can we automatically set the two consecutive user statuses ?
Means when the GR for process order is done i have set the user status as GR.
Next user status is CLSD.
So after completing the closing of process order by settlement transactions can i set the staus as CLSD automatic?
I am trying to do it but i am getting error as-
"Status CLSD is not allowed (ACT 30000292 0010)"
Your help is highly appriciated
Regards
VivekHi,
1) Still your order is carrying cost, it has not settled properly
2) you can check in CO02 itself, Go to tool bar at top
3) here Go to > Costs > Analysis & check whether order is set to Zero
4) you can check in KKBC_ORD also
Also, pls refer below link
Re: HOW automatic order status change to CLSD
regards,
Sankaran -
User status for bid invitation
Hi all!
Could you give me a hand with user status for bid invitation? I made some statuses for Bid and allowed them to transaction type u201Cbid invitationu201D u2013 it seems OK. But when I try to create a bit invitation, Iu2019ve got a system error u201Cstatus profile is not allowed for bidding headeru201D
What can I do to settle this problem?
ThanksEverything OK, I select object type for u201CBidding Headeru201D
-
Hi all,
I have 3 queries-
1) What is the meaning of business transaction "GOODS MOVEMENT" in BS02-status profile / user status screen
2) I have an order with 2 operations in it.
I have created a user status for the "PP/PM operation" business object type and the following business transactions are marked as forbidden.
Confirm transaction
Delete operation
Determine costs
Goods Movement
Partially confirm operation
I want that when the status is assigned to the operation the system that the system should not any confirmation, goods movement (issue/resceipt), activity posting for that operation.
When i assign the user status and make the confirmation by co11 then such messege is issued by the system which is OK.
But when i issue the component by 261 mvt type by mb1c to the order, the system carries out the transaction.???
How it is??
I think this issue is carried out at order level that is why it is.
3) What is the meaning of all the business transactions in bs02 screen???
Regards,
MHPHi Rajesh,
Thanx for the reply. I'd rewared with the points.
I am not clear from ur answers as follows.
ANS 2-- I AM NOT CLEAR THAT IN MB1A WHEN SYSTEM WILL ALLOW & WHEN SYSTEM WILL NOT ALLOW??
U MEAN TO SAY IF IT IS PLANNED THEN SYSTEM WILL ALLOW & IF IT IS UNPLANNED SYSTEM WILL DISALLOW. IS IT SO??
BUT THEN WHAT IS THE USE OF FORBIDDING "GOODS MOVEMENT".
ANS 3-- I KNOW WHAT U HAD REPLIED WITH. BUT I WANT THE MEANING OF ALL
BUSINESS TRANSACTIONS
REGARDS,
MHP -
User status for Service Issue{for particular Sales order} in CRM
Hi Experts,
I've an issue related to the User status in CRM.
I've a Sales Order and I'm creating a service issue for it in CRM.
For the service issue number has some user status and I want to know from where it is coming.
Is there any configuration involved in it, or is it coming from the standard coding part.
Please let me know how to find the user status for a service issue.
Thanks
SubbuThank you PePe,
I'm asking about the user status not the system status.
The user status has only the values{open, worked & closed}.
now for a service issue if it is rejected then the user status are automatically changed into "Closed".
So if you have any idea in this please help me.
thanks
Subbu -
User status for Notification and Work order
We generate Service Notification IW26. I have already configured user status like PMND (Planning order not done), AWOP (Awaiting ordered parts) etc. in the Work order a while ago. Now the user wants same User status to the Notification as well. I like to know from experts what is the value added to have the same user status for both Notification and Work Order?
Do you have any suggestions?Hey Chandra,
The customer intent behind this requirement must be to check in reporting / List Display Transaction about the Order Status. If they want to know looking at a Pending Notification List about the Order Status, you can always provide similar report using SAP Query Builder or with help of your Developer.
Apart from that If the Requirement is to have these User Statuses in Notification itself, Please advice them that it will be extra activity while performing transaction.
I dont see any other benefit of having User Statuses added to Notification as well.
Do let me know if you have some more info on Why Customer is requesting this....
Regards,
Avi
Maybe you are looking for
-
Windows Message"No Disk in Drive" appears @ itunes startup & w every click
When itunes starts up I get this message box "There is no disk in drive. Please insert disk into drive." I can click on continue or cancel to close box but it reappears whenever I click on a song. It sometimes won't close even if I do insert a disk.
-
Problem setting up Network User
I am running Mac OS X 10.5 Server with clients running 10.5 also. Currently, there are several users on the server, but in Workgroup Manager, their home directory is set to null. The users have local accounts on certain 10.5 clients which are linked
-
In CS6 InDesign (8.0.1) I tried looking for Folio Overlays panel and it doesn't appear. So, I tried to go to Updates under Help menu but the Updates button is deactivated. Any ideas?
-
Evaluating eventual port of app to 8.1
Currently our app is on wl 6.1. The whole build with compile, deployment and unittesting is done via ANT (+Junit & Cactus ) and we use Cruisecontrol to run a central build each time source is checked in ( StarTeam) sending mail to the developer if an
-
InfoPath combined with Excel Rest services gives State service error
Hi I'm having a problem with InfoPath and Excel Services. I have a InfoPath form that calls Excel to do a fairly simple calculation, but I also have another form at a client that is doing the same calling a much more complicated function. The error I