Valuation class change for finished goods

Hi,
I want to change the valuation class for one material.The stock is zero.the order has status as belows.
TECO Technically completed   
CNF  Confirmed               
DLV  Delivered               
PRC  Pre-costed              
DLFL Deletion Flag           
BASC Batch assignment complet
BCRQ Order to be handled in b
GMPS Goods movement posted   
MANC Mat.availability not che
ORRQ Order record required   
SETC Settlement rule created 
VCAL Variances calculated    
I am trying to set deletion flag & deletion indicator  through the program PRARCHP1 but the system is not picking the order.Please revert back urgently.Thanks in advance.
regards,
kaushik

Hi,
it is not possible, to change the valuation class for any material, once a stock entry is passed in the system.( even thought the stock you have made zero )
if you try to change it in MM02,  an error log shows, please go thr' it. it shows open items or transactions, due to which we can't
change valuation class.
please check other option, instead of changing valuation class.
Rrd1

Similar Messages

  • Valuation class changes for open orders

    what are the reason SAP doesn't recommend to change the Valuation class for open orders or when the  material is in transit.

    Hi,
    System will not allow to change the Valuation classes of a Material in the Following cases:
    1. Material Stock should be zero. If any stock is there it wont allow to change vc.
    2. Material should not have any open Purchase Requisitions/ Purchase orders/ Reservations etc.
    So, If if you want to change the Valuation class Transfer allthe stock of the material to another plant and delete all the related Transactions.
    Reg,
    Ashok
    Assign points if useful.

  • Batch class 022 for Finished goods

    Dear Gurus,
    I have a scenerio of variable configuration in that i have to note the characteristics value of batch class(022) in during the confirmation of production order in co11n.
    please guide as.
    vimal

    Hi ,
    Do you mean Variant Configuration with Super BOM ?
    If VC , why should you have to note the characteristics value of batch class ? Can you give more information with example please?
    TQ.

  • Inventory Valuation Difference for Finished Goods

    Dear Experts,
    I have a following query below when the FG Inventory valuation differences are posted
    Finished goods price control is set as u201CSu201D
    Eg: In Jan 2010 stock value 1000 ( 100*10)
    Feb 2010 , opening stk of 1000 ( 100 units * 10 per piece)
    In Feb 2010 , FG price has changed to 12 per piece ( Standard cost estimate executed)
    System  has posted the price difference entry
    Debit FG stock 200/-
    Credit Inv Price Diff 200/-
    Now the query is,  stocks pertaining to Jan 2010 are lying in Feb 2010,
    When Inventory  valuation is done,  my profit is overstated in Feb 2010 for Jan 2010 stocks by 200/-
    Is there any way to handle in SAP that it would post the price diff in Jan 2010, instead of Feb2010.
    Advance thanks
    Sanjai

    Dear Ajay,
    I will release std cost est  in Jan and also in Feb.
    But since the Jan stock is carried to Feb, during the month end when I value the FG , price difference for Jan stock is posted in Feb .
    Currently the client wants to value the stock on actual basis, what is the best option to overcome. we are in BBP stage
    Eg Jan stock value is 2000 ( 200*10)
         Feb Stock Value of goods produced in Feb is (100*12) 1200
         Feb end stock as per the client it should be 2000+1200 = 3200
         Note - But as per standard costing my price will be 3600 ( 300*12
    Thanks
    Sanjai

  • Split valuation for Finished Goods - Target cost was not updated

    Hi,
    We are following split valuation for 'Finished goods'.
    Valuation typte 1 is for 'manufacture' and
    Valuation type 2 is for 'External procurement'
    For production orders with this material, we are not getting target costs. It is showing zero.
    We have done release of standard cost estimate before creation of production orders and goods receipt for these orders. But still it is not updating.
    Pls guide me.
    Regards
    MadhuSekhar Gupta

    Hi,
    Thanks for your reply.
    At the time of variance calculation only the credit part of target cost will update and at the time of goods receipt debit part of the target cost will update.
    Our client has done goods receipt but debit part of the target cost was not updated. and the order status is DLV.
    I simulated the scenario in QAS by creating new finished goods materials (Industry-Construction) one is with split valuation and another is without split valuation, then the debit part of target cost was updated at the time of goods receipt and credit part was updated at the time of variance calculation for both the materials. So this problem was not arised because of split valuation.
    Was this problem arising because of the material master data, because for one material it is updating and for another it is not for the same configuration?
    Regards
    MadhuSekhar Gupta
    Edited by: gms gupta on Oct 22, 2011 3:39 PM
    Edited by: gms gupta on Oct 22, 2011 3:41 PM

  • If Excise invoice required for finished goods.

    Hi All
    I have doubt, whether excise invoice is required for finished goods or not. As I am trying to create MIGO doc for PO of finished material, and it is saying, no excise invoice possible for finished material RG1.
    Can you advise please.
    Regards
    Mukta

    HI
    Thanks for this. When we are executing Utilization transaction J2IU, it is giving dump after prompting popup with  'Data will be lost PLA NCCD B35', 'No record selected , excise invoice cancelled'.
    Run time error is saying -
    Short text
        Structure-type conflict when calling a FORM
    What happened?
        Error in the ABAP Application Program
        The current ABAP program "J_1IRUTZ" had to be terminated because it has
        come across a statement that unfortunately cannot be executed.
    An exception occurred that is explained in detail below.
    The exception, which is assigned to class 'CX_SY_DYN_CALL_ILLEGAL_TYPE', was
    not caught and
    therefore caused a runtime error.
    The reason for the exception is:
    The call of the FORM "DETERMINE_DEFAULT_VALUES" is incorrect:
    The actual parameter no. 2 is at PERFORM not compatible with the
    structure type requested by FORM "DETERMINE_DEFAULT_VALUES".
    The FORM "DETERMINE_DEFAULT_VALUES" is defined in program "SAPMJ1II".
    This error occurs in Unicode if the fragment view of the types is
    incompatible.
    Can some one suggest if we need to apply any OSS NOTE.
    Regards
    Mukta

  • Material Valuation Class Changes

    Hi All
    For the Material Valuation class changes it is showing one open IMPORT PO.
    For the Import PO the GRN & INVOICES are completed for the total qty. During the deletion of this PO it is giving error message Invoices pending for delivery costs (function not possible)
    Because there is difference of Rs 1800 through IR.
    how it will not show as open po ? How to proceed? how to delete the po
    Thanks in advance
    Rajesh

    Hi
    Delivery for the all qty is completed & delivery indicator is also set but still for changing the Valuation class for the material this PO is coming as open PO. How to close the same.
    As there is difference of exchange rate betn GRN & INVOICES ( -1800 RS) PO & invoices are in  EURO
    Please help
    Regards
    Rajesh

  • Moving average price for finished goods produced inhouse

    Hi All
    How does system caliculate moving average price for a finished product which has BOM, Routing when we do goods receipt for the production order...does MAP change for every goods receipt based on the goods isuues or confirmations to the production order.
    Thanks in advance

    Hi,
    The price will not change during the goods receipt, but when you settle the production oder and there is some danger in it.
    Take the contents of that note into account [ Note 81682 - Pr.contr.V for semi-finished and finished products|https://service.sap.com/sap/support/notes/81682]
    best regards, Udo

  • Moving average price for finished goods

    Hi All
    I am using moving average price for finished goods.  My question is, Does the price on the material master record adjusts, when we do goods receipt on a production order( If there are variances)?
    here is a scenario:
    Moving avrage price  of finished goods=2$ and total stock =1
    it has two components in the Bom
    Raw1-3$
    Raw2-3$
    Now when I am producing 1 qy of finished goods with 6 $ of Raw materials, moving average price of fert should  be 6+2/2=4 $. But I noticed the moving average price  in the material master record is not changing.
    My question is, Does the MVP changes with production order goods receipt, If so, what setting should I change to acheive that functionality.
    Thanks
    Steve

    Hi Guys
    Thanks for responding
    I am aware that sap does not recommend MAP for finished goods. But we have a weird requirement. And I am doing a demo on this. My thought on MAP is, It changes for every goods receipt. But when I am doing goods receipt on production order, It is not changing the MAP, Even though there is variance on production order. So, My question is, Did I miss any configuration ?

  • Service "No valuation class exists for account reference"

    Hi,
    in AC01 trx, I cannot create a Service.
    The error is:
    No valuation class exists for account reference
    I tried with trx OMSK to link the account category reference to material type but won't work.
    The error is always: No valuation class exists for account reference

    Hi,
    try also to check from SPRO, Materials Management, External Services Management, Service Master, "Define Service Category", you have to set the standard "Account category reference" 0006 or the one (custom) you have set in customizing also check (Valuation and Account Assignment trx OMSK)
    Regards

  • Validation of batch nos. in migo for finished goods (fert)

    I want to validate batch number entered by user at the time of migo for finished goods (fert) against the batchs in mcha. how can i do this? also is it possible to give f4 help to user for available bach nos. for the particular material ?

    Hi,
    Cannot you use message M7 668 for this purpose?
    Problem is "batch has been already posted in stock"
    Regards,
    Csaba

  • How to get unit cost for finished goods in prod order

    HI all,
    IN a production order of type PP04, there is cost analysis you can get from CO03.  This shows the cost for finished goods and BOM components.  Would anyone know how the cost for finished goods are calculated ?  The issue i have is that the unit cost of the finished goods is not correct.  It is higher than what it should be.  I looked at the moving avg price at material master but the cost used in calculation is different than in material master.   Can anyone shed light how finished goods are calculated and why it is picking up a higher unit cost ?  Where is the higher cost coming from  for finished goods material as shown in CO03 ?  The BOM materials are picking unit cost correctly.  Would this have anything to do with cost settlement ?
    thank you.
    joyce

    Hi,
    Finished goods price will depend on BOM componenet price,  activity price and overhead price. Check whether this prices are picking correctly or not.
    Regards,
    Sreekanth

  • PO for Finished Goods with Tax Code - Inventorise

    Hi All,
    Our Client is procuring Finished Goods from Domestic Vendor & Excise Duty is paid to the Vendor for that i am defining the tax code in PO. Over here For the Finished Good in Tax Code it is not capturing - (Condition Type - JMO2). I have checked it in PO for ROH, HALB tax code is working perfectly with (Condition Type - JMO2). I like to know will it work for finished goods or not. In J1ID i have maintained Excise Rate.
    I had followed the following steps.
    1) Material code- Chapter id maintained in J1ID
    2) Vendor code excisable in J1ID
    3) Maintain condition record in FV11 for the correct validity period
    4) Check the PO creation date whcih should fall between condition record validity period
    Every thing is maintained i have checked it Thoroughly fot this particular material i am not getting it. This one is a finished goods material.
    I am not able to identify what is happening.
    I will give the flow so that you can help me out.
    1. Created Material - Finished with all views except - Classification, Forecasting,
    Work Scheduling & QM
    2. Create Info Record - Tax Code given
    3. J1ID - Chapter ID, Chap ID with Material, *** Val for Mat, Vendor Excise Detail, Excise ind. for Plant, Excise ind. for Plant & Vendor, & Excise Tax Rate.
    4. FV11 - Maintained till - 31.12.9999.
    5. FTXP - Tax Code is Maintained & it's working fine with other PO.
    6. ME21N - PO is done for Domestic vendor with Standard PO With no condition & With only tax code for ED & CST.
    7. In J1ID cenvat determination has been maintained.
    Also the material type should be raw in material chapter id combination instead of RG1 even though the material is finished to take credit of excise it should be maintained as RAW .
    Over Here if i see i am not able to capture (JMO2 A/P Eduty for Inven 0.000%) &
    For Sale tax i have maintained it in FTXP as (A/P C Sales Tax Inv  NVV   12.500%  JIP1) but it is not appering in PO Tax code. I can See the sale tax is geting updated in Tax code for Inventorise if i give it with out ED in tax code. With ED it is not Appering in Taxcode.
    Can you help me resolving the issue.
    Once again thanks for youre help.
    Thanks in Advance,
    sapuser.
    Edited by: sapuser on Dec 26, 2008 10:10 AM

    Hi All,
    Just give a check by entering cenvat determination table. System checks this by default for excise details. Enter i/p and o/p material as same.
    Hope this will resolve you Problem,
    Pherasath

  • Uploading Production Requirements For Finished Goods From External System To Run MRP For Components in SAP.

    Hello Production Planning experts,
    I'm looking to solve the current business problem:
    The company bought a third party software (JD Edwards) to calculate production requirements instead of using SAP's standard Production Planning or a tool like SAP's APO. They run a batch job to query Sales Orders, Deliveries, available stock, stock in transit, etc. from sap and feed/upload it to the third party software so it can calculate the Finished Goods Production Requirements for them. They love the third party software, so replacing it is not an option. Since the third party software is already taking into account Sales Orders, Deliveries, available stock, stock in transit, etc. from SAP, it just outputs a "Finished Goods Production Schedule" by week.
    My questions are:
    1) What's the best way to upload something like that in SAP in the form of Planned Orders or something of that nature?
    After i get that schedule in SAP:
    2) Is there any way to calculate components' requirements for that "Finished Goods Production Schedule" alone? The company would like to IGNORE existing stock AND expected-goods-issues in the future (sales orders, deliveries, etc) for Finished Goods ONLY. The components calculations would work the standard MRP way, taking into account existing stock and AND expected-goods-issues in the future (sales orders, deliveries, etc)
    I started looking into Master Production Schedule (MPS), but I don't know if that's the right approach since I'm not very familiar with it.
    Thanks in Advance! I will gladly reward points for helpful/correct answers.

    Hello Oscar
    I suggest you to upload your production plan in the for of "Planned Independent Requirements" using BAPI BAPI_REQUIREMENTS_CREATE. Later, MRP will create planned orders to cover the PIRs.
    If you don't want to consider the existing stock of the finished product, you should use the planning strategy 11 to create your PIRs. Take a look on the following link for more details about this planning strategy:
    Gross Requirements Planning (11) - Demand Management (PP-MP-DEM) - SAP Library
    Here you will find the following information:
    The make-to-stock strategy gross requirements planning is particularly useful in mass production environments; it is often combined with repetitive manufacturing. This strategy is particularly useful if you need to produce, regardless of whether you have stock or not. For instance, steel or cement producers might want to use this strategy because they cannot shut down production; a blast furnace or a cement factory must continue to produce, even if this means having to produce to stock.
    This strategy is also frequently used if there is a Material Requirements Planning system in a legacy system that needs to be linked to an SAP system which serves as a production execution system. The legacy system calculates a specific production plan, which has to be executed, regardless of the stock situation in the SAP system
    It looks like this planning strategy is exactly what you are looking for.
    BR
    Caetano

  • Discontinuity and Follow-up Materials for Finish Goods

    Dear all,
    We have used for a long time the Discontinuity functionality and Follow-up Materials for Raw and Packaging materials (components in BOMs).
    We would like to use the same functionalities for Finish Goods, but after setting fields in MRP4 View, it seems not to work as it did for components.
    Is it possible to reproduce the same effect in Finish Goods as we had with components, i.e., use some kind of Discontinuity and Follow-up materials for Finish Goods?
    We currently work with R/3 V.4.7.
    Thank you all in advance for any support.
    Best Regards,
    Alberto

    Dear Alberto,
    If my understanding is correct then this discontinued material concept works only for the components and not for the finished
    product during MRP.
    Discontinuation Data Use
    In MRP, the discontinuation functionality is used to transfer dependent requirements of a component to one or several follow-up
    materials, if the requirements are no longer covered by stock. You can also define a follow-up material in the bill of material.
    Check this link to explore more.
    http://help.sap.com/erp2005_ehp_05/helpdata/EN/b1/c044d1439a11d189410000e829fbbd/frameset.htm
    Regards
    Mangalraj.S

Maybe you are looking for

  • Need to restrict users from adding or modifying folders or reports

    Requirement: Need to restrict users from adding or modifying folders or reports through Info view and to reflect the modifications only thriough LCM. Issue: Customer wants to restrict users from adding or modifying existing reports from Infoview and

  • Remove VPP Token from Profile Manager

    Hello, I recently set up a test OSX Mavericks server and enrolled our VPP for testing purposes. To continue testing other options, I signed up for a Meraki account, and wanted to see how their VPP process compared with OSX Server. However, when I tri

  • The true randomness of the Shuffle feature... ?

    I have the iPhone 3GS with well over 2,000 songs copied over.I generally like to "Shuffle" so that I can have some sense of random sound experience. What I've found is that the Shuffle function may not be as random as we might expect. For example, wh

  • Accounting Document error in VF02

    Hi All, when i was trying to post the accounting document from VF02, system throwing message " Account 4XXXXX requires an assignment to a CO object " Message No KI235. This account created for handling charges, and cost element category as 1 (Primary

  • My iphone 3g is broke

    hi my iphone 3g is broke and i want to save my msg that i have had since i got it a year ago, is there a way to do this? x sue