Variable Authorizations for Cost elements (K_REPO_CCA)

Hi everybody.
I have a doubt regarding the posible options for an authorization on object K_REPO_CCA. Our system is R/3 version 5.0. Is it possible to create a variable, "$COST_ELEMENT" for example, and fill the values dinamically by a user_exit or maybe a z-program that reads in a Z-table??
Did you know if this is possible?? If yes, do you know the user-exit??
Many thanks and best regards.
Ismael Bermúdez

Hi,
I would be really interested to find out more about what you did here.
"<i>In fact at a client we determined the authorised cost centres at run time based on the users mapping to the HR org structure."</i>
This sounds like exactly what we need at our organisation. We are a large company with around 40000 staff and have the following business requirement.
- Cost centre reporting is expected to be hierarchical in nature but current Cost Centre structure in Australia is flat in structure.[/li]
- Natural hierarchies already exist within the NAB by organisational structure: Total Company, Business, Zone, Region, Area and Branch.
- As a high level requirement, cost centre data should only be available to the manager of the organisational unit that they are managing and any lower level organisational units. Managers should only be able to view their organisational unit costs or lower organisational unit costs. They should not be able to view cost centre data across structures (peer organisational units) or higher levels of responsibilities (parent organisational units).
- The ability to access cost centre reporting data should take into account HR delegations and substitution processes. This also needs to take into account the granting of the correct authority to the delegated person to run reports.
- One possible option is to utilise the A250 Cost Centre Manager relationship in SAP to facilitate the security for cost centre reports.
I will be handling these requirements from a security perspective and would liike to achieve this without creating hundreds of roles and a maintenance nightmare.
A finance version of structural authorisations would be good
Any input would be greatly appreciated.
Barb

Similar Messages

  • KB15N_No adjustment account found for cost element Message no. K5112

    When I am trying to post Manual Cost Allocation through TC KB15N with the following input data I am getting the following error message and the same could not be posted.  Kindly advise.
    Screen Variant used: 01 SAP Cost Center
    Input Type: List Entry
    Item No.1
    Sender Cost Center : 3402100942
    Cost Element: 6200001
    Amount : 62,201.56
    Receiving Cost Center: 3405100945
    First four digits represent profit center code.  If first four digits are equal the above error is not coming. But posting is needed with different profit centers.
    No adjustment account found for cost element
    Message no. K5112
    Diagnosis
    Neither standard account determination nor the enhanced function found an adjustment account for the reconciliation posting.
    System Response
    No adjustment account could be determined for cost element  in company code SCCL.
    Procedure
    Maintain the standard or enhanced account determination for transaction KAMV. Information on maintenance can be found in the program documentation.
    Execute

    Hi all,
    I face the issue like this but with transaction KOAP - Plan settlement
    But, the problem is that, I do not active reconciliation ledger, so I do not maintain any thing relate to reconciation ledger or adjustment posting? I can do transaction "actual settlement"  without error
    So, How this error come to me?
    And how I can fix it?
    Thanks all!

  • No Adjustment account found for cost element

    Dear Gurus,
    I am getting Three errors  msg "No Adjustment account found for cost element" when i try to run the conformation of production order create  ( T Code : C015 )"  and I am not able to save the record . like
    1 ).No adjustment account found for cost element
    Message no. K5112
    Diagnosis
    Neither standard account determination nor the enhanced function found an adjustment account for the reconciliation posting.
    System Response
    No adjustment account could be determined for cost element  in company code XXXX
    Procedure
    Maintain the standard or enhanced account determination. Information on maintenance can be found in the program documentation.
    Execute
    2) . No adjustment account found for cost element XXXXXXXX
    Message no. K5112
    Diagnosis
    Neither standard account determination nor the enhanced function found an adjustment account for the reconciliation posting.
    System Response
    No adjustment account could be determined for cost element XXXXXXX in company code XXXX.
    Procedure
    Maintain the standard or enhanced account determination. Information on maintenance can be found in the program documentation.
    Execute
    3 ) No account is specified in item 0000000002
    Message no. F5670
    Diagnosis
    No account was specified for account type "S" in item "0000000002" of the FI/CO document.
    System Response
    The Financial Accounting program cannot process the document.
    Procedure
    A system error has probably occurred in the application you called up. Check the data transferred to item "0000000002" of the FI/CO document.
    Could anyone please help me with this.
    Regards
    SAP CO

    Hi,
    iam not able to understand of this  SAP Notes: 531606 and 1027645
    Could you pl give me full details for come out this problem.
    Regards
    SAP CO

  • BEx:Hierarchies in DIM and FAC are different for Cost Element

    Hi Experts,
    Whenever we execute a report we are getting a warning message as "Hierarchies in DIM and FAC are different for Cost Element", but in report level we are not maintaining hierarchy properties for Cost Element.
    We have executed Master Data tests in RSRV also and still the problem.
    Is any other to do to get rid of this warning message?
    Thanks in Advance.
    Regards,
    RAO.

    Hi all,
    I face the issue like this but with transaction KOAP - Plan settlement
    But, the problem is that, I do not active reconciliation ledger, so I do not maintain any thing relate to reconciation ledger or adjustment posting? I can do transaction "actual settlement"  without error
    So, How this error come to me?
    And how I can fix it?
    Thanks all!

  • Copy Detailed planning for cost elements in CJ9BS

    hi PS gurus,
    What is the purpose of selecting this option (Copy Detailed planning for cost elements)? What does it do?
    Many ThanKs
    MM

    Hi,
    In case you have done detailed planning for your project you can specify whether you want to copy the detailed planning data using this check box.Planning done using cost elements is called detailed planning in PS. CJR2 is the transaction to do that. For more details you can hit F1 on the field and check.
    Regards,
    Gokul

  • Selection variant for cost element GROUPS

    Community!
    Is there a way to create a selection variant for cost element groups? Through customizing I can only create them for cost elements but not for groups!
    Thanks,
    Bjoern

    Ashok,
    thanks for your reply but I am looking for a way to create a variant for groups!!!!!
    The help just depicts how to create variants for cost elements. You actually do have the feature to display all cost elements from <u>one</u> group within the collective processing but I would need to select many different groups, which is just not possible.
    Therefore I would like to create a variant of cost element <b>groups</b>!!!!!
    Regards,
    bjoern

  • Value BLANK/SPACE not valid for cost element "Fund"

    Hi!
    We use funds management in our solution. It has worked fine in development but when doing the module tests we get the following error when creating a shopping cart:
    Value BLANK/SPACE not valid for cost element "Fund"
    When creating a PR in backend we do not get an error. So it should not be a problem in funds management.
    Everything works fine when using BBPSC01 (central)
    Any ideas?
    Sincerely
    Anders
    Edited by: Anders Öhrling on Sep 29, 2008 11:33 AM

    Ple provide the solution for Problem Resolve.

  • Formula Variable - Key of Cost Element (Query crashing)

    Hi everyone,
    I have created a formula variable which returns the Key of the Cost Element (0costelmnt) which resides in a Key figure structure. I have used this in a number of formula (If Cost Element = 50000 * (A * B) and its working fine.
    Formula Variable
    Formula Variable Properties
    My issue is that this query crashes constantlywhen you are in the Query Designer in both our Dev and Production environments, yet the query runs fine in the Analyser.
    The only thing I note is the icons in the key figure structure, some squares which are standard key figures / formulas and formula variables but my Cost Element Form Vari and the Bonus and Salary Increase Formula variables are represented by a triangle which normally means characteristics!!
    Any suggestions?
    With thanks
    Gill

    They query runs perfectly,  there are no null values in the output.
    I have already regenerated it and no change.  I do not have an issue with the output so RSRT is going to give me the same results as I get in the Analyser.
    The issue I have is that any changes I make in Query Designer, the programs shuts down.

  • There are values for cost element 80000 that are not assigned to any line I

    Hi,
    While calulating WIP I am getting below error:
    There are values for cost element 80000 that are not assigned to any line ID
    Message no. KJ161
    Diagnosis
    Not all values for the cost element are assigned to a line ID.
    Procedure
    Assign the cost element to a line ID. If you don't want to include the cost element in results analysis, assign it to a line ID of category N.
    You can access a detailed list of unassigned cost elements as follows: Start results analysis in the individual processing mode (transaction KKA1, KKA2, or KKA3). Select the field Full log. Execute the function. On the next screen, choose Logs -> Parameter List in the menu. A list is generated. The unassigned values are shown at the end of the list.
    If cost element "+++++++++" was shown in the message, this is because in the assignment of costs and revenues to line IDs, you have not used a cost element other than the full masking "+++++++++". In this case a presummarization eliminates the information on the cost element.
    Cost Element 80000 is of type 43 Internal activity allocation, I have Masked this in OKGB as below:
    Controlling Area = FLGP
    RA Version = 0
    Masked Cost Element = 000008++++
    Masked Cost Center = ++++++++++
    Masked Activity Type = +++++
    ReqToCap= COS (Secondary Cost)
    I have Configure OKGA also but still system is giving error.
    Please help me to understand.
    Regards,
    Vivek

    I was wondering if you could help me I am trying to configure the RA key for Refurb orders and when I go into txn OKGB for the Assignment of C/E for WIP there is sample config already there which I copied.  But I am having difficulty getting the KK1A to work I am getting the message as outlined above.  Could you explain how this OKGB works and how to configure it a bit more fully.  In my sample config there is a ReqTOCap section and in it there are letters like ABR, EK, FK, EL what do they mean.  This is a screen shot of it.  I am not sure how to go about this entirely so any light you could shed would be greatly appreciated.  Can you suggest a good resource or documentation you may have, would be greatly appreciated.

  • Duplicate Entries For Cost Elements

    Hi All,
    We have a situation in which in a particular inventory org duplicate entries of a cost elements have got created. eg: Material Cost Element has appeared twice or thrice for an item, similarly material overhead, resource etc. due to which the item cost has shoot up.
    Can someone please suggest what could be the possible reason for the same? Its lil urgent.
    Thanks!!!

    Dear
    Can please confirm  wether this depdends are for any MTO order ? I mean you have Sales Order for FERT with MTO item categoery and running MRP  in MD02 .In that case whether , it is generating multiple similar MRP  elements.
    Basically , this is happen based on the Planning Horizon as well as Re-schedule horizon kept into OPPQ /MRP relevent paramentrs/OPPR in case of MRP group  .If your firm reciept like Production Order are boyond the planning horizon during your MRP run , demnad will be re-considerde to create Planned order .So chek the PH/Rescheduling horizon .So keep bit larger Re-scheduling Horzon .
    Refer our earlier posting :  new planned orders on next  MRP run
    Other possibilites can  be explored in the SAP notes  from sales stand point : SAP Note : 744305/744484/80891
    Regards
    JH
    Edited by: Jiaul Haque on Nov 22, 2010 1:13 PM

  • Why authorization for cost center groups does not worked ?

    hello all,
    I would like to give authorization for a CO report (S_ALR_87013625) based on authorization values : cost center groups.
    But, unfortunately, it doesn't work. I get a message : No authorization for x of x read records.
    Is it only possible to give authorization on standard hierarchy and cost center ?
    Please, help me
    Thanks and best regards

    hi,
    Run the su53 transaction.See what authorization was missing

  • SAP Standard Report for Cost Element Category

    Hi All,
    I just wanted to know that if there are any report(s) involving Cost element categories. Say for example, if the cost element category is provided the report fetches the cost elements associated with the category and the documents posted.
    Thanks and Regards,
    Gnanasambanthan.V

    Hi,
    There is no standard report based on cost element category, but of course, you can use, for example, KSB5 and give the selection of the cost elements you want to present. I presume, you have different number range for each category and it could be easily distinguished in the selection screen.
    Regards,
    Eli

  • Authorizations for cost centers or profit centers on FI documents

    Hi,
    We need to assign some users to a role so they are allowed only to post documents that are related only to a specific cost centers or profit centers in the document.
    We try to do it using role authorizations transaccion PFCG, however we cannot find the appropiate object to do it. Does someone know how to do it ?
    We appreciate any help and reward points will be granted.
    Thanks !

    Hello,
    try the K_CSKS authorisation object for cost center

  • LSMW for cost element upload

    Hi all,
    Could anyone let me know if anz standard LSMW available for uploading cost element.  If not do we have to do recording through LSMW?
    thanks in advance,
    Balaji

    Solved.

  • Authorization for cost centers in KSV8  allocation T-code

    Hi all,
    I know it is possible to set an authorization in allocation T-code KSV8 based on the cost center. In the KSV8 transaction, there is a sender, a receiver and obviously in my case the sender is different to the receiver. The following step for me is to identify the possibility to make an authorization for the partner cost center (which is the receiver). The authorization is for the modification of the allocation. Can anyone help me?
    Thanks in advance
    Cheers
    Pascal

    To complete my question, in fact I need to identify an allocation table which makes the difference between the sender and the receiver. Tables marked "T811" are allocation tables...thanks for your help
    Pascal