Hi
When ever the Purchase Requisition of the Variable size material is
raised, how do i view,for reference,the Variable Size Item data from
Bill of materials .
Steps for the Reconstruction 
1.Create a Variable size Item Bill of material.
2.Run MRP agianst the Variable size material's dependent demand.
3.View the Purchase requisition of the Variable size Item, to take a
note of the Item Data.

Thread closed

Similar Messages

  • BOM:  Variable-size item  Question

    Hi,
    As you all know, we can set the item category as <b>R: Variable-size</b> item in BOM when creating or editing BOM via Tcode CS01, CS02,
    My question is, when we need to use Variable-size item, what's its main fuctions? could you please give me an example?
    Thanks and best regards.

    This item category is used for components that are cut to size. If you assign a material with this item category to an activity , you must also enter data for the item. The system then calculates the necessary variable-size item quantity. Otherwise processing is as for item category L.
    Example: Variable-Size Item Data for a Sheet of Metal
    Size             dimension          Entry      Size unit
    1                 Lenght             200         MM
    2                  Width             300          MM
    If you do not enter a formula, the system calculates the quantity for the variable-size item according to the standard formula:
    Size 1 * Size 2
    The result has the dimension area:
    200 MM * 300 MM = 60,000 MM2 (square millimeters)
    The variable-size item unit must have the dimension area (MM2, CM2, or M2) or you must maintain conversion factors in the material master record.
    In the customizing of Bill of materials you must maintain the formula key for variable size item category for R.
    The variable-size item quantity is used for calculating raw material requirements:
    Raw material requirement =
    Number of variable-size items * Variable-size item quantity * Required quantity
    Base quantity
    Regards
    TAJUDDIN
    Message was edited by:
            TAJUDDIN MOHAMMED
    Message was edited by:
            TAJUDDIN MOHAMMED

  • Reqmt qty of variable size item in purchase requisition

    Hello All
    I am having a FG "A" & components "B" & "C" out of these two components "B" is variable size item with Base UOM as M, I have given two sizes of "B" as 3M & 2M in the BOM., i.e. material "B" is added two times as a component with variable size item.
    For 1SQM of A"  require 3M & 2M of "B" & 1KG of "C". When am having a reqmt of 10SQM of "A" the sys calculates the dependent reqmt correctly as 30M, 20M of "B" & 10KG of "C", but the purchase requisition of "B" is coming as of 50M.
    My problem here is that how the user would come to know how many qty of "B" is reqd of 3M &  2M length.
    Please throw some light on this behavior of the system. Looking forward to your valuable inputs & guidance.
    Regards,
    J K Tharwani

    jitendra,
    as i post in my earlier reply ,
    there is one work around which will work for you is that , use lead time offset ( with positive + or negative quantity of day ) in component detail screen for one of the position of B in the BOM so in that case you will have 2 different purchase requisition for B.
    Check it out and revert back , i am sure it will work for you.
    Only problem is the date will be delayed by one day or prepone by one day for the second position where B is assigned.
    other wise there for getting this information in PO , you need to go for Z development.
    for it you need to keep a check on specific plant , what are the purchase requisition that have material which are being used as variabble size item category in BOM and for this material you need to Pull values from Variable size field of Item, details screen.
    ROM1 and ROM2 and publish it in text of PR and PO.
    Check and revert back.
    Regards
    Ritesh

  • Variable size item problem in BOM

    hi all,
    We have semi-finished material with componets as variable size items (item cat. R)
    Now in the variable size tem data, Size 1 = 1,406 MM, Size 2 = 1,220 MM. Numner is 1 ST, formaula place is blank.
    Qty Var-Sz Item is calculated by system is 3.957 M2. On what basis this value is calculated?
    In the component material we have maintained a componenet scrap quantity as 15%.
    BOM ratio of header : component = 1NOS : 1 ST
    Again when we create a production order for the header, for 1 NOS header quantity component qty becomes 2.
    For 2 NOS of header qty, component becomes 3 like this.
    Why this happens..
    Regards,
    Srijit.

    Thread closed

  • No selectable items exist for purchase requisition l_banfn

    Hi,
    While creating PO with ref to PR getting the below error :
    no selectable items exist for purchase requisition l'banf .
    Checked if the PO is created, its not created,.
    checked if the item is blocked/cancelled/deleted. Nothing is set.
    PR looks fine. Dont know if any authorization data is missing?

    Check the status tab in ME53N whether all the qty in PR are already used up
    Or
    Check the line item in PR whether it is deleted
    Edited by: Karthik on Jul 20, 2011 12:37 PM

  • BOM creation with variable size item

    Dear Experts,
    I want to create BOM with 'R'-Variable size item, Can U tell me exact procedure step by step to How to create BOM with R- Variable size item?
    Regards,
    Shivkumar Dachawar

    Hi,
      T-Code-CS01
    1. Enter the material for which you want to create BOM, Plan and BOM usage.
    2. Select the item category "R", enter the component. Now you will be taken to the "Variable item data" screen.
    3. Enter the datas of Size 1, 2 & 3 (as required) and the unit of the size & number. System will calculate the "Qty of var- size item" in the unit assigned to the basic data of the material master of the component.
    4. Save
    Note: You can change the unit of the variable size item as per your requirement in OS28
    Hope this helps.
    -Thaila Shree

  • Due date in purchase requisition

    Hi experts,
    I want to know in which table "Due Date" will be stored during the purchase requisition generation???

    Dear Nandakumar,
    Please check in table EBAN for the following fields
    BEDAT = Purchase Order Date
    BADAT = Requisition (Request) Date
    LFDAT = Item Delivery Date
    FRGDT =Purchase Requisition Release Date
    Check and revert back.
    Thanks & Regards,
    Hegal K Charles

  • Variable size item:

    Hi
    Company procures copper sheet of certain thickness with different sizes. Stock keeping dimension is KG. Material master has alternative unit of measure and conversion factor for KG and cubic centimeter. Design department will enter this sheet dimension like 15005003 in BOM and it will correctly calculate KG with formula entered.
    My problem is shop floor person will come to know the dimension and KG relation but how store person will come to know what size he has to cut and issue against production order. As while issuing goods he can only see quantity in KG and not in cubic centimeters ?
    Surendra

    SDBSAP ,
    If its unanswered why you flaged it answered .......?
    and solution to your problem in standard sap is not possible.
    You need to go for development, logic can be , for all variable size items from a BOM you need to pick size 1 size 2 and size 3 to print on issue slip . It will give exact dimension to your storage person to issue the correct dimension sheet to shop floor.
    Regards
    Ritesh

  • Variable size items.

    Hi, im a PP consultant from bombay, i had a query regarding a client who is inti\o wooden frame manufacturing it is a strictly discrete industry and the client specifications vary with almost every request. at the moment the client is creating a new mat master for every new product thus causing the master materials to run into 50-60 thousand currently. i want to know if i can use variable size items to reduce the number of materials defined as all of the materials are from standard sized planks. stock is required to be maintained for all components individually.

    Hi,
    "If you want different-sized sections of a material (raw material) to be represented by one material number in BOM items, you use this item category."
    Ans lies in the your last statement(stock is required to be maintained for all components individually)You cannot go for variable size item as you need to maintain stock individually
    Revert if you have further query
    Reward points if useful
    Regards,
    SVP

  • Variable size item formulla key funtion module,

    I am developing user interface for manual reservation (cutsom development). User wants to calculate quantity of material if he enters size1, size2 and size3. Also he wants that a formula key option to be provided so that he can mention conversion formula. Is there any standard function module for variable size formulla funtion module.
    I want to use same logic of variable size item formulla of bom in the above custom template.
    Please suggest.

    Hi
    The function module EVAL_FORMULA and FORMULA_EVALUATION may help you as they all export calculated values as output. Please go to SE37 to click the button 'Function module documentation' to see more information.
    Or go to SE80 to check the function group CALC to see more function.
    Best Regards
    Leon.

  • Variable size item Vs Stock item

    Hi Experts,
    I have a doubt regarding the use of variable size item over standard stock item. I will give an example as under.
    I have an item called cable which is to be added to a header material. This cable will be used in many header materials. I tried using variable size item as an item category and given the following parameters
    Size 1 as 5 M(UOM)
    Formula (L1)
    Number (1) ST
    System calculates the value as 5 M for qty var sz item
    In the item over view screen, quantity against the material 1 ST
    My query is instead of giving the qty as 5 M and use a formula, what if i directly give the item as stock item "L" and directly define the qty as 5M. If there is no difference between the above, why should we use the variable size item? instead we can directly calculate and give the qty for the item right. Kindly clarify the application of variable size item over standard stock item category.
    In both the cases I will be having one material code in the system and the qty will be changed in the respective BOM of two different header materials.
    Regards,
    Sridharan M

    Hi
    In addition to the stock keeping unit you can provide the details like length, width and thickness, say for example if you want to fabricate a metal part. You may need length width and thickness of the plate to be used for fabrication. This details you will be entering in the variable size items and using the formual you can calculate the required quantity in KG.
    This kind of variable size items you need not calcualte the weight of the material you just need to enter the sizes as per the drawing as you prepare the BOM.
    This varies with respect to size.... Variable Size Items
    Soundar

  • Storage location selection for variable size item

    Hi All
    There is a BOM of finished good Material "XYZ" and there is a component "A" in the BOM. This Component A is a variable size item, its a metallic bar of length 4 meters.  In BOM XYZ, only 1.5 meters is consumed.
    Now when a production order is made for XYZ and the confirmation is done with movement type 261. All the materials are backflushed along with component A . The client's requirement is to transfer the remaining length of component A (i.e. 4 - 1.5 = 2.5 meters ) to a different storage location at the time of confirmation.
    Please let me know how is it possible.
    Thanks in Advance
    Rohit

    FULL STEPS:
    1.first do mb1b 311 mvmt transfer posting  for the components from raw-stor location to prod stor location. you can do for A
    2.  do GI for the components. for A for that final product . consume 1.5 so. the remaining component will be (3 ) there in the stor. location as per sap. (check in mmbe)
    3. then do mb1b 311   transfer posting for the A component to raw-stor location. from the prod stor location.
    or rever the  transfer posting mb1b 312.

  • Variable Size Item, Material Setting

    Dear All,
    I have a requirement, from  users,
    They want to use Formula as
    ROMS1 * ROMS2 * ROMS3 * 1160  where 1160 is Density, and out put is Mass.
    Material Should be issued in Nos/Pc in Shop and not in KG,
    I want to know how this material to be used in System, Its BUM, Unit of issue etc..
    Please help,
    Regards
    Raghu M
    Edited by: raghu m on Nov 2, 2009 9:08 PM

    Hi Raghu,
    1. Maintain KG as BUM in material master for the component
    2. Maintain alternative unit of measure for volume (meter Cube) and BUM (KG)
    3. Maintain Default values for BOM in configuration (T-Code OS28) for Variable Size item as EA
    4. Maintain Formula key in configuration (T-Code OS15) for the formula to be used ie ROMS1 8 ROMS2 * ROMS3 * 1160
    5. While creating BOM give Item category as R for the component and give the qty, the system will pop up a screen for variable sizes. Enter Variable sizes.
    Hope the above satifies your requirement.
    Please try and revert back
    Regards
    Suri

  • "No selectable item exist for purchase requisition I_Banfn"

    Dear all
    While creating Po system show a massage"no selectable item exist for purchase requisition I_Banfn"
    Please help.

    Hi,
    PR status in status TAB in item details  You have following:
    Processing status :Specifies the current processing status of the purchase requisition: IS PO Created or RFQ created etc...
    Block ID:The requester (PR creator)can block a requisition item to prevent it from being converted to a purchase order
    Processing State: Released or not Released
    You need check above & then act to unblock if blocked , release it if it is not released  or check if this PR already converted to PO.
    Follow the steps to create PO from PR:
    Enter ME21N T.Code
    Click u201CDocument Overview onu201D
    Click u201CSelection Variantu201D and Select Purchase requisition and double click & Execute
    Now  you will PR Numbers,Select your PR Number , you will have line items(10,20,30 etc..) , you will have all the details of PR (like item category,material , quanitites for each line items) and Now click u201CAdoptu201D and u will see all PR related copy to PO.
    Regards,
    Biju K

  • Commitment Item Change in Purchase Requisition

    Hi All ,
    I want to change the commitment Item in the Purchase Requisition at the change of Material Group in the PR .
    I tried all the Exits and BADI but its not working  .
    Can any body suggest some  , how to do this ???
    Thanks n Regards
    Manik L Dhakate

    Hi,
    check this BADI is working or not..
    ME_COMMITMNT_PARKING                    BAdI for Redefining Commitment Interface When Parking