Variance report for planned vs actual 261

Hi Experts,
Is there a variance report for planned v/s actual raw material consumption for an order when the order is still running? I mean when only the partial quantities are confirmed (PCNF, PDLV)?
Regards,
Sachin

Hi,
Always the plannig is done for ordered quantity and the actual quantity is what actually used.
Pl. use T code CO02/CO03 - Goto - Cost Analysysis, you will get the details which you are looking for. If the layout doesn't suits your requirement, change layout with change options.
Madhava

Similar Messages

  • Is there standard report for planned and actual devlivery date?

    Hi Guru,
    Could you help me to find standard report to compare planned delivery date in PO and actual delivery date (GR Posting date)?
    I wonder, Is there standard report for planned and actual delivery date?
    or I have to create a customizing report.
    Thank you very much.

    hi
    i dont think it is possible to see both in one pan so try to create some Z report
    u try ME80fn here u have to change the views ,in del shedule view u can see the delivery dtae and in PO histry view u can see the posting date
    regards
    kunal

  • Report for extracting the actual and planned cost from service orders

    HI all
    we are creating a report in BI for Module - Customer service . LIke , the report is all about how many complaints created in the system and how many completed technically and what is the cost involved for each complaint .
    Like we want the comparision between the planned cost and the actual cost .
    Now to give the logic to the BI Team for planned cost and actual cost , please suggest the flow of logic or table flow to arrive the planned and actual cost
    thanks in advance

    Hi Marthand,
    I am not sure which datasource your are using. In this case, you can use the 0VALUETYPE to differencitae between th eplan and actuals. Normally Plan which is budget will have value 050 and for actuals will have 010. For costs, you will have one key figure and at the reporting level, you will have the costs restricted by the value type for plan and actual to make comparisons.
    Hope this helps.
    Regards,
    Srinivas

  • Report S_PL0_86000029 - Plan Vs Actual

    Hello Experts,
    I have successfully  uploaded the plan through GP12N manually monthwise .
    When I run the report  S_PL0_86000029 , I do get the values GL account wise, only issue is, I am getting these values cumulative. That is if I run report from May  2011 to May 2011, I am getting cumulative plan vlaues (& actuals as well)  that is for April 2011 and May 2011.
    If I want ot see monthwise vlaues for plan vs actual what should I do?
    Please advise.
    Regards
    Shailesh

    I think you can only start it on a monthly base, individually.
    Regards
    Hein

  • Report for Planned Delivery Costs

    Hi,
    Is there any Report for Planned delivery costs per month/day.One of our client needs separate report for frieght charges so that he can be able to pay service tax (GTA) for the same.
    Thanks
    Prasad

    Hai,
    Did you check thro' Tcode MIR5.

  • Best practice for Plan and actual data

    Hello, what is the best practice for Plan and actual data?  should they both be in the same app or different?
    Thanks.

    Hi Zack,
    It will be easier for you to maintain the data in a single application. Every application needs to have the category dimension, mandatorily. So, you can use this dimension to maintain the actual and plan data.
    Hope this helps.

  • How can I activate drill down report for planned line items please urgent?

    Hi Everyone,
    Please suggest me how can i activate drill down report for planned line items in internal orders. S_ALR_87012993. Please suggest me, I'll award full points. I am unable to do it in client system, which has already line items. I tried in my sys with new config it is working.
    Kind regards
    Arvey.

    Hi
    It is based on the reports attached in the Report Group - TCODE: GR53
    In the Report Group screen
    Press CONFIGURE – This is to attach any Drill Down reports.
    Press the “Insert Line” icon
    As is the screen may be used to insert a Report Writer report group. To add an ABAP, press “other report type”
    Double click on “ABAP Reports”
    Enter the name of the ABAP and ENTER
    <b>RCOPCA08                       Profit Center: Plan Line Items</b>
    VVR

  • PIE chart report for planned, Actual and variants cost

    Hi Gurus,
    Is there any report provides information of Plan cost, Actual cost and Variants cost for sales order or production Plan in PIE CHART format or any other chart diagram.
    Regards,
    Ram Krishna

    Hello,
    Go to relevant S_ALR* report.
    For example execute
    S_ALR_87013611
    Settings ==> Options
    Office Integration => Microsoft Excel
    Remove Worksheet Protection
    ignore the warning message.
    Go to insert tab on the MS excel.
    Select the report data.
    Click on pie chart.
    You will be able to see the pie chart.
    Regards,
    Ravi

  • Report for plan/actual

    I have a requirement plan vs actual report and the report format is as below .Please let me know is it possible to create a single report as per the below format .
    jan
    feb
    march
    april
    may
    jun
    july
    volume
    formula 1
    formula 2
    formula 3
    formula 4
    formula 5
    formula 6
    formula 7
    formula 8
    formula 9
    formula 10
    formula 11
    formula 12
    value
    formula 13
    formula 14
    formula 15
    formula 16
    formula 17
    formula 18
    formula 19
    formula 20
    formula 21
    formula 22
    formula 23

    Hi Surya,
    Create two structures in ROWS
    1 Volume -->Under this create formulas
    2 Value   --> Under this create formulas
    Place calendar month in COLUMNS.
    Added reference screenshot.
    Thank you,
    Nanda

  • Variance Report between G/L Actual Balance v/s G/L Budgeted amount.

    Dear Sir,
    I have G/L Account wise company budget.
    I want to compare the same with G/L actual balance and arrive at a variance report.
    While executing the financial report at F.01 if I select Plan version as 0
    the report is displaying the actual figure and at planned column it is not showing any amount.
    I understand that this is because I have not yet maintained any amount in Planed version.
    I want to know How to maintain G/L account wise planned amount that can be compared while executing F.01?
    or
    is there any other means by which my above referred objective can be achieved?
    Regards
    Chirag Shah

    Hi,
    Please refere the below link.
    [Entering Plan Data|http://help.sap.com/saphelp_dimp50/helpdata/en/27/94fa40fe14f423e10000000a155106/content.htm]
    Tcode: FSE5N
    Regards,
    Srinu

  • Copc...Tcode CO02...Where the system pull the figure for plan and actual?

    Hi all,
    Inside CO02, i go to "go to" then go to "costs" then click on "analysis" one report will come out.
    Inside the report, can i know that how the figure in the report come out?
    Inside the report for column like plan cost and actual cost. Where the system pull the figure out?
    I know the system will pull the material cost out from MM and overhead from costing sheet. But what is the different between plan cost and actual cost? The figure the system pull out will put in plan cost or actual cost?
    Best regards,
    Lucas

    Yes it needs to be licensed
    Regards
    Rob
    http://oemgc.wordpress.com

  • Report for planned or prodcution order for production in Alternate plants

    Hai gurus,
    I have two plants - X and Y
    Plant x have finished goods A and B to be produced  and procured from plant - Y
    plant Y have finished goods C and D to be produced  and procured from plant - X
    The production in alternate plant concept is used in plant X  for Product A and B
    The production in alternate plant concept is used in Plant Y for Product C and D.
    Now my requirement is how to get the report for the Purchase order raised by the
    plant X for the Finished product A and B , also how to know the planned order
    and production order with reference to purchase order for Finished product A and B
    under plant - Y
    and VIce versa for the Finished product C and B in plant X and Y
    Waiting for the positive reply.
    Regards,
    Sekar chand

    There are a few reports that you can use to display STO requisitions and orders, by supplying plant, material, or MD04 like was mentioned.
    The only thing that you don't have in a report is the link to the production order. In SAP in a MTS situation there's no fixed link (pegging) between the requirement (STO) and the supply (prod Ord).
    You can view the pegging dynamically, for example in MD04.
    Edited by: Mario Adler on Oct 27, 2011 12:13 PM

  • What is equivalent ASCP report for Planned Order&Order Reschedule Report

    What is equivalent report for Supply Chain Planned Order Report & Supply Chain Order Reschedule Report
    We are currently on MRP and running Supply Chain Planned Order Report successfully. We are planning to go to ASCP(Decentralized) next month ,what is the equivalent reports in ASCP?
    Edited by: SanDan on Jan 9, 2013 1:57 PM

    Hi ,
    You can explore the Planning Detail Report which you can run against your ascp plan. However there are few standard reports available in ascp. I suggest you can explore option of building custom report which will be best suited to your business needs (i.e. using Discoverer or if you are also implementing obiee you can build a custom report based on standard views or noitex views (- for ascp)
    Regards
    narendra

  • How to get the Price variance report for PO's?

    Hi all,
    Please help me by giving the exact T Code which gives the price variance for the PO's,which must be
    showing the difference between the GR value and the price(std.price) maintained in the material master.
    Waiting for your suggestions.
    Regards
    Mangalraj.S

    Hi,
    Take an easy way, you can go to the PO with t-code ME23N, at tab page PO history of the item detail, you can find the price variance for the item.
    Or you can use t-code MB5S to display the multi-POs' price variance report!
    Cheers
    Tao

  • Standard report for budget allocated, actual consumed, amount capitalize

    Hi,
    I need report for following condition: Is there any standard report for the same?
    Once the project is capitalized, the system should provide in one report
    the budget allocated, amount incurred, amount capitalized,
    Date of capitalization and remaining expenses in desired WBS as on desired date.
    Please suggest me, if any standard reports are available?
    Regards
    Bipin

    Dear Bipin,
    1) S_ALR_87013558 - This report will give you information about Budget, Actual, Commitment, Assigned, Budget Avail.
    2) S_ALR_87011990 - Asset History Sheet or S_ALR_87012050 - Direct Capitalization ( Asset Acquistion )
    Hope this will meet you requirement.
    If found useful reward the points.
    Regard's
    Sandeep N.Theurkar

Maybe you are looking for

  • What can I do when all of my printers have disappeared and can't be updated?

    I have lost all my printers.  They no longer show up when I go to select a printer.  I've tried going to Epson to reinstall drivers, however, they refer me back to apple update software.  Apple runs the scan and says there are not updates.  I've been

  • How do you install windows bootcamp on a second internal hard drive?

    I have a SSD as my main hard drive then installed the old hard drive internally in the internal optical bay slot. Whenever I try to install Windows and reboot, I get the No Bootable Disk error. Any ideas?

  • How to stop logging external jar debug statements

    Hi, I am developing a java app which uses FOP to convert xml to PDF. Log4j is used for logging and in my appender's threshold is set to "debug". I only want debug output of my app not the FOP, how can I achieve that. At this stage I get thousands of

  • Using the toggleOnOff()

    right now my buttons are public and i was woundering how i can make them private and when i make them private i cant use the if else statement. So i need help incorporating the public void toggleOnOff() method to my program so that it works the same

  • Struts exception handling - Exception handler

    Hi , I need some help for struts exception handling . Global exception is working fine in my struts application . But I need to show the exception stack trace also in the screen whenever the exception occurs.I guess this can be achieved if we use a c