hi,
If you have any of the reference docuements made for the current vendor, then yes ofcourse you have to make the changes in it:
You have to make changes in:
1. Doc like schedule agreement, contract, PR, PIR etc....you can have to change your vendor here....
2. change the source list as per the new vendor....
And then generate the PO....
OR
You can have the Partner functions:
So that you can deliver the materials to the other one....and you can can pay on the given bank account...
ie. you can change the bank account in VMR....
But this is possible if you can have the same vendor name.....
Hope it helps...
Regards
Priyanka.P

Similar Messages

  • Info record source list

    HI Everyone,,
    What is exactly the need for purchase info records.... wjhat activities we cant perform if we dont maintain and info record for each mat and vendor... and what is the need of SOURCE LIST other than using it in quota arrangement and for contracts... Can you please tell me.... Thanks a lot

    1. SCAT will be a simple to use..
    2. Go to the transaction code SCAT it will be easy for you ..and then do a recording with the relevant Tcode like me11.
    3. for more details about the scat
    you can use this area<a href="http://help.sap.com/saphelp_47x200/helpdata/en/d7/e21407408e11d1896b0000e8322d00/frameset.htm">SCAT</a>
    try this and let me know if u need any more details

  • Mass change in PIR, Source list

    Hi Gurus,
    If there is something wrong in a large number of PIRs, sourcelists, is there any way to change them on a mass scale, rather than going to each and every PIR and changing them manually?
    All the PIRs or source lists have the same correction.
    Thanks,
    Kumar

    Dear,
    Please check t-code MASS.
    Here you can mass change for material, vendor, purchase info record, purchase requisition etc.
    Regards,
    Mahesh Wagh.

  • Vendor update / generation in source list

    Hi,
    is there any solution that vendor update / generate in source list with reference to info record creation date.
    standard system behave in a way to generate / update source list on current date of updation.
    Regards,
    Ali

    Even I had the same problem.  source determination in MRP is different when compared to source determination in PR. MRP just picks the first vendor in the source list no matter whether the other vendor is fixed or not.
    Even SAP doesn't have proper answer on this issue in OSS note 206684.
    As others said, you need to copy ME05 and create a new TCODE with different logic for source list date.

  • Vendor material info record

    hi,
    When am trying to create vendor material info record,i see the<b> valid to</b> is <b>mandatory feild</b> but it is <b>disabled .</b>.
    i cannot enter any value in that.
    i:e    In <b>T/C me11</b> after i enter the details in the first screen,click enter it takes to the next screen. In that screen you can see conditions area you can see Net price and to its side you can see valid to that feild is mandatory feild but its blocked or disabled from entering values.
    hope you can understand guys,what and where am navigating.
    Thanks and regards
    Rajasekaran.

    hi
    go to img---materials managementpurchasingpurchasing info record--
    define screen layout
    here you click on the me11  and in the screen " maintain table t162 field selection groups" select conditions and on the net price put u r selection
    regards
    prashanth

  • Single material , two vendors how to maintaint source list

    Dear Experts,
                         we are buying  same material from two vendors, how to maintain source list for both material?. if i its possible , whether system will generate schedule lines for both material? please advice.
    regards
    rajakarthik

    Hi,
    Source list is the list for the number of vendors for a material in a purchase org .You can also fix a vendor here.You can procuire the material from both the vendors creating aggrement( ME31K).If you have delivery schedule lines you can go for SA--and schedules for both of them but while creating the PO you need to refer the relevamt aggrement.If not you can aslo the use the functionality of quota AT MEQ1.Source list caters only to some generic needs.
    Regards,

  • BAPI to change INFO record and Scheduling Agreement (ME32)

    Can anybody tell me what is the bapi function module used to change the info record and a bapi function module used to change the scheduling agreemnent (ME32)

    check in Tcode BAPI
    or Search in SE37
    BAPISChe
    Regards
    Peram

  • Selection of vendor in RFQ from source list

    Hi,
    I want to use source list in RFQ.While creating RFQ for a material,system should give the list of sources which now I am able to see in the enviornment tab but iam not able to select by means of double clicking or any other means.Is there any way to select multiple vendors from the source list tab and generate RFQ's against the selected vendors
    Regards
    RD

    I had also come across the Similar requirement. After much R&D I found that this is not possible.
    You ave to enter the Vendor code manually.
    Biswajit

  • Inco terms--vendor master& info record

    Hi Stephen  & Friends,
    I need your input on this subject.
    Incoterms we can maintain at vendor level and in info record also.
    If you maintain different incoterms info record.
    In the purchase order ,, you can find header inco terms will be the vendor,,,, and at item level,,,inco terms will be adopted from infor record.
    Which inco terms has got precedence over other.
    What exactly system detmines the from this,
    please respond.
    Regards,
    Sudhakar babu.

    Hi Sudhakar,
    The Inco-terms are internationally accepted rules for world trade. In this way, purchasers can collaborate with their vendors to define delivery conditions and connected buyer and seller obligations. - SAP Help Document
    Now coming to the specific case which you have mentioned:
    The inco-term maintained at item level takes precedence over the one maintained at header level. The reason SAP provides this option is because, in a single PO you might have multiple items & each one of those might have to be transported in a different manner. But if no inco-term is maintained at item level, then the header level inco-term is used.
    Hope this answers your question.
    Regards,
    Vivek

  • Please reconcile source list records - source list

    Hi,
        I am getting the following error while trying to add a line to the source list - purchasing.
    Please reconcile source list records
    Message no. 06 329
    Diagnosis
         One or more source list records contain(s) conflicting data (e.g. two
         records defined as fixed sources in the same period).
    Procedure
         Make sure your entries are correct.
    But only one line has fixed flag set.
    Data:
    01/01/2005     12/31/2007     BU86     E090
    01/01/2005     12/31/2007     BU86     E090          BTL     4600000429     10
    01/24/2007     03/31/2008     BU86     E090          BTL     4600000459     30
    01/01/2008     03/31/2008     BU86     E090          BTL     4600000459     30
    02/01/2008     03/31/2008     BU86     E090          BTL     4600000459     30
    03/01/2008     03/31/2008     BU86     E090          BTL     4600000459     30
    04/01/2008     12/31/2008     bu86     e090               4600000537     10
    I am trying to add the last row as above.
    Any help? Thanks,

    01/01/2008 03/31/2008 BU86 E090 BTL 4600000459 30
    02/01/2008 03/31/2008 BU86 E090 BTL 4600000459 30
    03/01/2008 03/31/2008 BU86 E090 BTL 4600000459 30
    Why do have the same contract item 3 times in your source list?
    Maybe this causes the error but i am not certain.
    check OSS, there are about 10 notes when searching with 06329

  • Change info record condition pricing unit.

    i would like to change pricing  unit via me12, but the pricing  unit can't be modified. how can i achive this. (ps: i change the info record via lsmw.)

    are you manage to change the info record price unit using ME12?, i dont think that the price unit can be change after you enter and save it, you need to mark delete the condition line first, then create a new condition line record for that validity period.

  • LSMW-Change Info Record

    Hi all,
    I need to use LSMW to change infor records, they are standard, consignment and subcontracting info records.
    How can I make the system to choose the right info record type? Do I need a recording with these three fields?
    NORMB                Indicator: Standard info record
    LOHNB                Indicator: Subcontractor purchasing info record
    KONSI                Indicator: Consignment info record
    Thanks!

    How do you know which info record you need to change?
    Based on what field  do you do this decision?
    I recommend not to use recordings, SAP has developed  LSMW import methods for info records that really work well.
    Recordings are only needed if SAP has not given anything in standard, mainly to load data into Z-tables.
    I recommend to have a look into the info record tables EINA and EINE
    EINE table has only  field ESOKZ that determines which type of info record it is.

  • [权限控制]关于价格控制查询的问题_MM_info record&source list

    公司上SAP系统,对于每个部门的Key User都开通了QUERY和SE16的权限
    现在的状况是只要开通了QUERY和SE16的用户都可能查询表EINE将价格查的一清二楚
    然而我们老板采购的主管不想让其他的部门查询到价格及供应商信息
    主要是针对价格的控制,表EINE能否设置权限让具有QUERY和SE16的权限的用户也不是每个人都可以查询呢?
    谢谢!

    SE16对表格的权限控制是由S_TABU_DIS来做的,他有两个field,一个是activity,用来控制动作的,如现实,更改等;另外一个是DICBERCLS (Authorization Group),用来定义对象范围的,通常可以在TDDAT表格里找出相应的表格和authorization group的关系。但是由此可见,SE16里无法对某一个表格做出规定。

  • Difference between source list and info records

    Dear All,
    What is the difference between Source List and Info Records?
    Thanks N Regards
    Anandasiva

    Hi,
    The source list is the list which shows the sources from which you can procure the material. If you have ticked the source list requirement in the material master, then you can procure the material only from the vendors mentioned in the source list.
    In Inf Record, you maintain the data for a material supplied by a vendor. e.g. Material price, tax code, other conditions,, buyer code, delivery & payment terms.
    Hope your requirement is fulfilled.
    Reward points if the answer is helpful.
    Regards,
    Prashant Kolhatkar

  • Purchasing Info Record- Different Regular Vendor for different Plant

    Dear Guru,
    I'm encounter a problem with PIR.
    I have this PIR 9001 (Vendor A) and 9002 (Vendor B) for material A, which i have extended to 2 different Pur.Org 0001 under company code 0001 and Pur.Org 0002 uner Company code 0002.
    For Pur.Org 0001, i set the Regular Vendor as Vendor A, but when i trying to set the regular vendor for Pur.Org 0002 to be as Vendor B, i receved the message as "Up to now, vendor A has been regular vendor for this material".
    And After i changed this Regular vendor to vendor B, this changed have also affected the PIR for Pur. Org 0001.
    Can i know if there is a way to change the PIR Regular vendor at Pur.Org or Plant level?
    Thank you very much,
    Regards,
    Chee Wee

    Hi,
    Regular vendor is at client level.
    That's why, you cann't maintain more then one vendor (Source of supply) for the same material.
    If you want to maintin separate vendor for the each plant and same material combination, then don't activate / select regular vendor option in the info record. You have to maintain source list.
    Sour list is nothing but a list of source of supplies for the specific plant and material combination with in the validity period of time. If there are more then one vendor for the specific plant and material combination for the same validity period of time, then you can activate fixed vendor option in the source list. Then at the time of creating PO, SAP will pick fixed vendor for the Plant and Material combination.
    So first, system will check whether regular vendor is there for this material in the info record. If is there,system will pick regular vendor in the PO. If not, then system will check fixed vendor in the source list for the material and plant combination. If yes, then system will pick fixed vendor from the source list. If not system will propose all the vendors in the source list. If the source list it self not created, then user has to give vendor number manually.
    Regards